DELAWARE RIVERKEEPER NETWORK; MAYA VAN ROSSUM, thе Delaware Riverkeeper, Petitioners v. SECRETARY OF THE PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION; PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION, Respondents Tennessee Gas Pipeline Co., Intervenor
No. 17-1533
UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT
Argued July 13, 2017 (Filed: August 30, 2017)
PRECEDENTIAL. On Petition for Review from the Pennsylvania Department of Environmental Protection WQ02-002 E52-253 E63-305 FERC-1 : FERC CP16-4
Aaron J. Stemplewicz [ARGUED]
Delaware Riverkeeper Network
925 Canal Street, Suite 3701
Bristol, PA 19007
Counsel for Petitioners
Alexandra C. Chiaruttini
Joseph S. Cigan III [ARGUED]
Commonwealth of Pennsylvania
Department of Environmental Protection
2 Public Square
Wilkes-Barre, PA 18701
Kimberly Hummel Childe
Office of Attorney General of Pennsylvania
Department of Environmental Resources
9th Floor
P.O. Box 8464
Harrisburg, PA 17105
Counsel for Respondents
Pamela S. Goodwin
Saul Ewing
650 College Road East, Suite 4000
Princeton, NJ 08540
John F. Stoviak [ARGUED]
Saul Ewing
1500 Market Street
Centre Square West, 38th Floor
Philadelphia, PA 19102
Elizabeth U. Witmer
Saul Ewing
1200 Liberty Ridge Drive, Suite 200
Wayne, PA 19087
Counsel for Intervenor Respondent
OPINION OF THE COURT
SMITH, Chief Judge.
Tennessee Gas Pipeline Co. (“Tennessee Gas“) submitted applications to several federal and state agencies seeking approval to build an interstate pipeline project. One such agency is the Pennsylvania Department of Environmental Protection (“PADEP“),1 which issued a permit approving the
We will exercise jurisdiction because PADEP‘s decision was final. We will also uphold PADEP‘s decision on the merits because the agency‘s unique interpretation of water dependency is reasonable and worthy of deference. Furthermore, the agency considered and rejected the compression alternative for reasons that are supported by the record. We will therefore deny the petition for review.
I
At issue is the so-called Orion Project—12.9 miles of pipeline looping that would transport 135,000 dekatherms of natural gas per day via Pennsylvania. Approximately 99.5% of the new pipeline would run alongside existing pipelines.
Full background information on the Orion Project is provided in a companion case, Delaware Riverkeeper Network v. U.S. Army Corps of Engineers, No. 17-1506 (3d Cir. 2017). For purposes of this opinion, we will focus on the aspects of the state administrative procedures at issue here.
Under the Natural Gas Act of 1938, the Federal Energy Regulatory Commission (“FERC“) is the “lead agency” for evaluating interstate pipeline projects.
As a condition of obtaining a Water Quality Certification, PADEP requires applicants to obtain other state permits, including a Water Obstruction and Encroаchment Permit issued under Pennsylvania‘s Dam Safety and Encroachment Act and its implementing regulations,
Chapter 105 gives special protection to “exceptional value” wetlands. Wetlands are considered to have exceptional value if, inter alia, they are located along a drinking water supply or serve as habitat for endangered species. See
PADEP cannot issue a Chapter 105 permit for a project affecting exceptional-value wetlands unless it certifies in writing that seven requirements are met.
(2) The project is water-dependent. A project is water-dependent when the project requires access or proximity to or siting within the wetland to fulfill the basic purposes of the project.
(3) There is no practicable alternative to the proposed project that would not involve a wetland or that would have less effect on the wetland, and not have other significant adverse effects on the environment.
On September 20, 2016, PADEP issued a conditional Water Quality Certification for the Orion Project. Then, on February 23, 2017, PADEP issued two Chapter 105 permits approving the Orion Project‘s strеam and wetland crossings—Permit Nos. E52-253 (Pike County) and E64-305 (Wayne County). In doing so, PADEP certified that the Orion Project “[i]s water dependent” and would be “the least environmentally damaging alternative.” JA 49, 180.
On March 10, 2017, Riverkeeper filed this petition for review. We granted Tennessee Gas‘s motion to intervene on March 17, 2017. Riverkeeper filed a motion for an emergency stay, which this Court denied on April 7, 2017. Riverkeeper then filed a motion to expedite the case. We granted that motion on May 8, 2017.
II
The parties ask us to resolve two jurisdictional issues: (1) whether we may review nonfinal administrative orders under the Natural Gas Act; and (2) whether the petition was timely filed. We need not reach the first question. The agency decision at issue is final, and therefore jurisdiction would be proper under either interpretation of the Natural Gas Act. As for the second question, we conclude that the petition was timely filed.
A
First, Riverkeeper argues that we lack jurisdiction because we may only review final orders, and PADEP‘s order is not final until it has been reviewed by a separate administrative entity, Pennsylvania‘s Environmental Hearing Board. Riverkeeper asks us to transfer the case to the Board.2 We conclude that jurisdiction is proper because PADEP‘s order is final.
1
Our jurisdiction is controlled by Section 19(d) of the Natural Gas Act, as amended in 2005. Where an intеrstate pipeline project is proposed to be constructed, see
In a recent precedential opinion, this Court exercised jurisdiction over a similar PADEP decision involving the “Leidy Line” pipeline project. Del. Riverkeeper, 833 F.3d 360. The petitioner, also Riverkeeper, challenged PADEP‘s decision to issue a Water Quality Certification. This Court concluded that “the issuance of a Water Quality Certification is not purely a matter of state law” because the certification “is an integral element of the regulatory scheme established by the Clean Water Act.” Id. at 371. Thus, PADEP was “acting pursuant to Federal law” within the meaning of the Natural Gas Act.
First, Berkshire held that
Second, Berkshire concluded that the particular agency decision at issue was not final. It evaluated “[t]he substance of the Massachusetts regulatory regime,” Berkshire, 851 F.3d at 112, and concluded that the applicant (also Tennessee Gas) was required to go through an additional adjudicatory hearing
Although the Leidy Line case was procedurally similar to this one, the finality issue was not presented and remains unresolved in this circuit. We must therefore address it. See, e.g., Ehleiter v. Grapetree Shores, Inc., 482 F.3d 207, 211 (3d Cir. 2007) (“[A] court of appeals has both the inherent authority and a continuing obligation to assess whether it has jurisdiction over a case or contrоversy before rendering a decision on the merits.“).
2
Riverkeeper argues that we should follow Berkshire‘s holding and read a finality requirement into
“Our cases have interpreted pragmatically the requirement of administrative finality, focusing on whether judicial review at the time will disrupt the administrative process.” Bell, 461 U.S. at 779. Final agency action “must mark the ‘consummation’ of the agency‘s decisionmaking process,” “must not be of a merely tentative or interlоcutory nature,” and “must be one by which ‘rights or obligations have been
According to Riverkeeper, Pennsylvania‘s administrative process does not reach a final conclusion until PADEP‘s order has been reviewed by a separate administrative entity, the Environmental Hearing Board. In support of that proposition, Riverkeeper cites the Pennsylvania statute governing the Board‘s jurisdiction:
[N]o action of the department [PADEP4] adversely affecting a person shall be final as to that person until the person has had the opportunity to appeal the action to the board . . . . If a person has not perfеcted an appeal in accordance with the regulations of the board, the department‘s action shall be final as to the person.
Assuming (without deciding) that
Apart from
Thus, by combination of
B
PADEP argues that, because Riverkeeper‘s petition would be untimely before the Environmental Hearing Board, it is also
Under Rule 15 of the Federal Rules of Appellate Procedure, “[r]eview of an agency order is commenced by filing, within the time prescribed by law, a petition for review.”
According to PADEP, “the time prescribed by law,”
But this is not an appeal before the Environmental Hearing Board, and the Board‘s regulations are not binding on us. Rather, Rule 15 “defin[es] the time for filing a petition for review with reference to the statute providing for review of the agency‘s orders.” United Gas Pipe Line Co. v. FERC, 824 F.2d 417, 435 (5th Cir. 1987). That refers to Section 19(d) of the Natural Gas Act. See Islander E. Pipeline Co., LLC v. Conn. Dep‘t of Envtl. Prot., 482 F.3d 79, 83–84 (2d Cir. 2006) (“[T]he NGA . . . provides an expedited direct cause of action in the federal appellate courts to challenge a state administrative agency‘s order . . . .“).
Accordingly, jurisdiction is proper under the Natural Gas Act and under Rule 15 of the Federal Rules of Appellate Procedure.
III
Turning to the merits, we review for arbitrary or capricious agency action. Del. Riverkeeper, 833 F.3d at 377.8 Riverkeeper argues that PADEP erred under that standard for two reasons. First, Riverkeeper argues that PADEP made an erroneous
A
PADEP determined that the Orion Project is “water dependent.” According to Riverkeeper, that finding was erroneous because linear infrastructure projects (like pipelines and roads) are categorically not water dependent. PADEP acknowledges that, under federal law, Riverkeeper might bе right. But under Pennsylvania law, PADEP argues, water dependency operates differently. We conclude that PADEP has provided a reasonable explanation for how its regulations differ, and we will defer to its interpretation.
Because the Orion Project would construct pipeline looping through “exceptional value” wetlands,
Riverkeeper thus argues, by reference to federal law, thаt pipelines and other types of linear infrastructure are categorically not water dependent. It relies on the following explanation of water dependency by a federal agency, the United States Army Corps of Engineers:
[T]he purpose of a residential development is to provide housing for people. Houses do not have
to be located in a special aquatic site to fulfill the basic purpose of the project, i.e., providing shelter. Therefore, a residential development is not water dependent. . . . Examples of water dependent projects include, but are not limited to, dams, marinas, mooring facilities, and docks. The basic purpose of these projects is to provide access to the water.
Sierra Club v. Van Antwerp, 709 F. Supp. 2d 1254, 1261 (S.D. Fla. 2009) (quoting Army Corps of Engineers Standard Operating Procedures for the Regulatory Program (October 15, 1999)), aff‘d, 362 F. App‘x 100 (11th Cir. 2010). Under that understanding, Riverkeeper argues that pipeline projects are not water dependent because, unlike a dam, marina, or dock, pipelines are not by their nature dependent on being in or near water—even if the desired construction path would cross a wetland or waterbody. See, e.g., Coastal Conservation League v. U.S. Army Corps of Eng‘rs, No. 4:16-cv-03008, 2016 WL 6823375, at *14 (D.S.C. Nov. 18, 2016) (noting that a road project is not water dependent even though “expanding and improving the road cannot occur without impacting special aquatic sites“).
In the context of the federal regulatory scheme, that understanding of water dependency makes sense. If a project is water dependent, like a dam, it is impossible to construct without impacting an aquatic site. But if a project is not water dependent, “practicable alternatives that do not involve special aquatic sites are presumed to be available, unless clearly demonstrated otherwise.”
PADEP took a different approach. It observed that the proposed pipeline looping “needs to cross the wetland areas to access land on either side of the wetland system” because “there are no practicable crossing alternatives to avoid the crossing.” JA 49, 180. Indeed, “[l]inear infrastructure projects of any significant length proposed in Pennsylvania will encounter surface waters, including wetlands.” Resp. Br. 14. By rejecting alternatives to the Orion Project and observing the pipeline‘s path would unavoidably traverse wetlands, PADEP concluded that the Orion Project is water dependent. Rather than treating water dependency and alternatives analysis as two distinct inquiries, PADEP combined them into one step.
Riverkeeper argues that the federal understanding of water dependency should control. The definition of water dependency in
PADEP responds that Riverkeeper‘s emphasis on federal law is misplaced because PADEP relied on a regulatory provision unique to Pennsylvania:
(b) In reviewing a permit application under this chapter, the Department will use the following factors to make a determination of impact:
. . .
(7) The extent to which a project is water dependent and thereby requires access or proximity to or siting within water to fulfill the basic purposes of the project. The dependency must be based on the demonstrated unavailability of any alternative location, route or design and the use of location, route or design to avoid or minimize the adverse impact of the dam, water obstruction or encroachment upon the environment and protect the public natural resources of this Commonwealth.
In light of these conflicting provisions, we conclude that the meaning of “water dependent” in
Pennsylvania specifically recognizes Auer-style deference for its agencies. See, e.g., Buffalo Twp. v. Jones, 778 A.2d 1269, 1276 n.8 (Pa. Commw. Ct. 2001) (“In reviewing an agency‘s interpretation of . . . its own regulations, unless the language is clear, we are required to defer to the agency‘s interpretation . . . .“), aff‘d, 813 A.2d 659 (Pa. 2002). Nothing in the Natural Gas Act or our system of federalism compels us
Applying that deferential standard, we conclude that PADEP‘s interpretation of water dependency is reasonable.
Second, PADEP‘s flexible approach to water dependency is public and longstanding. See, e.g., Barnhart v. Walton, 535 U.S. 212, 220 (2002) (“[T]his Court will normally accord particular deference to an agency interpretation of ‘longstanding’ duration.” (quoting North Haven Bd. of Ed. v. Bell, 456 U.S. 512, 522 n.12 (1982))). In 1991, when the relevant regulations were first promulgated, PADEP stated its intention to evaluate the water dependency of linear infrastructure projects on a case-by-case basis. For example, in response to a public comment, PADEP stated that “[r]oads may be considered water dependent on a case by case basis.” DEP Addendum 12; see also DEP Addendum 9 (“[T]he Department believes that haul roads, depending on their location, may be water dependent and will make that determination on a case by case basis.“). Such case-by-case analysis belies the categorical approach urged by Riverkeeper.
And third, watеr dependency plays a different role in Pennsylvania‘s administrative scheme. Under the federal regulations, water dependency is a procedural consideration that affects the applicant‘s burden. See
Thus, we conclude that PADEP did not act arbitrarily or capriciously by incorporating an alternatives analysis as part of its water-dependency finding. While PADEP‘s interpretation of water dependency appears to be unique, it is nonetheless reasonable in light of the text and structure of Pennsylvania‘s regulatory scheme. We will therefore defer to PADEP‘s interpretation and reject Riverkeeper‘s categorical approach.
B
Riverkeeper finally argues that, even if PADEP‘s water-dependency finding was not arbitrary or capricious, PADEP‘s alternatives analysis was erroneous. Specifically, Riverkeeper asserts that PADEP was required to embrace a compression alternative. That alternative would have increased the amount of natural gas transported through existing pipelines—avoiding all impacts on wetlands and waterbodies that would be caused by constructing new pipeline looping. We conclude, however, that PADEP considered the compression alternative and rejected it for reasons supported by the record.
In addition to certifying that the project is water dependent, PADEP must also certify that “[t]here is no [1] practicable alternative to the proposed project that [2] would not involve a wetland or that would have less effect on the wetland, and [3] not have other significant adverse effects on the environment.”
The compression alternative would “us[e] gas- and electric-powered turbines to increase the pressure and rate of flow at given points along the pipeline‘s route.” Del. Riverkeeper, 833 F.3d at 369.11 As part of its application to PADEP, Tennessee Gas included an alternatives analysis that rejected that approach. Tennessee Gas stated that “adding a new (greenfield) compressor station would require Tennessee [Gas] to obtain approximately 40-acres per site,” and that construction “would require permanent vegetation clearing from the area in order to install permanent access roads, fencing, buildings and other appurtenance equipment . . . resulting in increased impacts to the environment.” JA 266, 279. Tennessee Gas also observed that “a new (greenfield) compressor stаtion would be an
While PADEP did not explicitly mention compression in its alternatives analysis, it did consider “System Alternatives,” i.e., alternatives that make use of existing transportation systems. JA 45, 176. Compression is one type of system alternative. See JA 294. PADEP also adopted Tennessee Gas‘s reasoning as its own: “The Department has reviewed [Tennessee Gas‘s] report and finds no cause to disagree with the conclusions and final alternative presented.”
As part of a checklist reflecting the criteria for approving projects that would affect exceptional-value wetlands, PADEP certified that the Orion Project is “the least environmentally damaging alternative.” JA 49, 180. In support of that conclusion, PADEP references its alternatives analysis, which in turn adopted Tеnnessee Gas‘s reasoning. As discussed at length in the federal companion case, the agency‘s statement amounts to a judgment that the permanent environmental impacts from the compression alternative are “significant.” See Motor Vehicle Mfrs. Ass‘n of U.S. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (“We will . . . uphold a decision of less than ideal clarity if the agency‘s path may reasonably be
Accordingly, we conclude that PADEP did not arbitrarily or capriciously disregard the compression alternative.
IV
For the foregoing reasons, we will uphold PADEP‘s decision to issue the Chapter 105 permits and deny the petition for review.
