ISLANDER EAST PIPELINE COMPANY, LLC, Petitioner, v. State of CONNECTICUT DEPARTMENT OF ENVIRONMENTAL PROTECTION, Respondent.
Docket No. 05-4139-AG
United States Court of Appeals, Second Circuit
Decided Oct. 5, 2006.
Reargued April 11, 2006.
467 F.3d 73
Argued Jan. 4, 2006.
Lastly, the evidence on the other counts on which Jones was convicted was more than adequate. The evidence as to the existence of a RICO enterprise and as to Jones‘s participation in that enterprise and in the alleged narcotics conspiracies, for example, was, as discussed in Part II.A.2. above, overwhelming. In all the circumstances, we see no realistic possibility that the evidence as to the murder of Lawrence affected the jury in its assessment of the evidence on the other counts against Jones.
E. Sentencing
Finally, Jones contends that he is entitled to be resentenced because his sentences were imposed under the then-mandatory Guidelines regime that was subsequently invalidated in Booker, 543 U.S. at 244, 259, 125 S.Ct. 738. As Jones did not challenge the mandatory application of the Guidelines in the district court, his challenge is subject only to plain-error analysis. See
CONCLUSION
We have considered all of Jones‘s arguments on this appeal and have found in them no basis for disturbing his convictions. We remand to the district court for such further proceedings as may be warranted in accordance with the foregoing.
Richard Blumenthal, Attorney General, State of Connecticut (Kimberly P. Massicotte, David H. Wrinn, Assistant Attorneys General, on the brief), Office of the Attorney General, Hartford, CT, for Respondent.
Before KEARSE and RAGGI, Circuit Judges, and RESTANI,* Judge.
Judge KEARSE dissents in a separate opinion.
RESTANI, Chief Judge.
Petitioner Islander East Company, LLC (Islander East) is a natural gas company, formed under the laws of Delaware, with its principal place of business in Houston, Texas. Petitioner seeks to construct an interstate natural gas pipeline, originating in North Haven, Connecticut, and crossing the Long Island Sound to terminate in Brookhaven, Long Island. In furtherance of this project, Petitioner asks the Court to review an order of the State of Connecticut Department of Environmental Protection (CTDEP) denying Petitioner‘s application for a Water Quality Certificate (WQC) for discharge into the waters of the Long Island Sound. Although we review such an agency denial deferentially, in this case, it appears that the challenged agency decision was arbitrary and capricious because the CTDEP (1) failed adequately to explain or support its denial with record evidence, (2) did not acknowledge or explain contradictory record evidence, and (3) neglected to consider important aspects of the problem. Accordingly, we remand to the agency for further proceedings consistent with this opinion.
BACKGROUND
This case involves a petition to review a state agency determination pursuant to a recent amendment to the
* The Honorable Jane A. Restani, Chief Judge of the United States Court of International Trade, sitting by designation.
A. Statutory and Regulatory Scheme
The NGA provides comprehensive federal regulation for the transportation or sale of natural gas in interstate commerce.
In conjunction with the FERC‘s review of a natural gas project application, it must ensure that the project complies with the requirements of all relevant federal laws, including the
[t]he United States Court of Appeals for the circuit in which a facility subject to section 717b of this title or section 717f of this title is proposed to be constructed, expanded, or operated shall have original and exclusive jurisdiction over any civil action for the review of an order or action of a Federal agency (other than the Commission) or State administrative agency acting pursuant to Federal law to issue, condition, or deny any permit, license, concurrence, or approval (hereinafter collectively referred to as “permit“) required under Federal law, other than the Coastal Zone Management Act of 1972.
The limited legislative history accompanying the EPACT indicates that Congress enacted section 19(d) because applicants, like Islander East, were encountering difficulty proceeding with natural gas projects that depended on obtaining state agency permits. See Reg‘l Energy Reliability & Sec.: DOE Auth. to Energize the Cross Sound Cable: Hearing Before the H. Subcomm. on Energy & Air Quality, 108th Cong. 8 (2004) (statement of Rep. Barton) (discussing an earlier version of the EPACT, and explaining that “the comprehensive energy bill requires States to make a decision one way or another, and removes the appeal of that decision to Federal court,” which “will help get projects, like the Islander East natural gas pipeline, constructed“); Natural Gas Symposium: Symposium Before the S. Comm. on Energy & Natural Res., 109th Cong. 41 (2005) (statement of Mark Robinson, Director, Office of Energy Projects, FERC) (observing that, prior to the enactment of the EPACT, NGA applicants were subject to “a series of sequential administrative and State court and Federal court appeals that [could] kill a project with a death by a thousand cuts just in terms of the time frames associated with going through all those appeal processes“).
B. Islander East‘s NGA Application
On June 15, 2001, Islander East filed an application with the FERC under section 7(c) of the NGA for a certificate of public convenience and necessity to construct, own, and operate a new interstate pipeline to transport gas in Connecticut and New York. See Islander East Pipeline Co., 2001 WL 1638769, 97 F.E.R.C. ¶ 61,363, at 62,685 (2001). In pertinent part, Islander East proposed to construct: (1) approximately 44.8 miles of 24-inch pipeline from an interconnection with an existing pipeline near North Haven, Connecticut, across the Long Island Sound to Brookhaven, New York on Long Island; and (2) approximately 5.6 miles of 24-inch pipeline from the proposed Islander East mainline near Wading River, New York, to a power plant in Calverton, New York. Id. Approximately 22.6 miles of the pipeline would cross the Long Island Sound, with the remaining 27.8 miles onshore. See
On December 21, 2001, the FERC issued a Preliminary Determination on Non-Environmental Issues relating to pipeline construction, which indicated that authorization for the construction and operation of the proposed work would be in the public convenience and necessity as required for approval under section 7(c) of the NGA. See Islander East Pipeline Co., 97 F.E.R.C. at 62,685. On August 21, 2002, the FERC issued a Final Environmental Impact Statement (FEIS), pursuant to the requirements of NEPA. Fed. Energy Regulatory Comm‘n, Islander East Pipeline Project, Final Environmental Impact Statement (2002); see also Islander East Pipeline Co., 2003 WL 245811, 102 F.E.R.C. ¶ 61,054, at 61,113–14 (2003). The FEIS determined that one project system alternative to Islander East‘s proposal would be environmentally preferable because that alternative, based on the Iroquois Pipeline‘s ELI Extension Project, had a shorter Long Island Sound crossing, avoided more shellfish leases, and would only have air quality and noise impacts onshore in Connecticut. See FEIS at ES-5. Nevertheless, the FEIS concluded that, if Islander East constructed the project as proposed and in accordance with the recommended mitigation measures, it would be an environmentally acceptable action. See id.
On September 19, 2002, the FERC issued a final order granting Islander East‘s requests for authorization to construct and operate its proposed interstate natural gas pipeline, conditioned on its compliance with various environmental requirements prior to beginning construction on the pipeline. Islander East Pipeline Co., 100 F.E.R.C. at 62,102. The FERC concluded that because the Islander East Project would be an environmentally acceptable action and because it would provide significant benefits, it was required by public convenience and necessity under the NGA. The FERC pointed out that Islander East‘s proposal would provide Long Island with a second source of natural gas supply, providing the benefits of pipeline-to-pipeline competition, and would provide a second facility to access natural gas supplies in the event of a problem with one of the facilities.5 See id.
Pursuant to the CZMA and the CWA, Islander East filed applications with the States of New York and Connecticut seeking the following state authorizations under federal law: (1) a certificate of consistency with the state‘s Coastal Zone Management Plan (CZMP) pursuant to section 307(c)(3)(A) of the CZMA,
Second, Islander East proposed to use a mechanical bucket dredge to excavate an exit basin that would serve to contain and restrict the release of drill fluid at the HDD exit point. From the exit basin, Islander East would continue to use the mechanical bucket dredge to excavate a trench to approximately MP 12. In order to reduce the impacts of sediment deposition, Islander East would place dredge spoil onto hopper barges, instead of sidecasting it onto the sea floor for later use as backfill. Next, the pipeline would be laid into the trench, and the trench would be covered with engineered backfill, in the form of bank-run gravel.
Finally, for the deeper waters between MP 12 and MP 32, Islander East proposed to use a vessel with a sub-sea plow and mooring system. Using this method, the towing vessel would move along the pipeline route by pulling in its bow anchor lines and releasing its stern anchor lines, while an anchor handling tug would move the anchors ahead of the towing vessel. To minimize anchoring impacts, Islander East proposed to lower the pipeline with a single pass of the sub-sea plow. Following the pass, a backfill plow would return the displaced spoil to the trench. See generally Islander East Pipeline Co., Permit Application for: 401 Water Quality Certificate, Marine Pipeline Installation Methodology 1-6 (2003) (Pipeline Installation Methodology).
On February 5, 2004, the CTDEP denied Islander East‘s application for a WQC, finding the proposed pipeline work to be inconsistent with the Connecticut Water Quality Standards (CTWQS). See Islander East Pipeline Co., CTDEP Denial Letter (Feb. 5, 2004) (CTDEP Denial).
While the state proceedings were pending, EPACT was signed into law on August 8, 2005. That same day, pursuant to the newly enacted section 19(d) of the NGA, Islander East filed a petition for expedited review of the CTDEP Denial with this Court, see Dkt. No. 05-4139, and moved to stay the Connecticut state court proceedings. Subsequently, the CTDEP moved to dismiss Islander East‘s petition for review in this court for lack of subject matter jurisdiction, and Islander East moved to amend its petition to add current CTDEP Commissioner Gina McCarthy as a respondent. On January 23, 2006, this court ruled that it would consider the above motions along with the merits of Islander East‘s petition.
DISCUSSION
Islander East brings this petition for review to contest the CTDEP‘s denial of its WQC application, so that it may begin construction of its FERC-approved natural gas pipeline project. Petitioner contends that the denial of its application for a WQC (1) prevents the construction of a pipeline facility subject to section 7 of the NGA, and (2) violates federal law because the pipeline facility is consistent with the CTWQS. Thus, Petitioner asks the Court to find in its favor on both the aforementioned grounds and to remand this proceeding to the CTDEP with instructions to issue the requested WQC.
As an initial matter, the CTDEP challenges the Court‘s subject matter jurisdiction to review this petition, contending that the Tenth and Eleventh Amendments to the United States Constitution bar Petitioner‘s suit against the CTDEP on the basis of state sovereignty, and arguing that Section 19(d) of EPACT may not be retroactively applied to confer jurisdiction on this court.7 The CTDEP also asks the Court to deny Petitioner‘s motion to add the Commissioner as a respondent, arguing that the Ex parte Young doctrine allowing suits against state officials does not provide an exception to the State‘s Eleventh Amendment immunity in this case. See Ex parte Young, 209 U.S. 123, 28 S.Ct. 441, 52 L.Ed. 714 (1908). In the event that the Court reaches the merits of Petitioner‘s section 19(d) suit, Respondent contends that the CTDEP Denial is consistent with federal law.
I. Jurisdiction over the CTDEP and the Commissioner
A. Eleventh Amendment Immunity
The Eleventh Amendment provides that United States courts may not consider “any suit in law or equity, commenced or prosecuted against one of the United States by Citizens of another State....”
Respondent argues that section 19(d) of the NGA violates the Eleventh Amendment because it permits a private company to bring suit in federal court to challenge a decision by a state agency. Respondent acknowledges two circumstances in which private citizens may sue state agencies in federal court: (1) when Congress unequivocally expresses its intent to abrogate state sovereign immunity pursuant to a valid grant of constitutional authority, see Fitzpatrick v. Bitzer, 427 U.S. 445, 456, 96 S.Ct. 2666, 49 L.Ed.2d 614 (1976); and (2) when a State voluntarily waives its Eleventh Amendment immunity, see Coll. Sav. Bank v. Fla. Prepaid Postsecondary Educ. Expense Bd., 527 U.S. 666, 686-87, 119 S.Ct. 2219, 144 L.Ed.2d 605 (1999) (inferring State waiver of immunity from the State‘s acceptance of a “gratuity” offered by Congress conditioned on the State‘s willingness to be subject to suit in federal court). Respondent argues that the CTDEP is entitled to a presumption of immunity, and that neither of the above exceptions to Eleventh Amendment immunity exist here. See id. at 682, 119 S.Ct. 2219 (stating that “[c]ourts indulge every reasonable presumption against waiver” of sovereign immunity (quoting Aetna Ins. Co. v. Kennedy ex rel. Bogash, 301 U.S. 389, 393, 57 S.Ct. 809, 81 L.Ed. 1177 (1937))).
Islander East analogizes the Court‘s jurisdiction under section 19(d) of the NGA to the federal regulatory scheme established by the
Respondent does not dispute that by accepting a role as deputized regulator under the CWA, a state agrees to waive its immunity from suit under section 19(d) of the NGA. Instead, Respondent argues that it never waived its Eleventh Amendment immunity from suit under section 19(d) because this provision was passed into law only after the CTDEP denied Islander East‘s WQC application. Thus, Respondent argues that Connecticut did not knowingly agree that its participation in the NGA and CWA regulatory scheme would be conditioned upon accepting federal jurisdiction over its decisions made pursuant to that scheme.
Respondent‘s argument is flawed by a fatal omission: Respondent does not assert that Connecticut ever withdrew its participation from the CWA and NGA regulatory scheme following the enactment of the
As a case in point, the CTDEP Denial continues to prevent Islander East from proceeding with its FERC-approved natural gas pipeline project, and the CTDEP has chosen to defend its denial of Islander East‘s WQC application in this litigation. The principles underlying State sovereign immunity do not justify applying Connecticut‘s waiver solely on a prospective basis, that is, only for new CWA determinations, especially where the state‘s decision continues to serve as a bar to proceeding with a federally approved natural gas project. This conclusion is particularly warranted where, as in this case, after the state becomes aware that it is subject to federal jurisdiction, it continues actively to litigate in defense of its earlier decision and elects not to abdicate its deputized authority back to the federal government. See AT&T Commc‘ns v. BellSouth Telecomms., Inc., 238 F.3d at 645 (“[A]fter College Savings, Congress may still obtain a non-verbal voluntary waiver of a state‘s Eleventh Amendment immunity, if the waiver can be inferred from the state‘s conduct in accepting a gratuity after being given clear and unambiguous statutory notice that it was conditioned on waiver of immunity.“); see also In re Charter Oak Assocs., 361 F.3d 760, 767 (2d Cir.2004) (noting that the doctrine of “waiver by litigation” derives not from a state‘s “actual preference or desire, but rather upon the judicial need to avoid inconsistency, anomaly, and unfairness” (quoting Lapides v. Bd. of Regents, 535 U.S. at 620, 122 S.Ct. 1640)). Thus, we conclude that once Congress enacted section 19(d), Connecticut was on notice that its continued participation in the NGA and CWA regulatory scheme would constitute a waiver of its Eleventh Amendment immunity with respect to all suits under section 19(d).
Accordingly, in this case, Connecticut knowingly and intelligently waived its Eleventh Amendment immunity from section 19(d) suit. Because we hold that the Eleventh Amendment does not bar Petitioner‘s suit against the CTDEP, it is unnecessary for us to consider Petitioner‘s motion to add the Commissioner as a Respondent, or to address the application of the Ex parte Young doctrine to suits under section 19(d). Therefore, Petitioner‘s motion to add the Commissioner is denied as moot.
B. Tenth Amendment Immunity
The Tenth Amendment prescribes that “[t]he powers not delegated to the United States by the Constitution, nor prohibited by it to the States, are reserved to the States respectively, or to the people.”
“[W]here Congress has the authority to regulate private activity under the Commerce Clause, [the Supreme Court has] recognized Congress’ power to offer States the choice of regulating that activity according to federal standards or having state law pre-empted by federal regulation.” Id. at 167, 112 S.Ct. 2408. Congress‘s offer of shared regulatory authority does not run afoul of the Tenth Amendment. See Hodel v. Va. Surface Mining & Recl. Ass‘n, 452 U.S. 264, 290, 101 S.Ct. 2352, 69 L.Ed.2d 1 (1981) (“We fail to see why [the statute at issue] should become constitutionally suspect simply because Congress chose to allow the States a regulatory role.“).
In this case, there is no question that “the Federal Government under the Commerce Clause of the Constitution (
Respondent does not dispute that under the CWA the Federal Government elected to maintain control over the mechanism of regulating discharges into navigable waters. Rather, Respondent argues that federal court review of a WQC decision infringes upon Connecticut‘s jurisdiction over its own public trust lands, i.e., the land underlying the Long Island Sound. See Idaho v. Coeur d‘Alene Tribe of Idaho, 521 U.S. 261, 283, 117 S.Ct. 2028, 138 L.Ed.2d 438 (1997) (concluding that the court order sought “would divest the State of its sovereign control over submerged lands, lands with a unique status in the law and infused with a public trust the State itself is bound to respect“); Utah Div. of State Lands v. United States, 482 U.S. 193, 195-98, 107 S.Ct. 2318, 96 L.Ed.2d 162 (1987) (stating that lands underlying navigable waters have historically been considered “sovereign lands,” and state ownership of them is “considered an essential attribute of sovereignty“).
The Supreme Court cases cited by Respondent are inapposite, and we conclude that granting Islander East‘s petition for review would not interfere with Connecticut‘s control over its sovereign lands. The Supreme Court‘s decisions in Coeur d‘Alene and Utah Div. of State Lands involved challenges to state sovereignty over state land: in Coeur d‘Alene, a private party brought an action for declaratory and injunctive relief against the State claiming ownership of various submerged lands, 521 U.S. at 261, 117 S.Ct. 2028, while in Utah Div. of State Lands, the State brought an action for declaratory and injunctive relief contending that it was the owner of a lake bed, 482 U.S. at 200, 107 S.Ct. 2318. Here, the grant or denial of a WQC does not involve an issue of land ownership. Islander East‘s authorization to exercise the power of eminent domain to obtain a right of way for the natural gas pipeline unquestionably comes from the FERC in accordance with its authority under the NGA. Thus, in this case, federal court review involves no infringement of state jurisdiction over its lands. Such review, at most, intrudes upon the State‘s authority to determine whether the anticipated construction of Islander East‘s federally ap
C. Retroactivity of NGA Section 19(d)
Respondent argues that it cannot be sued under NGA section 19(d) because section 19(d) does not state that it is retroactive, and the CTDEP Denial was issued eighteen months before the statute‘s enactment. We disagree.
In Landgraf v. USI Film Prods., 511 U.S. 244, 273, 114 S.Ct. 1483, 128 L.Ed.2d 229 (1994), the Supreme Court held that “[e]ven absent specific legislative authorization, application of new statutes passed after the events in suit is unquestionably proper in many situations.” The Court explained that statutes applying new jurisdictional rules are typically retroactive because such statutes regulate the conduct of the courts, not the parties:
We have regularly applied intervening statutes conferring or ousting jurisdiction, whether or not jurisdiction lay when the underlying conduct occurred or when the suit was filed.... Application of a new jurisdictional rule usually takes away no substantive right but simply changes the tribunal that is to hear the case. Present law normally governs in such situations because jurisdictional statutes speak to the power of the court rather than to the rights or obligations of the parties.... Because rules of procedure regulate secondary rather than primary conduct, the fact that a new procedural rule was instituted after the conduct giving rise to the suit does not make application of the rule... retroactive.
Id. at 274-75, 114 S.Ct. 1483 (internal citations and quotation marks omitted); accord Hughes Aircraft Co. v. United States, 520 U.S. 939, 951, 117 S.Ct. 1871, 138 L.Ed.2d 135 (1997).
Respondent is correct in noting that a presumption against retroactivity applies when new provisions affect contractual or property rights. See Landgraf v. USI Film Prods., 511 U.S. at 270-71, 114 S.Ct. 1483 (“The largest category of cases in which we have applied the presumption against statutory retroactivity has involved new provisions affecting contractual or property rights, matters in which predictability and stability are of prime importance.“). But as discussed above in the context of Respondent‘s Tenth Amendment challenge, section 19(b) did not affect any of Connecticut‘s rights—property, contractual, or otherwise. The CTDEP‘s ability to issue WQCs was conferred by the federal government, which has exclusive control over navigable waterways. CTDEP therefore lacks independent rights in its WQC determinations.
Even if the CTDEP did have property or contract rights under the CWA, section 19(d) would not affect its exercise of those rights. The CTDEP is still entitled to make WQC determinations; those determinations simply are now reviewed in federal court as opposed to state court. Thus, we conclude that section 19(d) applies retroactively, and its provision of exclusive jurisdiction to this court controls this petition.
II. Merits of Petitioner‘s Section 19(d) Suit
A. Standard of Review
Proceeding to the merits, we first address the standard of review to be ap
By definition, the APA applies only to federal agency actions, see
We apply the same two-step standard to NGA review. Here, there is no question that the CTDEP complied with federal law in applying its state water quality standards to Islander East‘s permit application, as directed by the CWA. See
Pursuant to the arbitrary and capricious standard, an agency must examine the relevant data and articulate a satisfactory explanation for its action including a rational connection between the facts found and the choice made. In reviewing that explanation, we must consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment. Normally, an agency rule would be arbitrary and capricious if the agency has relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise. The reviewing court should not attempt itself to make up for such deficiencies; we may not supply a reasoned basis for the agency‘s action that the agency itself has not given. We will, however, uphold a decision of less than ideal clarity if the
B. The CTDEP Denial
In the instant case, the CTDEP denied Islander East‘s WQC application in a brief six-page letter of denial, determining that “the proposed work in the proposed location is inconsistent with the Water Quality Standards,” because the project would “adversely affect water quality and prohibit the existing and designated uses of the receiving waters.” CTDEP Denial at 1. The CTDEP cited three bases for its conclusion: (1) temporary water quality disturbance and habitat alteration would be inconsistent with the CTWQS, Surface Water Quality Standard No. 1;10 (2) degradation of water quality and disruption of existing uses would be inconsistent with the anti-degradation policy set forth in the CTWQS;11 and (3) disruption of habitat would be inconsistent with section 22a-98 of the Connecticut Coastal Management Act (CCMA). Id. at 2-5. The CTDEP explained that “[t]hese elements do not stand alone, but must be read in such a fashion as to be internally consistent within the Water Quality Standards and consistent with the goals of the [CWA].” Id. at 2. Based on a close analysis of the CTDEP‘s justifications and the record, we conclude that the CTDEP did not adequately examine the relevant record evidence, and failed to articulate rational connections between the facts in the record and the bases for its decision. To explain our conclusion, we examine each of the agency‘s three grounds for the Denial.
1. Water Quality Impacts and Habitat Alteration
a. Findings
The CTDEP determined that the “dredging, plowing, backfilling, equipment anchoring, and anchor cable sweeping” associated with pipeline installation would cause temporary water quality disturbance, permanent change to the benthic substrate, and negative impacts to the aquatic biota, which it found inconsistent with the goal of the CTWQS to “restore or maintain the chemical, physical, and biological integrity of surface waters.” CTDEP Denial at 4 & n. 11.12
According to the CTDEP Denial, installation would cause direct disturbance to the benthic substrate (sea floor), and
Additionally, the CTDEP Denial concluded that direct habitat disturbance caused by sediment deposition would “dramatically alter natural habitats and adversely impact the existing community of organisms.” Id. Specifically, the Denial noted that once the original seabed has been disturbed, the “high-order or late successional stage species such as clams and oysters that lived in the original substrate can no longer exist,” and that instead, “early-stage opportunistic species such as polychaete worms” would populate the new habitat. Id. The CTDEP concluded that it was “uncertain whether the associated diverse assemblage of bottom dwelling organisms currently present in this area could be reestablished” because “[n]o studies exist from which one may predict a known recovery time for both these benthic communities and the substrate, if, indeed, there is any significant recovery.” Id. The only record evidence to support this conclusion was a report issued by Peter E. Pellegrino entitled “Macrobenthic Community Structure Along the Proposed Islander East Pipeline Route in Long Island Sound” (Pellegrino Report), which was cited by the CTDEP without discussion of its substance.
b. Analysis
(i) Impact on Water Quality
The record shows that the pipeline installation‘s impact on water quality would be short-term, and Respondent does not suggest that such a result would be inconsistent with the CTWQS. See id. at 3 (acknowledging that “[t]urbidity of the water column would be relatively short-term“); FEIS at 5-3 (stating belief that “impacts to water quality [of the Sound near the Connecticut shore] would be short-term in nature,” because “elevated turbidity levels caused by sediment dispersion through the water column typically return to background levels within days of completion of backfilling,” and therefore impacts on Long Island Sound water quality should last “no more than several months“); John C. Roberge, “Potential Sedimentation Impacts Which Could Result from Dredging” at 3 (2003) (Roberge Report) at 4 (noting that dredging in the Long Island Sound historically causes “suspended sediment concentrations returning to pre-project levels almost immediately following cessation of the trenching operations“); TRC Envtl. Corp., “Evaluation of Benthic Impacts Associated with Islander East‘s Modified Offshore Construction Techniques,” at 6 (2003) (TRC Report) (estimating that organisms along the pipeline route would be exposed to increased turbidity at any one location for only “around 6 hours“). Thus, we do not read the CTDEP Denial to place signifi
(ii) Impact of Sediment Deposition and Direct Disturbance on Benthic Substrate and Natural Habitats
While the CTDEP acknowledged that the water quality disturbance caused by pipeline installation was not particularly problematic, it did conclude that the sediment deposition and direct benthic substrate disturbances resulting from installation would “permanently change the substrate and negatively impact the existing aquatic biota that depend on such substrate.” CTDEP Denial at 4. The CTDEP cited no scientific studies or other evidence that directly supported the latter findings, and the Denial failed to acknowledge or respond to contradictory data in the record.
An analysis of the record reveals considerable evidence indicating that direct pipeline installation and accompanying sediment deposition would not have a permanent effect on the benthic environment. For example, the FEIS noted that, although “most sessile benthic organisms and demersal fish eggs in [the disturbed] area would be smothered by [sediment],” most fish and mobile benthic organisms would relocate and avoid it. FEIS at 3-64. The FEIS concluded that “recovery of most of the disturbed benthic communities along the pipeline route could be expected to occur within 2 to 5 years.” Id. at 3-66; see also id. at 3-70, 3-71 (predicting the recovery of disturbed shellfish beds within “3 to 5 years“).
Significantly, reports prepared for both Islander East and the Town of Branford projected similar limited impacts. The TRC Report, prepared for Islander East, concluded that, “[c]onsidering only the maximum[ ] [estimates of sediment deposition], and if the predictions are correct, this degree of sediment deposition onto the sea floor should have little impact on sea floor habitats and communities, and may approach background/natural levels of sediment resuspension and deposition in the area.” TRC Report at 5 (quoting the opinion of Dr. Roman Zajac, an independent marine biologist consulting on the project); see also id. at 6 (concluding that “no mortality is expected and stress factors will be minimal” as a result of sediment deposition caused by pipeline installation with 1.5 feet depth of cover). Similarly, the Garrett Group Report, prepared for the town of Branford, concluded that the anticipated “bottom damage” caused by construction would “alter an existing productive shellfish habitat, and an existing invertebrate community structure,” but that “[a]fter all project related activities and secondary conditions associated with the construction have ceased, the bottom will recover after several years and return to the existing condition.” Garrett Group, Ltd., “Preliminary Report on the Anticipated Biological Impacts Associated with the Proposed Islander East Pipeline Project” at ES-2 (2003) (Garrett Report) (emphasis added); see also id. at 15. Additionally, the Pellegrino Report, cited in the Denial, explicitly discusses the “recovery process” after sediment deposition, noting that the process typically concludes with the reestablishment of high-order species. Id. at 6.
The Denial thus failed to mention that at least four scientific studies in the record concluded that the substrate was capable of a return to its existing condition—findings directly opposite to its conclusion that pipeline installation would “permanently change the substrate” and “dramatically alter natural habitats.” Denial at 4. Such failure alone could be deemed arbitrary and capricious. See State Farm, 463 U.S.
The CTDEP Denial cited two studies during its analysis of the project‘s impact on the benthic substrate, however, neither of these studies supported its conclusion that the benthic substrate would be “permanently changed” and the surrounding natural habitats would be “dramatically altered].” The Denial cited the Roberge Report simply as a source for its citation of the amount of sediment deposition that would result from pipeline installation.14 See Denial at 3. The Roberge Report does not make any predictions as to the impact of this activity on water quality, the benthic substrate, or the aquatic habitat. See Roberge Report at 17 (stating that going forward “[i]t is essential that the potential impacts upon pelagic, demersal and benthic fauna as well as subtidal flora imposed by the sedimentation processes be evaluated and quantified“).15 Indeed, any conclusions that Roberge later made as to mortality caused by sedimentation apparently were drawn from the Garrett Report,
which found that sedimentation would not cause permanent damage.16 See Sept. 30, 2003 Roberge Report at 4 (discussing Garrett Report‘s conclusions regarding sedimentation). The Denial also cited the Pellegrino Report to support its description of the changes that the benthic substrate would undergo as a result of disturbance caused by pipeline installation. However, rather than commenting on the damage that such disturbances cause, the Pellegrino Report describes the natural recovery process from such disturbances, concluding that such recovery is a matter of course. See Pellegrino Report at 6.17 If anything, the Pellegrino Report demonstrates that benthic communities are naturally shaped by disturbances similar to those that would be caused by the Islander East pipeline project:Pellegrino Report at 6. Indeed, the FEIS confirms this assessment, stating that “fine sediments along coastal margins are regularly resuspended by tidal currents.” FEIS at 3-49. In sum, we see no rational connection between the CTDEP‘s conclusion that the pipeline project would cause a permanent harmful change to the benthic substrate and the record evidence cited by the CTDEP. Further, the CTDEP offers no explanation for dismissing record evidence that runs counter to its findings. Neither of the studies cited by the CTDEP support its conclusion that pipeline installation and resultant sediment deposition would “permanently change” the benthic substrate and “dramatically alter” the surrounding natural habitat. Denial at 4. The dissent points to portions of the record indicating that installation would directly harm large areas of the substrate, disturb shellfish habitats, and cause significant shellfish mortality in certain locations. See post atThe structure of benthic communities is usually controlled by infrequent severe events (disturbances) that disrupt the community and return the successional process to an earlier stage. Disturbances can be physical, biotic, or chemical in nature and may have multiple direct and indirect impacts on community structure. The recovery process in soft-sediment communities is characterized by a succession of community types, usually beginning with the appearance of opportunistic species (Stage I) and progressing to the establishment of high order (Stage III) successional assemblages....
2. Antidegradation Policy
a. Findings
The CTDEP also concluded that the proposed pipeline construction would violate the anti-degradation policy set forth in the CTWQS, which requires “the maintenance and protection of water quality in high quality waters and protection and maintenance of existing uses in all cases.” CTWQS at Appx. E-1. According to the CTDEP, “where water quality is better than the criteria established in the Water Quality Standards, such existing high quality must be maintained except under exceptional and very limited circumstances.” CTDEP Denial at 4.
The CTDEP determined that the high quality waters in the Thimble Islands ecosystem would be degraded because the “discharge of backfill associated with pipeline installation would result in approximately 5.5 acres of nearshore bottom habitat being permanently degraded and rendered unsuitable for supporting the diverse assemblage of shellfish and other bottom dwelling organisms currently inhabiting this area.” Id. at 4. The CTDEP concluded that impact on shellfish harvesting would “extend well beyond the 5.5 acres of direct disturbance” because the bank-run gravel used as engineered backfill would interfere with harvesting techniques. Id.
Moreover, the CTDEP concluded that “the resulting topographic irregularities over the entire 3,700-acre Islander East corridor caused by sedimentation, backfill with gravel, plow utilization, anchor strikes, and cable sweeps” would “adversely affect the population of resident benthic organisms and shellfish as well as the efficiency and safety of the existing shellfish harvesting operations and handling of shellfish harvesting equipment.” Id. at 5. The CTDEP dismissed as unrealistic Islander East‘s projection that it would achieve a finished substrate with topographic variations of no more than +2’ to -1‘, explaining that, “based on the experience of the Department with the installation of the Iroquois pipeline in 1991, the Department does not agree that such a minimal impact restoration of the work site contours can, in practice, be achieved.” Id. The CTDEP also appeared to dismiss even Islander East‘s proposed minimal variation rate as unacceptable because traditional shellfish harvesting techniques were employed throughout the pipeline route. See id. The CTDEP did not cite any studies or record evidence to support these findings.
b. Analysis
(i) Impacts on Existing Shellfish Harvesting
As mentioned above, the CTDEP Denial asserts that “sedimentation, backfill with gravel, plow utilization, anchor strikes, and cable sweeps” would impact the “entire 3,700 acre [pipeline] corridor,” adversely affecting “benthic organisms and shellfish as well as the efficiency and safety of the existing shellfish harvesting operations.” CTDEP Denial at 5. The Denial, however, fails to support its contention that 3,700
The CTDEP Denial points to no evidence supporting its claim that an area of 3,700 acres would be impacted. This apparent assumption is belied by evidence on the record, which the CTDEP did not address. The FEIS refers to a total impacted area of only 3,140 acres across the entire project, including New York and Connecticut waters. FEIS at 3-45 (finding total disturbance to be 3,140 acres, including subsea plowing with buoys, HDD exit hole and “dredge trench and associated spoil mounds“). The FEIS calculation of 3,140 acres is itself likely exaggerated, because it is based on Islander East‘s proposal before Islander East agreed to ship approximately 24,000 cubic yards of dredged material away on barges.18 See Islander East Pipeline Co., Offshore Dredge Disposal Permit Amendment at 1 (July 29, 2003); see also TRC Report at 4 (discussing changes in proposed construction methodologies that would reduce impact area of HDD exit hole and narrow the dredging trench). To explain clearly how the pipeline would degrade a particular area, the CTDEP must first define the area in question. The CTDEP Denial fails to address this “important aspect of the problem.” State Farm, 463 U.S. at 43.
Similarly, the Denial cites a threat to commercial interests that collect shellfish using “traditional harvest shellfishing techniques” in the affected area. CTDEP Denial at 5. CTDEP asserts in general terms that the pipeline is sited “within and adjacent to extensive shellfish grants, leased shellfish grounds and public shellfishing lands,” id. at 2, yet fails to point to even one specific lease that would be impacted. Furthermore, the Denial‘s repeated reference to “dredging, plowing, backfilling, equipment anchoring, and anchor cable sweeping,” see id. at 3-4, obscures the fact that these activities would occur in discrete areas, and that particular shellfish beds, to the extent they actually do reside near the construction zone, would be subject to different potential injuries of different magnitudes.19 Although it may be argued that the FEIS contains a description of shellfish beds and leases that lie in the pipeline‘s path, see FEIS at 3-69, we may not supply a rationale for agency action where the agency has provided none, nor may we construct support for an agency‘s conclusion when the agency has not pointed to evidence on the record favoring its decision. See State Farm, 463 U.S. at 50 (“The reviewing court should not attempt itself
(ii) Impact of Backfill
As discussed above, the CTDEP failed to cite any record evidence supporting its conclusion that pipeline installation would permanently degrade the benthic substrate along the pipeline route. It similarly failed to point to any record evidence supporting its conclusion that the use of engineered bank-run gravel as trench backfill would permanently degrade the nearshore bottom, rendering it unsuitable for shellfish and other bottom-dwelling organisms.
To the contrary, the record reflects that Islander East‘s use of engineered backfill was proposed to serve a beneficial purpose and, indeed, would have benefited shellfish habitats. Midway through Islander East‘s planning process, a representative from the National Marine Fisheries Service expressed concern that non-engineered (all-rock) trench backfill would cause damage to commercial shellfish operations. See Elizabeth Dolezal, Islander East Pipeline Co., LLC, Project Meeting Minutes: Multi Agency Construction Consultation, at 1-2 (Feb. 3, 2003) (Feb. Minutes). At a subsequent meeting, a representative from the Connecticut Bureau of Aquaculture suggested that Islander East use engineered backfill, which would be more “conducive to shellfish.” Elizabeth Dolezal, Islander East Pipeline Co., LLC, Project Meeting Minutes: Multi Agency Construction Consultation, at 4 (March 4, 2003) (March Minutes) (“A general discussion about the 1991 Iroquois installation resulted in agreement that installation methods have greatly improved and that [engineered] backfilling process and equipment being considered on Islander East have the potential to result in the restoration of shellfish habitat.“).
Indeed, several studies in the record, commissioned by both proponents and opponents of the pipeline, support the conclusion that the use of engineered backfill could produce future habitats even more diverse than those currently existing. See TRC Report at 6 (“Engineered backfill has value as hard substrate for attachment of organisms and plants, which could promote habitat diversity.... This [new] substrate mosaic [created by the backfill] has the potential to increase habitat diversity, supporting greater species richness than a single substrate type.“); see also id. at 7 (“[T]he use of engineered backfill may increase biological diversity, and has the potential to improve conditions for two valuable commercial species, oyster and lobster.“); Garrett Report at 15 (“The use of engineered fill will create a varied benthic habitat, shelter/relief, and should enhance nearshore bottom conditions.“).20
The CTDEP‘s failure to acknowledge this record evidence directly contradicting its conclusion is arbitrary and capricious. See State Farm, 463 U.S. at 43 (holding that an agency‘s failure to “consider an important aspect of the problem,” or to “offer[] an explanation for its decision that runs counter to the evidence before the agency” is arbitrary and capricious). One document in the record supports the CTDEP‘s conclusion that shellfish harvesting will be negatively af-
Id. at 48 (internal quotation marks omitted).There are no findings and no analysis here to justify the choice made, no indication of the basis on which the [agency] exercised its expert discretion.... Expert discretion is the lifeblood of the administrative process, but unless we make the requirements for administrative action strict and demanding, expertise, the strength of modern government, can become a monster which rules with no practical limits on its discretion.
(iii) Impact of Topographic Irregularities
The CTDEP justified its finding that Islander East would be able to achieve its benthic topography restoration goal solely by referencing its “experience” with the 1991 installation of the Iroquois Pipeline. Denial at 5. Again, the agency cited no data or studies to support this conclusion.
First, the Denial points to no record evidence demonstrating that the Iroquois project permanently degraded the benthic substrate of Long Island Sound waters. Even if the record contained evidence indicating that those waters have yet to recover, we again emphasize that it is not our province to mine the record for data supporting the agency‘s blanket conclusions.
Second, and more important, the CTDEP failed to acknowledge the extensive work Islander East did to modernize and improve its technology so as to avoid causing similar environmental harm to that wrought by the Iroquois Pipeline. Islander East proposed to: (1) use HDD technology to drill under the seabed so as not to disturb the sea floor, as opposed to Iroquois, which dredged the seafloor from the shore to the 15-foot water mark; (2) place dredge spoil on barges, and backfill trenches with engineered bank-run gravel designed to increase habitat diversity, whereas Iroquois sidecast dredged material back onto the sea floor and backfilled the trenches with some of the sidecast spoil; and (3) restore the sea bottom contours without dragging a 40-ton steel box over the sea floor, as Iroquois had done at the request of CTDEP, apparently with unfortunate results. See generally Islander East WQC Application. Additionally, as indicated by the record, it was acknowledged at two multi-agency meetings that “installation technology [has] significantly improved since the Iroquois line installation.” Feb. Minutes at 1; see also March Minutes at 4 (“A general discussion about the 1991 Iroquois installation resulted in agreement that installation methods have greatly improved ....“).
The CTDEP‘s conclusion that the proposed pipeline would violate its antidegradation policy was unsupported and contradicted by evidence in the record, and therefore must be rejected as arbitrary and capricious.
3. Connecticut Coastal Management Act
As the third basis for its WQC Denial, the CTDEP concluded that the proposed pipeline violates the Connecticut Coastal Management Act (CCMA),
4. Miscellaneous Factors Supporting the Arbitrary and Capricious Determination
Two additional factors contribute to our conclusion that the Denial is arbitrary and capricious. First, the Denial‘s brevity is troubling. After a two-and-a-half page introduction, the Denial contains a mere two-and-a-half pages of analysis, supported by five record citations, none of which, for reasons already discussed, reasonably support the broad conclusions reached. As points of comparison, the two other governmental entities that have considered the Islander East project to date, FERC and the Secretary of Commerce, each issued voluminous reports on the po-
Additionally, there is some evidence in the record suggesting that CTDEP knew it was not adequately prepared to support the Denial, and that its issuance had become more a matter of “strategy” in opposing the pipeline than of fact-finding. See CTDEP email from Sue Jacobson to Peter Francis and Ron Rozsa (May 15, 2003) (“[W]e met with folks from the AG‘s office this morning and they were aghast that we have not yet begun collecting the data.“); CTDEP email from Jane Stahl to Peter Francis (May 28, 2003) (“No surprises in Islander East response and I don‘t think any change in our strategy.“); CTDEP email from Sue Jacobson to Jonathan Goldman (Oct. 2, 2003) (“[O]ur biggest hook will be the [pipeline‘s] potential to lower surface water quality ....“); CTDEP email from Peter Francis to Betsey Wingfield (Jan. 21, 2004) (“Sue and I did some work on the 401 letter this week but it still feels incomplete and a bit artificial/manufactured.“).
Any effort by the CTDEP to pursue a “strategy” to justify a foreordained opposition to the pipeline would be incompatible with a reviewing agency‘s mandate to use its expertise to come to a reasoned decision supported by substantial evidence. In fulfilling its statutory prerogative to review Islander East‘s WQC application, CTDEP was entrusted with identifying the conditions for construction that would adequately safeguard the environment. To the extent some evidence indicates a greater concern with mounting a public relations campaign to preclude building the pipeline than with neutrally evaluating the record evidence, that evidence further supports the conclusion that the Denial was arbitrary and capricious.
CONCLUSION
For the foregoing reasons, we conclude that the CTDEP‘s Denial of Islander East‘s application for a WQC was arbitrary and capricious. We draw no conclusion as to whether the record evidence obligates the CTDEP to grant Islander East‘s application; we require only that the CTDEP conduct the sort of complete and reasoned review required by law. Accordingly, we REMAND to the CTDEP to conduct the type of review contemplated by federal law, within seventy-five days of issuance of this opinion, or if the CTDEP is unwilling or unable to do so, to abdicate its authority to issue a WQC in this case.
With all due respect, I dissent from the majority‘s view that the February 5, 2004 decision (“Decision“) of respondent State of Connecticut Department of Environmental Protection (“CTDEP“), denying the application of petitioner Islander East Pipeline Company (“Islander East“) for a Water Quality Certificate (“WQC“) under the Clean Water Act,
A. Jurisdiction
Preliminarily, I note my assumption that, under § 19 of the Natural Gas Act,
I do not endorse the majority‘s view that, in light of EPACT‘s conferral of jurisdiction on the federal courts of appeals to review orders such as denials of CWA certificates, Connecticut has waived its sovereign immunity with respect to its denial of Islander East‘s application for such a certificate. A state may of course waive its sovereign immunity; but for a waiver to be inferred from the state‘s conduct, that conduct must have been “knowing[], cognizant of the [waiver] consequences.” Pennhurst State Sch. & Hosp. v. Halderman, 451 U.S. 1, 17 (1981). CTDEP denied Islander East‘s application in February 2004; EPACT was not enacted until August 2005. I cannot view CTDEP‘s action in denying Islander East‘s petition as a knowing waiver of sovereign immunity on the basis of a law that did not become effective until 18 months later.
The majority finds that Connecticut has waived its sovereign immunity in the present matter by failing to discontinue its participation in Clean Water Act regulation of natural gas pipeline projects after EPACT was enacted. I do not agree. The fact that Connecticut, with awareness of the effect of EPACT since mid-2005, elects to continue to decide applications for CWA certificates may perhaps constitute a waiver with respect to its post-EPACT decisions; but its present actions do not establish knowledge or voluntariness with respect to its past actions.
Nonetheless, the fact that CTDEP, a state agency, is immune from suit does not mean that relief under EPACT, if merited, would be unavailable. If Islander East‘s motion to add the CTDEP Commissioner were granted, as discussed above there would be no sovereign-immunity bar to entertaining its petition, which seeks prospective relief; and “[w]hen the intervening statute authorizes or affects the propriety of prospective relief, application of the new provision is not retroactive,” Landgraf, 511 U.S. at 273.
Accordingly, I turn to the merits of Islander East‘s petition and the standard under which the petition is to be reviewed.
B. The Merits
1. Standard of Review
Although EPACT provides little guidance as to the contours of what it refers to as a “civil action for the review of an order,”
The APA provides, in pertinent part, that a court reviewing an agency decision is to set aside a decision that is “found to be ... arbitrary[ or] capricious,” and that in making such a determination, “the court shall review the whole record or those parts of it cited by a party.”
Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168 (1962). In reviewing that explanation, we must “consider whether the decisionThe scope of review under the “arbitrary and capricious” standard is narrow and a court is not to substitute its judgment for that of the agency. Nevertheless, the agency must examine the relevant data and articulate a satisfactory explanation for its action including a “rational connection between the facts found and the choice made.”
Motor Vehicle Manufacturers Ass‘n of the United States, Inc. v. State Farm Mutual Automobile Insurance Co., 463 U.S. 29, 43 (1983) (”State Farm“) (emphases added); see also id. at 42 (“[U]nder this standard, a reviewing court may not set aside an agency rule that is rational, based on consideration of the relevant factors[,] and within the scope of the authority delegated to the agency by the statute.“).
“A court reviewing an agency‘s adjudicative action should accept the agency‘s factual findings if those findings are supported by substantial evidence in the record as a whole.” Arkansas v. Oklahoma, 503 U.S. 91, 113 (1992) (emphasis omitted); see also State Farm, 463 U.S. at 44 (agency‘s factual findings are to be upheld if “supported by substantial evidence on the record considered as a whole” (emphasis added) (internal quotation marks omitted)). Since an agency‘s findings are to be upheld if they are supported “by substantial evidence on the record as a whole,” State Farm, 463 U.S. at 44 (emphasis added), the statement in State Farm that an order may be found arbitrary and capricious if it “runs counter to the evidence before the agency,” id. at 43 (emphasis added), means that it may be so found if it runs counter to all of the substantial evidence. Thus, the Court has stated that this facet of the arbitrary-and-capricious determination is in essence a “deci[sion as to] whether on th[e] record it would have been possible for a reasonable jury to reach the [agency‘s] conclusion,” Allentown Mack Sales & Service, Inc. v. NLRB, 522 U.S. 359, 366-67 (1998) (emphasis added). Where there is evidence in the record from which a reasonable jury could have reached the agency‘s decision, the “court is not to substitute its judgment for that of the agency,” State Farm, 463 U.S. at 43.
The majority takes the position that “[i]t is not our province to mine the record for evidence that would support [an agency decision].” Majority Opinion ante at 100. That characterization of the scope of review confuses the reasons for a decision with the evidence to support that decision. We are not to supply the rationale for an agency decision; but where the agency has stated its rationale, or where its rationale “may reasonably be discerned,” State Farm, 463 U.S. at 43, we
Given these principles, I cannot conclude that CTDEP‘s denial of Islander East‘s application should be disturbed.
2. The Contents of the CTDEP Decision
Preliminarily, I note that the CTDEP Decision is not so sketchy as the majority suggests. Although the text of the Decision is six pages, the Decision annexes and refers to appendices covering some 300 pages. The appendices to the Decision include a United States Environmental Protection Agency-funded survey of water quality in Long Island Sound (see Decision Appendix B); a report on “Potential Sedimentation Impacts Which Could Result from Dredging,” authored by Roberge Associates Coastal Engineers, LLC, comprising a series of analyses, dated May 5, 2003, September 30, 2003, and February 4, 2004 (collectively the “Roberge Reports“), of the likely effects of the Islander East pipeline as initially proposed and as subsequently amended (see Decision Appendix E); a report by coastal resource analyst Peter H. Pellegrino entitled “Macrobenthic Community Structure along the Proposed Islander East Gas Pipeline Route in Long Island Sound” (“Pellegrino Report“) (see Decision Appendix F); and a 12-page July 29, 2003 letter from CTDEP to Islander East explaining CTDEP‘s objections to Islander East‘s initial proposal and requesting additional specified information (see Decision Appendix G). Materials that an agency cites and attaches to its decision must be taken into account in determining whether the decision is arbitrary and capricious. See
Given the text of the CTDEP Decision, which I attach as an appendix to this dissent, and the contents of the Appendices that were appended to the Decision, I think it clear that CTDEP denied Islander East‘s application on the basis that the proposed pipeline, which is not a water-dependent use, would be routed through prime shellfish habitat, would have a lengthy, significant, adverse impact of unknown duration on the shellfish industry, and would displace the obviously water-dependent activity of shellfishing. (See Decision at 2-6.)
The majority appears to suggest that the shellfish-injury rationale is a creation of this dissent rather than a rationale given by CTDEP, as the majority opinion (a) states that “[t]he dissent points to portions of the record indicating that installation would directly harm large areas of the substrate, disturb shellfish habitats, and cause significant shellfish mortality in certain locations,” and (b) continues by stating, “[h]owever, ‘we may not supply a reasoned basis for the agency‘s action that the agency itself has not given,‘” Majority Opinion ante at 99-100 (quoting State Farm, 463 U.S. at 43). In suggesting that injury to shellfish and the shellfish industry was not a basis relied on by CTDEP (and in stating as well that CTDEP “fail[ed] to identify with any specificity the shellfish communities that would be impacted by the pipeline,” Majority Opinion ante at 101), the majority ignores even the text of the Decision. With respect to the issue of shellfish habitat alteration, the Decision stated in part as follows:
(Decision at 2-4 (footnotes omitted) (emphases added).) Thus, it is clear that CTDEP denied Islander East‘s application based principally on the finding, in short, that if its project were carried out, where now there is an abundance of oysters and clams, there could well be only worms.Islander East has proposed a regulated activity in coastal waters of the State in the nearshore waters of the Thimble Islands complex in the Town of Bran-
ford. Overall, chemical and bacteriological water quality conditions in this location are consistently excellent.... In concert with excellent water quality, the Thimble Islands region also exhibits an abundance of high quality habitat. These physical conditions combine to support a diverse and abundant assemblage of marine life.... The United States Fish and Wildlife Service, for example, has designated this particular area a “significant habitat complex in need of protection.” In addition to providing habitat for a variety of demersal and pelagic species, these diverse bottom habitats of the Thimble Islands region also support eastern oyster (Crassostrea virginica), hard clams (Mercenaria mercenaria), soft clams (Mya arenaria), blue mussels (Mytilus edulis), and channel whelk (Busycon canaliculatum).
These species, clams and oysters in particular, support significant commercial shellfish harvesting operations. The pipeline corridor, as proposed by Islander East, is sited within and adjacent to extensive shellfish grants, leased shellfish grounds and public shellfishing lands. The submerged land through which the pipeline route is proposed that is not currently leased is also productive shellfish habitat and is significant for potential future expansion of the shellfish industry, particularly in as much as the western reaches of Long Island Sound have been more affected in recent decades by lower dissolved oxygen levels and other environmental impacts that affect shellfish and benthic abundance. The shellfish industry is an economically-significant and long-established water-dependent use in Connecticut. In fact, Connecticut‘s nationally-recognized shellfish industry produces the highest quality oysters in the United States....
The shellfishing industry in the Thimble Islands region thrives because of the excellent water quality and exceptional habitat conditions....
[T]he water is of sufficiently high quality to allow for direct consumption of shellfish from these beds without the requirement for relocation and depuration of the shellfish prior to human consumption.... [T]he waters off Branford support approximately 46% of shellfishing areas approved for direct harvest in eastern Connecticut....
.... Th[e] proposed installation would include dredging, plowing, backfilling, equipment anchoring, and anchor cable sweeping. These activities would result in negative impacts to both the water quality and substrate. Turbidity of the water column would be relatively short-term. When this material precipitates out of the water column, it will result in sediment deposition on the benthic substrate. At the request of the Town of Branford‘s Blue Ribbon Committee, John Roberge, P.E., LLC, prepared an assessment of sedimentation impacts associated with pipeline installation as modified by Islander East to mitigate sediment dispersion. The following sediment deposition pattern was estimated in Mr. Roberge‘s study:
1 mm up to 100 meters from the trench centerline (approximately 70 acres); and
3 mm up to 40 meters from the trench centerline (approximately 35 acres).
The Department has determined that the negative impacts resulting from this depositional layer, in addition to direct substrate disturbance associated with dredging, plowing, backfilling, equipment anchoring, and anchor cable sweeping, are inconsistent with the
Water Quality Standards. Pipeline installation would not only temporarily disturb water quality, it would permanently change the substrate and negatively impact the existing aquatic biota that depend on such substrate. The Connecticut Water Quality Standards define biological integrity as the ability of any aquatic ecosystem to support and maintain a balanced, integrated, adaptive community of organisms having a species composition, diversity, and functional organization comparable to that of the natural habitats of a region. The combined assaults of direct habitat disturbance and temporary water quality impacts resulting in sediment deposition negatively impact the overall biological integrity of the Thimbles [sic] Islands ecosystem and are therefore inconsistent with Standard No. 1 of the Connecticut Water Quality Standards. Pipeline installation through the Thimble Islands ecosystem will dramatically alter natural habitats and adversely impact the existing community of organisms. As discussed in a study entitled “Macrobenthic Community Structure Along The Proposed Islander East Pipeline Route In Long Island Sound,” by Pellegrino, there are dramatic differences in community structure associated with a disturbed versus a non-disturbed substrate. Once the original bottom has been disturbed, a soft sediment, referred to as the nephloide layer, covers the bottom and fills in any depressions left on the disturbed surface. Thus, the high-order or late successional stage species such as clams and oysters that lived in the original substrate can no longer exist. The community structure of the original substrate changes to that of early-stage opportunistic species such as polychaete worms. It is uncertain whether the associated diverse assemblage of bottom dwelling organisms currently present in this area could be reestablished. No studies exist from which one may predict a known recovery time for both these benthic communities and the substrate, if, indeed, there is any significant recovery.
CTDEP also noted that the Connecticut antidegradation policy requires the maintenance and protection of water quality in high-quality-water areas and “mandates that existing uses must continue to be supported in all cases.” (Decision at 4.) The Decision stated that the above findings showed that the Islander East pipeline would not be consistent with this policy:
(Id. at 6 (emphases added).)As previously described, the pipeline is proposed to be sited within and adjacent to extensive shellfish grants, leased shellfish grounds and public shellfishing lands. The discharge of backfill associated with pipeline installation would result in approximately 5.5 acres of nearshore bottom habitat being permanently degraded and rendered unsuitable for supporting the diverse assemblage of shellfish and other bottom dwelling organisms currently inhabiting this area. (Id.) The Decision concluded that CTDEP had determined that the regulated activity in the proposed location will permanently alter the existing high quality physical and biological integrity and productivity of this area to the extent that the existing uses for habitat for marine fish, other aquatic life and wildlife and shellfish
harvesting for direct human consumption will be impaired. Essential shellfish habitat will be lost due to the temporary and permanent alteration of the benthic environment resulting from the proposed work. Finally, the siting of the non-water dependent pipeline through prime shellfish habitat would cause a significant and permanent adverse impact to a water-dependent use by displacing the water-dependent use of shellfishing with the non-water-dependent use of natural gas transmission.
The majority states that CTDEP failed to cite any studies or record evidence to support its findings. See, e.g., Majority Opinion ante at 97 (“The CTDEP cited no scientific studies or other evidence that directly supported the ... findings” that the “sediment deposition and direct benthic substrate disturbances resulting from installation would ‘permanently change the substrate and negatively impact the existing aquatic biota that depend on such substrate.‘” (quoting Decision at 4)). The majority also states that CTDEP
Majority Opinion ante at 97 (quoting Decision at 4). By these “opposite” opinions, the majority apparently refers to (1) an opinion by consulting marine biologist Dr. Roman Zajac (“Zajac opinion“); (2) a report by TRC Environmental Corp. entitled “Evaluation of Benthic Impacts Associated with Islander East‘s Modified Offshore Construction Techniques” (“TRC Report“), which quotes and relies on the Zajac opinion; (3) a report by the Garrett Group, Ltd., entitled “Preliminary Report on the Anticipated Biological Impacts Associated with the Proposed Islander East Pipeline Project, Through the Nearshore Area of Long Island Sound—Branford, Connecticut” (“Garrett Group Report“); and (4) the Pellegrino Report. See Majority Opinion ante at 97-98.failed to mention that at least four scientific studies in the record concluded that the substrate was capable of a return to its existing condition—findings directly opposite to its conclusion that pipeline installation would “permanently change the substrate” and “dramatically alter natural habitats.”
But both the contention that CTDEP cited nothing to support its findings and the contention that CTDEP failed to consider the “opposite” opinions are contradicted by the record. First, CTDEP pointed out that coastal engineering consultant John Roberge had “prepared an assessment of sedimentation impacts associated with pipeline installation as modified by Islander East to mitigate sediment dispersion” (Decision at 3), and it attached his series of reports to the Decision as Appendix E (see id. n. 10). The Roberge Reports predicted that “benthic species will likely be killed even in areas receiving a thin veneer of deposited sediments” (Roberge Report dated February 4, 2004, at 2; Roberge Report dated September 30, 2003, at 3) and that “[t]his seafloor burial has the potential to result in significant mortality within the benthic communities” (Roberge Report dated February 4, 2004, at 3; Roberge Report dated September 30, 2003, at 4). In making this prediction, the Roberge Reports stated, inter alia, that the Islander East pipeline would cover 69.8 acres with up to 1 mm of sediment and cover 34.9 acres with up to 3 mm of sediment, and noted that a study by the United States Army Corps of Engineers had found “that sediment deposits of up to 1 mm will cause up to 50% mortality, and deposits of up to 2 mm will cause 100% mortality to some benthic species.” (Roberge Report dated February 4, 2004, at 3 (emphasis added); Roberge Report dated September 30, 2003, at 4 (emphasis add-
Second, the Roberge Reports expressly mentioned two of the studies on which the majority relies for the opposite conclusion:
(Decision Appendix E, Roberge Report dated February 4, 2004, at 2 (emphases added); Roberge Report dated September 30, 2003, at 4 (emphases added).) Although the majority opinion states that “any conclusions that Roberge ... made as to mortality caused by sedimentation apparently were drawn from the Garrett Report, which found that sedimentation would not cause permanent damage,” Majority Opinion ante at 98-99 (emphasis added), it is plain from the above language of the Roberge Reports themselves that the Roberge Reports explicitly rejected the views of the Garrett Group and Dr. Zajac in light of the contrary findings of the Army Corps of Engineers—in studies to which the Garrett Group Report itself had adverted. Further, given the reliance of the TRC Report on the opinion of Dr. Zajac, see Majority Opinion ante at 97 (quoting TRC Report‘s quotation of the Zajac opinion), the Roberge Reports can properly be regarded as implicitly rejecting the views of the TRC Report as well. Although the majority suggests that CTDEP should have granted Islander East‘s application based on the reports such as that of the Garrett Group, it is the very antithesis of “deferential” review to conclude that an agency was required to credit a report that cites evidence contradicting the report‘s own conclusions.As reported in the “Preliminary Report on the Anticipated Biological Impacts Associated with the Proposed Islander East Pipeline Project, through the Nearshore Area of Long Island Sound—Branford, CT“, prepared by The Garrett Group, LTD and dated May 8, 2003, near and far-field deposition of suspended solids may cause a measurable cover, or a thin veneer of fine particles cover over proximal hard bottom substrate. The Garrett report references benthic studies performed by the US Army Corps of Engineers (LaSalle et all [sic] 1991) which note[], contrary to Dr. Zajac‘s opinion, that sediment deposits of up to 1 mm will cause up to 50% mortality, and deposits of up to 2 mm will cause 100% mortality to some benthic species.
The fourth report advanced by the majority as one of the “opposite” opinions supposedly ignored by CTDEP is the Pellegrino Report. The majority‘s suggestion that this report was ignored by CTDEP is peculiar, given that the report is annexed to the Decision as Appendix F. Further, the majority‘s reliance on the Pellegrino Report as a basis for the conclusion that the CTDEP Decision is arbitrary and capricious is puzzling. The conclusion of this report stated that “[t]he structure of benthic communities is usually controlled by infrequent severe events (disturbances) that disrupt the community and return the successional process to an earlier stage,” and that the “recovery process in soft-sediment communities is characterized by a succession of community types, usually beginning with the appearance of opportunistic species,” i.e., polychaete worms, and eventually “progressing to the establishment of high order ... successional assemblages,” such as bivalves and gastropods (Pellegrino Report at 6 (emphasis added)); but the Pellegrino Report contained no discussion whatsoever of the impact on such communities by a pipeline construction process—a process that surely is not the “usual[]” type of “disturbance[].” Indeed, the stated purpose of the Pellegrino Report was simply to describe the results of a benthic survey along
In sum, I cannot agree with the majority‘s view that the CTDEP “fail[ed] to acknowledge the existence of the above studies,” Majority Opinion ante at 98 n. 13. I think it appropriate, in conducting a review that is to be deferential, to infer that CTDEP must have acknowledged the study it attached to its Decision and, in relying on the Roberge Reports, implicitly acknowledged the existence of studies that were explicitly mentioned and disputed in the Roberge Reports.
I note that the majority also relies on many statements in the Final Environmental Impact Statement (“FEIS“) on Islander East‘s proposed pipeline, issued by the United States Federal Energy Regulatory Commission (“FERC“), see, e.g., Majority Opinion ante at 96-97, 99. The FEIS, however, also included many findings not mentioned by the majority that are consistent with CTDEP‘s conclusion that the Islander East pipeline would adversely impact benthic communities. For example, the FEIS indicates that construction of the trench and installation of the pipeline would directly impact 3,140 acres of Sound bottom, including 298 acres disturbed by trenching, 23.8 acres by the creation of an “exit hole” needed for horizontal directional drilling, 2,807 acres disturbed by cable sweep, and 9.7 acres by anchor strikes. (See FEIS at 3-45.) Islander East expected to make more than 2,000 anchor strikes, each causing a 1376-cubic-foot hole in the Sound floor (see id. at 3-65); “lobsters ... in the direct area of anchor placement would suffer mortality” (id. at 3-72), and “[t]he persistence of these depressions would represent a long-term conversion of benthic habitat” (id. at 3-65 (emphasis added)); “[d]ue to the weight of the anchor and the depth of the [anchor] scar, the impact on shellfish likely would be complete mortality within the footprint of the scar” (id. at 3-71 (emphasis added)). The record shows that CTDEP had considered the FEIS. (See Decision Appendix G at 9 (“Staff have reviewed FERC‘s Final Environmental Impact Statement (FEIS) FERC/EIS-0143F dated August 2002.“)).
The majority repeatedly faults the CTDEP Decision for “not point[ing] to evidence” in support of its rationale that the shellfish industry would be negatively impacted, Majority Opinion ante at 101 (emphasis added); see also id. (Decision “fails to point to even one specific lease that would be impacted“), and states that “[t]he reviewing court should not attempt itself to make up for such deficiencies,” id. at 101-02 (quoting State Farm, 463 U.S. at 43). However, as can be seen from the more complete State Farm passage quoted above in Part B.1. of this dissent, the Supreme Court‘s reference to “such” deficiencies did not include a failure to “point to evidence,” Majority Opinion ante at 104; rather, that passage referred to an agency‘s reliance on factors unintended by Congress, or an “entire[]” failure “to consider an important aspect of the problem,” or proffering of explanations “so implausible that [they] could not be ascribed to a difference in view or the product of agency expertise,” State Farm, 463 U.S. at 43.
Further, I disagree with the majority‘s view that the record evidence indicates with certainty “that direct pipeline installation and accompanying sediment deposition would not have a permanent effect on the benthic environment,” Majority Opinion ante at 97 (emphasis added). The majority cites the FEIS and the four “opposite” opinions that it contends CTDEP
It was hardly irrational, therefore, for CTDEP to conclude from these hedged opinions that “[n]o studies exist from which one may predict a known recovery time.” (Decision at 4 (emphasis added).) Not one of the reports relied on by the majority was unequivocal; and CTDEP‘s own experience with the Iroquois Pipeline project—completed more than a dozen years earlier—supported CTDEP‘s view that the adverse impacts of such a project were likely permanent. CTDEP stated that habitat lost in the Iroquois Pipeline installation in 1991 “has not recovered to date.” (Decision Appendix G at 6 (emphasis added).)
Although the majority states that the Iroquois Pipeline installation is not comparable because Islander East proposes to use horizontal directional drilling (“HDD“), rather than dredging, in order to mitigate topography problems, the record does not indicate that Islander East carried its burden of showing that that proposal would have a substantial mitigating effect. The total length of the proposed pipeline was to be 44.8 miles, of which 22.7 miles would be under the waters of Long Island Sound. While the majority opinion might give the impression that nearly half of the pipeline to be laid underwater would be installed by means of HDD, see Majority Opinion ante at 87 (describing the proposed HDD as “initiat[ing] the pipeline installation at a point onshore in Connecticut, approximately 700 feet inland from the shoreline [and] continu[ing] until mile post (MP) 10.9“), in fact mile post 10.9 is only 3,500 feet offshore. The mile posts begin in North Haven, Connecticut, 10.1 miles from the point in Branford at which the pipeline was to enter the Sound. (See FEIS at 2-12.) Thus, Islander East planned to use HDD under water only for the nearshore 3,500 feet of the pipeline (see Decision at 3), i.e., less than two-thirds of one mile, and not for the remaining 22+ miles of underwater installation. For the 97% of the underwater section of the pipeline in the Thimble Islands region and beyond, Islander East proposed to dredge and plow, as was done for the Iroquois Pipeline. And the needed HDD exit hole—a 23.8-acre underwater pit that would be the dirtiest part of the pipeline installation, as it must be created by mechanical dredging and is the area into which the muds and lubricants used in the HDD process would
Finally, the majority states that CTDEP “fails to support” its “claim that an area of 3,700 acres would be impacted” by the Islander East pipeline, Majority Opinion ante at 100-01, and states that “[t]he FEIS refers to a total impacted area of only 3,140 acres,” Majority Opinion ante at 101. It does not appear to me that the CTDEP Decision was intended to mean that all 3,700 acres would be uniformly impacted. The Decision states that “topographic irregularities” would occur “over the entire 3,700-acre Islander East corridor,” Decision at 5 (emphasis added), and it is plain that the pipeline construction process would not result in uniform conditions on the floor of the Sound. The FEIS, for example, discussed the fact that Islander East proposed to make 2,628 anchor strikes (see FEIS at 3-65); each of them would cause a 1376-cubic-foot hole in the Sound floor (see id. at 3-45, 3-65), holes that would “persist[]” and cause “a long-term conversion of benthic habitat” (id. at 3-65). In any event, even if “only 3,140,” Majority Opinion ante at 101 (emphasis added), out of 3,700 acres would be impacted as the FEIS found, I would be hard-pressed to find that an absence of anticipated impact on 560 acres out of 3,700 (i.e., 15% of the project) made the denial of the requested permit arbitrary and capricious.
To summarize, the CTDEP Decision explained that the Islander East application was being denied because construction of the pipeline planned by Islander East—to be routed through the waters of the Thimble Islands, a thriving shellfishing area that the United States Fish and Wildlife Service has designated as a significant habitat complex in need of protection—would likely permanently change the benthic substrate, depositing layers of sediment in which clams and oysters, which lived in the original substrate, could no longer survive; that this would have adverse effects on shellfish and the shellfish industry, given that although early-stage opportunistic species such as polychaete worms could be expected to return to the areas disturbed by pipeline construction, it is uncertain when the higher-order organisms currently present in these areas would return, if ever. CTDEP‘s denial and rationale are supported by evidence in the record as a whole, and other opinions were addressed in reports cited by CTDEP and attached to its Decision. Accordingly, I dissent from the majority‘s conclusion that CTDEP‘s Decision is arbitrary and capricious.
APPENDIX A
CTDEP DECISION of February 5, 2004, DENYING WATER QUALITY CERTIFICATE [omitting only a paragraph that addressed the Connecticut Coastal Management Act, on which CTDEP places no reliance]
On March 14, 2003, the Islander East Pipeline Company, LLC (“Islander East“) submitted a Water Quality Certificate (WQC) application for discharges to the waters of the State pursuant to
Determination
The proposed work was evaluated for compliance with the applicable provisions
Connecticut Water Quality Standards
As required by the Act, Connecticut‘s Water Quality Standards include:
- beneficial designated uses for each waterbody (e.g., aquatic life, swimming, drinking, navigation, etc.) that are assigned on the basis of the waterbody‘s classification;
- narrative and/or numeric water quality criteria that must be met to support each designated use; and
- policy statements including an anti-degradation policy and implementation procedures designed to maintain and protect water quality in high quality waters, and protect and maintain existing uses in all cases.22
Coastal Water Classification and Designated Uses
Islander East has proposed a regulated activity in coastal waters of the State in the nearshore waters of the Thimble Islands complex in the Town of Branford. Overall, chemical and bacteriological water quality conditions in this location are consistently excellent. Long-term water quality monitoring initiated in 1991 by the Department as part of the Long Island Sound Study23 shows that only rarely are these waters subjected to the impacts of low dissolved oxygen conditions that gen-
In concert with excellent water quality, the Thimble Islands region also exhibits an abundance of high quality habitat. These physical conditions combine to support a diverse and abundant assemblage of marine life. The Thimble Islands typically emerge from relatively shallow waters, approximately 30’ deep. In addition to this significant area of shallow water-land interface where biological diversity is rich and productive, this area hosts unique subtidal conditions including submerged rock reefs and a diversity of benthic habitats that range from soft mud to compacted sand and gravel all of which contribute to the biological integrity of the aquatic ecosystem. The United States Fish and Wildlife Service, for example, has designated this particular area a “significant habitat complex in need of protection.”27 In addition to providing habitat for a variety of demersal and pelagic species, these diverse bottom habitats of the Thimble Islands region also support eastern oyster (Crassostrea virginica), hard clams (Mercenaria mercenaria), soft clams (Mya arenaria), blue mussels (Mytilus edulis), and channel whelk (Busycon canaliculatum).
These species, clams and oysters in particular, support significant commercial shellfish harvesting operations. The pipeline corridor, as proposed by Islander East, is sited within and adjacent to extensive shellfish grants, leased shellfish grounds and public shellfishing lands. The submerged land through which the pipeline route is proposed that is not currently leased is also productive shellfish habitat and is significant for potential future expansion of the shellfish industry, particularly in as much as the western reaches of Long Island Sound have been more affected in recent decades by lower dissolved oxygen levels and other environmental impacts that affect shellfish and benthic abundance. The shellfish industry is an economically-significant and long-established water-dependent use in Connecticut. In fact, Connecticut‘s nationally-recognized shellfish industry produces the highest quality oysters in the United States. Despite a devastating blow to oyster production from MSX28 in 1997, the annual com-
The shellfishing industry in the Thimble Islands region thrives because of the excellent water quality and exceptional habitat conditions. Of particular importance to maintaining the existing shellfishing use of this area is authorization by the State of Connecticut Department of Agriculture, Aquaculture Division (DA/AD) for harvest of shellfish for direct human consumption. The DA/AD “Approved” designation, which is the most stringent and, therefore, the most difficult to achieve, recognizes that the water is of sufficiently high quality to allow for direct consumption of shellfish from these beds without the requirement for relocation and depuration of the shellfish prior to human consumption (see map in Appendix D). Although many of Connecticut‘s marine waters are classified SA or SB/SA, the designated areas where suitable habitat exists and monitoring data documents the exceptionally good water quality necessary to receive an “Approved” designation by DA/AD are in fact limited. In general, the waters off Branford support approximately 46% of shellfishing areas approved for direct harvest in eastern Connecticut. A more detailed description of the specific parameters and required criteria relating to authorization for direct harvest of shellfish is referenced in the Water Quality Standards at page seventeen (Appendix A).
Water Quality Impacts and Habitat Alteration
The landward-most segment of pipeline, approximately 3500 feet, is proposed to be installed in-water from Juniper Point utilizing the horizontal directional drilling (HDD) method. At the HDD exit point a pit of approximate dimensions 18’ deep × 130’ wide × 310’ long is proposed to be excavated. From this exit pit, a trench approximately 5’ deep × 37’ wide × 5520’ long is proposed to be dredged to approximately Milepost 12. (A trench width of 37’ is based on a 3:1 angle of repose.) The exit pit and 5520’ long trench are proposed to be backfilled with bank-run gravel. From Milepost 12 for nine miles to the Connecticut/New York state line, three passes of a sub-sea plow are proposed to: create a trench 5’ deep × 25’ wide at the top of slope; lay the pipe; and backfill previously sidecast sediment mounds. This proposed installation would include dredging, plowing, backfilling, equipment anchoring, and anchor cable sweeping.
These activities would result in negative impacts to both the water quality and substrate. Turbidity of the water column would be relatively short-term. When this material precipitates out of the water column, it will result in sediment deposition on the benthic substrate. At the request of the Town of Branford‘s Blue Ribbon Committee,30 John Roberge, P.E., LLC, prepared an assessment of sedimentation impacts associated with pipeline installation as modified by Islander East to mitigate sediment dispersion.31 The following sediment deposition pattern was estimated in Mr. Roberge‘s study:
3 mm up to 40 meters from the trench centerline (approximately 35 acres).
The Department has determined that the negative impacts resulting from this depositional layer, in addition to direct substrate disturbance associated with dredging, plowing, backfilling, equipment anchoring, and anchor cable sweeping, are inconsistent with the Water Quality Standards. Pipeline installation would not only temporarily disturb water quality, it would permanently change the substrate and negatively impact the existing aquatic biota that depend on such substrate. The Connecticut Water Quality Standards define biological integrity as the ability of any aquatic ecosystem to support and maintain a balanced, integrated, adaptive community of organisms having a species composition, diversity, and functional organization comparable to that of the natural habitats of a region. The combined assaults of direct habitat disturbance and temporary water quality impacts resulting in sediment deposition negatively impact the overall biological integrity of the Thimbles [sic] Islands ecosystem and are therefore inconsistent with Standard No. 1 of the Connecticut Water Quality Standards.32
Pipeline installation through the Thimble Islands ecosystem will dramatically alter natural habitats and adversely impact the existing community of organisms. As discussed in a study entitled “Macrobenthic Community Structure Along The Proposed Islander East Pipeline Route In Long Island Sound,” by Pellegrino,33 there are dramatic differences in community structure associated with a disturbed versus a non-disturbed substrate. Once the original bottom has been disturbed, a soft sediment, referred to as the nephloide layer, covers the bottom and fills in any depressions left on the disturbed surface. Thus, the high-order or late successional stage species such as clams and oysters that lived in the original substrate can no longer exist. The community structure of the original substrate changes to that of early-stage opportunistic species such as polychaete worms. It is uncertain whether the associated diverse assemblage of bottom dwelling organisms currently present in this area could be reestablished. No studies exist from which one may predict a known recovery time for both these benthic communities and the substrate, if, indeed, there is any significant recovery.
Antidegradation Policy
Connecticut‘s Water Quality Standards include an Anti-degradation policy34 as required by the Act (see
As previously described, the pipeline is proposed to be sited within and adjacent to extensive shellfish grants, leased shellfish grounds and public shellfishing lands. The discharge of backfill associated with pipeline installation would result in approximately 5.5 acres of nearshore bottom habitat being permanently degraded and rendered unsuitable for supporting the diverse assemblage of shellfish and other bottom dwelling organisms currently inhabiting this area. Because the bank-run gravel would also interfere with harvesting techniques, the area of impact to shellfish harvesting would extend well beyond the 5.5 acres of direct disturbance. While the gravel-filled trench would be 37’ wide, the area that the commercial shellfish harvesting equipment would need to avoid would be much wider because of the required turning radius of the vessels with gear in tow.
Additionally, the resulting topographic irregularities over the entire 3,700-acre Islander East corridor caused by sedimentation, backfill with gravel, plow utilization, anchor strikes, and cable sweeps will adversely affect the population of resident benthic organisms and shellfish as well as the efficiency and safety of the existing shellfish harvesting operations and handling of shellfish harvesting equipment. The application materials indicate that it is the goal of the applicant to achieve a finished substrate equivalent to the adjacent benthic surface with a proposed acceptable tolerance of +2’ to -1‘. Based on the experience of the Department with the installation of the Iroquois pipeline in 1991, the Department does not agree that such a minimal impact restoration of the work site contours can, in practice, be achieved. While such a range in tolerance level might be less significant in an area of lower environmental value, where shellfish resources were scarce due to lack of suitable habitat, or where traditional harvest shellfishing techniques were not employed, that is not the case in respect to the area through which the pipeline route has been proposed by Islander East.
....
Summary
The Department therefore finds that Islander East‘s proposed work is inconsistent with Connecticut‘s federally-approved Water Quality Standards. Due to the sensitive nature of the receiving waters and the ecological system dependent upon such water, the Department has determined that the regulated activity in the proposed location will permanently alter the existing high quality physical and biological integrity and productivity of this area to the extent that the existing uses for habitat for marine fish, other aquatic life and wildlife and shellfish harvesting for direct human consumption will be impaired. Essential shellfish habitat will be lost due to the temporary and permanent alteration of the benthic environment resulting from the proposed work. Finally, the siting of the non-water dependent pipeline through prime shellfish habitat would cause a significant and permanent adverse impact to a water-dependent use by displacing the water-dependent use of shellfishing with the non-water-dependent use of natural gas transmission.
