BERKSHIRE ENVIRONMENTAL ACTION TEAM, INC.; Jean Atwater-Williams; Ronald M. Bernard; Cathy Kristofferson; Cheryl D. Rose; Irvine Sobelman; Paula L. Terrasi; Susan K. Theberge; Rosemary Wessel; Kathryn R. Eiseman; Ariel S. Elan; Elliot Fratkin; Martha A. Nathan; Kenneth Hartlage; Ronald R. Coler; Jane Winn; Heather Morrical, Petitioners, v. TENNESSEE GAS PIPELINE COMPANY, LLC; Massachusetts Department of Environmental Protection, Respondents.
No. 16-2100
United States Court of Appeals, First Circuit.
March 15, 2017
Although we conclude that the district court erred, we think it would be premature to vacate Hernandez‘s sentence. Instead, we remand so that the district court may hold a hearing and afford the parties an opportunity to present evidence anent Hernandez‘s prior convictions. Should the district court find that the evidence presented is sufficiently reliable and establishes the existence of the requisite number of predicate offenses, it should, within sixty days from the date hereof, report its findings and conclusions to this court. If, however, the court finds to the cоntrary, it should, within sixty days from the date hereof, report its findings and conclusions to this court and proceed to vacate Hernandez‘s sentence and resentence him without reference to the career offender guideline.
III. CONCLUSION
We need go no further. For the reasons elucidated above, we affirm the judgment in appeal number 15-1812, thus affirming Dunston‘s conviction and sentence. We likewise affirm the judgment in appeal number 15-2000, thus affirming Wooldridge‘s conviction and sentence. With resрect to appeal number 15-1999 (Hernandez), we remand for further proceedings consistent with this opinion and for the time being retain appellate jurisdiction over this appeal.
So ordered.
Richard A. Kanoff, with whom Susan E. Stenger, Saqib Hossain, and Burns & Levinson LLP, Boston, MA, were on brief, for petitioners.
James L. Messenger, with whom Brian J. Wall, Gordon Rees Scully Mansukhani, LLP, Boston, MA, J. Curtis Moffatt, and Mosby G. Perrow were on brief, for Tennessee Gas Pipeline Company, LLC.
Before Kayatta, Circuit Judge, Souter, Associate Justice,* and Selya, Circuit Judge.
KAYATTA, Circuit Judge.
In this unusual petition for review arising out of a state administrative proceeding, the petitioners themselves argue that we lack jurisdiction to hear their comрlaints about what has transpired to date before the state agency. Because the agency itself has not yet finally acted on the matter that is before it as is required to invoke our jurisdiction under
I. Background
The Natural Gas Act (“NGA“) requires a natural gas company to obtain from the Federal Energy Regulatory Commission (“FERC“) a certificate of public convenience and necessity before it may construct new natural gas transportation facilities or expand existing onеs.
On July 31, 2014, Tennessee Gas Pipeline Company, LLC (“Tennessee Gas“) applied to FERC for a certificate of public convenience and necessity, which FERC eventually issued in March 2016 subject to, among other things, filing of proof that Tennessee Gas has received “all applicable authorizations required under federal law (or evidence of waiver thereof).” In pursuit of one such authorization (or waiver thereof), Tennessee Gas submitted an application to the Massachusetts Department of Environmental Protection (“MassDEP“)
The letter contained over forty conditions to the project‘s approval, including a condition—“Condition 15“—forbidding Tennessee Gas from conducting any “work subject to this Certification, including the cutting of trees,” until “the expiration of the Appeal Period set forth below and any appeal proceedings that may result from an appeal.” The conditional certification аlso described the appeal process, explaining that “[c]ertain persons shall have a right to request an adjudicatory hearing concerning certifications by the Department,” including “[a]ny person aggrieved by this certification who has submitted written comments during the public comment period.” In accordance with Massachusetts regulations on the subject, the conditional certification provided that any person who wished to appeal was required to submit a Notice of Claim for Adjudicatory Hearing within twenty-one days of the certification‘s issuance.
Petitioners took advantage of this provision, filing a Notice of Claim for Adjudicatory Hearing on July 20, 2016. In response, Tennessee Gas opposed Petitioners’ request for a hearing and sought a stay of further administrative proceedings, claiming that once the agency had issued a conditional water quality certification, the state‘s involvement in the process was аt an end, with any further review to be pursued through a petition to this court. Petitioners disagreed, as did MassDEP, which denied Tennessee Gas‘s request for a stay and moved forward, scheduling a final decision to be issued by April 3, 2017. In early August 2016, Tennessee Gas filed suit in the District of Massachusetts seeking to bar MassDEP from engaging in further review. Petitioners, in turn, hedged their bets. They filed the petition now before us in order to preserve some review of the June 29 conditional water quality certification in the event that Tennessee Gas was correct. At the same time, they asked us to reject their petition on the grounds that Tennessee Gas is not correct; that is to say, they claim that our review is premature until MassDEP completes its adjudicatory process.
II. Discussion
A.
We begin with the language of the statute that grants us the jurisdiction putatively invoked by this petition. We have exclusive jurisdiction “over any civil action for the review of an order or action of a ... State administrative agency acting pursuant to Federal law [in ruling on an application, as pertinent here, for a water quality certification under
Pushing back on this common sense conclusion, Tennessee Gas points to the fact that
Such a negative inference might have interpretative force in dealing with some other subject matter. See generally, e.g., Barnhart v. Sigmon Coal Co., 534 U.S. 438, 452 (2002) (articulating the rule of statutory construction that courts should typically infer that Congress intends differences in statutory language to effect differences in statutory application). Here, though, the subject matter is judicial review of agency action, which review Congress creates in the context of a long-standing and well-settled “strong presumption ... that judicial review will be available only when agency action becomes final.” Bell v. New Jersey, 461 U.S. 773, 778 (1983) (citing FPC v. Metro. Edison Co., 304 U.S. 375, 383-85 (1938)). To say that silenсe on the subject implies no requirement of finality would be to recognize this “strong presumption” only when it is of little benefit.
It is also unclear that Congress‘s reference to FERC‘s internal review process in
Further reinforcement for the strong presumption restricting review until an agency has taken final action resides in Congress‘s numerous efforts to prevent states from unreasonably delaying the performance of their reserved roles in connection with natural gas projects. In connection with any permit required by federal law,
Tennessee Gas contends that finding a final agency action requirement in
Tennessee Gas also appears to argue that reading
We disagree with Tennessee Gas‘s premise. Finding that a statute requires final agency action is different from finding that it requires exhaustion. “[T]he judicial doctrine of exhaustion of administrative remedies is conceptually distinct from the doctrinе of finality“: whereas exhaustion “refers to administrative and judicial procedures by which an injured party may seek review of an adverse decision and obtain a remedy if the decision is found to be unlawful or otherwise inappropriate,” finality “is concerned with whether the initial decisionmaker has arrived at a definitive position on the issue that inflicts an actual, concrete injury.” Darby v. Cisneros, 509 U.S. 137, 144 (1993) (second and third quo
We therefore conclude that thеre is ample reason to stick to the strong presumption restricting our review to final agency action of a type that is customarily subject to judicial review.
B.
The foregoing brings us to Tennessee Gas‘s alternative, and principal, argument: that the June 29, 2016, letter from MassDEP constituted final agency action granting its application, albeit with conditions. Under this view, the continuing proceeding at MassDEP is in the nature of the type of appellate review that falls within the exclusivе province of this court.
An agency action is “final” only where it “represents the culmination of the agency‘s decisionmaking process and conclusively determines the rights and obligations of the parties with respect to the matters at issue.” Rhode Island v. EPA, 378 F.3d 19, 23 (1st Cir. 2004); cf. Bennett v. Spear, 520 U.S. 154, 177-78 (1997) (holding that “final agency action” under the APA,
In form, there is something to Tennessee Gas‘s argument that the June 29 letter constituted final agency action. The MassDEP officials did issue a formal document that states “the Department grants a Water Quality Certification ... subject to the following conditions ... necessary to maintain water quality, to minimize impact ... and to ensure compliance with appropriate state law.” The regulations (and the certification itself) refer to the adjudicatory hearing following an application for water quality certification as an “appeal.” See, e.g.,
The substance of the Massachusetts regulatory regime, however, shows the contrary: an initial letter granting a water quality certification subject to Condition 15, either before the twenty-one day window to request a hearing has lapsed or after a timely notice of claim is filed, is not a final agency action. Three aspects of the water quality certification that MassDEP issued in this case and the regulatory regime that gave rise to it lead us to this conclusion.
First, Massachusetts law makes clear that Tennessee Gas‘s application seeking a determination of its rights in the form of a water quality certification initiated a single, unitary proceeding, an essential part of which is the opportunity (of which petitioners have availed themselves) to have an adjudicatory hearing. Under Massachusetts law, “a proceeding bеfore an agency in which the legal rights, duties or privileges of specifically named persons are required by constitutional right or by any provision of the General Laws to be determined after opportunity for an agency hearing” is an “[a]djudicatory proceeding.”
Second, the review to be provided in the adjudicatory hearing is a review of Tennessee Gas‘s application, rather than a review of a prior agency decision. MassDEP accords no deference to the preliminary findings included in the certification, see Conservation Comm‘n of Falmouth v. Pacheco, 49 Mass. App. Ct. 737, 733 (2000), and the regulations expressly provide that the agency may even consider “new substantive issues arising from material changes to the scope or impact of the activity and not apparent at the time of public notice” from persons who did not participate in the notice-and-comment process.
Third, the manner in which Massachusetts has chosen to structure its internal agency decision-making strikes us as hardly unusual or contrived. It allows for unopposed actions to proceed to finality without the time and expense of full-blown adjudicatory proceedings, while preserving the parties’ rights to such proceedings when sought. With the taking of evidence and de novo consideration, it bears the hallmarks of decision-making by expert administrative agencies rather than those of judicial review. Its chief drawback, as demonstrated here, is its duration. Congress, though, has addressed the matter of delay directly, see
III. Conclusion
There is, as yet, no order or action of MassDEP in connection with Tennessee Gas‘s application for a water quality certification that we may review under
UNITED STATES of America, Appellee, v. Sirewl COX, Defendant, Appellant.
No. 14-1033
United States Court of Appeals, First Circuit.
March 20, 2017
from the Commonwealth of Massachusetts has been waived. See
