NE HUB PARTNERS, L.P., Appellant, v. CNG TRANSMISSION CORPORATION; Penn Fuel Gas, Inc.; James M. Seif; George J. Miller; Michelle A. Coleman; Thomas W. Renwand; Bernard A. Labuskes, Jr.
No. 00-3387.
United States Court of Appeals, Third Circuit.
Argued Oct. 6, 2000. Filed Jan. 29, 2001.
239 F.3d 333
Stanley R. Geary (argued), Buchanan Ingersoll, Pittsburgh, PA, Attorney for Appellee CNG Transmission Corporation.
Karol L. Newman (argued), Hogan & Hartson, Washington, DC, Attorney for Appellee Penn Fuel Gas, Inc.
D. Michael Fisher, Attorney General, J. Bart DeLone (argued), Deputy Attorney General, Calvin R. Koons, Senior Deputy Attorney General, John G. Knorr, Harrisburg, PA, George J. Miller, Michelle Coleman, Thomas W. Renwand, and Bernard A Labuskes, Jr., Attorney for Appellees.
BEFORE: NYGAARD, GREENBERG, and COWEN, Circuit Judges.
OPINION OF THE COURT
GREENBERG, Circuit Judge.
After detailed examination of numerous technical, safety, and environmental issues, the Federal Energy Regulatory Commission (“FERC“) issued a certificate of public convenience and necessity for plaintiff-appellant NE Hub Partners, L.P.‘s (“NE Hub“) natural gas storage facility (the “Facility“) in Tioga County, Pennsylvania. The Commonwealth of Pennsylvania may seek to revisit those issues in consolidated administrative appeals in its own permitting process in a costly proceeding that will delay NE Hub‘s construction of the Facility. Consequently, NE Hub brought a district court action seeking an injunction against the state appellate proceedings in an attempt to bar aspects of them on federal preemption grounds. The district court, however, rejected the claim without reaching its merits, principally on the jurisdictional ground that it was not ripe for decision before the state process concluded. See NE Hub Partners, L.P., No. 1: CA-99-0082 (M.D.Pa. Apr. 7, 2000) (“NE Hub“). We disagree with the district court on the ripeness issue and accordingly will reverse its order dismissing the action and will remand the case for further proceedings.
I. BACKGROUND
A. Factual History1
Since 1995 NE Hub has been seeking a plethora of federal and state permits to
Because the Facility will store natural gas for use in interstate commerce it is subject to FERC‘s jurisdiction and thus its construction requires a certificate of public convenience and necessity (the “Certificate“) pursuant to section 7(c) of the Natural Gas Act,
FERC reviewed the entire range of technical, safety, and environmental issues relating to the Facility, and, at the instance of Penn Fuel and CNGT, convened a technical conference on the application in September 1996 at which they raised the following 23 issues relating to the technical, safety, and environmental soundness of the Facility:
- Whether NE Hub‘s Drilling and Construction Program, utilizing a large diameter drill bit, would result in massive mud loss to the Oriskany sand formation;
- Whether circulation materials would satisfactorily mitigate the mud loss into the surrounding geological strata;
- Whether test drilling performed on well TW 501 indicated that the Drilling and Construction Program would lead to massive fluid loss to the Oriskany sand formation;
- Whether NE Hub‘s Drilling and Construction Program had sufficient documentation relating to rates of penetration that could reasonably be expected from the use of large diameter (28“) drilling bits to penetrate the Oriskany sand formation;
- Whether NE Hub‘s Drilling and Construction Program had properly taken into account fracture permeability of the Oriskany sand formation;
- Whether NE Hub‘s Drilling and Construction Program had accounted for the pressure fluctuations it might encounter during drilling operations due to existing gas storage facilities;
- Whether NE Hub‘s Drilling and Construction Program would result in cement invasion to the Oriskany sand formation;
- Whether mud loss and cement invasion caused by NE Hub‘s Drilling and Construction Program would result in irremediable damage to the deliverability of gas from the CNGT/Penn Fuel Storage;
- Whether NE Hub‘s Drilling and Construction Program would lead to increased risk of gas leaks and catastrophic blowouts;
- Whether the use of large quantities of loss circulation materials in NE Hub‘s Drilling and Construction Program would cause a ‘cake’ to form across the Oriskany sand formation and reduce the likelihood of achieving an adequate ce-
ment bond between the wall of the well and the casing string; - Whether NE Hub‘s Drilling and Construction Program would achieve the turbulent flow required to remove loss circulation material from the Oriskany sand formation and permit the development of an adequate cement bond;
- Whether NE Hub‘s Drilling and Construction Program required or contained sufficient contingencies in the event an adequate cement bond was not achieved;
- Whether NE Hub‘s Drilling and Construction Program included procedures for the use of a cement bond log tool to evaluate the integrity of the cement bond between the well and casing string;
- Whether NE Hub‘s Drilling and Construction Program would lead to fracturing of the casing shoe;
- Whether NE Hub‘s Drilling and Construction Program would lead to overpressuring of shallow formations;
- Whether NE Hub‘s Drilling and Construction Program would increase the likelihood of gas loss or gas migration for the CNGT/Penn Fuel Storage;
- Whether NE Hub‘s Drilling and Construction Program would result in salt cavern subsidence;
- Whether NE Hub‘s Drilling and Construction Program relied on proper research and data regarding the tensile and compressive strengths for salt;
- Whether NE Hub‘s Drilling and Construction Program relied on proper mechanical integrity testing of the salt caverns;
- Whether NE Hub had failed to consider alternate sites for cavern development;
- Whether the Sandia National Laboratories report used in development of the Drilling and Construction Program adequately addressed cavern operating pressures, cavern creep and subsidence, and rock mechanics;
- Whether the geologic conditions at locations targeted by NE Hub‘s Drilling and Construction Program were adequate for cavern development; and
- Whether NE Hub should be required to obtain insurance and/or indemnities that would be available to compensate CNGT and/or Penn Fuel for potential losses arising from the construction or operation of the Facility.
App. at 20-22.
For the next year and a half FERC, in consultation with NE Hub, Penn Fuel, and CNGT and with the assistance of an outside consulting firm, exhaustively reviewed NE Hub‘s proposal for the Facility, taking Penn Fuel‘s and CNGT‘s objections into account. In connection with this review NE Hub, Penn Fuel, and CNGT led what NE Hub has characterized as “a parade of experts and technical consultants before F.E.R.C.” See app. at 24. FERC also made an Environmental Impact Assessment of the Facility pursuant to the National Environmental Policy Act, treating at least seven issues:
- Requirements for NE Hub to create more than the two salt caverns approved by the Certificate;
- Locations of structures and facilities necessary for the Facility, including right-of-ways and the freshwater intake structure;
- Whether the Facility could be constructed and operated with insignificant effects on bodies of water, including rivers and streams;
- Whether NE Hub‘s erosion and sedimentation plans were sufficient to minimize impacts on soil and bodies of water;
Whether NE Hub‘s air pollution control plans were sufficient to minimize air quality impacts, including impacts from fugitive dust; - Whether NE Hub‘s water quality management and N.P.D.E.S. stormwater discharge plans were sufficient to minimize impacts on water quality; and
- Whether NE Hub‘s land use and reclamation plans were adequate.
See app. at 23. We call these seven issues along with the 23 issues enumerated above the “30 Issues“. In addition, FERC considered competitive and market issues.
On April 20, 1998, FERC issued the Certificate in a 93 page order. See app. at 39 et seq. The order stated that FERC had exercised its jurisdiction over the Facility and found that it could be constructed and operated safely. See app. at 24. The order, however, imposed various conditions on the construction and operation of the Facility, and stated that “NE Hub must comply with the State of Pennsylvania‘s drilling regulations,” app. at 101, and that “[r]egulation of underground storage safety is at the state level.” App. at 66. It also stated:
Any state or local permits issued with respect to the jurisdictional facilities authorized herein must be consistent with the conditions of this certificate. The Commission encourages cooperation between interstate pipelines and local authorities. However, this does not mean that state and local agencies, through application of state or local laws, may prohibit or unreasonably delay the construction or operation of facilities3 by this Commission.4
App. at 109.
Even before FERC issued its order NE Hub had applied to the Pennsylvania Department of Environmental Protection (“Pa.D.E.P.“) for the requisite state permits and thus it was proceeding on parallel regulatory paths. See app. at 25. While Pa.D.E.P. had monitored the FERC proceedings, it chose not to seek to intervene in them as it could have under
Over the next year Penn Fuel and CNGT filed three appeals protesting issuance of the state permits with the Environmental Hearing Board for the Commonwealth of Pennsylvania (“E.H.B.“), which is authorized to hear such appeals. All the individual defendant-appellees remaining in this action, i.e., all defendants except Penn Fuel and CNGT, are administrative law judges on the E.H.B., to whom we will refer collectively as E.H.B. In the appeals to E.H.B., which have since been consolidated, see app. at 26, Penn Fuel and CNGT again raised each issue they had advanced before FERC, including the 30 Issues, and presented testimony and documentation they had presented to FERC. See app. at 27. E.H.B. has not decided the appeals but the Pa.D.E.P. permits are valid pending its decision. See app. at 1021.
B. Procedural History
On January 15, 1999, NE Hub filed a complaint in the district court against Penn Fuel, CNGT, E.H.B. and James M. Seif, the Secretary of Pa.D.E.P., asking for a declaratory judgment that the NGA preempted the Pa.D.E.P. and E.H.B. review process. NE Hub also requested an order enjoining the E.H.B. proceedings and “such other relief as this Court deems
Secretary Seif settled with NE Hub on June 30, 1999, stipulating that Pa.D.E.P. lacked authority to regulate the Facility with respect to the 30 Issues, and thus the district court dismissed him as a party on July 2, 1999. See NE Hub, slip op. at 9; app. at 842-59. All other defendants, i.e., the appellees here, moved to dismiss the complaint under
The district court, in a Memorandum and Order dated April 7, 2000, granted the appellees’ motions and dismissed NE Hub‘s complaint without prejudice. See id. at 21. The court parsed NE Hub‘s claim against E.H.B. into two theories of preemption: one claiming preemption only insofar as the state process conflicted with the Certificate, the other claiming a right to be completely free from any state regulation. The court dismissed the action with respect to the conflict theory for lack of ripeness because E.H.B. had not yet taken an action that could interfere with the federal regulations and the court believed that the requirement that NE Hub go through the state review process was not in itself a cognizable harm in the conflict preemption context. See id. at 15-18. The court dismissed the action with respect to the total exemption from regulation theory on the grounds that NE Hub‘s contentions challenged the terms of the Certificate requiring the obtaining of state permits and thus should have been presented to FERC for rehearing under
NE Hub then timely filed this appeal contending that the district court erred in dismissing its preemption claim for lack of ripeness. See NE Hub‘s Br. at 3. NE Hub further contends that it is not challenging FERC‘s order and thus it argues that the district court erred in holding that this action is barred because it has not sought rehearing of the FERC order.
II. JURISDICTION
We have jurisdiction over this appeal of a final judgment of the district court pursuant to
III. STANDARD OF REVIEW
Our review of a dismissal for lack of ripeness is plenary. See Philadelphia Fed‘n of Teachers v. Ridge, 150 F.3d 319, 321 (3d Cir.1998); see also Gould Elecs. v. United States, 220 F.3d 169, 176 (3d Cir.2000). Moreover, when, as here, defendants move to dismiss a complaint under Rule 12(b)(1) for failure to allege subject matter jurisdiction we treat the allegations of the complaint as true and afford the plaintiff the favorable inferences to be drawn from the complaint.7 See Mortensen v. First Fed. Sav. & Loan Ass‘n, 549 F.2d 884, 891 (3d Cir.1977); see also
IV. ANALYSIS
A. Ripeness
The Supreme Court stated the purpose and effect of the ripeness doctrine in the context of interfering with an administrative process in Abbott Labs. v. Gardner, 387 U.S. 136, 148-49, 87 S.Ct. 1507, 1515, 18 L.Ed.2d 681 (1967):
[T]o prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.
In some circumstances the ripeness requirement is drawn from Article III limitations on judicial power and in others from prudential limitations. See Suitum v. Tahoe Regional Planning Agency, 520 U.S. 725, 733 n. 7, 117 S.Ct. 1659, 1664 n. 7, 137 L.Ed.2d 980 (1997); see also Ridge, 150 F.3d at 323 n. 3 (noting ambiguity over whether ripeness is a prudential limitation on federal jurisdiction or is required by the case-or-controversy requirement of Article III of United States Constitution); Travelers Ins. Co. v. Obusek, 72 F.3d 1148, 1154 (3d Cir.1995) (same); Armstrong World Indus., Inc. v. Adams, 961 F.2d 405, 411 n. 12 (3d Cir.1992) (same). Ripeness is a matter of degree whose threshold is notoriously hard to pinpoint. See, e.g., Maryland Cas. Co. v. Pacific Coal & Oil Co., 312 U.S. 270, 273, 61 S.Ct. 510, 512, 85 L.Ed. 826 (1941) (“The difference between an abstract question and a ‘controversy’ contemplated by the Declaratory Judgment Act is necessarily one of degree, and it would be difficult, if it would be possible, to fashion a precise test....“); McCahill v. Borough of Fox Chapel, 438 F.2d 213, 215 (3d Cir.1971) (“The considerations, while catholic, are not concrete.“); Step-Saver Data Sys., Inc. v. Wyse Tech., 912 F.2d 643, 646 (3d Cir.1990) (“it is difficult to define the contours of the ripeness doctrine with precision“) (footnote omitted).
The Supreme Court in Abbott Labs laid out two fundamental considerations for determination of a ripeness question: (1) “the fitness of the issues for judicial decision,” and (2) “the hardship to the parties of withholding court consideration.”8 387 U.S. at 149, 87 S.Ct. at 1515.
1. Adversity
NE Hub claims that the state permit process with respect to the 30 Issues is preempted but that E.H.B. nevertheless will continue with that process unless enjoined. In these circumstances, NE Hub‘s and E.H.B.‘s interests hardly could be more adverse.
Nevertheless, the district court held NE Hub‘s interests insufficiently adverse to E.H.B.‘s because:
In order to demonstrate that its claims are ripe, NE Hub must show that the probability of the EHB Defendants acting adversely to NE Hub is real and substantial.... [T]he Environmental Hearing Board Defendants have not, as yet, taken any action or issued any decision potentially conflicting with the 7(c) certificate. Further, it is entirely possible that the Environmental Hearing Board will uphold the issuance of the permits by [Pa.D.E.P.] and will never issue any decision conflicting with the federal regulatory scheme.
See NE Hub, slip op. at 15-16.10 This analysis, which focuses on the possible ultimate result of the state regulatory process, does not take into account the case law that preemption may operate to spare a party from that very process. In fact, the process itself may give rise to adversity so that an action challenging the process is ripe even before the process concludes. Thus, in Freehold Cogeneration Associates, L.P. v. Board of Regulatory Commissioners, 44 F.3d 1178 (3d Cir.1995), we held that a preemption challenge to ongoing proceedings before the New Jersey Board of Regulatory Commissioners invading FERC‘s domain was ripe even though “the plaintiff did not challenge the ultimate substantive decision, but rather its authority to conduct proceedings“:
[T]he issue here is ripe for adjudication. The proceedings before the [state agency] have been ongoing for nearly one year. The interest that Freehold seeks to vindicate in this proceeding is the right to be free from ‘state laws ... respecting the rates ... of electric utilities’ and from the expense, delay, and uncertainty inherent in the administration of such laws. If, as Freehold insists, the ongoing [state agency] proceedings constitute state regulation of utility rates and the burdens on Freehold occasioned by those proceedings are the kinds of burdens which Congress intended [certain facilities] to be spared, Congress’ mandate would be frustrated if Freehold‘s right to judicial review were postponed. There is a concrete dispute that has already worked a severe hardship upon Freehold, and a determination of the legal issue of preemption need not await any further developments....
In Sayles Hydro Associates v. Maughan, 985 F.2d 451, 453-54, 456 (9th Cir.1993), a California state water board withheld a hydroelectric plant permit because the applicant did not supply certain reports and studies. The court held that a claim that the Federal Power Act preempted the ongoing state permitting process by occupying the field of power projects regulation was ripe, explaining as follows:
The hardship is the process itself. Process costs money. If a federal licensee must spend years attempting to satisfy an elaborate, shifting array of state procedural requirements, then he must borrow a fortune to pay lawyers, economists, accountants, archaeologists, historians, engineers, recreational consultants, biologists, and others, with no revenue, no near-term prospect of revenue, and no certainty that there ever will be revenue. Meanwhile, politics, laws, interest rates, construction costs, and costs of alternatives change. Undue process may impose cost and uncertainty sufficient to thwart the federal determination that a power project should proceed.
Id. at 454. Similarly the court in Middle South Energy, Inc. v. Arkansas Public Service Commission, 772 F.2d 404 (8th Cir.1985), found ripe a claim based on preemption and the Commerce Clause against ongoing Arkansas state agency proceedings determining whether to void certain interstate power purchase contracts claimed to be within FERC‘s sole jurisdiction. The plaintiff successfully
challenge[d] not the state‘s ultimate substantive decision but its authority even to conduct the contemplated proceeding. It can hardly be doubted that a controversy sufficiently concrete for judicial review exists when the proceeding sought to be enjoined is already in progress.
Courts have found insufficient adversity for ripeness where the chance of the defendant acting against plaintiff is but a “contingency.” See, e.g., Presbytery of N.J. v. Florio, 40 F.3d 1454, 1464-68, 1470 (3d Cir.1994) (insufficient adversity where state said it would not enforce challenged law against plaintiff); Armstrong World Indus., 961 F.2d at 413-14 (insufficient adversity between state and plaintiffs challenging validity of takeover law, because takeover of plaintiffs was “contingency which may not occur,” in which case they would not suffer from law). Here, however, there is little doubt that E.H.B. will continue with the permit review process, and that the process itself is the alleged harm.
We recognize that E.H.B. in its proceedings has not yet taken a position on whether it will reconsider the 30 Issues, and if so in what depth. Thus, arguably its interest is not substantively adverse to that of NE Hub. See Step-Saver, 912 F.2d at 648. Nevertheless, inasmuch as the process creates the adversity and E.H.B. has not disclaimed a right to reexamine the issues we hold that its interest is adverse to that of NE Hub. See Supplemental letter brief of
2. Conclusiveness
Conclusiveness is a short-hand term for whether a declaratory judgment definitively would decide the parties’ rights. See Step-Saver, 912 F.2d at 648. It also addresses the extent to which further factual development of the case would facilitate decision, so as to avoid issuing advisory opinions, or whether the question presented is predominantly legal. See Travelers Ins. Co., 72 F.3d at 1155. In this case, a declaratory judgment would establish that E.H.B. may or may not review and base its permit decision on a consideration of the 30 Issues, a conclusive result.
Furthermore, additional factual development is unnecessary. We need not await the result of the E.H.B. process to ascertain whether a judgment will be conclusive because NE Hub‘s contention is that the process itself is preempted as to the 30 Issues regardless of what the outcome of a proceeding before the E.H.B. would be as to those issues. Moreover, a determination of whether there is preemption primarily raises a legal issue, a circumstance which facilitates entry of a declaratory judgment. See Pacific Gas & Elec. Co. v. State Energy Res. Conservation & Dev. Comm‘n, 461 U.S. 190, 201, 103 S.Ct. 1713, 1720-21, 75 L.Ed.2d 752 (1983) (“The question of preemption is predominantly legal, and although it would be useful to have the benefit of [the state‘s interpretation and application of its regulations], resolution of the pre-emption issue need not await that development.“); Travelers Ins. Co., 72 F.3d at 1155 (preemption is predominantly legal question conducive to declaratory judgment); Freehold Cogeneration Assocs., 44 F.3d at 1188 (judgment would be conclusive because, inter alia, factual developments at ongoing state proceedings would not add to construction of allegedly preemptive federal statute); cf. Abbott Labs., 387 U.S. at 149, 87 S.Ct. at 1515 (issue ripe for decision because, inter alia, it is “a purely legal one“).
The district court held that a judgment would be inconclusive because
without knowing whether Commonwealth will ultimately deny project authority and on what ground, it is impossible to determine whether its requirements burden or delay the NE Hub Project to such an extent so as to be preempted by the 7(c) certificate.
See NE Hub, slip op. at 16. Again, this statement overlooks that the state regulatory process itself can be the preempted burden. See discussion, infra, in part IV B of Freehold Cogeneration Assocs., Sayles Hydro Assocs., and Middle South; see also National Fuel Gas Supply Corp. v. Public Service Comm‘n, 894 F.2d 571, 578 (2d Cir.1990) (finding state regulations of gas lines preempted for inconsistency with FERC permits because “[e]ven if a [gas] transporter were successful before the [state commission], the practical effect would be to undermine the F.E.R.C. approval by imposing the costs and delays inherent in litigation that must be undertaken without any guidelines as to the limits on the exercise of state authority“); cf. Pacific Gas & Elec. Co., 461 U.S. at 201-02, 103 S.Ct. at 1721 (preemption claim against moratorium on new nuclear power plants ripe because “to require the industry to proceed without knowing whether the moratorium is valid would impose a palpable and considerable hardship on the utilities, and may ultimately work harm on the citizens of California“).
3. Practical Utility
Practical utility goes to “whether the parties’ plans of actions are likely to be affected by a declaratory judgment,” Step-Saver, 912 F.2d at 649 n. 9, and considers
A holding that the state proceedings are preempted obviously would be useful to NE Hub, which would be spared the hardships associated with the E.H.B. proceedings. NE Hub alleges that it is being put to considerable delay and expense by these proceedings in connection with the issues already dealt with by FERC.11 See, e.g., app. at 981-82. As we stated above, the requirement to go through a burdensome process can constitute hardship for purposes of ripeness. See, e.g., Freehold Cogeneration Assocs., 44 F.3d at 1188-89; Sayles Hydro Assocs., 985 F.2d at 453-56; National Fuel Gas, 894 F.2d at 578-79; Middle South Energy, 772 F.2d at 410-411. Resolving the preemption question now also will eliminate the possibility that E.H.B. may overturn the Pa.D.E.P. permits on allegedly preempted grounds. Cf. Pacific Gas & Elec., 461 U.S. at 201-02, 103 S.Ct. at 1720-21 (uncertainty entailed by existence of state procedures part of harm cognizable in assessing ripeness of preemption claim); Sayles Hydro Assocs., 985 F.2d at 454 (same); but see Ridge, 150 F.3d at 323-26 (uncertainty as to way new procedures for determining pension levels would be applied insufficient hardship to ripen due process claim).
The district court found that there was not a hardship because (1) the E.H.B. proceedings would not necessarily result in meaningless rehashing of issues, (2) additional process cannot constitute ripeness hardship, and (3) no state regulation presently stands in NE Hub‘s way. See NE Hub, slip op. at 17-18.
The first proposition is correct but beside the point: there may be some issues that E.H.B. can consider outside of the 30 Issues. Indeed, NE Hub asks that the proceedings before the E.H.B. be preempted only to the extent of precluding review of the 30 Issues. Thus, NE Hub does not suggest that federal preemption precludes E.H.B. from considering other issues.12 If the state process is preempted with respect to the 30 Issues, then undergoing the E.H.B. process with respect to those issues is a hardship cognizable for preemption purposes, and thus for determining ripeness of NE Hub‘s preemption claims.
For the second proposition, the district court quoted two cases:
[T]he Court has not considered ... litigation cost-saving sufficient by itself to justify review in a case that would otherwise be unripe. The ripeness doctrine reflects a judgment that the disadvantages of a premature review that may prove too abstract or unnecessary ordinarily outweigh the additional costs of—even repetitive—post-implementation litigation.
[T]he burden of participating in further administrative and judicial proceedings
do[es] not constitute sufficient hardship for the purposes of ripeness.
Florida Power & Light Co. v. EPA, 145 F.3d 1414, 1421 (D.C.Cir.1998). See NE Hub, slip op. at 17. But neither case involved a claim of preemption. When such a claim has been advanced, the need to participate in a state regulatory process in conflict with federal policy has been recognized as a hardship. See, e.g., Freehold Cogeneration Assocs., 44 F.3d at 1188-89; Sayles Hydro Assocs., 985 F.2d at 453-56; National Fuel Gas, 894 F.2d at 578-79; Middle South Energy, 772 F.2d at 410–11; cf. First Iowa Hydro-Elec Co-op v. Federal Power Comm‘n, 328 U.S. 152, 66 S.Ct. 906, 90 L.Ed. 1143 (1946) (hydroelectric plant project subject to jurisdiction of Federal Power Commission (FERC‘s predecessor) need not obtain permit from Iowa, despite law apparently conditioning federal license on compliance with state laws). Thus, while the district court‘s quotations are accurate they are not controlling precedent in the circumstances here.
Moreover, the extra litigation or administrative burden at issue in the cases quoted by the district court was apparently the burden of filing the same lawsuit later, not of undergoing an expensive and time-consuming state process. The cases quoted by the district court involved challenges to a Plan issued by the United States Forest Service and a rule allegedly issued by the Environmental Protection Agency, respectively. See Sierra Club, 118 S.Ct. at 1668; Florida Power & Light, 145 F.3d at 1416. In both cases, how and even whether the Plan and rule would be applied was unclear; in Florida Power & Light, the court held the EPA had not even issued a rule. See Florida Power & Light, 145 F.3d at 1418-19. In Sierra Club, the Court stated that requiring a challenger to a rule to engage in post-implementation litigation over the rule does not constitute sufficient hardship to ripen “a case that would otherwise be unripe.” Sierra Club, 118 S.Ct. at 1671. Clearly, that holding is hardly controlling when the plaintiff‘s challenge is to the conduct of an administrative process that imposes an ongoing burden.
The district court‘s third proposition also misses the point that process can constitute hardship. While it is true that the Pa.D.E.P. permits are valid pending the E.H.B. outcome, it is not a regulation but the regulatory process that afflicts NE Hub. If the process is preempted it is quite immaterial that the effectiveness of the permits challenged has not been stayed. Moreover, if NE Hub goes forward construction of the Facility while the E.H.B. proceedings are pending it may find itself in a difficult situation if Penn Fuel and CNGT are successful before E.H.B.
B. State regulatory process is susceptible of preemption by conflict or by field occupation.
E.H.B. contends that the cases holding a state regulatory process preempted have involved only field occupation preemption, and should be so confined and thus preemption principles are not applicable here as, in E.H.B.‘s view, the NGA and FERC have not occupied the field. See E.H.B.‘s br. at 17-23. The district court agreed that this case does not involve field occupation. We, however, strongly doubt that the district court was correct in this conclusion. See Schneidewind v. ANR Pipeline Co., 485 U.S. 293, 295 n. 1, 300-05, 108 S.Ct. 1145, 99 L.Ed.2d 316 (1988); Sayles Hydro Assocs., 985 F.2d at 453; Pennsylvania Med. Soc‘y v. Marconis, 942 F.2d 842, 847 (3d Cir.1991); Public Utils. Comm‘n v. FERC, 900 F.2d 269, 274 (D.C.Cir.1990). Nevertheless, we need not characterize definitively the type of preemption implicated here to determine ripeness, which is the only issue before us. To the extent the district court already tacitly has decided what type of preemption is involved, on remand, if it reaches the issue, it should reconsider its decision.13
Nevertheless, the process preemption cases do not confine themselves to the field occupation context, nor would such a limitation be wise. Even where a field has not been occupied to the exclusion of state regulation, certain state regulatory acts clearly would conflict with federal law, and it is as logical to preempt state process concerning such matters as state actions in occupied fields.14 Indeed, even if this is a conflict preemption case, it would be quite remarkable to hold that there cannot be process preemption here inasmuch as Secretary Seif on behalf of Pa.D.E.P. in settling the case recognized that, to the extent that FERC exercised jurisdiction, Pa.D.E.P. “[d]oes not have jurisdiction to consider and cannot conduct final appealable decisionmaking.” App. at 855. This recognition broadly extended to “all construction activities related to the [Facility], including the drilling and construction of the brining facilities and the technical, safety, and environmental issues which were raised before and considered by FERC.” App. at 846. While this stipulation may not be binding on the appellees, inasmuch as the state administrator himself recognizes the preemptive effect of the NGA and FERC‘s exercise of jurisdiction, we have good reason to recognize that conflict preemption principles might bar E.H.B. from upholding Penn Fuel‘s and CNGT‘s appeal on the 30 Issues.
We also point out that, as the Supreme Court recently has emphasized, the different categories of preemption are not rigidly distinct. Indeed, field pre-emption may be understood as a species of conflict pre-emption: A state law that falls within a pre-empted field conflicts with Congress’ intent (either express or plainly implied) to exclude state regulation.
English v. General Elec. Co., 496 U.S. 72, 79 n. 5, 110 S.Ct. 2270, 2275 n. 5, 110 L.Ed.2d 65 (1990); see also Crosby v. National Foreign Trade Council, 530 U.S. 363, 372 n. 6, 120 S.Ct. 2288, 2294 n. 6, 147 L.Ed.2d 352 (2000); Gade v. National Solid Wastes Management Ass‘n, 505 U.S. 88, 98, 104 n. 2, 112 S.Ct. 2374, 2383, 2386 n. 2, 120 L.Ed.2d 73 (1992) (plurality opinion) (“Our ultimate task in any pre-emption case is to determine whether state regulation is consistent with the structure and purpose of the statute as a whole.” (Emphasis added.)); Sayles Hydro Assocs., 985 F.2d at 456 (“The dichotomy between the two types of preemption [conflict and field] is not so sharp in practical terms as the legal categorization makes it appear....“).
A comparison of the standards for identifying these two types of preemption15 shows the reason for the blurring.16 Conflict preemption exists where state law stands as an obstacle to the accomplishment and execution of the full purposes
We therefore hold that state regulatory process may be preempted by conflict with federal law,17 as well as by field occupation. Moreover, we reiterate that we are quite unable to understand why, regardless of the type of preemption asserted, that a claim that a state administrative process is preempted necessarily cannot be ripe when the alleged preemption is of the process itself rather than the possible outcome of the process. We also note that it would be entirely logical in an appropriate case to hold that the process is not preempted but to hold later that the result of the process is preempted.
Furthermore, if it is evident that the result of a process must lead to conflict preemption, it would defy logic to hold that the process itself cannot be preempted and that a complaint seeking that result would not raise a ripe issue. Thus, in view of the substantial showing here that E.H.B. by upholding Penn Fuel‘s and CNGT‘s position on the 30 Issues might well reach a result that would be preempted, the process preemption claim is ripe. Of course, we hasten to add that we do not state a conclusion on whether the process actually is preempted here for, as even NE Hub recognizes, the district court should make that decision on the remand. See Presbytery of N.J., 40 F.3d at 1470.18
C. The need for FERC rehearing
Finally we reject the district court‘s and appellees’ view that NE Hub by bringing this action was circumventing FERC‘s rehearing process. In the first place, the district court reached that conclusion on the erroneous theory that NE Hub was contending “that Pennsylvania lacks authority to subject the NE Hub Project to any regulation whatsoever.” NE Hub, slip op. at 18. In fact, NE Hub does not challenge FERC‘s requirement that it obtain state permits and cooperate with state and local agencies. Indeed, it has done these things. It simply contends that the E.H.B. state proceedings are preempted but only to the extent that they involve the 30 Issues considered by FERC. We see nothing in the Certificate or the NGA that precludes NE Hub‘s preemption argument and it therefore follows that in making that argument NE Hub is not
V. CONCLUSION
For the foregoing reasons we will reverse the order of April 7, 2000, dismissing this action and will remand the case to the district court to reinstate this action. On the remand the district court should consider the preemption argument on the merits unless it upholds another defense to this action.
NYGAARD, Circuit Judge, dissenting:
I would affirm the District Court‘s disposition of N.E. Hub‘s field preemption claim. Therefore, I dissent. Central to the Majority‘s holding is its assertion that “we need not characterize definitively the type of preemption implicated here.” Majority at 346. I believe that characterizing N.E. Hub‘s claim is the first and most important issue in this case. By failing to resolve it, the Majority ignores binding Supreme Court precedent and unnecessarily complicates a well-settled area of law. Especially troubling are its proposal of a new class of “hybrid” preemption, and its reference to a mysterious “process” preemption.
Congress intended to occupy the field of law at issue. Therefore, the disputed appeals are subject to federal field preemption. Nonetheless, I would affirm the District Court‘s decision, because FERC properly exercised its congressionally delegated authority by requiring compliance with state permitting procedures. More importantly, even if FERC overstepped its bounds, the proper course for N.E. Hub would have been to challenge FERC directly under the guidelines established by federal statute. Because N.E. Hub failed to do so, I agree with the District Court that we lack jurisdiction to consider the current claim.
I.
A brief review of the law of preemption is instructive. Assuming it has the constitutional power to legislate in a given area, Congress can preempt state law whenever it intends federal law to control. See Freehold Cogeneration Assocs., L.P. v. Board of Regulatory Comm‘rs of State of New Jersey, 44 F.3d 1178, 1190 (3d Cir.1995) (“[T]he application of the preemption doctrine requires a determination of congressional intent in enacting a federal law.“). The key inquiry is congressional intent, which can either be explicit or implied. When it is implied, intent can take one of two forms. First, “[i]f Congress evidences an intent to occupy a given field, any state law falling within that field is preempted.” Silkwood v. Kerr-McGee Corp., 464 U.S. 238, 248, 104 S.Ct. 615, 621, 78 L.Ed.2d 443 (1984). Congressional intent to occupy a field can be inferred from:
a ‘scheme of federal regulation so pervasive as to make reasonable the inference that Congress left no room to supplement it,’ ‘because the Act of Congress may touch a field in which the federal interest is so dominant that the federal
system will be assumed to preclude enforcement of state laws on the same subject,’ or because ‘the object sought to be obtained by the federal law and the character of obligations imposed by it may reveal the same purpose.’
Pacific Gas & Elec. Co. v. State Energy Res. Conservation & Dev. Comm‘n, 461 U.S. 190, 204, 103 S.Ct. 1713, 1722, 75 L.Ed.2d 752 (1983). Second, if Congress has not occupied an entire field, “state law is still preempted to the extent it actually conflicts with federal law, that is, when it is impossible to comply with both state and federal law.” Id.
In sum, there are three circumstances under which federal law preempts state law: (1) when Congress, through explicit statutory language, defines an area in which federal law controls, (2) when Congress implicitly indicates an intent to occupy a given field to the exclusion of state law, and (3) when federal law actually conflicts with state law. See Cipollone v. Liggett Group, Inc., 505 U.S. 504, 516, 112 S.Ct. 2608, 2617, 120 L.Ed.2d 407 (1992); Buzzard v. Roadrunner Trucking, Inc., 966 F.2d 777, 780 (3d Cir.1992). We have consistently analyzed preemption claims according to this framework. See Abdullah v. American Airlines, 181 F.3d 363, 367 (3d Cir.1999).
II.
Next, I turn to N.E. Hub‘s specific claim. In Schneidewind v. ANR Pipeline Co., the Supreme Court held that Congress intended to occupy the field at issue.1 See 485 U.S. 293, 308, 108 S.Ct. 1145, 1155, 99 L.Ed.2d 316 (1988) (“[T]he control of rates and facilities of natural gas companies ... are precisely the things over which FERC has comprehensive authority.“). The Court noted that it “is now well settled[that] Congress occupied the field of matters relating to wholesale sales and transportation of natural gas in interstate commerce.” Id. at 305, 108 S.Ct. at 1153. An overwhelming amount of authority supports this assertion.2 Even in Maritimes & Northeast Pipeline, L.L.C., No. CP97-238-001, 1997 WL 812154, at *8 (F.E.R.C. Nov. 4, 1997), the case most heavily relied upon by CNGT and Penn Fuel, FERC noted that “the NGA preempts State and local agencies from regulating the construction and operation of interstate pipeline facilities.” It is simply beyond peradventure that Congress intended the NGA to occupy the field of law at issue.
Both the Majority and the District Court disagree and hold that field preemption does not apply. The District Court expressly rejected field preemption, but nonetheless addressed and rejected the claim on its merits. The Majority purports to avoid categorizing the claim, but still implicitly endorses conflict preemption. I believe that field preemption does apply, but I agree with the District Court that the claim fails on its merits. This is an important question. If field preemption applies but FERC validly exercised its authority, we should affirm the District Court‘s decision and not remand the case. Fundamentally, the resolution of this question—whether field preemption applies—controls whether this case is remanded or affirmed. I therefore review the opinions of the Majority and District Court in turn.
A.
The Majority at first seems to agree with me that field preemption should apply. It states that “[t]he district court [held] that this case does not involve field occupation. We, however, strongly doubt that the district court was correct.” Majority at 346 (emphasis added). The Majority fails to apply field preemption, however, and instead holds that “we need not characterize definitively the type of preemption implicated here to determine ripeness.” Majority at 346. In spite of this, I believe that the Majority tacitly does characterize N.E. Hub‘s claim. It rejects field preemption and endorses conflict preemption, even though its reasoning assumes that Congress has occupied the field.
The District Court‘s decision requires us to categorize the claim in this case, because it addressed N.E. Hub‘s two preemption “theories” and reached different outcomes for each. The court held that conflict preemption was not ripe, but rejected field preemption on separate grounds.3 The Majority states that ripeness “is the only issue before us.” Majority at 346. The District Court discussed ripeness only in connection to conflict preemption. Therefore, the Majority‘s opinion, to the extent that it exclusively focuses on ripeness, holds that only conflict preemption is at issue.
Furthermore, because courts need only address conflict preemption in the absence of field preemption, see Silkwood, 464 U.S. at 248, 104 S.Ct. at 621 (“If Congress has not entirely displaced state regulation over the matter in question, state law is still preempted to the extent it actually conflicts with federal law.“), the Majority‘s focus on ripeness tacitly rejects field preemption. If field preemption applied, there would be no reason to analyze the ripeness of the conflict preemption claim.4 In fact, the Majority explicitly holds that N.E. Hub never raised a field preemption claim. See Majority at 349. Thus, even though it “strongly doubt[s] that the district court was correct [to reject field preemption],” Majority at 346, the Majority rejects it as well.
Instead, the Majority suggests that we have a “hybrid situation” in which “there is field occupation but FERC ... has converted the case into a conflict preemption matter.” Majority at 346-47 n. 13. I disagree with this characterization for two reasons. First, neither law nor logic suggests the existence of such a thing, and second, for reasons I explain more fully in Section II.B., supra, FERC does not have the authority to abdicate its congressionally delegated authority.5 In addition, I fail to see how this “hybrid” differs practically from pure conflict preemption considering that FERC “has converted the case into a conflict preemption matter.” Majority at 346-47 n. 13 (emphasis added). If a “hy-
The Majority offers two additional arguments to support its position: (1) field and conflict preemption overlap and are difficult to distinguish, and (2) the existence of a legal process can form the basis of a field or conflict preemption claim. See Majority at 348-49. When reviewed carefully, neither support the Majority‘s holding; in fact, both ironically assume that Congress has preempted the field.
First, the Majority argues that it need not characterize N.E. Hub‘s claim, because field and conflict preemption are not “rigidly distinct,” see English v. General Elec. Co., 496 U.S. 72, 79 n. 5, 110 S.Ct. 2270, 2275 n. 5, 110 L.Ed.2d 65 (1990),6 implying, based upon its definitions, that field and conflict preemption are indistinguishable. Technically, all forms of federal preemption can be described as (and meet the definition of) conflict preemption,7 for the simple reason that preemption only occurs when a state action conflicts with congressional intent.8 In spite of its extremely broad definition, however, conflict preemption does not refer to the entire range of all federal preemption. Instead, courts use the term quite narrowly—it applies when a state regulation conflicts with federal law in a non-occupied field.9 See Silkwood, 464 U.S. at 248, 104 S.Ct. at 621 (“If Congress has not entirely displaced state regulation over the matter in question, state law is still preempted to the extent it actually conflicts with federal law.“).
The Majority fails to make this distinction. It compares the definitions of conflict and field preemption and argues that field preemption is simply a presumption of conflict preemption over an entire area of law.10 Because all three categories of federal preemption technically fall within the definition of conflict preemption, any state regulation (or judicial proceeding, as in this case) subject to field preemption would also be barred under the technical definition of conflict preemption. See English, 496 U.S. at 79, 110 S.Ct. at 2275 (defining conflict preemption, in part, to apply when “state law ‘stands as an obstacle to the accomplishment and execution of the full purposes and objectives of Congress’ “).
However—and this is the critical point—in this case, the only reason that the challenged state actions (the appeals) satisfy the definition of conflict preemption is because Congress has preempted the field. The Majority never asserts that the appeals at issue make it “impossible to comply with both state and federal law,” but merely that they frustrate congressional intent to legislate exclusively in this area. In other words, as the Majority phrases it, conflict preemption holds because the state proceedings “interfere with the purposes and objectives of the federal plan.” Majority at 348. The “federal plan,” I suppose, refers to Congress’ intent to occupy the field at issue. Thus, the Majority‘s argument, when closely scrutinized, goes something like this: (1) Congress preempted the field, and (2) the appeals at issue constitute state action within that field; therefore, (3) the appeals conflict with congressional intent to legislate exclusively. The Majority‘s reasoning implicitly recognizes that Congress intended to occupy the field at issue. As such, I would affix the proper “label” to N.E. Hub‘s preemption claim. When a state law “conflicts” with “the purposes and objectives” of Congress to occupy a given field, courts label it field, not conflict, preemption.11
The Majority‘s second argument further underscores its implicit recognition that Congress has preempted the field.12 The Majority argues that it need not classify the claim at issue, because either field or conflict preemption can bar a legal process such as the appeals in this case.13 See Majority at 347 (“[T]he process preemption cases do not confine themselves to the field occupation context.“). The Majority cites no case in which any court has held that conflict preemption bars an unfinished legal process with an indeterminate outcome. I too was unable to find such a case.14
In sum, the Majority purports to avoid categorizing N.E. Hub‘s claim. In reality, however, it rejects field preemption and requires the District Court to apply conflict preemption upon remand, even though its reasoning assumes that Congress has occupied the field. According to the Supreme Court, conflict preemption should be applied only if “Congress has not entirely displaced state regulation over the matter in question” explicitly or through implied field preemption. Silkwood, 464 U.S. at 248, 104 S.Ct. at 621. In this case, the overwhelming weight of Supreme Court precedent indicates that Congress intended the NGA to occupy the field at issue. As a result, I disagree with the Majority‘s approach and would instead apply field preemption.
B.
The District Court addressed the classification issue explicitly. It held that field preemption does not apply, because FERC had affirmatively limited its own jurisdiction. It noted that “[a]lthough the Natural Gas Act might be read to completely preempt any state regulation of the transport, storage and sale of natural gas in interstate commerce, FERC has interpreted its jurisdiction under the Natural Gas Act to allow for some state regulation.” MemOp. at 13. In effect, the District Court held that FERC refused to occupy the given field and instead partially delegated its responsibilities to the states. The Majority seems to endorse this conclusion hesitantly in a footnote, terming this case a “hybrid” situation. See Majority at 346-47 n. 13.
The District Court‘s analysis, and the Majority‘s reference to it, is flawed. Admittedly, Chevron v. NRDC, 467 U.S. 837, 842-43, 104 S.Ct. 2778, 2781-82, 81 L.Ed.2d 694 (1984), often requires courts to defer to an agency‘s statutory interpretation, and we have held that Chevron deference extends to an agency‘s interpretation of its own jurisdiction. See Puerto Rico Mar. Shipping Auth. v. Valley Freight Sys., Inc., 856 F.2d 546, 552 (3d Cir.1988) (“This rule of deference is fully applicable to an agency‘s interpretation of its own jurisdiction.“). However, courts need only defer to an agency when the intent of Congress is unclear. See Chevron, 467 U.S. at 842-43, 104 S.Ct. at 2781-82 (“If the intent of Congress is clear, that is the end of the matter.“).16 Here, as previously discussed, the intent of Congress to occupy the entire field is, and has been for decades, clearly established by the Supreme Court. As a result, FERC could not limit its jurisdiction in the face of contrary, clear congressional intent. See id. at 843 n. 9, 104 S.Ct. at 2781 n. 9 (“The judiciary is the final authority on issues of statutory construction and must reject administrative constructions which are contrary to clear congressional intent.“).
Furthermore, based upon my reading of Maritimes, FERC did not intend to restrict its jurisdiction. See 1997 WL 812154, at *8. Quite the contrary—it exercised its wide-ranging jurisdiction in order to require that natural gas companies comply with state regulations as a condition to granting a 7(c) certificate. After reaffirming the NGA‘s preemption of state and
It is undisputed by both the Majority and the District Court that Congress intended federal law to occupy the entire field at issue. Because neither FERC nor this Court have the discretion to contravene clear congressional intent, field preemption should apply. The ripeness of N.E. Hub‘s conflict preemption claim is therefore irrelevant.
III.
Finally, I address the merits of N.E. Hub‘s field preemption claim. First of all, it is clearly ripe. We require that a claim satisfy three elements in order to be ripe for decision: “adversity of the interests of the parties, conclusiveness of the judicial judgment and the practical help, or utility, of that judgment.” Step-Saver Data Systems, Inc. v. Wyse Technology, 912 F.2d 643, 647 (3d Cir.1990). All three are satisfied. The state proceedings themselves constitute an injury establishing adversity of interest. See Sayles Hydro Assocs. v. Maughan, 985 F.2d 451, 454 (9th Cir.1993) (holding that in the field preemption context, “[t]he hardship is the process itself.“).17 A decree indicating that FERC‘s
Apparently, the District Court agreed that if field preemption applied, N.E. Hub‘s claim was ripe. After a lengthy and unnecessary discussion of the ripeness of the conflict preemption claim, it moved immediately to the merits of the field preemption claim (without discussing its ripeness). The court held that the claim failed on its merits:
NE Hub‘s alternative theory, that Pennsylvania lacks authority to subject NE Hub Project to any regulation whatsoever, must also fail on jurisdictional grounds. Such an attack constitutes a challenge to the express provisions of the 7(c) certificate issued by FERC to NE Hub, which clearly contemplate and even direct NE Hub‘s compliance with state regulation. As pointed out by Defendants CNGT and Penn Fuel in their motions to dismiss, the Court lacks jurisdiction over such a challenge to the 7(c) certificate, as NE Hub failed to apply to FERC for a rehearing of its April 29, 1998 Order issuing the 7(c) certificate.
MemOp. at 18-19 (citations omitted). I agree with the Court‘s reasoning and outcome, but it would be helpful to elaborate further. FERC‘s 7(c) certificate required compliance with state and local regulations. Specifically, it stated that:
Any state or local permits issued with respect to the jurisdictional facilities authorized herein must be consistent with the conditions of this certificate. The Commission encourages cooperation between interstate pipelines and local authorities. However, this does not mean that state and local agencies, through application of state or local laws, may prohibit or unreasonably delay the construction or operation of facilities by this Commission.
J.A. at 109. The District Court interpreted this language to require that N.E. Hub obtain “any and all necessary state or local permits required to carry out the drilling and construction program.” MemOp. at 5. In addition, the 7(c) certificate also contained a number of more specific provisions that required compliance with individual state regulations. See MemOp. at 14-15.
FERC‘s discretion in granting a 7(c) certificate is far-reaching. Section 717f(e) of the NGA provides that, “[t]he Commission shall have the power to attach to the issuance of the certificate and to the exercise of the rights granted thereunder such reasonable terms and conditions as the public convenience and necessity may require.”
This interpretation is consistent with FERC‘s discussion of state regulations in Maritimes, 1997 WL 812154, at *8. In that case, FERC described its “requirement” that applicants cooperate with state and local authorities as being something it had “imposed” as “a matter of policy.” Id. A plain reading suggests that FERC was simply exercising its wide jurisdiction over the field, requiring applicants to comply with state and local regulations that impose additional, non-conflicting measures. Were an actual conflict to arise, FERC noted that its decisions would control.
FERC could have required, subsequent to its § 717f(e) authority, that applicants comply with conditions identical to those found in state regulations. It is unclear why, and indeed N.E. Hub has failed to argue that, requiring compliance with
IV.
I would affirm the District Court‘s decision based upon its disposition of the one legitimate claim at issue—N.E. Hub‘s argument that the state proceedings at issue are field preempted by FERC‘s 7(c) certificate. Field preemption does apply, but FERC exercised its wide-ranging authority to require compliance with state regulations. Because N.E. Hub failed to challenge FERC‘s authority directly, it cannot now challenge the 7(c) certificate in this Court. The District Court properly held that it lacked jurisdiction over the claims at issue, and as a result, N.E. Hub‘s claims were properly dismissed.
Charles CRISSMAN; Wendy Crissman; *Christine Crissman, Appellants, v. DOVER DOWNS ENTERTAINMENT INC.; Dover Downs, Inc.
No. 00-5178.
United States Court of Appeals, Third Circuit.
Argued Dec. 5, 2000. Filed Jan. 29, 2001.
* (Dismissed as Party per Court‘s 11/8/2000 Order)
Notes
ADVERSITY:
- Whether the claim involves uncertain and contingent events, or presents a real and substantial threat of harm. See, e.g., Presbytery of N.J. v. Florio, 40 F.3d 1454, 1466 (3d Cir.1994).
CONCLUSIVENESS:
- Whether issues are purely legal (as against factual).
- Whether further factual development would be useful. See, e.g., id. at 1468; Travelers Ins. Co., 72 F.3d at 1155.
UTILITY:
- Hardship to the parties of withholding decision.
- Whether the claim involves uncertain and contingent events. See, e.g., Travelers Ins. Co., 72 F.3d at 1155-56.
