RYAN CONTRACTING COMPANY, Respondent, v. O‘NEILL & MURPHY, LLP, et al., Appellants.
No. A14-1472.
Supreme Court of Minnesota.
Aug. 3, 2016.
883 N.W.2d 236
CHUTICH, J., not having been a member of this court at the time of submission, took no part in the consideration or decision of this case. HUDSON, J., took no part in the consideration or decision of this case.
OPINION
DIETZEN, Justice.
Ryan Contracting Company (Ryan) brought suit against O‘Neill & Murphy, LLP (O‘Neill) for legal malpractice arising out of O‘Neill‘s representation of Ryan in a legal malpractice claim against Meagher & Geer, PLLP (MG) for alleged errors in the foreclosure of Ryan‘s mechanic‘s liens. O‘Neill moved for summary judgment, arguing that Ryan could not establish that “but for” MG‘s alleged errors in filing the mechanic‘s liens, the underlying claims would have yielded a more favorable outcome. The district court granted the motion, concluding, among other things, that Ryan‘s error in not filing the pre-lien notice required by
This case arises out of the foreclosure of mechanic‘s liens by Ryan, which was a contractor on the project, for improvements it made to real property located in Wright County that was owned by Darrel A. Farr Development Corp. The development was known as the Kittredge Crossing Development Project. After Farr obtained the necessary zoning approvals from the City of Otsego, Farr and Ryan entered into two contracts in December 2003 and September 2004, which provided that Ryan would construct certain utility and street improvements on Phase I and Phase II of the development project for agreed-upon compensation. The work consisted of placing sewer lines, grading the streets, and then paving the streets with asphalt. Ryan did not serve Farr with a written pre-lien notice upon commencement of the work.
In July 2006, Ryan alleged that Farr failed to pay for the work performed on the development project and filed a notice to terminate the contracts. Thereafter, MG, acting on Ryan‘s behalf, filed 26 mechanic‘s lien statements, covering 289 lots, in the amount of $362,546 for each lot in the project. Throughout the litigation there has been a sharp dispute over whether Ryan was justified in filing for the total amount of the lien for each lot. Farr responded by filing an action in Wright County District Court alleging that Ryan breached the contracts with Farr and claimed damages. Ryan answered the complaint and commenced a separate action to foreclose on those mechanic‘s liens. At the time Ryan foreclosed the liens, 203 lots were still owned by Farr, and 86 lots had been sold to third parties.1 The two cases were consolidated by the district court.
In June 2007, Ryan terminated MG, and substituted Wilkerson & Hegna, PLLP as
The district court granted Farr‘s motion for summary judgment as to the non-Farr-owned lots. The district court reasoned that because those lots were no longer owned by Farr,
But the court denied summary judgment as to the Farr-owned lots based upon section
Ryan and Farr subsequently settled the two lawsuits. The terms of the agreement required Ryan to release its mechanic‘s liens on the Farr-owned lots and its contract claims against Farr in exchange for a payment of $280,000. Ryan, however, reserved any claims it had against third parties, including MG, for damages arising out of the foreclosure of Ryan‘s mechanic‘s liens.
Ryan, now represented by O‘Neill, brought suit against MG for legal malpractice arising out of MG‘s allegedly defective filing and foreclosure of Ryan‘s mechanic‘s liens on the development project. MG moved to dismiss the lawsuit on the ground that O‘Neill failed to timely file expert witness affidavits as required by In the current lawsuit, Ryan, which is now represented by Sortland Law Office, sued O‘Neill for legal malpractice arising out of O‘Neill‘s representation of Ryan in the MG lawsuit. O‘Neill moved for summary judgment, arguing that Ryan is unable to establish causation. Specifically, O‘Neill argues that Ryan cannot establish that “but for” MG‘s alleged errors in filing The court of appeals affirmed in part, reversed in part, and remanded the case to the district court for further proceedings. The court concluded that Ryan was exempt from the pre-lien notice requirement under On appeal, O‘Neill argues that the court of appeals erred in concluding that Ryan: (1) was not required under O‘Neill first argues that Ryan was required under We review the district court‘s summary judgment decision de novo. Premier Bank v. Becker Dev., LLC, 785 N.W.2d 753, 758 (Minn.2010); Riverview Muir Doran, LLC v. JADT Dev. Group, LLC, 790 N.W.2d 167, 170 (Minn.2010). Our role is to “determine whether the district court properly applied the law and whether there are genuine issues of material fact that preclude summary judgment.” Riverview Muir Doran, 790 N.W.2d at 170. Statutory interpretation is a question of law that we review de novo. In re Welfare of J.J.P., 831 N.W.2d 260, 264 (Minn.2013). The goal of all statutory interpretation is to ascertain and effectuate the intent of the Legislature. To prevail in an action for legal malpractice the plaintiff must show: “(1) the existence of an attorney-client relationship; (2) acts constituting negligence or breach of contract; (3) that such acts were the proximate cause of the plaintiff‘s damages; and (4) that but for defendant‘s conduct, the plaintiff would have been successful in the prosecution or defense of the action.” Blue Water Corp., Inc. v. O‘Toole, 336 N.W.2d 279, 281-82 (Minn.1983). A plaintiff must provide sufficient evidence to satisfy each of these elements. Id. at 282. The primary focus of O‘Neill‘s motion for summary judgment is on the fourth element. To survive a summary judgment motion on the causation element in this situation, Ryan must show that in the absence of MG‘s malpractice, it would have A mechanic‘s lien is a statutory remedy available to those who furnish labor or materials in the improvement of real property. Riverview Muir Doran, 790 N.W.2d at 170-71. The rights and liabilities of the parties to a mechanic‘s lien are governed by Minnesota‘s pre-lien notice statute requires every person who enters into a contract with an owner for the improvement of real property, and who has contracted or will contract with any subcontractors or material suppliers to provide labor, skill, or materials for the improvement, to provide pre-lien notice to the owner. The pre-lien notice requirement in section The notice required by this section shall not be required to be given in connection with an improvement to real property which is not in agricultural use and which is wholly or partially nonresidential in use if the work or improvement: . . . (c) is an improvement to real property which contains more than 5,000 square feet and does not involve the construction of a new building or an addition to or the improvement of an existing building. Id. The crux of the dispute is over the meaning of the phrase “in connection with an improvement to real property which is not in agricultural use and which is wholly or partially nonresidential in use” in subdivision 4c. O‘Neill does not dispute that Ryan‘s improvement to the real property satisfied the criterion of subdivision 4c(c). Instead, O‘Neill argues that the phrase “in use” in subdivision 4 refers to the current use of the real property, and that undeveloped raw land does not constitute a use of the land. According to O‘Neill, the property had no current use at the relevant time, and therefore the notice exception in subdivision 4c does not apply. We will first address to what “in use” refers and when the use of land When applied to subdivision 4c, the last-antecedent canon leads to the conclusion that the phrase “in use” refers to “real property” because it is the nearest reasonable antecedent noun. Our conclusion is supported by the two principles we articulated in Butler. See 803 N.W.2d at 397-98. First, there is no comma separating the “which” phrases, and thus the presumption is that the last-antecedent rule applies in this case. Id. at 397. Second, we must determine whether the application of the last-antecedent rule would render any language in the statute superfluous. Id. at 398. Here, if we do not apply the rule, then the phrase before the colon in the statute—immediately following the “which” phrases—would be rendered superfluous. Only by applying the grammatical rule of the last antecedent does that phrase do any work. Accordingly, the last-antecedent rule applies, and the phrase “which is wholly or partially nonresidential in use” modifies “real property.” We next address at what point in time “in use” is determined under subdivision 4c. The term “land use” in the context of municipal planning has acquired a special or technical meaning. See We conclude that the phrase “in use” in O‘Neill relies on our decision in S.M. Hentges & Sons, Inc. v. Mensing, 777 N.W.2d 228 (Minn.2010), to argue that exceptions to the pre-lien notice requirements in section But the language of section In sum, we conclude that under In the original litigation between Farr and Ryan, the district court found that the liens filed by Ryan on the non-Farr-owned lots were void. O‘Neill asserts that MG was not at fault, as a matter of law, for failure to file valid liens given the combination of (1) the district court‘s finding in the original litigation that, under may file one statement for the entire claim, embracing the whole area so improved; or, if so electing, the lienholder may apportion the demand between the several improvements, and assert a lien for a proportionate part upon each, and upon the ground appurtenant to each, respectively. Id. The claimant has the option of filing one lien “for the entire claim” that “embrac[es] the whole area so improved.” Id. Under this option, the lien filed is a blanket lien for the entire claim covering all of the property subject to the lien. Id. Alternatively, a lien claimant may elect to file separate liens, “apportion[ing] the demand between the several improvements, and assert[ing] a lien for a proportionate part upon each.” Id. “The purpose of giving lien claimants a blanket lien option, provided the work is performed under one general contract, is to relieve lien claimants of the burden of keeping separate accounts and filing separate liens for each lot.” Premier Bank, 785 N.W.2d at 760 (citing Johnson v. Salter, 70 Minn. 146, 151, 72 N.W. 974, 975 (1897)). “By electing to file In Premier Bank, we considered, among other things, whether a lien claimant that files a blanket lien under section O‘Neill argues, however, that Section (a) If the contribution is made under a contract with the owner and for an agreed price, the lien as against the owner shall be for the sum agreed upon. (b) In all other cases, it shall be for the reasonable value of the work done, and of the skill, material, and machinery furnished. Here, section Section More importantly, neither section We conclude that a lien claimant that makes improvements to property that falls within the scope of O‘Neill next argues that: (1) Ryan is judicially estopped from asserting a blanket lien in this lawsuit because Ryan‘s position in the Farr lawsuit bars it from arguing for a blanket lien; and (2) because the district court in the Farr lawsuit concluded that Ryan could not apportion the value of its work for individual lots prior to filing a lien, we may not revisit the issue. These arguments are without merit. Generally, the doctrine of judicial estoppel provides that when a party assumes a certain position in a legal proceeding, and succeeds in maintaining that position, he may not thereafter, simply because his interests have changed, assume a contrary position, especially if it prejudices the party who acquiesced in the position taken by him. See New Hampshire v. Maine, 532 U.S. 742, 749, 121 S.Ct. 1808, 149 L.Ed.2d 968 (2001). We have not It is not necessary to adopt or reject the doctrine of judicial estoppel because Ryan is not taking a position in the current lawsuit that is contrary to the position it took in the Farr lawsuit. In the Farr lawsuit, Ryan stated that it was unable to apportion the value of the improvements applicable to the individual lots prior to filing the mechanic‘s liens. In the current O‘Neill lawsuit, Ryan argues that MG was negligent in not advising Ryan that it could have filed a blanket lien under Moreover, O‘Neill‘s argument that the findings of fact and conclusions of law in the district court‘s order in the Farr lawsuit bar Ryan‘s present claim lacks merit. The district court concluded that Ryan, by its own admission, was unable to apportion the value of the improvements applicable to each lot. That conclusion does not resolve the question of whether Ryan could have filed a blanket lien and then spread the amount of the blanket lien on a pro-rata basis. In fact, the district court concluded that Ryan could have filed a blanket lien.5 Accordingly, we conclude that Ryan is not precluded from arguing that it could have filed a blanket lien in this case. Finally, O‘Neill argues that Ryan‘s 2010 settlement resolved its damages claim against MG and precludes its legal malpractice claim against O‘Neill. According to O‘Neill, Ryan compromised its claim for the full amount of its lien when it settled. O‘Neill urges us to not allow Ryan to settle and then sue its legal counsel because Ryan recovered the full value of its claims relating to its contracts with Farr. O‘Neill also argues that Ryan is misrepresenting the reason for its settlement, and that it is precluded from proceeding with its suit because such “settle-and-sue” strategies are contrary to our precedent. A settlement agreement is a contract, and we examine the language of a settlement agreement to determine the intent of the parties. Dykes v. Sukup Mfg. Co., 781 N.W.2d 578, 581-82 (Minn.2010); see also Ryan v. Ryan, 292 Minn. 52, 55, 193 N.W.2d 295, 297 (1971) (noting that a settlement is contractual in nature). We have not required specific language to validly release claims; rather, we examine the language on a case-by-case basis to assess an agreement‘s validity and effect. Dykes, 781 N.W.2d at 582. A settlement agreement may result in only a partial release of a party‘s claims. See, e.g., We have considered the legal principles involved when a client settles a lawsuit upon the advice of an attorney, and then sues the attorney for legal malpractice to recover against the attorney solely on the ground that a jury might have awarded the client more than the settlement. Rouse v. Dunkley & Bennett, P.A., 520 N.W.2d 406 (Minn.1994); Glenna v. Sullivan, 310 Minn. 162, 245 N.W.2d 869 (1976). In Glenna, the client brought an action against an attorney to recover damages for malpractice in negligently recommending that the client accept an allegedly inadequate settlement in a personal injury lawsuit. 310 Minn. at 163, 245 N.W.2d at 869. We concluded that the trial court properly directed a verdict in favor of the defendant after the plaintiff failed to produce any evidence to show that the defendant attorney‘s professional recommendation to accept a settlement offer was based on insufficient or inaccurate information. Id. at 169, 245 N.W.2d at 872. We reasoned that “[t]o allow a client who becomes dissatisfied with a settlement to recover against an attorney solely on the ground that a jury might have awarded them more than the settlement is unprecedented.” Id. at 170, 245 N.W.2d at 873. We noted that such a rule would allow clients to “second-guess [an] attorney on questions of professional judgment and trial tactics which arise every day in every lawsuit.” Id. at 170 n. 3, 245 N.W.2d at 873 n. 3 (quoting David O. Haughey, Lawyers’ Malpractice: A Comparative Appraisal, 48 Notre Dame Law. 888, 901 (1973)). In Rouse, a client brought suit for legal malpractice alleging that his lawyers were negligent in representing him in a lawsuit against his former employer. 520 N.W.2d at 407. In the absence of a fact-finder‘s determination as to whether the plaintiff would have succeeded in the underlying action, we held that to survive a summary judgment motion on causation in a legal malpractice action, the plaintiff must show that he would have survived summary judgment on the underlying, but foregone, claim. Id. at 409-10. In a footnote, we stated that “[w]e continue to disapprove of allowing a client who has become dissatisfied with a settlement to recover against an attorney solely on the ground that a jury might have awarded him more than the settlement.” Id. at 410 n. 6 (citing Glenna, 310 Minn. at 170, 245 N.W.2d at 873). We do not accept O‘Neill‘s invitation to read Glenna and Rouse to bar every malpractice claim arising out of settlement negotiations. Ryan‘s claim is not that O‘Neill‘s advice about settlement violated the applicable standard of care. Its claim is that MG breached the standard of care in the lien-filing process and that, in turn, O‘Neill breached the standard of care in pursuing Ryan‘s claim against MG. The court of appeals applied the appropriate summary judgment standard to the case-within-a-case in this dispute, namely Ryan‘s mechanic‘s lien claim against Farr.6 We therefore affirm the decision of the court of appeals as modified by this opinion, and remand to the district court for further proceedings consistent with this opinion. Affirmed as modified.I.
II.
A.
B.
III.
