History
  • No items yet
midpage
Ryan Contracting Company v. O'Neill & Murphy, LLP
2016 Minn. LEXIS 483
| Minn. | 2016
Read the full case

Background

  • Ryan Contracting performed street and utility improvements on the Kittredge Crossing development under contracts with developer Farr; Ryan did not serve pre-lien notice to Farr before work began.
  • After payment disputes, Ryan (through counsel Meagher & Geer) filed many mechanic’s lien statements covering 289 lots, seeking the contract amount per lot; some lots had already been sold to third parties when liens were filed.
  • Farr sued Ryan for breach; Ryan counterclaimed and separately sought foreclosure of the liens; the actions were consolidated and later settled: Ryan released liens against Farr-owned lots for $280,000 but reserved claims against third parties and counsel for alleged malpractice in lien filing.
  • Ryan sued its original counsel (MG) for malpractice; that suit was dismissed on procedural grounds. Ryan then sued subsequent counsel (O’Neill) for malpractice for their handling of the MG claim; O’Neill moved for summary judgment arguing lack of causation because Ryan’s liens were void.
  • The district court granted summary judgment for O’Neill on grounds including Ryan’s failure to give required pre-lien notice and inability to apportion lien amounts for non-Farr lots; the court of appeals reversed in part, concluding Ryan fell within a pre-lien notice exception and that material fact issues remained. This Court granted review.

Issues

Issue Plaintiff's Argument (Ryan) Defendant's Argument (O’Neill) Held
Whether pre-lien notice was required under Minn. Stat. §514.011 Ryan: Exception in §514.011 subd.4c(c) applies because land was nonresidential (vacant/development) when lien attached O’Neill: "in use" means active use; raw/vacant land had no use so exception doesn't apply and liens are void Held: "in use" covers active and passive uses at time lien attaches; vacant non-agricultural land satisfied subd.4c(c), so no pre-lien notice required
Whether Ryan could validly file a blanket lien and later pro rata apportion amounts under Minn. Stat. §514.09 Ryan: Could file a single blanket lien for the whole area and spread the contract amount pro rata even if unable to apportion at filing O’Neill: §514.03(1)(b) and inability to apportion preclude blanket lien enforcement on sold lots Held: §514.09 permits a blanket lien when work is under one general contract; §514.03(1)(a) (contract amount) and §514.09 are compatible—blanket lien and pro rata spread are allowed; apportionment can occur later
Whether Ryan is judicially estopped or precluded by prior Farr litigation findings from asserting the blanket-lien theory Ryan: Prior admission that apportionment was impossible is consistent with electing a blanket lien and later pro rata allocation O’Neill: Ryan’s earlier position that it couldn’t apportion bars a contrary position now Held: Not estopped—positions are not inconsistent; the Farr court even noted a blanket lien was available; prior findings do not foreclose the blanket-lien theory
Whether Ryan’s settlement with Farr bars the malpractice claim (settle-and-sue concern; causation) Ryan: Settlement reserved claims against third parties (including MG); causation and damages (whether Ryan would have recovered more) remain fact issues O’Neill: Settlement recovered full value; Ryan can’t settle and then sue counsel claiming greater recovery Held: Settlement language reserved third-party claims; Glenna/Rouse do not automatically bar malpractice claims arising from malpractice in lien-filing (but plaintiff must still prove the "case-within-a-case" causation standard)

Key Cases Cited

  • Premier Bank v. Becker Dev., LLC, 785 N.W.2d 753 (Minn. 2010) (blanket-lien enforcement as one lien pro rata across improved lots)
  • Riverview Muir Doran, LLC v. JADT Dev. Group, LLC, 790 N.W.2d 167 (Minn. 2010) (when a mechanic’s lien attaches; statutory mechanics of liens)
  • S.M. Hentges & Sons, Inc. v. Mensing, 777 N.W.2d 228 (Minn. 2010) (interpretation of pre-lien notice exceptions; canons of construction)
  • Rouse v. Dunkley & Bennett, P.A., 520 N.W.2d 406 (Minn. 1994) (legal-malpractice causation: plaintiff must show would have survived summary judgment on underlying claim)
  • Glenna v. Sullivan, 245 N.W.2d 869 (Minn. 1976) (limits on permitting malpractice recovery solely because a settlement may have been less than a jury award)
Read the full case

Case Details

Case Name: Ryan Contracting Company v. O'Neill & Murphy, LLP
Court Name: Supreme Court of Minnesota
Date Published: Aug 3, 2016
Citation: 2016 Minn. LEXIS 483
Docket Number: A14-1472
Court Abbreviation: Minn.