Premier Bank v. BECKER DEVELOPMENT, LLCPremier Bank v. BECKER DEVELOPMENT, LLC
OPINION
In this consolidated action, appellant Premier Bank brought a lawsuit to foreclose its development mortgage (development mortgage action), and another lawsuit to foreclose three construction mortgages (construction mortgage action) arising out of a residential development project. The general contractor, respondent Kuechle Underground, Inc. (Kuechle), filed a blanket mechanic’s lien under
The material facts are undisputed. River Bend is a residential housing development located on 40 acres in Becker, Minnesota. The project originally contemplated developing the property into approximately 150 lots in three phases.
In September 2005, Premier Bank еntered into a loan agreement with Becker Development, LLC (Becker), in which Premier Bank agreed to lend Becker $3.2 million for the purchase of the land and the cost of the site work required to develop the land. Becker executed a promissory note in favor of Premier Bank, and Becker and Boone Family Investments, LLC, jointly executed a mortgage to secure the loan. The mortgage was recorded in September 2005.
In February 2006, Premier Bank entered into three loan agreements with Boone Builders,' Inc., for the construction of three model homes, each on its own lot
In April 2006, Kuechle and Becker entered into a written contract in which Kuechle agreed to serve as the general contractor for the project, and perform the site work for the project consisting of initial grading, and street and sewer work. Previously, the parties had entered into an oral agreement that was consistent with the written contract and Kuechle had begun its first visible work on the project in October 2005.
In October 2006, Premier Bank and Becker, together with Boone Family Investments, entered into a loan modificаtion agreement that extended the maturity date of the promissory note. As part of that agreement, Premier Bank released its mortgages on the three model-home lots. The site work for the first phase of the project was completed, and the property improved consisted of 52 lots and 7 outlots. Becker paid Kuechle $817,108, which left an unpaid balance of $266,623. 2 In February 2007, Kuechle served and filed its mechanic’s lien statement for the unpаid amount against all 59 lots in the project.
Becker defaulted on its $3.2 million development loan, and Boone Builders defaulted on its three construction loans. Premier Bank then commenced two separate foreclosure actions. In the first action, Premier Bank sought to foreclose the $3.2 million development mortgage (development mortgage action). It alleged that Becker was in default, that its mortgage had first priority, and that it was entitled to foreclose and a decree of foreclosure. In the second action, Premier Bank sought to foreclose its three mortgages securing the three construction loans to Boone Builders for the construction of the three model homes (construction mortgage action). Premier Bank named Kuechle and other lien claimants as defendants in both actions. In each action, Kuechle asserted various claims and sought to foreclose its mechanic’s lien.
The district court consolidated the two actions, and Premier Bank and Kuechle brought cross-motions for summary judgment. In the development mortgage action, the court ruled, among other things, that Premier Bank’s mortgage was prior and superior to Kuechle’s lien. Also, the court denied Kuechle’s lien-foreclosure claim against the non-model-home lots because the bank’s mortgage was recorded before the first visiblе improvement to the project. Thus, the district court granted Premier Bank a decree of foreclosure in the development mortgage action and entered judgment against Becker for the full amount of the loan. In the construction mortgage action, the court granted Kuechle’s motion for summary judgment reasoning that Kuechle’s mechanic’s lien had priority over Premier Bank’s construction mortgages as to the three model-home lots relеased by the loan modification agreement. The court concluded that Kuechle could foreclose its entire lien claim against the three model-home lots because
In a published opinion the court of appeals reversed the district court and concluded, among other things, that under
I.
Premier Bank argues that the court of appeals erred in concluding that
A. Standard of Review
We review a decision to grant or deny summary judgment de novo.
Kratzer v. Welsh Cos.,
Minnesota’s mechanic’s lien statute allows a person or entity that contributes to the improvement of property through labor, skill, material, or machinery to place a lien against the property improved.
4
See
Kuechle argues that
In Minn.Stat. ch. 645 (2008), the legislature has provided the judiciary with canons of construction that govern the interpretation of the statutes of this state.
See
When the language of a statute is unclear or ambiguous, we will go beyond the specific language of the statute to determine the intent of the legislature.
We conclude that when the language of a mechanic’s lien statute is unclear аnd ambiguous, it should be liberally construed in favor of a mechanic’s lien claimant. This principle of statutory construction is predicated upon
B. Section 511.09
We turn to the language of the statute.
A lienholder who has contributed to the erection, alteration, removal, or repair of two or more buildings or other improvements situatеd upon or removed to one lot, or upon or to adjoining lots,under or pursuant to the purposes of one general contract with the owner, may file one statement for the entire claim, embracing the whole area so improved; or, if so electing, the lienholder may apportion the demand between the several improvements, and assert a lien for a proportionate part upon each, and upon the ground appurtenant to each, respectively.
Kuechle argues that
We agree that
Kuechle’s argument that a lien claimant is entitled to foreclose a blanket lien against less than all of the property subject to the hen improperly conflates the substance of a blanket lien and the manner of foreclosure. The substance of a blanket lien created under
We first examine the substance of a blanket lien. When a lien
We conclude that a blanket lien must be enforced as one lien against the whole area improved for the entire amount of the lien. Although Kuechle argues that
Kuechle urges us to apply equitable principles to protect the value of its work.
See Northland Pine Co. v. Melin Bros.,
Kuechle relies on
Reilly v. Williams,
Kuechle also argues that
In summary, when a lien claimant elects to file a blanket lien pursuant to
Reversed and remanded.
Notes
. Kuechle did not appeal the decree оf foreclosure in favor of Premier in either the development mortgage action or the construction mortgage action as to the 56 lots upon which Kuechle did not have priority. It is only the three model-home lots in the construction action that are at issue in this appeal.
. The original contract price was $931,037. Subsequently, Becker and Kuechle adjusted the contract price to $1,083,731 to cover additional work on the projeсt.
. Premier Bank attempts to bolster its argument by pointing to
. Minnesota’s mechanic’s lien statute was enacted in 1858. Act of Aug. 12, 1858, ch. 54, §§ 1-18, 1857-58 Minn. Laws 121, 121-26 (codified as amended at
. The predecessor to
. The total amount of improvements was $1,083,731 spread over 59 lots, for about $18,368 per lot, of which $817,108 was paid, leаving $266,623 unpaid, for about $4,519 per lot.
. We observe that the Uniform Construction Lien Act expressly allows a lien claimant to foreclose on less than the whole area improved by a blanket lien. It provides:
If a recorded notice of commencement covers more than one lot in a platted subdivision of record, a claimant may apportion the claimant's construction lien to the various lots covered by the notice of cоmmencement in any proportion the claimant chooses and states in the claimant’s recorded construction lien and may assign all of the lien to a particular lot.
Unif. Constr. Lien Act § 203(d) (1987) (emphasis added). The legislature has not amended
. Premier Bank relies on two cases to argue that a lien claimant must foreclose a blanket lien on a pro-rata basis.
See Albert & Harlow, Inc. v. Great N. Oil Co.,
283 Minn, at 253,
. A "certificate of sale” is the "document reflecting a successful bid for property at a judicial sale.” Black’s Law Dictionary 240 (8th ed. 1999).