RYAN CONTRACTING COMPANY, Appellant, v. O‘NEILL & MURPHY, LLP, et al., Respondents.
No. A14-1472.
Court of Appeals of Minnesota.
July 27, 2015.
867 N.W.2d 473
Kay Nord Hunt, Phillip A. Cole, Lommen Abdo, P.A., Minneapolis, MN, for respondents.
Considered and decided by WORKE, Presiding Judge; HUDSON, Judge; and SMITH, Judge.
OPINION
SMITH, Judge.
We reverse and remand the district court‘s grant of summary judgment to respondent because appellant raised genuine issues of material fact regarding whether its 2007 lien-foreclosure action would have been successful but-for the negligence of its attorney. In the interests of judicial economy, we affirm the district court‘s analysis in its alternative holding, challenged in respondents’ related appeal, that appellant raised genuine issues of material fact precluding summary judgment regarding whether its 2010 settlement agreement precluded its malpractice suit.
FACTS
In 2003 and 2004, appellant Ryan Contracting Company contracted with Farr Development Corporation and Darrel A. Farr Development Corporation (Farr) to perform utility and street improvements for the first two phases of a mixed-use development plan approved by the City of Otsego. The contracts for the work did not contain the pre-lien notice set out in
In July 2006, Ryan terminated the contracts due to Farr‘s nonpayment of amounts owed. Farr sued Ryan, alleging breach-of-contract and slander of title. Ryan retained Meagher & Geer, P.L.L.P. to record mechanic‘s liens for the work it had performed, valued at $356,073.23. Ryan had not provided a pre-lien notice before retaining Meagher & Geer. Meagher & Geer advised Ryan that no pre-lien notice was required because “Ryan‘s work arguably fell within the pre-lien notice exception for multiple dwellings ... allowing Ryan to record its liens within 120 days of furnishing its last item of work or materials.” Based on Ryan‘s reported last day of work on the project, Meagher & Geer believed that it had “a little over two weeks to record Ryan‘s mechanic[‘s] liens.” Based on its conclusion that “Ryan was unable to apportion the value of the improvements to any particular lot or outlot, given the nature of the street and utility improvements” it had made, and the fact that Farr no longer owned all the lots, Meagher & Geer “adopted a conservative approach and recorded a blanket lien in the amount of $356,073.23 on the parcels that Farr still owned, and also blanket liens in the same amount ... on each
The district court consolidated Farr‘s and Ryan‘s actions and considered their competing motions for summary judgment. Quoting
The district court acknowledged Ryan‘s argument that it could not apportion the value of its work to each lot. It opined, however, that “Ryan could have filed one lien for the entire amount claimed and listed all properties which would share a burden of the claim.” It concluded that
In December 2010, Ryan settled its remaining claims against Farr for $280,000. In the settlement agreement, Ryan released its liens and Farr released all its claims against Ryan. But Ryan reserved its claims against Meagher & Geer.
In March 2012, Ryan, represented by respondents Patrick H. O‘Neill and O‘Neill & Murphy, LLP (collectively O‘Neill), commenced a malpractice action against Meagher & Geer. O‘Neill failed to timely file an expert-disclosure affidavit as required by
In July 2013, Ryan commenced a malpractice action against O‘Neill. In July 2014, the district court granted O‘Neill‘s motion for summary judgment. It ruled that Ryan‘s “failure to file [pre-lien] notice as required by
The district court also based its grant of summary judgment on the alternative ground that Meagher & Geer was not at fault for Ryan‘s inability to record liens against the non-Farr-owned lots on the property. It determined that Ryan‘s inability to apportion the value of the improvements was caused by Ryan‘s choice of when to file the liens, rather than by Meagher & Geer‘s methods. In addition,
Although it granted summary judgment to O‘Neill for lack of causation, the district court also stated that, if it had not done so, it would have ruled that Ryan‘s decision to settle with Farr did not preclude Ryan from pursuing a malpractice action. The district court opined that “the reasonableness of the settlement would be a jury issue at trial if [Ryan] prevailed on the lien issues as a matter of law” because “the amount of damages suffered by [Ryan] as a result of [O‘Neill‘s] negligence, as well as the reasonableness of the settlement [with] Farr, are questions to be determined by the jury.” It also predicted that, “[i]f [Ryan] had prevailed in the Farr litigation, there would, in all likelihood, have been an award of reasonable costs and attorneys’ fees” and “if [Ryan‘s] malpractice case [against] Meagher [&] Geer had gone forward and [Ryan] prevailed, there is a probability that costs and attorneys’ fees would have been awarded, at some level.”
Ryan appealed the district court‘s grant of summary judgment to O‘Neill and, in a properly noticed related appeal, O‘Neill appealed the district court‘s dicta stating that Ryan‘s settlement with Farr did not preclude its pursuit of a malpractice action.
ISSUES
- Did the district court err by granting summary judgment to O‘Neill?
- Did the district court err by stating that Ryan‘s settlement agreement with Farr did not preclude it from suing for malpractice?
ANALYSIS
I.
Ryan challenges the district court‘s grant of summary judgment to O‘Neill, arguing that it erred by ruling that Ryan‘s own failure to give pre-lien notice obviated any harm from O‘Neill‘s negligence. We review a district court‘s grant of summary judgment de novo. Riverview Muir Doran, LLC v. JADT Dev. Grp., LLC, 790 N.W.2d 167, 170 (Minn. 2010). “In doing so, we determine whether the district court properly applied the law and whether there are genuine issues of material fact that preclude summary judgment.” Id.
To survive summary judgment in a legal-malpractice case, a plaintiff must show that, “but for defendant‘s conduct, the plaintiff would have been successful in the prosecution or defense of the action.” Jerry‘s Enters., Inc. v. Larkin, Hoffman, Daly & Lindgren, Ltd., 711 N.W.2d 811, 816 (Minn. 2006) (quotation omitted). This requires that we assess the merits of the case underlying a malpractice action to determine if there was a “win[n]able case-within-a-case.” Rouse v. Dunkley & Bennett, P.A., 520 N.W.2d 406, 409 (Minn. 1994) (quotation omitted). Here, the merits of Ryan‘s malpractice action against O‘Neill depend on the merits of its malpractice action against Meagher & Geer, which in turn depend on the potential enforceability of its liens against the non-Farr-owned lots in the development project.
The parties implicitly agree that O‘Neill‘s conduct was negligent. They dispute, however, whether O‘Neill‘s negligence caused damage to Ryan because they disagree about whether Ryan‘s liens on the non-Farr-owned properties were void as a matter of law before Meagher & Geer got involved in the matter and
A. Application of Minn.Stat. § 514.011, subd. 4c
Ryan argues that the district court erroneously concluded that Ryan was required to give pre-lien notice because the exception in
Every person who enters into a contract with the owner for the improvement of real property and who has contracted or will contract with any subcontractors or material suppliers to provide labor, skill or materials for the improvement shall include in any written contract with the owner the notice required in this subdivision and shall provide the owner with a copy of the written contract.
“Interpretation of a statute presents a question of law, which we review de novo.” Swenson v. Nickaboine, 793 N.W.2d 738, 741 (Minn. 2011). Our goal when interpreting statutory provisions is to ascertain and effectuate the intention of the legislature. If the meaning of a statute is unambiguous, we interpret the statute‘s text according to its plain language. If a statute is ambiguous, we apply other canons of construction to discern the legislature‘s intent. Brua v. Minn. Joint Underwriting Ass‘n, 778 N.W.2d 294, 300 (Minn. 2010) (quotation and citations omitted).
We must first determine whether
When interpreting an ambiguous statute, we seek to “ascertain and effectuate the intention of the legislature.”
Under these principles, Ryan has the better interpretation of the statute.
This interpretation of the statute also fits how subdivision 4c has implicitly been interpreted in our caselaw. In Christle v. Marberg, we held that a “property was wholly residential in nature” for purposes of
Similarly, in C. Kowalski, Inc. v. Davis, we held that “[p]re-lien notice is unnecessary where the area of an improvement exceeds 5,000 square feet of usable floor space and the improvement is intended wholly or partially to be used for nonresidential purposes.” 472 N.W.2d 872, 873 (Minn. App. 1991) (emphasis added), rev. denied (Minn. Sept. 13, 1991). We concluded that the contractor was exempt from the pre-lien notice requirement because the record indicated that operation of a business was the “planned” use of the improvement and “[t]he fact that the use of the room changed at a later date has little relevance to the issue of whether pre-lien notice should have been given.” Id. at 877. That a planned-for commercial use of a property never materializes does not mean that pre-lien notice is then required.
O‘Neill argues that the district court in the original lien-foreclosure action made a fact finding that the property was residential. This argument is unavailing. The portion of the district court‘s order that
B. Cause of Ryan‘s Inability to Record Liens on Non-Farr-Owned Properties
Ryan also challenges the district court‘s alternative basis for granting summary judgment, arguing that the district court misstated the law when it concluded that Meagher & Geer was not at fault for failing to file a blanket lien against the properties because such a blanket lien was not available as a matter of law. A party “who has contributed to ... improvements situated upon ... adjoining lots, under or pursuant to the purposes of one general contract with the owner, may file one statement for the entire claim, embracing the whole area so improved; or, if so electing, ... may apportion the demand between the several improvements.”
1. Blanket Lien
“[W]hen a lien claimant elects to file a blanket lien pursuant to section 514.09, one lien is created which encumbers the whole area improved.” Premier Bank, 785 N.W.2d at 762-63. O‘Neill argues that this option was not available to Meagher & Geer because “Ryan performed the work under two separate contracts and there was an issue as to whether the lots were all adjoining.” But the district court in the original lien-foreclosure matter found that “there are material issues of fact regarding whether the contracts constitute two separate contracts requiring separate liens, as opposed to one continuing contract.” Accordingly, the district court‘s grant of summary judgment to O‘Neill was erroneous to the degree that it rests on the contention that Meagher & Geer could not have filed a blanket lien because Ryan had two contracts with Farr instead of one.
O‘Neill‘s doubts about whether the lots were adjoining are similarly insufficient to support summary judgment.
All liens, as against the owner of the land, shall attach and take effect from the time the first item of material or
O‘Neill contends, however, that LaValle requires the opposite conclusion when read in concert with
The fact that Farr no longer owned some of the lots at the time that Ryan sought to file its liens is therefore irrelevant; the issue is whether the lots were sold before or after “the actual and visible beginning of the improvement on the ground.” See
2. Apportionment
O‘Neill also contends that it “is undisputed that Ryan was not able to apportion the value of the improvements to any particular lot.” O‘Neill cites the district court‘s finding in the lien-foreclosure matter that Ryan had conceded the impossibility of apportionment and the testimony of a non-Meagher & Geer attorney opining that the “apportionment of that lien was not a possibility.” But O‘Neill‘s argument highlights the factual dispute that precludes summary judgment. The district court in the lien-foreclosure matter noted Ryan‘s concession that apportionment was impossible in the context of discussing the refusal by Meagher & Geer attorneys of the district court‘s invitation to amend the liens. It did not find that apportionment was impossible; rather, it found that Ryan‘s attorneys had represented it as
O‘Neill also contends that apportionment was impossible as a matter of law. In accordance with the district court in the lien-foreclosure matter, O‘Neill argues that
II.
After granting summary judgment to O‘Neill, the district court went on to alternatively address whether Ryan would be entitled to a jury trial on damages if it had not lost the summary-judgment motion. We address this holding in the interests of judicial economy because it is likely to arise on remand. See In re Estate of Vittorio, 546 N.W.2d 751, 756 (Minn. App. 1996) (“Because this issue will arise on remand, we address it here in the interest of judicial economy.“).
O‘Neill argues that Ryan obtained the full value of all of its claims related to its contracts with Farr, discounted by the inherent risks of litigation, when it settled for $280,000, that its attempt to obtain more by pursuing a malpractice action is therefore barred, and that O‘Neill is entitled to summary judgment on that ground. The district court held, however, that the question of whether Ryan received the maximum reasonable value available to it in the settlement agreement was an issue of fact that precluded summary judgment for O‘Neill.
The district court‘s analysis is correct. Although O‘Neill cites the testimony of Ryan‘s attorney during the settlement period opining that Ryan obtained everything it could reasonably expect to recover on its claims against Farr, that opinion is not dispositive. A fact-finder could conclude that Ryan‘s settlement and its failure to recover the entire value of its claim were caused by Meagher & Geer‘s negligence. As the district court noted, a fact-finder could also award Ryan its costs and attorney‘s fees, and these were not included in the settlement agreement.
O‘Neill cites caselaw expressing disapproval towards “settle-and-sue” strategies where a client enters into a settlement agreement and then brings a malpractice action to attempt to recover more. See, e.g., Rouse, 520 N.W.2d at 410 n. 6; Glenna v. Sullivan, 310 Minn. 162, 170 n. 3, 245 N.W.2d 869, 873 n. 3 (1976). The supreme court‘s disapproving comments, however, relate to situations where a client settles a claim under the advice of an attorney and then sues that same attorney, alleging that, but for the attorney‘s advice to settle, the client could have received more. See Rouse, 520 N.W.2d at 410 n. 6 (limiting the supreme court‘s disapproval to situations where the client “thinks the [settlement] might have been more favorable had the attorney advised him differently“); Glenna, 310 Minn. at 170 n. 3, 245 N.W.2d at 873 n. 3 (disavowing the notion of “leaving to a jury the opportunity to second-guess the attorney on questions of professional judgment and trial tactics which arise every day in every lawsuit” (quotation omitted)). Ryan alleges that the settlement value was undermined by a prior attorney‘s negligent acts, so this case is easily distinguishable.
O‘Neill‘s argument that Premier Bank posed a risk to Ryan is correct, but only in a way that bolsters Ryan‘s argument rather than undermines it. In Premier Bank, the supreme court held that a blanket lien applying to an entire improvement results in a pro rata share applied to each lot in the area covered. 785 N.W.2d at 762-63. Thus, Premier Bank tends to support Ryan‘s argument that the loss of the liens on the non-Farr-owned lots that Ryan attributes to Meagher & Geer‘s negligence undermined the value of its claim, resulting in a settlement amount less than the full value of its claim. O‘Neill‘s allegation that Ryan‘s settlement attorney negotiated a settlement amount greater than what remained under Premier Bank may reflect positively on that attorney, but it only mitigates the loss that Ryan alleges it suffered due to Meagher & Geer‘s purported negligence. Because the amount Ryan obtained in the settlement did not reflect the full value of what it claims it was due but for Meagher & Geer‘s negligence, we conclude that summary judgment for O‘Neill on the grounds O‘Neill asserts in its related appeal was not appropriate, and we affirm the district court‘s dicta explaining as such.
DECISION
Genuine issues of material fact exist as to whether, but for Meagher & Geer‘s negligence, Ryan would have been able to enforce mechanic‘s liens against the non-Farr-owned properties in the development. We therefore reverse the district court‘s grant of summary judgment to O‘Neill and remand for further proceedings consistent with this opinion.
Genuine issues of material fact also exist as to whether, but for O‘Neill‘s negligence, Ryan would have been able to recover more than the $280,000 it received from its settlement with Farr. We therefore affirm the district court‘s dicta in the interests of judicial economy.
Affirmed in part, reversed in part, and remanded.
