Allen v. United StatesAllen v. United States
OPINION AND ORDER GRANTING DEFENDANT‘S MOTION TO DISMISS
On the evening of May 19, 2020, thousands of Midland County and Gladwin
Plaintiffs Daniel and Cathleen Allen are Midland County residents whose home was damaged by the flooding. On February 26, 2021, they filed a complaint against the United States of America (“the Government” or “the United States“) under the Federal Tort Claims Act (FTCA),
On June 25, 2021, the Government filed a motion to dismiss, arguing that this Court lacks jurisdiction because the Government is entitled to sovereign immunity. For the reasons stated hereafter, the Government‘s Motion to Dismiss will be granted, and this case will be dismissed.
I.
For nearly a century, four dams have sat along a 39-mile stretch of the Tittabawassee River. Starting with the most upstream, they are the Secord, Smallwood, Edenville, and Sanford Dams (the “Dams“).1
Originally constructed in 1924, the Edenville Dam consists of two earthen embankments spanning the Tittabawassee River and the Tobacco River. The water held by the Edenville Dam forms a 2,600-acre reservoir known as Wixom Lake.2 Like Sanford Lake, further downstream, Wixom Lake had become a popular recreation site before the Edenville Dam failed, with hundreds of homes and docks lining its shores.
FERC is an independent agency tasked with regulating the sale and transmission of electricity under the Federal Power Act (FPA),
operate the Dam safely before Boyce could purchase it. See
With the license secured, Boyce proceeded to generate electricity at the Edenville Dam for the better part of two decades. It was only a matter of months, however, before Boyce was the target of federal regulators.
Shortly after FERC approved the transfer, Boyce sent a letter to FERC conveying plans to build auxiliary spillways at the Dam. Boyce Hydro Power, LLC, 164 FERC ¶ 61,178 at P 5 (2018).
The need for additional spillway capacity was old news to FERC. In 1999, FERC sent a letter to Wolverine describing the need for more spillway capacity as its “primary concern.” Id. at P 4. The fear was that, without additional spillway capacity, the Edenville Dam could not withstand the “Probable Maximum Flood” (PMF), defined as “the flood that may be expected from the most severe combination of critical meteorologic and hydrologic conditions that is reasonably possible in the drainage basin under study.” Id. at P 3. The “[f]ailure of the Edenville Dam,” FERC later warned, “could result in the loss of human life and the destruction of property and infrastructure.” Boyce Hydro Power, LLC, 162 FERC ¶ 61,115 at P 3 (2018).
Despite assurances, Boyce‘s plan to increase the Dam‘s spillway capacity never materialized. On June 15, 2017, after over a decade of project delays, missed deadlines, and “patently deficient” construction proposals, FERC issued a compliance order directing Boyce to submit specific plans for the construction of auxiliary spillways. 164 FERC ¶ 61,178 at P 9; Boyce Hydro Power, LLC, 159 FERC ¶ 62,292 at P 2 (2017). When Boyce did not comply, FERC ordered it to stop generating power. Boyce Hydro Power, LLC, 161 FERC ¶ 62,119 at P 2 (2017).
Boyce appealed FERC‘s order to the Court of Appeals for the District of Columbia Circuit, which stayed the order and allowed Boyce to keep generating power. See In re Boyce Hydro Power, LLC, No. 17-1270 (D.C. Cir. Feb. 7, 2018). One week
Boyce did not request an evidentiary hearing or “dispute that it . . . failed to comply with the Commission‘s directives.” 164 FERC ¶ 61,178 at P 40. Instead, it argued that revocation of its licenses was not in the public interest because, inter alia, “revoking the license would not address
the Commission‘s primary concern regarding the inadequate spillway capacity.” Id. FERC disagreed, noting that once it revoked Boyce‘s license, regulatory jurisdiction over the Edenville Dam would transfer to the Michigan Department of Environmental Quality, which had its own spillway-capacity standards. See id. at P 55.
On September 10, 2018, FERC revoked Boyce‘s license for the Edenville Dam. Id. at P 1. As anticipated, the Michigan Department of Environmental Quality, now called the Michigan Department of Environment, Great Lakes, and Energy (“EGLE“), assumed jurisdiction over the Dam.6 ECF No. 1 at PageID.12. But Boyce continued to operate it.
In 2019, Boyce began negotiating the sale of the Edenville Dam to the Four Lakes Task Force (FLTF), a statutory entity formed under Part 307 of the Michigan Natural Resources and Environmental Protection Act,
In the months leading up to the Dam disaster, Boyce, the FLTF, and EGLE disputed the appropriate water level at Wixom Lake. Their dispute escalated into several lawsuits, the details of which are irrelevant here.8 Nonetheless, it bears noting that FERC was not a party to any of those lawsuits.
B.
During the week of May 18, 2020, The Tittabawassee watershed experienced unusually heavy rain, leading the National Weather Service and local authorities to warn of potential flash floods. On May 19, 2020, at about 5:30 PM EDT, the Tittabawassee
Plaintiffs own a home downstream from the Edenville Dam, along Sanford Lake. ECF No. 1 at PageID.21. The failure of the Edenville Dam, and consequent failure of the Sanford Dam, flooded their home, displacing Mrs. Allen‘s 86-year-old mother. Id. at PageID.22. To date, Plaintiffs have spent roughly $157,000 in home repairs and have lost about $150,000 in personal property. Id.
C.
Not long after the flooding subsided, dozens of lawsuits were filed in this Court and Michigan courts primarily targeting Boyce and related entities. On July 31, 2020, with thousands of potential creditors lining up, Boyce sought bankruptcy protection. On February 25, 2021, after
months of bankruptcy proceedings, Judge Daniel Opperman approved the Boyce entities’ bankruptcy plan. Most of the cases filed in this Court have since been voluntarily dismissed.
On February 26, 2021, Plaintiffs brought this action under the FTCA, claiming that FERC negligently entrusted Boyce with the Edenville Dam and then failed to monitor its safety. See ECF No. 1 at PageID.15-21. Plaintiffs seek to recover their losses and believe FERC should be held accountable.
On June 25, 2021, the Government filed a motion to dismiss under Rule 12(b)(1) for lack of subject-matter jurisdiction. ECF No. 15. The Government‘s Motion has since been fully briefed. ECF Nos. 20; 24.
II.
Plaintiffs bear the burden of proving subject-matter jurisdiction. See Moir v. Greater Cleveland Reg‘l Transit Auth., 895 F.2d 266, 269 (6th Cir. 1990). “Motions to dismiss for lack of subject matter jurisdiction fall into two general categories: facial attacks and factual attacks.” United States v. Ritchie, 15 F.3d 592, 598 (6th Cir. 1994). When the moving party challenges the complaint‘s sufficiency—a facial attack—“the court must take the material allegations of the petition as true and construed in the light most favorable to the nonmoving party.” Id. at 598. But when the moving party challenges the factual basis for jurisdiction, “no presumptive truthfulness applies to the factual allegations and the court is free to weigh the evidence and satisfy itself as to the existence of its power to hear the case.” Id. (internal citation omitted).
The Government argues, inter alia, that the Federal Power Act exempts it from liability for Plaintiffs’ damages. See ECF No. 15 at PageID.71-75. This argument is a facial attack. See Ritchie, 15 F.3d at 598. Therefore, this Court must take the well-pleaded factual allegations of the Complaint as true and construe them in the light most favorable to Plaintiffs. Id.; see also Hartman
v. Acton, 499 F. Supp. 3d 523, 528 (S.D. Ohio 2020) (“A facial attack on subject matter jurisdiction is reviewed under the same standard as a 12(b)(6) motion to dismiss.“).
III.
The analysis begins with a principle as old as the common law itself: “[T]he King or Crown, as the font of justice, is not subject to suit in its own courts.” Seminole Tribe of Fla. v. Florida, 517 U.S. 44, 103 (1996) (Souter, J., dissenting). This principle survives today under a more familiar name: sovereign immunity.9
The Supreme Court has long held that the “United States may not be sued without its consent and that the existence of consent is a prerequisite for jurisdiction.” United States v. Navajo Nation, 537 U.S. 488, 502 (2003); Hercules Inc. v. United States, 516 U.S. 417, 422-23 (1996); United States v. Mitchell, 463 U.S. 206, 212 (1983) (collecting cases); United States v. Sherwood, 312 U.S. 584, 586 (1941); United States v. Thompson, 98 U.S. 486, 489 (1878). Accordingly, “[s]uits brought against the United States [must be] dismissed unless a claimant can point to an
express waiver of sovereign immunity.” Jackson v. United States, 751 F.3d 712, 716 (6th Cir. 2014). To that end, “[a]ny waiver of sovereign immunity must be unequivocally expressed in statutory text and must be strictly construed, in terms of its scope, in favor of the sovereign.” Gaetano v. United States, 994 F.3d 501, 506 (6th Cir. 2021) (internal citations and quotation marks omitted).
Plaintiffs bring their claims under the FTCA, which “waives sovereign immunity for certain actions in tort by giving district courts exclusive jurisdiction over those types of civil actions.” Premo v. United States, 599 F.3d 540, 544 (6th Cir. 2010). A claim is actionable under the FTCA if it is:
[1] against the United States, [2] for money damages, . . . [3] for injury or loss of property, or personal injury or death [4] caused by the negligent or wrongful act or omission of any employee of the Government [5] while acting within the scope of his office or employment, [6] under circumstances where the United States, if a private person, would be liable to the claimant in accordance with the law of the place where the act or omission occurred.
Brownback v. King, 141 S. Ct. 740 (2021) (quoting
Plaintiffs allege that FERC violated at least two statutory duties imposed by the Federal Power Act: (1) the duty to determine whether Boyce had the ability to “manage, operate, and maintain the [Dams] safely“; and (2) the duty to “monitor and investigate [Boyce‘s] compliance with [the] license.” See ECF No. 1 at PageID.15-21 (quoting
The Government advances three arguments in defense: (1) the Federal Power Act expressly exempts the Government from liability for Plaintiffs’ damages;10 (2) FERC‘s conduct falls within the FTCA‘s discretionary exception;11 and (3) FERC was not negligent under Michigan law.12 This Court finds that the Federal Power Act exempts the Government from liability for Plaintiffs’ damages. For that reason, this Court declines to address whether the FTCA‘s discretionary exception applies or whether FERC‘s conduct would be actionable under Michigan law.
A.
The Government‘s sovereign-immunity defense turns on § 10(c) of the Federal Power Act (FPA), codified at
Until 1920, the licensing of hydroelectric facilities was divided among the Secretaries of Interior, War, and Agriculture, each of whom was tasked with issuing licenses for hydroelectric projects within his respective jurisdiction. See GEORGE CAMERON COGGINS & ROBERT L. GLICKSMAN, 4 PUB. NAT. RES. L. § 37:2 (2nd ed. 2021) (discussing history of federal hydropower regulation). With the 1920 passage of the FPA, Congress sought “to eliminate the inefficiency and confusion caused by the piecemeal, restrictive, negative approach to licensing prevailing under prior law.” Escondido Mut. Water Co. v. La Jolla, Rincon, San Pasqual, Pauma, & Pala Bands of Mission Indians, 466 U.S. 765, 773 (1984).
The FPA centralized the piecemeal licensing of prior decades by establishing one federal agency as gatekeeper for most hydropower developments: the Federal Power Commission, now known as FERC.13 See
operat[ing], or maintain[ing] any dam . . . across, along, or in any of the navigable waters of the United States,” for the “purpose of developing electric power,” unless authorized by a “permit or valid existing right-of-way granted prior to June 10, 1920, or a license granted pursuant to [the FPA]“); id. at
Accordingly, those seeking to construct, operate, or maintain a dam within federal jurisdiction must first apply for a license from FERC. The contents of those applications are strictly governed by federal law. As a general matter, applications must include “maps, plans, specifications, and estimates of cost,” and “[s]atisfactory evidence that the applicant has complied with the requirements of [state law].” See id. at
Once an application is submitted, FERC must then play gatekeeper. The Agency‘s basic task is to determine which applicant‘s proposal is “best adapted to serve the public interest.” See id. at
If FERC finds the applicant and proposal suitable, it will award a license of some duration up to 50 years. See id. at
The Government‘s sovereign-immunity argument relies on a statutorily imposed condition found in § 803(c). As explained in Section III.B., infra, the Government argues that because § 803(c) exempts the Government from liability for damages caused by the “construction, maintenance, or operation” of “project works,” the Government is exempt from liability for Plaintiffs’ damages. See ECF No. 15 at PageID.71-75. (quoting
B.
As always, the answer “begins with the text.” Ross v. Blake, 578 U.S. 632, 638 (2016). If “the statutory text is plain and unambiguous,” the inquiry ends, and the
“according to its terms.” See Carcieri v. Salazar, 555 U.S. 379, 387 (2009). “But if the text is unclear, [courts] may look at the ‘[t]he broader context’ of the statute and statutory purpose together to resolve the ambiguity.” United States ex rel. Felten v. William Beaumont Hosp., 993 F.3d 428, 431 (6th Cir. 2021) (quoting Robinson v. Shell Oil Co., 519 U.S. 337, 345-46 (1997)). Whether the language is “plain and unambiguous” depends on “the language itself, the specific context in which the language is used, and the broader context of the statute as a whole.” Id. (quoting Robinson, 519 U.S. at 340-41).
Section 803(c) provides:
That the licensee shall maintain the project works in a condition of repair adequate for the purposes of navigation and for the efficient operation of said works in the development and transmission of power, shall make all necessary renewals and replacements, shall establish and maintain adequate depreciation reserves for such purposes, shall so maintain and operate said works as not to impair navigation, and shall conform to such rules and regulations as the Commission may from time to time prescribe for the protection of life, health, and property. Each licensee hereunder shall be liable for all damages occasioned to the property of others by the construction, maintenance, or operation of the project works or of the works appurtenant or accessory thereto, constructed under the license, and in no event shall the United States be liable therefor.
Plaintiffs argue that the clause “constructed under the license” applies to both of its antecedents: “the project works” and “the works appurtenant or accessory thereto.” See ECF No. 20 at PageID.160-62. Thus, they conclude that the Government is exempt from damages only
when the project works were “constructed under the license.” By contrast, the Government reads “constructed under the license” as modifying only its immediate antecedent, “the works appurtenant or accessory thereto.” See ECF No. 24 at PageID.227. So under the Government‘s interpretation, § 803(c) exempts the Government from damages regardless of when the project works were constructed.
The question, then, is whether “constructed under the license” modifies both antecedents—including “the project works“—or only the immediate antecedent—“the works appurtenant or accessory thereto.”
The answer is critical because the Edenville Dam was not constructed under Boyce‘s license. Therefore, if “constructed under the license” modifies “the project works,” then § 803(c) does not exempt the Government from liability for Plaintiffs’ damages.
Recognizing that “the rules of grammar govern statutory interpretation,” see Nielsen v. Preap, 139 S. Ct. 954, 965 (2019) (internal quotation marks omitted), both sides marshal competing grammatical canons in support.
i.
First, the parties invoke two syntactic canons that purport to govern modifying clauses.
Plaintiffs invoke the so-called “series-qualifier canon.” See ECF No. 20 at PageID.161-62. The series-qualifier canon provides that “[w]hen there is a straightforward, parallel construction that involves all nouns or verbs in a series,’ a modifier at the end of the list ‘normally applies to the entire series.” Facebook, Inc. v. Duguid, 141 S. Ct. 1163, 1169 (2021) (quoting ANTONIN SCALIA & BRYAN A. GARNER, READING LAW: THE INTERPRETATION OF LEGAL TEXTS 147 (2012)). Plaintiffs contend that “constructed under the license” should be construed to modify both “the
project works” and “the works appurtenant or accessory thereto” because they are part of the same parallel construction.
The Government invokes the “rule of the last antecedent.” See ECF No. 24 at PageID.227-28. The last-antecedent rule provides that “a limiting clause or phrase . . . should ordinarily be read as modifying only the noun or phrase that it immediately follows.” United States v. Mateen, 764 F.3d 627, 631 (6th Cir. 2014) (quoting Barnhart v. Thomas, 540 U.S. 20, 21 (2003)); see also 2A NORMAN J. SINGER & J.D. SHAMBIE SINGER, SUTHERLAND STATUTORY CONSTRUCTION § 47:33 (7th ed. 2021) (“Referential and qualifying words and phrases, where no contrary intention appears, refer solely to the last antecedent.“). So, under the last-antecedent rule, “constructed under the license” would apply only to “the works appurtenant or accessory thereto.”
But the Government‘s interpretation has one significant weakness: the presence of a comma before the clause “constructed under the license.” “As several leading treatises explain, ‘[a] qualifying phrase separated from antecedents by a comma is evidence that the qualifier is supposed to apply to all the antecedents instead of only to the immediately preceding one.‘” Duguid, 141 S. Ct. at 1170 (quoting WILLIAM M. ESKRIDGE JR., INTERPRETING LAW: A PRIMER ON HOW TO READ STATUTES AND THE CONSTITUTION 67-68 (2016); then citing SINGER & SINGER, supra, § 47:33; and then citing SCALIA & GARNER, supra, at 161-62). Consequently, some courts have refused to limit a modifying clause to its immediate antecedent where a comma separated the two. See, e.g., Am. Int‘l Grp. v. Bank of Am. Corp., 712 F.3d 775, 782 (2d Cir. 2013) (interpreting
Despite Duguid and other authority, this Court declines to mechanically apply a general exception to an equally general rule. See Duguid, 141 S. Ct. at 1170 (“The rule of the last antecedent is context dependent.“); id. (“[A] comma is evidence that the qualifier is supposed to
apply to all the antecedents.” (emphasis added) (quoting ESKRIDGE, supra, at 67-68)). The Supreme Court has long warned that “a purported plain-meaning analysis based only on punctuation is necessarily incomplete and runs the risk of distorting a statute‘s true meaning.”17 See U.S. Nat‘l Bank of Or. v. Indep. Ins. Agents of Am., Inc., 508 U.S. 439, 454 (1993).
Indeed, canons of construction are “[not] absolute and can assuredly be overcome by other indicia of meaning.” Lockhart v. United States, 577 U.S. 347, 352 (2016) (quoting Barnhart, 540 U.S. at 26); see also Jama v. Immigr. & Customs Enf‘t, 543 U.S. 335, 355 (2005) (noting other indicia of meaning “have counseled [the Court] against invoking the rule [of the last antecedent] . . . at least as many times as [the Court] has relied on it“) (Souter, J., dissenting); United States v. Cmty. Health Sys., Inc., 666 F. App‘x 410, 418 (6th Cir. 2016) (finding “other indicia of meaning” rendered contract term ambiguous despite last-antecedent rule).
The Supreme Court‘s admonition seems especially salient here, given that Sutherland‘s comma rule would produce strange inconsistencies in the statute. For example, construing § 803(c)‘s liability rule as conditional (i.e., as dependent on whether the project works were
“constructed under the license“) seemingly undermines § 803(c)‘s safety rule, which unconditionally requires a licensee to “conform to . . . [rules] prescribe[d] for the protection of life, health, and property.”
Plaintiffs’ reading would also make § 803(c) an outlier within the statute. In other places where the FPA allocates some risk to the licensee, it provides no special rules for project works constructed under the license. See id. at
Accordingly, this Court declines to rely exclusively on either the last antecedent rule or the series-qualifier canon.
ii.
Next, the parties both invoke the “canon against surplusage,” which represents “the idea that ‘every word and every provision [in a statute] is to be given effect [and that n]one should needlessly be given an interpretation that causes it to duplicate another provision or to have no consequence.‘” Nielsen v. Preap, 139 S. Ct. 954, 969 (2019) (quoting SCALIA & GARNER, supra, at 174).
Under Plaintiffs’ interpretation, the relevant portion of § 803(c) could be rewritten as: “Each licensee hereunder shall be liable
The Government‘s argument is unpersuasive. “The canon against surplusage is not an absolute rule.” Marx v. Gen. Revenue Corp., 568 U.S. 371, 385 (2013). “While it is generally presumed that statutes do not contain surplusage, instances of surplusage are not unknown.” Id. (quoting Arlington Cent. Sch. Dist. Bd. of Educ. v. Murphy, 548 U.S. 291, 299 n.1 (2006)). Additionally, the canon is only helpful when “a competing interpretation gives effect to every clause and word of a statute.” Id. (quoting Microsoft Corp. v. I4I Ltd., 564 U.S. 91, 106 (2011)).
Here, neither interpretation would avoid the redundancy. Under the Government‘s interpretation, “construction” and “constructed under the license” would both modify “the works appurtenant or accessory thereto.” For that reason, even if Plaintiffs’ interpretation produces surplusage,18 the Government has not shown that such surplusage is avoidable. Cf. id. (declining to decide statute‘s meaning based on redundancy where neither party‘s interpretation “g[ave] effect to every word“).
Plaintiffs’ reliance on the canon against surplusage is similarly misplaced. Plaintiffs correctly note that the FPA “limits FERC‘s licensing authority to ‘issuing licenses . . . for the purpose of constructing, operating, and maintaining dams . . . or other project works.‘” ECF No. 20 at PageID.162-63 (quoting
Having considered the language in question, its specific context in the statute, and the canons of construction, see Felten, 993 F.3d at 431, this Court finds that § 803(c) is “subject to more than one reasonable interpretation.” See Donovan v. FirstCredit, Inc., 983 F.3d 246, 256 (6th Cir. 2020). Accordingly, this Court must rely on legislative history and other “extra-textual
C.
It is well-settled that the FPA‘s primary purpose was to promote the development of the nation‘s “long idle water power resources.” See First Iowa Hydro-Elec. Coop. v. Fed. Power Comm‘n, 328 U.S. 152, 171 (1946) (“[The legislative history] discloses both a vigorous determination of Congress to make progress with the development of the long idle water power
resources of the nation and a determination to avoid unconstitutional invasion of the jurisdiction of the states.“); COGGINS & GLICKSMAN, supra, § 37:2 (“The [FPA and FWPA], which were unapologetically promotional, were meant to encourage private investment in hydropower development on a basis consistent with the public interest.” (internal footnotes and quotation marks omitted)).
But redesigning the nation‘s hydropower scheme was no small feat. One of the many issues Congress faced was whether to craft a new system for determining liability for project-related damages. By enacting § 803(c), Congress ultimately decided to preserve the state-law system that was already in place. See DiLaura v. Power Auth. of N.Y., 786 F. Supp. 241, 248 (W.D.N.Y. 1991) (“Most courts that have considered the meaning of § 803(c) have similarly concluded that Congress intended simply to preserve any existing cause of action under state law.” (collecting cases)), aff‘d, 982 F.2d 73 (2d Cir. 1992).
That move made good practical and political sense. In the decades before the FPA, litigants determined liability for project-related damages with state-law actions in state courts. Congress had no interest in “oust[ing] the States of their traditional authority,” and presumably, the state courts had no purpose for, or notion of, federal tort liability. See id. Indeed, the FTCA was not enacted until 1946—over twenty years after Congress enacted § 803(c). Thus, in enacting § 803(c)—and thereby preserving the state-law system of liability—Congress simply meant to ensure that developers would remain subject to suit, and that the Government, though acting as licensor, would not be treated as guarantor.
The original version of § 803(c) arguably expressed that purpose better than the current version. The original version reported to the House of Representatives provided: “No license hereunder shall have the effect of relieving the licensee from liability for any injury or damage
occasioned by the construction, maintenance, or operation of said project works; and the United States shall in no event be liable therefor.” H.R. 715, 65th Cong. (2nd Sess. 1918). That original version was met with skepticism from some members of Congress, but not because it was too harsh on licensees.
During the floor debate, Representative William Graham of Illinois expressed concern that § 803(c) was “awkward[ly]” drafted and would offer little aid to injured property owners. See 56 CONG. REC. 9913 (1918). He relayed the story of a dam on the Mississippi River that caused “hundreds of thousands of dollars” in flooding damage in his district. Id. at 9914. Because the developer dammed the river without compensating those likely to be affected, nearby farmers were forced to spend years pursuing compensation in court. Id. Accordingly, Graham proposed amending the Bill so that “the licens[e] [would be] taken on condition that the damages be adjusted before [the licensee] start[s] work.” Id. at 9972. The House adopted his amendment. Id.
Had Graham‘s amendment become law, the Government would not be able to rely on § 803(c) as it does today. Graham‘s
“[P]rovid[ing] that licensee shall pay all damages caused to the property of others.” See id. (emphasis added).
The Conference Report is strong evidence of Congress‘s intent. See In re Credit Acceptance Corp. Sec. Litig., 50 F. Supp. 2d 662, 673 (E.D. Mich. 1999) (“The most reliable source for Congressional intent is the Conference Committee Report.” (citing Garcia v. United States, 469 U.S. 70, 76 (1984)). And because the Conference Report indicates that the “licensee shall pay all damages,” Congress likely intended for the Government‘s exemption to include all project works covered by the license, regardless of when they were constructed.
D.
Plaintiffs do not address Graham‘s amendment, the Conference Report, or any other part of § 803(c)‘s legislative history. Instead, they contend that the Government‘s interpretation is inconsistent with the FPA‘s general purpose.
First, Plaintiffs argue that Congress did not intend for § 803(c) to be “a general-purpose water-power immunity for the federal government.” See ECF No. 20 at PageID.165. Plaintiffs cite Beaunit Corp. v. Ala. Power Co., in which a manufacturer sued a licensee for decreasing the waterflow in a nearby river. 370 F. Supp. 1044 (N.D. Ala. 1973). In Beaunit Corp., the manufacturer argued that § 803(c) created a private cause of action against licensees who damaged nearby properties. Id. at 1050. The Beaunit court disagreed, explaining that it was not “[Congress‘s] intent to create a new cause of action sounding in tort, but rather to negate the general proposition that the doing properly of that which the law itself expressly authorizes is not actionable as a nuisance.” Id. at 1051 (citing 66 C.J.S. Nuisances § 17 (1973)).
Plaintiffs’ reliance on Beaunit is therefore misplaced. Although parts of the opinion are difficult to parse, Beaunit seems to hold only that Congress enacted § 803(c) to clarify that
licensees were not immune from state-law actions because of their federal licenses. More can and should be said about § 803(c) today, but nothing in Beaunit forecloses the Government‘s interpretation—which cannot be fairly characterized as advocating for a “general-purpose water-power immunity.” See ECF No. 20 at PageID.165.
Plaintiffs next argue that the Government‘s construction of § 803(c) is inconsistent with Congress‘s desire to incentivize water-power development. Plaintiffs begin by correctly noting that Congress wanted the FPA to “incentive[ize] . . . new water-power development” and to “ensur[e] accountability in that development.” See ECF No. 20 at PageID.165 (emphasis in original). Plaintiffs then, without a running start, leap to conclude that “[the immunity provisions of [§ 803(c)] only apply where the dam [was] originally constructed under a license.” Id. Although their reasoning is
First, Plaintiffs misunderstand how liability exposure affects private development. All things being equal, a rational developer would prefer to operate the project with the least exposure to liability. Accordingly, requiring licensees to accept liability for damages only when the project works are “constructed under the license” would discourage new development because it would make already constructed developments more attractive by comparison.19 In other words, under Plaintiffs’ construction, § 803(c) would have the opposite of Congress‘s intended effect. This Court will not “lightly conclude that Congress enacted a self-defeating statute.” See Quarles v.
United States, 139 S. Ct. 1872 (2019) (rejecting defendant‘s interpretation of the Armed Career Criminal Act because it would “defeat Congress‘s stated objective“).
Similarly, Plaintiffs misunderstand why developers were averse to hydropower before the FPA. The problem was not an oversized risk of liability but the dizzying process for obtaining a license. Before the FPA, developers were forced to navigate an array of approval requirements just to obtain a license that, in many cases, offered an uncertain tenure. See California ex rel. State Water Res. Control Bd. v. FERC, 966 F.2d 1541, 1554 (9th Cir. 1992) (discussing history of FPA). Indeed, Congress issued perpetual licenses “on a case-by-case basis” only, which “hindered the development of a strong hydroelectric power industry.” See COGGINS & GLICKSMAN, supra, § 37:2. Congress‘s solution was to replace that “piecemeal” and “inefficient” system with a comprehensive scheme that streamlined licensing and offered license durations of up to 50 years. See
Section 803(c) played a different role from the sections intended to streamline licensing. As indicated, Congress enacted § 803(c) to preserve the state-law liability system and to clarify that licensees—not the Government—would “pay all damages caused to the property of others.” See H.R. REP. NO. 65-1147 (1919) (Conf. Rep.). Simply put, there is no historical basis for believing that Congress either enacted § 803(c) to incentivize new development or wanted special liability rules for project works “constructed under the license.”
But the question remains: Why would Congress include “constructed under the license” if it simply intended to assign liability to the licensee? Although the legislative record is inconclusive, the answer is likely grounded in the practical realities of hydropower development.
Undoubtedly, Congress was aware that in some cases the licensee would have to acquire the property necessary for the project after obtaining the license. See
Absent any controlling authority to the contrary, this Court must do the same. Because § 803(c) exempts the Government from liability for Plaintiffs’ damages, this case will be dismissed for lack of subject-matter jurisdiction.
IV.
Accordingly, it is ORDERED that Defendant‘s Motion to Dismiss, ECF No. 15, is GRANTED.
Further, it is ORDERED that Plaintiffs’ Complaint, ECF No. 1, is DISMISSED.
Dated: November 16, 2021
s/Thomas L. Ludington
THOMAS L. LUDINGTON
United States District Judge
Notes
Wolverine Power Corp. Synex Energy Res., Ltd. Synex Mich., LLC, 107 FERC ¶ 62,266, at p. 64,498 n.4 (2004) (emphasis added). To date, FERC has offered no explanation for the apparent contradiction.While it appears that Synex Energy lawfully obtained (without prior Commission approval) project property and perhaps the project licenses in foreclosure proceedings, it also appears that Synex Energy‘s assignment of title to project property and its asserted sale of licenses to Synex Michigan required prior Commission approval. However, the record shows that the parties failed to obtain such approvals inadvertently.