SCHNEIDER ELECTRIC BUILDINGS CRITICAL SYSTEMS, INC. v. WESTERN SURETY COMPANY
No. 96, Sept. Term, 2016
Court of Appeals of Maryland.
July 28, 2017
165 A.3d 485
III
Conclusion
We hold that a contractual provision that purports to shorten the statutorily-prescribed time for bringing a civil action is enforceable only if: (1) there is no statute to the contrary; (2) the provision is not the product of fraud, duress, misrepresentation, or the like; and (3) the provision is reasonable in light of all the circumstances. In this case, the trial court must assess, in the first instance, whether the criteria for enforcement of the provision are met and, in particular, whether the provision is reasonable.
JUDGMENT OF THE CIRCUIT COURT FOR ANNE ARUNDEL COUNTY VACATED AND CASE REMANDED TO THAT COURT FOR FURTHER PROCEEDINGS CONSISTENT WITH THIS OPINION. COSTS TO BE PAID BY RESPONDENT.
Argued by Patrick J. Madigan (Patrick M. Pike, Pike & Gilliss, LLC, Towson, MD), on brief, for Respondent.
Argued before Barbera, C.J., Greene, Adkins, McDonald, Watts, Hotten, Getty, JJ.
Adkins, J.
This case asks us to define the scope of a mandatory arbitration clause incorporated by reference into a web of construction contracts. It presents the question of whether a surety who issued a performance bond on a subcontract is bound by that contract‘s arbitration clause when the surety is jointly and severally liable for the “performance of” the subcontract and the entire subcontract is incorporated into the bond by reference.
FACTS AND LEGAL PROCEEDINGS
In May 2009, Petitioner Schneider Electric Buildings Critical Systems, Inc. (“Schneider“) entered into a contract with National Control Services, Inc. (“NCS“), an electrical subcontractor, for the “labor, material, equipment and services necessary to perform work in connection with construction projects, from time to time” (“Master Subcontract Agreement“).1 The Master Subcontract Agreement included the following mandatory arbitration clause, which provided that disputes between the contractor and subcontractor would be subject to arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association:
19.2 Disputes between Contractor and Subcontractor. In the
event that the provisions for dispute resolution between the Contractor and its customer under the Contractor‘s Contract do not permit consolidation or joinder with disputes of third parties, such as the Subcontractor, or in the absence of a disputes resolution procedure in such Contract or if such dispute is only between the Contractor and Subcontractor, except for claims which have been waived by the making or acceptance of final payment and except for intellectual property issues which shall be settle[d] by litigation, then the parties shall resolve the dispute following procedures set forth below. 19.2.1 Any dispute or controversy between the parties shall be submitted by one party to the other in writing and the parties shall attempt to resolve the dispute through good faith negotiations and settlement.
19.2.2 If the parties are unable to resolve the dispute through good faith negotiations and settlement, then the dispute shall be submitted to binding arbitration within thirty (30) days after demand for arbitration and conducted in the locale of the project before a single arbitrator, unless the parties mutually agree otherwise ....
That October, Schneider was hired by Clark Construction Group, LLC, to help construct a medical research facility at Aberdeen Proving Ground in Harford County, Maryland. Pursuant to the Master Subcontract Agreement, Schneider entered into a subcontract with NCS to perform work on that project (“NCS Subcontract“). The NCS Subcontract incorporated the entire Master Subcontract Agreement, including the arbitration clause, by reference. It also required NCS to furnish a performance bond for 100 percent of the NCS Subcontract value, which was $2,050,000. NCS obtained a performance bond (“the Bond“) from Respondent Western Surety Company (“Western“). Referring to the NCS Subcontract, the Bond stated that the “Contractor and the Surety, jointly and severally, bind themselves ... to the Owner for the performance of the Construction Contract, which is incorporated herein by reference.” By incorporating the NCS Subcontract, the Bond also incorporated the Master Subcontract Agreement, including the arbitration clause.
In April 2014, Western filed a petition in the Circuit Court for Howard County seeking a stay of arbitration pursuant to
In the Circuit Court for Harford County, Western filed a motion for partial summary judgment asking the court to stay the arbitration proceedings. In a memorandum opinion, the Circuit Court granted partial summary judgment in favor of Western, holding that it could not be compelled to participate in the pending arbitration proceedings between Schneider and NCS. Western Sur. Co. v. Schneider Elec. Bldgs. Critical Sys., Inc., No. 12-C-14-2396, slip op. at 12 (Cir. Ct. Harford Cty.
The Court of Special Appeals affirmed. It held that “the ‘joint and several’ obligation clause in ... the performance bond does not evince Western Surety‘s assent to be bound by the arbitration clause in the incorporated-by-reference chain of documents.” Schneider Elec. Bldgs. Critical Sys., Inc. v. Western Sur. Co., 231 Md.App. 27, 46, 149 A.3d 778 (2016). Additionally, the intermediate appellate court held that Western “is not compelled to arbitrate any dispute involving the performance bond it issued[] simply because that bond incorporated by reference an agreement, to which it was not a party, containing a mandatory arbitration clause.” Id. at 49, 149 A.3d 778. Schneider filed a petition for a writ of certiorari, which we granted.
Schneider presented the following question for our review:
[Is] the surety on a performance bond issued for a subcontract [] bound by an arbitration clause set forth in the subcontract where the bond expressly incorporates, and states that the surety is jointly and severally bound for the performance of[] the subcontract?
Because we answer no to this question, we affirm the decision of the Court of Special Appeals.
STANDARD OF REVIEW
Schneider appeals from the Circuit Court‘s grant of partial summary judgment. A court may grant summary judgment in favor of the moving party “if the motion and response show that there is no genuine dispute as to any material fact
DISCUSSION
Schneider contends that Western is bound by the NCS Subcontract‘s arbitration clause because (1) Western is jointly and severally liable “for the performance of the Construction Contract,” which includes the arbitration clause, and (2) the arbitration clause is incorporated into the Bond by reference. Additionally, it argues that the presumption in favor of arbitration under the Federal Arbitration Act (“FAA“) requires us to compel Western to arbitrate. Western argues that the arbitration clause is not part of the “performance of the Construction Contract” and that its incorporation by reference does not bind Western. It contends that we should apply state contract law to interpret its obligations under the Bond. Without an enforceable arbitration clause between the parties, Western argues, the FAA is inapplicable. We first address the parties’ contentions regarding the FAA.
The Effect of the Federal Arbitration Act
Schneider argues that the FAA governs this case because the Bond “contains an agreement in writing providing for arbitration“—it incorporates the NCS Subcontract‘s arbitration clause by reference—and “evidences a transaction involving interstate commerce.” Therefore, Schneider contends, we must apply a presumption in favor of arbitration. Western urges us to apply state contract law to determine whether an agreement to arbitrate exists between the parties.
Maryland Contract Law
In Maryland, the “fundamental rule in the construction and interpretation of contracts is that the intention of the parties as expressed in the language of the contract controls the analysis.” O‘Brien & Gere Engs., Inc. v. City of Salisbury, 447 Md. 394, 421, 135 A.3d 473 (2016) (citation omitted). Accordingly, if “the language of the contract is unambiguous, we give effect to its plain meaning and do not delve into what the parties may have subjectively intended.” Rourke v. Amchem Prod., Inc., 384 Md. 329, 354, 863 A.2d 926 (2004) (citation omitted). As to arbitration clauses in particular, we have explained, “Arbitration is a process whereby parties voluntarily agree to substitute a private tribunal for the public tribunal otherwise available to them.” Hartford Accident & Indem. Co. v. Scarlett Harbor Assocs., 346 Md. 122, 127, 695 A.2d 153 (1997) (emphasis in original) (alterations, internal quotation marks, and citations omitted). Accordingly, an arbitration clause “cannot impose obligations on persons who are not a party to it and do not agree to its terms.” Id.
Here, we must interpret the Bond, which incorporates the NCS Subcontract by reference. The NCS Subcontract, in turn, incorporates the Master Subcontract Agreement. To determine the plain meaning of the Bond, we
The Bond‘s first paragraph provides: “The Contractor and the Surety, jointly and severally, bind themselves ... to the Owner for the performance of the Construction Contract, which is incorporated herein by reference.” Schneider argues that Western‘s liability for the “performance of the Construction Contract” makes Western “as much a party to the NCS Subcontract as NCS itself.” Thus, Schneider claims, Western is bound by the arbitration clause. Western responds that its obligations under the Bond are only triggered if NCS fails to perform—it is not interchangeable with NCS in the NCS Subcontract. Accordingly, it contends, it is not bound by the arbitration clause.
We look at this paragraph in the context of the entire contract. The second paragraph provides: “If [NCS] performs the Construction Contract, [Western] and [NCS] shall have no obligation under this Bond ....” (Emphasis added.) And the third paragraph states:
If there is no [default by Schneider], [Western‘s] obligation under this Bond shall arise after ... [Schneider] has notified [NCS] and [Western] ... that [Schneider] is considering declaring a [default by NCS] and has requested and attempted to arrange a conference with [NCS] and [Western] ... to discuss methods of performing the Construction Contract. If [Schneider], [NCS,] and [Western] agree, [NCS] shall be allowed a reasonable time to perform the Construction Contract ....
(Emphasis added.) As the Court of Special Appeals aptly explained, the use of the term “perform” in these subsequent provisions “refers to the performance of the work [NCS] agreed to complete and not to every contractual provision in
Next, Schneider argues that Western is bound by the arbitration clause because it is incorporated by reference into the Bond. The relevant portions of the arbitration clause provide:
19.2 Disputes between Contractor and Subcontractor. In the event that the provisions for dispute resolution between the Contractor and its customer under the Contractor‘s Contract do not permit consolidation or joinder with disputes of third parties, such as the Subcontractor, or in the absence of a disputes resolution procedure in such Contract, or if such dispute is only between the Contractor and Subcontractor, then the parties shall resolve the dispute following procedures set forth below.
* * *
19.2.2 If the parties are unable to resolve the dispute through good faith negotiations and settlement, then the dispute shall be submitted to binding arbitration within thirty (30) days after demand for arbitration ....
(Emphasis added.) The language within the clause unambiguously limits its application to disputes between Schneider and NCS. This section of the Master Subcontract Agreement is explicitly labeled “Disputes between Contractor and Subcontractor.” The clause specifically uses the terms “Contractor,” “Subcontractor,” and “parties.” An earlier provision within the contract defines “Contractor” as Schneider and “Subcontractor” as NCS. “Parties” is defined as “Contractor” and “Subcontractor.” Moreover, the term “surety” is used in other provisions of the Master Subcontract Agreement—“surety” and “Subcontractor” were clearly not intended to be interchangeable.
Recently, the U.S. District Court for the District of Columbia held that Western was not obliged to arbitrate its dispute with an owner under a similar arbitration clause incorporated in a performance bond by reference. In Western Surety Co. v. U.S. Engineering Co., 211 F.Supp.3d 302 (D.D.C. 2016), the
Furthermore, a clause within the Bond providing for legal remedy demonstrates the parties’ intent to litigate disputes arising under the Bond, not arbitrate them. The Bond‘s court action clause provides:
Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first.
(Emphasis added.) Schneider claims that we can read this clause in harmony with the arbitration clause. It contends that the Bond, with the arbitration clause incorporated, gives Schneider the option of bringing claims through arbitration or through the courts.
But the language of the arbitration clause belies Schneider‘s claim. It states that if “the parties” are unable to resolve their dispute through negotiations, “the dispute shall be submitted to binding arbitration within thirty (30) days after demand for arbitration ... unless the parties mutually agree otherwise.” (Emphasis added.) Western was a surety, not a party. If the arbitration clause binds Western, as Schneider contends, neither Western nor Schneider could unilaterally decide to liti-
We find support for our holding in Liberty Mutual Insurance Co. v. Mandaree Public School District # 36, 503 F.3d 709 (8th Cir. 2007), in which the U.S. Court of Appeals for the Eighth Circuit held that a surety was not bound by an arbitration clause that governed disputes between the School District and its contractor.5 Id. at 711. Like the case at hand, the arbitration clause “provided that disputes between [the School District] and ... [the] contractor would be resolved by arbitration.” Id. at 710. The surety‘s performance bond “incorporated the construction contract by reference” and included a court action clause identical to the one at issue here. Id. The Eighth Circuit reasoned that the court action clause “contemp-
CONCLUSION
We hold that the arbitration clause, as incorporated by reference into the Bond, does not compel Western to arbitrate its dispute with Schneider. Thus, the trial court properly granted partial summary judgment as to this issue. Accordingly, we affirm the Court of Special Appeals.
JUDGMENT OF THE COURT OF SPECIAL APPEALS AFFIRMED. COSTS TO BE PAID BY PETITIONER.
Notes
(a) Petition to stay.—If a party denies existence of the arbitration agreement, he may petition a court to stay commenced or threatened arbitration proceedings.
(b) Filing of petition.—(1) A petition to stay arbitration shall be filed with the court where a petition to order arbitration has been filed.
(2) If a petition for order to arbitrate has not been filed, the petition to stay arbitration may be filed in any court subject to venue provisions of Title 6 of this article.
(c) Determination of existence of arbitration agreement.—If the court determines that existence of the arbitration agreement is in substantial and bona fide dispute, it shall try this issue promptly and order a stay if it finds for the petitioner. If the court finds for the adverse party, it shall order the parties to proceed with arbitration.
