This is аn appeal from a district court ruling which dissolved a temporary restraining order and directed that the action proceed to arbitration. For the reasons set forth below, we affirm the decision of the Honorable Robert Taylor of the United States District Court for the Eastern District of Tennessee.
The apрellee, the Haskell Company, entered into an agreement with Mitchell Homes to build a shopping center. Appel *275 lee Haskell was the prime contractor, pursuant to the contract with Mitchell. Haskell subcontracted a portion of the work out to appellee, Rogersville Co. Under the subcontract, Rogersville agreed to install the parking lot for the shopping center. On August 12, 1980, Rogersville obtained a performance bond through appellant, Exchange Mutual Insurance Company. Exchange Mutual, as surety, issued the bond in favor of Haskell, conditioned upon Rogersville performing its obligations under the subcontrаct. The bond provided that Haskell would be indemnified for any loss it might sustain in the event Rogersville did not perform its obligations under the subcontract.
A dispute arose and Haskell made a claim under the performance bond. Pursuant to its claim, Haskell initiated arbitration proceedings against Exchange Mutual. Exchange Mutual filed а motion to restrain arbitration, which was granted by the Chancery Court. A hearing was held in United States District Court on August 29, 1983 wherein the trial judge dissolved the temporary restraining order and ordered the action to proceed to arbitration. We are in agreement with the district court’s order.
The Supreme Court has recently stated thаt the courts should give broad deference to the enforcement of arbitration clauses.
Although our holding in [Prima Paint Corp. v. Flood & Conklin Mfg. Corp.,388 U.S. 395 ,87 S.Ct. 1801 ,18 L.Ed.2d 1270 (1967] extended only to the specific issue presented, the Cоurts of Appeals have since consistently concluded that questions of arbitrability must be addressed with a healthy regard for the federal policy forming arbitratiоn. We agree. The Arbitration Act establishes that as a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in fаvor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or alike dеfense to arbitrability.
Moses H. Cone Memorial Hospital v. Mercury Construction Corp.,
The district cburt found appellant’s duty to arbitrate arose from a series of contract agreements between the parties. We agree.
The original arbitration contract between appellee Haskell and the оwner of the project, Mitchell Homes provided:
All claims, disputes and other matters in question arising out of, or relating to this contract or the breach thereof, except for claims which have been waived by the making or acceptance of final payment as provided by subparagraphs 8.6.5 and 8.6.6 and which cannot be settled by negotiation between the Contractor and the Owner, shall be decided in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. The award rendered by the arbitration shall be final, and judgement [sic] may be entered upon it in accordance with appliсable laws to any court having jurisdiction thereof. (emphasis supplied) (J.A. at 37).
The subcontract between the subcontractor Rogersville and the prime contractor Haskell stated that:
Subcontractor hereby assumes the same obligations and responsibilities with respect to his performance under this Subcontract, that Contractor assumes towards Owner with respect to his performance on the General Contract. If the General Contract, which is hereby incorрorated by reference, fails or conflicts with any provision of this Subcontract, or any modification hereof, this Subcontract shall govern. (J.A. at 39).
Finally, the pеrformance bond between Rogersville and Exchange Mutual stated:
KNOW ALL MEN BY THESE PRESENTS, That Rogersville Paving Company, Inc., ..., as principal and EXCHANGE MUTUAL INSURANCE COMPANY ..., as Surety, are held and firmly bound unto the Hаskell Company *276 ..., in the sum of One Hundred Eight Thousand and No/100 ($108,000) Dollars ..., jointly and severally, firmly by these presents.
WHEREAS, The Haskeil Company has been awarded a contract (hereinafter called the “Prime Contract”), by THE MITCHELL COMPANY, ... for ROCK-WOOD SHOPPING CENTER, and; WHEREAS, the principal has entered into a written Subcontract with The Haskell Company, dated 10/8/79 to perform as Subcontractor, certain portions of the work in connection with said Prime Contract, consisting of ... as stated in Subcontract No. 4234-06 ... which Subcontract is hereby referred to and made a part hereof. (J.A. at 42).
Although Exchange Mutual was not a signatory to the primary construction contract, the performance bond incоrporated by reference the terms of the underlying subcontract. The subcontract, in turn, incorporated by reference the terms of the primary construсtion contract which imposed an obligation to submit all unresolved disputes to arbitration.
In J
& S Construction Co. v. Travelers Indemnity Co.,
Although in the case at bar, the surety is not the party seeking arbitration, the same principles apply. Exchange Mutual contends that it cannot be compelled to arbitrate because it was not a signatory to the general contract. Yet as the court said in the Travelers case, a party does not have to be a signatory to the contract when the contract is specifically incorporatеd by reference in the surety bond. Here, the performance bond specifically referred to and incorporated the subcontract. The subcontract provides that the same obligations and responsibilities apply in the subcontract as apply in the general contract. And, finally, the general cоntract provides that there is a duty to arbitrate. Thus, the performance bond incorporates by reference the subcontract, the subcontract incorporates by reference the general contract and hence the duty to arbitrate.
Exchange Mutual places reliance upon a district court opinion in
Windowmaster v. B.G. Danis Co.,
Accordingly, the opinion and order of the Honorable Robert Taylor of the United States District Court for the Eastern District of Tennessee, is affirmed.
