History
  • No items yet
midpage
Schneider Electric Buildings Critical System, Inc. v. Western Surety Co.
165 A.3d 485
| Md. | 2017
Read the full case

Background

  • Schneider (subcontractor’s obligee on the project) contracted with NCS (subcontractor) under a Master Subcontract Agreement that included a mandatory arbitration clause for disputes between Contractor and Subcontractor.
  • NCS executed a project-specific subcontract incorporating the Master Subcontract Agreement and its arbitration clause, and obtained a 100% performance bond from Western Surety (the Bond), which incorporated the subcontract by reference.
  • NCS defaulted and abandoned the job; Schneider terminated the subcontract and claimed approximately $1.5M in damages and demanded arbitration against NCS, later adding Western.
  • Western sought a court stay of arbitration and declaratory relief that it was not bound to arbitrate; the trial court granted partial summary judgment for Western, holding the surety need not arbitrate.
  • The Court of Special Appeals affirmed; the Court of Appeals of Maryland granted certiorari and affirmed, holding the Bond did not bind Western to the subcontract’s arbitration clause.

Issues

Issue Schneider’s Argument Western’s Argument Held
Whether the surety’s promise to be “jointly and severally” liable for the “performance of the Construction Contract” makes it a party to the subcontract’s arbitration clause The phrase makes Western as much a party as NCS, so Western assented to arbitrate The bond only obligates Western if NCS defaults on performance of work; it does not make Western interchangeable with NCS or a party to the arbitration clause Held: No — context shows “performance” refers to work performance, not assent to all contractual provisions, so Western is not bound by the arbitration clause
Whether incorporation of the subcontract by reference in the Bond binds Western to the subcontract’s arbitration clause Incorporation by reference imports the arbitration clause into the Bond and triggers the FAA presumption in favor of arbitration Incorporation insured NCS’s promise to arbitrate but did not make Western a party to that promise; state contract law determines assent Held: No — incorporation insured NCS’s obligation but did not create Western’s agreement to arbitrate with Schneider
Whether the Federal Arbitration Act compels arbitration between Schneider and Western FAA applies because the Bond is a written agreement to arbitrate and involves interstate commerce, invoking a presumption favoring arbitration Whether an arbitration agreement exists between the parties is resolved under ordinary state-law contract principles; absent mutual assent, FAA does not compel arbitration Held: State contract-law governs formation; no mutual assent, so FAA does not compel arbitration
Whether the Bond’s court-action clause is compatible with compelling arbitration Arbitration and court clauses can coexist so incorporation should permit either forum The Bond’s court-action clause (allowing suit in court) demonstrates intent to permit litigation of Bond disputes, inconsistent with forcing arbitration Held: The court-action clause confirms parties intended litigation option; compelling arbitration would nullify that provision

Key Cases Cited

  • First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938 (courts apply ordinary state-law contract principles to determine arbitration assent)
  • Cain v. Midland Funding, LLC, 452 Md. 141 (contract-based challenges to arbitration governed by state law)
  • O’Brien & Gere Engs., Inc. v. City of Salisbury, 447 Md. 394 (contract interpretation: parties’ expressed intent controls)
  • Rourke v. Amchem Prods., Inc., 384 Md. 329 (ambiguous contracts: plain meaning controls; interpret as whole)
  • Hartford Accident & Indem. Co. v. Scarlett Harbor Assocs., 346 Md. 122 (surety who incorporated subcontract by reference not bound to subcontract arbitration clause between other parties)
  • Liberty Mut. Ins. Co. v. Mandaree Pub. Sch. Dist. #36, 503 F.3d 709 (8th Cir.) (performance bond incorporating contract with arbitration clause and a court-action clause did not compel surety to arbitrate)
Read the full case

Case Details

Case Name: Schneider Electric Buildings Critical System, Inc. v. Western Surety Co.
Court Name: Court of Appeals of Maryland
Date Published: Jul 28, 2017
Citation: 165 A.3d 485
Docket Number: 96/16
Court Abbreviation: Md.