ORDER
THIS MATTER IS BEFORE THE COURT on Plaintiff United States Surety Company’s (“US Surety” or “Plaintiff’) “Motion to Declare Bond Issues Are Not Arbitrable Issues And Motion To Stay Arbitration of Bond Issues (Document No. 6), filed September 21, 2007; and “Defendant Hanover R.S. Limited Partnership’s Motion to Dismiss Or Stay Litigation and Compel Arbitration” (Document No. 19), filed October 22, 2007. The parties have consented to Magistrate Judge jurisdiction pursuant to 28 U.S.C. § 636(c), and these motions are now ripe for disposition.
Having carefully considered the arguments, the record, and the applicable authority, Plaintiffs motion will be
denied;
I. FACTUAL AND PROCEDURAL BACKGROUND
Defendant Hanover is the general contractor for construction of a mixed-use residential/retail building known as “The Residence at SouthPark” located in Charlotte, North Carolina (the “Project”). Complaint (Document No. 1) at ¶ 5.
Hanover entered into a subcontract with Defendant Fuller Drywall, Ltd. (“Fuller”) dated April 10, 2006 (the “Subcontract”), whereby Fuller agreed to provide certain labor and materials for incorporation into the Project (the “Work”). Complaint (Document No. 1) at ¶ 6. A copy of the Subcontract is attached to the Complaint (Document No. 1) as Exhibit “A”.
On or about May 31, 2006, Plaintiff U.S. Surety issued a subcontract performance bond (the “Bond”) as surety for its principal, Fuller, and for the benefit of Hanover. See Complaint (Document No. 1) at ¶ 7. A copy of the Bond is attached to the Complaint (Document No. 1) as Exhibit “B”.
The Bond provides as follows: “... Subcontract is by reference made a part hereof. ...” See Complaint (Document No. 1), Exhibit “B” at 1; see also U.S. Surety’s “Memorandum in Support of Motion to Declare Bond Issues Are Not Arbitrable Issues ...” (Document No. 7) at 3 (“the Bond incorporate^] the Subcontract by reference”). The Bond further provides the following: “The responsibilities of the Obligee [Hanover] to the Surety [US Surety] shall not be greater than those of the Obligee under the Subcontract.” Complaint (Document No. 1), Exhibit “A”, Bond at p. 2, § 4.
The Subcontract contains an arbitration clause, which provides in relevant part as follows: “Any dispute arising out of or relating to • this Agreement shall ... be settled by ... binding arbitration conducted by a neutral arbitrator selected by the American Arbitration Association at its offices closest to the Project.” Complaint (Document No. 1), Exhibit “A”, Subcontract at § 19. In addition, the Subcontract provides that “Contractor may require the joinder of another person or party who may have a related claim or interest in the proceedings.” See Complaint (Document No. 1), Exhibit “A”, Subcontract at ¶ 19.
Disputes have arisen between Hanover and Fuller concerning performance under the Subcontract, each alleging the other has been and is in breach of the Subcontract. See Complaint (Document No. 1) at ¶ 9. On May 30, 2007, Hanover initiated arbitration proceedings against Fuller seeking, without limitation, breach of contract damages resulting from Fuller’s allegedly defective and incomplete work, including all costs associated with Hanover’s supplementation of Fuller’s Work. See Complaint (Document No. 1) at ¶ 10. On June 18, 2007, Fuller filed an Answering Statement and Counterclaim in the arbitration proceedings denying Hanover’s claims and seeking affirmative recovery resulting from Hanover’s alleged breach of contract, quantum meruit and negligence. See Complaint (Document No. 1) at ¶ 13.
On September 7, 2007, U.S. Surety filed the present action seeking a declaration that (a) “issues concerning its liability under the Bond are not arbitrable” and (b) “Hanover has failed to satisfy the Bond’s conditions precedent, and [US Surety’s] obligations under the Bond are fully discharged.” See Complaint (Document No. 1) at ¶¶ 21 & 24.
On September 21, 2007, U.S. Surety filed the pending Motion to Declare Bond Issues are not Arbitrable Issues and Motion to Stay Arbitration of Bond Issues. (Document Nos. 6 & 7). On October 22, 2007, Hanover filed its Motion to Dismiss or Stay Litigation and Compel Arbitration and its Response and Opposition to Plaintiffs Motion to Declare Bond Issues are not Arbitrable Issues and Motion to Stay Arbitration of Bond Issues. (Document Nos. 19 & 20). On October 31, 2007, U.S. Surety filed its Reply to Hanover R.S. Limited Partnership’s Response to Motion to Declare Bond Issues are not Arbitrable Issues and Motion to Stay Arbitration of Bond Issues. (Document No. 21). A hearing on the above motions was held by the Court with the undersigned presiding on January 29, 2008.
II. STANDARD OF REVIEW
A. Determination of Arbitrability
“The question whether the parties have submitted a particular dispute to arbitration, i.e., the ‘question of arbitrability,’ is ‘an issue for judicial determination ...’” as a matter of law.
Howsam v. Dean Witter Reynolds, Inc.,
[T]he heavy presumption of arbitrability requires that when the scope of the arbitration clause is open to question, a court must decide the question in favor of arbitration. Thus, we may not deny a party’s request to arbitrate an issue unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute ... [A]lthough the intention of the parties is relevant, the intentions of parties to an arbitration agreement are generously construed in favor of. arbitrability.
Long v. Silver,
B. Motion to Dismiss
“The purpose of a Rule 12(b)(6) motion is to test the sufficiency of a complaint.”
Republican Party v. Martin,
III. DISCUSSION
The arbitration provision at issue in the construction subcontract calls for arbitration of “[a]ny dispute arising out of or relating to this Agreement.” Complaint (Document No. 1), Exhibit “A,” Subcontract at § 19 (emphasis added). In its Complaint, U.S. Surety asserts that the Bond’s incorporation of the Subcontract’s arbitration provision does not require arbitration of its surety defenses. According to Plaintiff, “defenses unique to the surety, such as whether the Obligee [Hanover] has impaired the surety’s position or released the principal obligor, are not claims arising out of the performance of the Subcontract (and subject to the Subcontract’s arbitration clause), but are claims arising out of the Bond and therefore, are outside the scope of the Subcontract’s arbitration clause.” Complaint (Document No. 1) at ¶ 17.
According to the Fourth Circuit, “[b]oth the Supreme Court and this court have characterized similar formulations [of “arising out of or relating to”] to be broad arbitration clauses capable of an expansive reach.”
American Recovery Corp. v. Computerized Thermal Imaging, Inc.,
This Court finds that the defenses raised by U.S. Surety in this matter, whether allegedly “arising out of’ the Bond or the Subcontract, at the very least, are “related to” or have a “significant relationship” to the Subcontract, as the Bond’s purpose is to ensure Fuller’s performance under the Subcontract and the Bond incorporates the terms of the Subcontract without limitation. See Complaint (Document No. 1), Exhibit “B,” Bond at p. 2, § 4.
Hanover has presented authority from other jurisdictions supporting its position that all of U.S. Surety’s defenses are arbitrable, which precedent is consistent with the Fourth Circuit’s above-described strong presumption favoring arbitrability.
See, e.g., Hoffman v. Fidelity & Deposit Co. of Maryland,
Plaintiff has presented authority from other jurisdictions supporting its position that while the surety is required to arbitrate disputes arising out of and/or seeking to enforce the terms of the construction contract, the surety cannot be compelled to arbitrate disputes arising out of and/or seeking to enforce the terms of the surety bond.
Under the facts of this case, the undersigned is more persuaded by the applicability of Hanover’s arguments and ease law. Given the Fourth Circuit’s “heavy presumption” in favor of arbitrability, as well as concepts of judicial economy, this Court finds that Plaintiffs liability under the Bond and its surety defenses thereto are issues referable to arbitration under the Subcontract and they shall be adjudicated in the pending arbitration. Further, the Court finds no prejudice to U.S. Surety in submitting all of its defenses in the pending arbitration, and notes that to date U.S. Surety has participated in all aspects of the pending arbitration.
IV. CONCLUSION
IT IS, THEREFORE, ORDERED that Plaintiffs “Motion to Declare Bond Issues Are Not Arbitrable Issues And Motion To Stay Arbitration of Bond Issues” (Document No. 6) is DENIED.
IT IS FURTHER ORDERED that “Defendant Hanover R.S. Limited Partnership’s Motion to Dismiss Or Stay Litigation and Compel Arbitration” (Document No. 19) is DENIED in part, and GRANTED in part as follows: the “... Motion To Dismiss” is DENIED without prejudice, and the alternative motion to “Stay Litigation and Compel Arbitration” is GRANTED.
IT IS FURTHER ORDERED that all claims and defenses between the parties in this matter, arising out of or relating to the enforcement of the subcontract and/or surety bond are arbitrable and must be submitted for adjudication in the pending arbitration titled: Hanover R.S. Limited Partnership v. Fuller Drywall & Paint, Ltd. and United States Surety Company (AAA Case No. 31-110-Y-00116-07).
Notes
. The arbitration, including U.S. Surety as a party, is presently pending before the American Arbitration Association and titled: Hanover R.S. Limited Partnership v. Fuller Drywall & Paint, Ltd. and United States Surety Company (AAA Case No. 31-110-Y-00116-07).
