The primary, issue on appeal is whether United States Fidelity and Guaranty Company (“USF & G”) is bound to submit to arbitration by virtue of the fact that the performance bond which it issued incorporated by reference the underlying subcontract which in turn contained an arbitration clause. The district court held that USF & G was bound to arbitrate. USF & G appeals. We affirm.
West Point Construction Company, Inc.,_ the defendant-appellee, was general contractor to construct the Lee County Justice Center for the Lee County (Alabama) Commission. West Point attempted to institute arbitration proceedings following the default of the subcontractor, Pruett Brothers Paint Contractors (Pruett). The general contract between West Point and the Lee County Commission contained a general arbitration clause. The subcontract between West Point and Pruett set forth its own arbitration provision, and in a separate article modified that provision by reference to the arbitration provisions of the general contract. The performance bond, issued by USF & G as surety to Pruett, incorporated by reference the subcontract.
USF & G opposed arbitration, arguing that an incorporation by reference clause in the bond did not incorporate the arbitration clause in either the subcontract or the general contract.
*1508
The condition of the USF & G bond was proper performance of the subcontract by Pruett. The subcontract was referred to and made a part of the bond. Disputes arising under the contract, including disputes concerning the adequacy of Pruett’s performance, were subject to arbitration pursuant to the arbitration provisions of the subcontract. We conclude that the incorporation of the subcontract into the bond expresses an intention of the parties, including USF & G, to arbitrate disputes. Our conclusion is supported by the strong policy favoring arbitration expressed by Congress in the Federal Arbitration Act.
1
J.S. & H. Construction Company v. Richmond County Hospital Authority,
Our holding is consistent with
Exchange Mutual,
USF & G relies upon several cases which limit or deny the effect of clauses which incorporate a contract or subcontract by reference.
S. Leo Harmonay, Inc. v. Binks Manufacturing Company,
For the foregoing reasons, we conclude that the performance bond did incorporate by reference the arbitration provisions of the subcontract, and therefore USF & G is required to arbitrate.
All other issues are without merit and warrant no further discussion.
AFFIRMED.
Notes
. 9 U.S.C.A. §§ 1-14.
.
S. Leo Harmonay, Inc.,
. 40 U.S.C.A. § 270a et seq.
. This case was decided prior to the close of-business on September 30, 1981, and is binding precedent under
Bonner v. City of Prichard,
