FEDERAL ENERGY REGULATORY COMMISSION v. ELECTRIC POWER SUPPLY ASSOCIATION ET AL.
No. 14–840
Supreme Court of the United States
January 25, 2016
Syllabus
NOTE: Where it is feasible, a syllabus (headnote) will be released, as is being done in connection with this case, at the time the opinion is issued. The syllabus constitutes no part of the opinion of the Court but has been prepared by the Reporter of Decisions for the convenience of the reader. See United States v. Detroit Timber & Lumber Co., 200 U. S. 321, 337.
SUPREME COURT OF THE UNITED STATES
Syllabus
FEDERAL ENERGY REGULATORY COMMISSION v. ELECTRIC POWER SUPPLY ASSOCIATION ET AL.
CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT*
No. 14–840. Argued October 14, 2015—Decided January 25, 2016
The Federal Power Act (FPA) authorizes the Federal Regulatory Commission (FERC) to regulate “the sale of electric energy at wholesale in interstate commerce,” including both wholesale electricity rates and any rule or practice “affecting” such rates. 16 U. S. C. §§824(b), 824d(a), 824e(a). But it places beyond FERC’s power, leaving to the States alone, the regulation of “any other sale”—i.e., any retail sale—of electricity. §824(b).
In an increasingly competitive interstate electricity market, FERC has undertaken to ensure “just and reasonable” wholesale rates, §824d(a), by encouraging the creation of nonprofit entities to manage regions of the nationwide electricity grid. These wholesale market operators administer their portions of the grid to ensure that the network conducts electricity reliably, and each holds competitive auctions to set wholesale prices. These auctions balance supply and demand continuously by matching bids to provide electricity from generators with orders from utilities and other “load-serving entities” (LSEs) that buy power at wholesale for resale to users. All bids to supply electricity are stacked from lowest to highest, and accepted in that order until all requests for power have been met. Every electricity supplier is paid the price of the highest-accepted bid, known as the locational marginal price (LMP).
In periods of high electricity demand, prices can reach extremely
Syllabus
high levels as the least efficient generators have their supply bids accepted in the wholesale market auctions. Not only do rates rise dramatically during these peak periods, but the increased flow of electricity threatens to overload the grid and cause substantial service problems. Faced with these challenges, wholesale market operators devised wholesale demand response programs, which pay consumers for commitments to reduce their use of power during these peak periods. Just like bids to supply electricity, offers from aggregators of multiple users of electricity or large individual consumers to reduce consumption can be bid into the wholesale market auctions. When it costs less to pay consumers to refrain from using power than it does to pay producers to supply more of it, demand response can lower these wholesale prices and increase grid reliability. Wholesale operators began integrating these programs into their markets some 15 years ago and FERC authorized their use. Congress subsequently encouraged further development of demand response.
Spurred on by Congress, FERC issued Order No. 719, which, among other things, requires wholesale market operators to receive demand response bids from aggregators of electricity consumers, except when the state regulatory authority overseeing those users’ retail purchases bars demand response participation. 18 CFR §35.28(g)(1). Concerned that the order had not gone far enough, FERC then issued the rule under review here, Order No. 745. §35.28(g)(1)(v) (Rule). It requires market operators to pay the same price to demand response providers for conserving energy as to generators for producing it, so long as a “net benefits test,” which ensures that accepted bids actually save consumers money, is met. The Rule rejected an alternative compensation scheme that would have subtracted from LMP the savings consumers receive from not buying electricity in the retail market, a formula known as LMP-G. The Rule also rejected claims that FERC lacked statutory authority to regulate the compensation operators pay for demand response bids.
The Court of Appeals for the District of Columbia Circuit vacated the Rule, holding that FERC lacked authority to issue the order because it directly regulates the retail electricity market, and holding in the alternative that the Rule’s compensation scheme is arbitrary and capricious under the Administrative Procedure Act.
Held:
1. The FPA provides FERC with the authority to regulate wholesale market operators’ compensation of demand response bids. The Court’s analysis proceeds in three parts. First, the practices at issue directly affect wholesale rates. Second, FERC has not regulated retail sales. Taken together, these conclusions establish that the Rule complies with the FPA’s plain terms. Third, the contrary view would
Syllabus
conflict with the FPA’s core purposes. Pp. 14–29.
(a) The practices at issue directly affect wholesale rates. The FPA has delegated to FERC the authority—and, indeed, the duty—to ensure that rules or practices “affecting” wholesale rates are just and reasonable. §§824d(a), 824e(a). To prevent the statute from assuming near-infinite breadth, see e.g., New York State Conference of Blue Cross & Blue Shield Plans v. Travelers Ins. Co., 514 U. S. 645, 655, this Court adopts the D. C. Circuit’s common-sense construction limiting FERC’s “affecting” jurisdiction to rules or practices that “directly affect the [wholesale] rate,” California Independent System Operator Corp. v. FERC, 372 F. 3d 395, 403 (emphasis added). That standard is easily met here. Wholesale demand response is all about reducing wholesale rates; so too the rules and practices that determine how those programs operate. That is particularly true here, as the formula for compensating demand response necessarily lowers wholesale electricity prices by displacing higher-priced generation bids. Pp. 14–17.
(b) The Rule also does not regulate retail electricity sales in violation of §824(b). A FERC regulation does not run afoul of §824(b)’s proscription just because it affects the quantity or terms of retail sales. Transactions occurring on the wholesale market have natural consequences at the retail level, and so too, of necessity, will FERC’s regulation of those wholesale matters. That is of no legal consequence. See, e.g., Mississippi Power & Light Co. v. Mississippi ex rel. Moore, 487 U. S. 354, 365, 370–373. When FERC regulates what takes place on the wholesale market, as part of carrying out its charge to improve how that market runs, then no matter the effect on retail rates, §824(b) imposes no bar. Here, every aspect of FERC’s regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules. The Commission’s justifications for regulating demand response are likewise only about improving the wholesale market. Cf. Oneok, Inc. v. Learjet, Inc., 575 U. S. ___. Pp. 17–25.
(c) In addition, EPSA’s position would subvert the FPA. EPSA’s arguments suggest that the entire practice of wholesale demand response falls outside what FERC can regulate, and EPSA concedes that States also lack that authority. But under the FPA, wholesale demand response programs could not go forward if no entity had jurisdiction to regulate them. That outcome would flout the FPA’s core purposes of protecting “against excessive prices” and ensuring effective transmission of electric power. Pennsylvania Water & Power Co. v. FPC, 343 U. S. 414, 418; see Gulf States Util. Co. v. FPC, 411 U. S. 747, 758. The FPA should not be read, against its clear terms, to halt a practice that so evidently enables FERC to fulfill its statutory du-
Syllabus
ties of holding down prices and enhancing reliability in the wholesale energy market. Pp. 25–29.
2. FERC’s decision to compensate demand response providers at LMP—the same price paid to generators—instead of at LMP-G, is not arbitrary and capricious. Under the narrow scope of review in Motor Vehicle Mfrs. Assn. of United States, Inc. v. State Farm Mut. Automobile Ins. Co., 463 U. S. 29, 43, this Court’s important but limited role is to ensure that FERC engaged in reasoned decisionmaking—that it weighed competing views, selected a compensation formula with adequate support in the record, and intelligibly explained the reasons for making that decision. Here, FERC provided a detailed explanation of its choice of LMP and responded at length to contrary views. FERC’s serious and careful discussion of the issue satisfies the arbitrary and capricious standard. Pp. 29–33.
753 F. 3d 216, reversed and remanded.
KAGAN, J., delivered the opinion of the Court, in which ROBERTS, C. J., and KENNEDY, GINSBURG, BREYER, and SOTOMAYOR, JJ., joined. SCALIA, J. filed a dissenting opinion, in which THOMAS, J., joined. ALITO, J., took no part in the consideration or decision of the cases.
FEDERAL ENERGY REGULATORY COMMISSION, PETITIONER v. ELECTRIC POWER SUPPLY ASSOCIATION, ET AL.
No. 14–840
Supreme Court of the United States
January 25, 2016
Opinion of the Court
NOTICE: This opinion is subject to formal revision before publication in the preliminary print of the United States Reports. Readers are requested to notify the Reporter of Decisions, Supreme Court of the United States, Washington, D. C. 20543, of any typographical or other formal errors, in order that corrections may be made before the preliminary print goes to press.
SUPREME COURT OF THE UNITED STATES
Nos. 14–840 and 14–841
FEDERAL ENERGY REGULATORY COMMISSION, PETITIONER
14–840 v.
ELECTRIC POWER SUPPLY ASSOCIATION, ET AL.
ENERNOC, INC., ET AL., PETITIONERS
14–841 v.
ELECTRIC POWER SUPPLY ASSOCIATION, ET AL.
ON WRITS OF CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT
[January 25, 2016]
JUSTICE KAGAN delivered the opinion of the Court.
The Federal Power Act (FPA or Act), 41 Stat. 1063, as amended,
These cases concern a practice called “demand re-
Opinion of the Court
sponse,” in which operators of wholesale markets pay electricity consumers for commitments not to use power at certain times. That practice arose because wholesale market operators can sometimes—say, on a muggy August day—offer electricity both more cheaply and more reliably by paying users to dial down their consumption than by paying power plants to ramp up their production. In the regulation challenged here, FERC required those market operators, in specified circumstances, to compensate the two services equivalently—that is, to pay the same price to demand response providers for conserving energy as to generators for making more of it.
Two issues are presented here. First, and fundamentally, does the FPA permit FERC to regulate these demand response transactions at all, or does any such rule impinge on the States’ authority? Second, even if FERC has the requisite statutory power, did the Commission fail to justify adequately why demand response providers and electricity producers should receive the same compensation? The court below ruled against FERC on both scores. We disagree.
I
A
Federal regulation of electricity owes its beginnings to one of this Court’s decisions. In the early 20th century, state and local agencies oversaw nearly all generation, transmission, and distribution of electricity. But this Court held in Public Util. Comm’n of R. I. v. Attleboro Steam & Elec. Co., 273 U. S. 83, 89–90 (1927), that the Commerce Clause bars the States from regulating certain interstate electricity transactions, including wholesale sales (i.e., sales for resale) across state lines. That ruling created what became known as the “Attleboro gap”—a regulatory void which, the Court pointedly noted, only Congress could fill. See id., at 90.
Opinion of the Court
Congress responded to that invitation by passing the FPA in 1935. The Act charged FERC’s predecessor agency with undertaking “effective federal regulation of the expanding business of transmitting and selling electric power in interstate commerce.” New York v. FERC, 535 U. S. 1, 6 (2002) (quoting Gulf States Util. Co. v. FPC, 411 U. S. 747, 758 (1973)). Under the statute, the Commission has authority to regulate “the transmission of electric energy in interstate commerce” and “the sale of electric energy at wholesale in interstate commerce.”
In particular, the FPA obligates FERC to oversee all prices for those interstate transactions and all rules and practices affecting such prices. The statute provides that “[a]ll rates and charges made, demanded, or received by any public utility for or in connection with” interstate transmissions or wholesale sales—as well as “all rules and regulations affecting or pertaining to such rates or charges”—must be “just and reasonable.”
Alongside those grants of power, however, the Act also limits FERC’s regulatory reach, and thereby maintains a zone of exclusive state jurisdiction. As pertinent here,
Opinion of the Court
Since the FPA’s passage, electricity has increasingly become a competitive interstate business, and FERC’s role has evolved accordingly. Decades ago, state or local utilities controlled their own power plants, transmission lines, and delivery systems, operating as vertically integrated monopolies in confined geographic areas. That is no longer so. Independent power plants now abound, and almost all electricity flows not through “the local power networks of the past,” but instead through an interconnected “grid” of near-nationwide scope. See id., at 7 (“electricity that enters the grid immediately becomes a part of a vast pool of energy that is constantly moving in interstate commerce,” linking producers and users across the country). In this new world, FERC often forgoes the cost-based rate-setting traditionally used to prevent monopolistic pricing. The Commission instead undertakes to ensure “just and reasonable” wholesale rates by enhancing competition—attempting, as we recently explained, “to break down regulatory and economic barriers that hinder a free market in wholesale electricity.” Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U. S. 527, 536 (2008).
As part of that effort, FERC encouraged the creation of nonprofit entities to manage wholesale markets on a regional basis. Seven such wholesale market operators now serve areas with roughly two-thirds of the country’s electricity “load” (an industry term for the amount of electricity used). See FERC, Energy Primer: A Handbook of Energy Market Basics 58–59 (Nov. 2015) (Energy Primer). Each administers a portion of the grid, providing generators with access to transmission lines and ensuring that the network conducts electricity reliably. See ibid. And still more important for present purposes, each operator conducts a competitive auction to set wholesale prices for electricity.
These wholesale auctions serve to balance supply and
Opinion of the Court
demand on a continuous basis, producing prices for electricity that reflect its value at given locations and times throughout each day. Such a real-time mechanism is needed because, unlike most products, electricity cannot be stored effectively. Suppliers must generate—every day, hour, and minute—the exact amount of power necessary to meet demand from the utilities and other “load-serving entities” (LSEs) that buy power at wholesale for resale to users. To ensure that happens, wholesale market operators obtain (1) orders from LSEs indicating how much electricity they need at various times and (2) bids from generators specifying how much electricity they can produce at those times and how much they will charge for it. Operators accept the generators’ bids in order of cost (least expensive first) until they satisfy the LSEs’ total demand. The price of the last unit of electricity purchased is then paid to every supplier whose bid was accepted, regardless of its actual offer; and the total cost is split among the LSEs in proportion to how much energy they have ordered. So, for example, suppose that at 9 a.m. on August 15 four plants serving Washington, D. C. can each produce some amount of electricity for, respectively, $10/unit, $20/unit, $30/unit, and $40/unit. And suppose that LSEs’ demand at that time and place is met after the operator accepts the three cheapest bids. The first three generators would then all receive $30/unit. That amount is (think back to Econ 101) the marginal cost—i.e., the added cost of meeting another unit of demand—which is the price an efficient market would produce. See 1 A. Kahn, The Economics of Regulation: Principles and Institutions 65–67 (1988). FERC calls that cost (in jargon that will soon become oddly familiar) the locational marginal price, or LMP.1
Opinion of the Court
As in any market, when wholesale buyers’ demand for electricity increases, the price they must pay rises correspondingly; and in those times of peak load, the grid’s reliability may also falter. Suppose that by 2 p.m. on August 15, it is 98 degrees in D. C. In every home, store, or office, people are turning the air conditioning up. To keep providing power to their customers, utilities and other LSEs must ask their market operator for more electricity. To meet that spike in demand, the operator will have to accept more expensive bids from suppliers. The operator, that is, will have to agree to the $40 bid that it spurned before—and maybe, beyond that, to bids of $50 or $60 or $70. In such periods, operators often must call on extremely inefficient generators whose high costs of production cause them to sit idle most of the time. See Energy Primer 41–42. As that happens, LMP—the price paid by all LSEs to all suppliers—climbs ever higher. And meanwhile, the increased flow of electricity through the grid threatens to overload transmission lines. See id., at 44. As every consumer knows, it is just when the weather is hottest and the need for air conditioning most acute that blackouts, brownouts, and other service problems tend to occur.
Making matters worse, the wholesale electricity market lacks the self-correcting mechanism of other markets. Usually, when the price of a product rises, buyers naturally adjust by reducing how much they purchase. But consumers of electricity—and therefore the utilities and other LSEs buying power for them at wholesale—do not respond to price signals in that way. To use the economic term, demand for electricity is inelastic. That is in part because electricity is a necessity with few ready substitutes: When the temperature reaches 98 degrees, many people see no
grid. But those costs are not relevant here, and we therefore disregard them.
Opinion of the Court
option but to switch on the AC. And still more: Many State regulators insulate consumers from short-term fluctuations in wholesale prices by insisting that LSEs set stable retail rates. See id., at 41, 43–44. That, one might say, short-circuits the normal rules of economic behavior. Even in peak periods, as costs surge in the wholesale market, consumers feel no pinch, and so keep running the AC as before. That means, in turn, that LSEs must keep buying power to send to those users—no matter that wholesale prices spiral out of control and increased usage risks overtaxing the grid.
But what if there were an alternative to that scenario? Consider what would happen if wholesale market operators could induce consumers to refrain from using (and so LSEs from buying) electricity during peak periods. Whenever doing that costs less than adding more power, an operator could bring electricity supply and demand into balance at a lower price. And simultaneously, the operator could ease pressure on the grid, thus protecting against system failures. That is the idea behind the practice at issue here: Wholesale demand response, as it is called, pays consumers for commitments to curtail their use of power, so as to curb wholesale rates and prevent grid breakdowns. See id., at 44–46.2
These demand response programs work through the operators’ regular auctions. Aggregators of multiple users of electricity, as well as large-scale individual users like factories or big-box stores, submit bids to decrease electricity consumption by a set amount at a set time for a set price. The wholesale market operators treat those offers just like bids from generators to increase supply. The
Opinion of the Court
operators, that is, rank order all the bids—both to produce and to refrain from consuming electricity—from least to most expensive, and then accept the lowest bids until supply and demand come into equipoise. And, once again, the LSEs pick up the cost of all those payments. So, to return to our prior example, if a store submitted an offer not to use a unit of electricity at 2 p.m. on August 15 for $35, the operator would accept that bid before calling on the generator that offered to produce a unit of power for $40. That would result in a lower LMP—again, wholesale market price—than if the market operator could not avail itself of demand response pledges. See ISO/RTO Council, Harnessing the Power of Demand: How ISOs and RTOs Are Integrating Demand Response Into Wholesale Electricity Markets 40–43 (2007) (estimating that, in one market, a demand response program reducing electricity usage by 3% in peak hours would lead to price declines of 6% to 12%). And it would decrease the risk of blackouts and other service problems.
Wholesale market operators began using demand response some 15 years ago, soon after they assumed the role of overseeing wholesale electricity sales. Recognizing the value of demand response for both system reliability and efficient pricing, they urged FERC to allow them to implement such programs. See, e.g., PJM Interconnection, L. L. C., Order Accepting Tariff Sheets as Modified, 95 FERC ¶61,306 (2001); California Independent System Operator Corp., Order Conditionally Accepting for Filing Tariff Revisions, 91 FERC ¶61,256 (2000). And as demand response went into effect, market participants of many kinds came to view it—in the words of respondent Electric Power Supply Association (EPSA)—as an “important element[ ] of robust, competitive wholesale electricity markets.” App. 94, EPSA, Comments on Proposed Rule on Demand Response Compensation in Organized Wholesale Energy Markets (May 12, 2010).
Opinion of the Court
Congress added to the chorus of voices praising wholesale demand response. In the Energy Policy Act of 2005, 119 Stat. 594 (EPAct), it declared as “the policy of the United States” that such demand response “shall be encouraged.” §1252(f), 119 Stat. 966,
B
Spurred on by Congress, the Commission determined to take a more active role in promoting wholesale demand response programs. In 2008, FERC issued Order No. 719, which (among other things) requires wholesale market operators to receive demand response bids from aggregators of electricity consumers, except when the state regulatory authority overseeing those users’ retail purchases bars such demand response participation. See 73 Fed. Reg. 64119, ¶154 (codified
Opinion of the Court
Concerned that Order No. 719 had not gone far enough, FERC issued the rule under review here in 2011, with one commissioner dissenting. See Demand Response Competition in Organized Wholesale Energy Markets, Order No. 745, 76 Fed. Reg. 16658 (Rule) (codified
The two specified conditions ensure that a bid to use less electricity provides the same value to the wholesale market as a bid to make more. First, a demand response bidder must have “the capability to provide the service” offered; it must, that is, actually be able to reduce electricity use and thereby obviate the operator’s need to secure additional power. Id., at 16666, ¶¶48–49. Second, paying LMP for a demand response bid “must be cost-effective,” as measured by a standard called “the net benefits test.” Ibid., ¶48. That test makes certain that accepting a lower-priced demand response bid over a higher-priced supply bid will actually save LSEs (i.e., wholesale purchasers) money. In some situations it will not, even though accepting a lower-priced bid (by definition) reduces LMP. That is because (to oversimplify a bit) LSEs share the cost of paying successful bidders, and reduced electricity use makes some LSEs drop out of the market, placing a proportionally greater burden on those that are left. Each
Opinion of the Court
remaining LSE may thus wind up paying more even though the total bill is lower; or said otherwise, the costs associated with an LSE’s increased share of compensating bids may exceed the savings that the LSE obtains from a lower wholesale price.4
The net benefits test screens out such counterproductive demand response bids, exempting them from the Rule’s compensation requirement. See id., at 16659, 16666–16667, ¶¶3, 50–53. What remains are only those offers whose acceptance will result in actual savings to wholesale purchasers (along with more reliable service to end users). See id., at 16671, ¶¶78–80.
The Rule rejected an alternative scheme for compensating demand response bids. Several commenters had urged that, in paying a demand response provider, an operator should subtract from the ordinary wholesale price the savings that the provider nets by not buying electricity on the retail market. Otherwise, the commenters claimed, demand response providers would receive a kind of “double-payment” relative to generators. See id., at 16663, ¶24. That proposal, which the dissenting commissioner largely accepted, became known as LMP minus G, or more simply LMP-G, where “G” stands for the retail price of electricity. See id., at 16668, ¶60, 16680 (Moeller, dissenting). But FERC explained that, under the conditions it had specified, the value of an accepted demand response bid to the wholesale market is identical to that of an accepted supply bid because each succeeds in cost-effectively “balanc[ing] supply and demand.” Id., at 16667, ¶55. And, the Commission reasoned, that comparable value is
Opinion of the Court
what ought to matter given FERC’s goal of strengthening competition in the wholesale market: Rates should reflect not the costs that each market participant incurs, but instead the services it provides. See id., at 16668, ¶62. Moreover, the Rule stated, compensating demand response bids at their actual value—i.e., LMP—will help overcome various technological barriers, including a lack of needed infrastructure, that impede aggregators and large-scale users of electricity from fully participating in demand response programs. See id., at 16667–16668, ¶¶57–58.
The Rule also responded to comments challenging FERC’s statutory authority to regulate the compensation operators pay for demand response bids. Pointing to the Commission’s analysis in Order No. 719, the Rule explained that the FPA gives FERC jurisdiction over such bids because they “directly affect[ ] wholesale rates.” Id., at 16676, ¶112 (citing 74 id., at 37783, ¶47, and
C
A divided panel of the Court of Appeals for the District of Columbia Circuit vacated the Rule as “ultra vires agency action.” 753 F. 3d 216, 225 (2014). The court held that FERC lacked authority to issue the Rule even though “demand response compensation affects the wholesale market.” Id., at 221. The Commission’s “jurisdiction to regulate practices ‘affecting’ rates,” the court stated, “does not erase the specific limit[ ]” that the FPA imposes on
Opinion of the Court
FERC’s regulation of retail sales. Id., at 222. And the Rule, the court concluded, exceeds that limit: In “luring . . . retail customers” into the wholesale market, and causing them to decrease “levels of retail electricity consumption,” the Rule engages in “direct regulation of the retail market.” Id., at 223–224.
The Court of Appeals held, alternatively, that the Rule is arbitrary and capricious under the Administrative Procedure Act,
Judge Edwards dissented. He explained that the rules governing wholesale demand response have a “direct effect . . . on wholesale electricity rates squarely within FERC’s jurisdiction.” Id., at 227. And in setting those rules, he argued, FERC did not engage in “direct regulation of the retail market”; rather, “[a]uthority over retail rates . . . remains vested solely in the States.” Id., at 234 (internal quotation marks omitted). Finally, Judge Edwards rejected the majority’s view that the Rule is arbitrary and capricious. He noted the substantial deference due to the Commission in cases involving ratemaking, and concluded that FERC provided a “thorough” and “reasonable” explanation for choosing LMP as the appropriate compensation formula. Id., at 236–238.
Opinion of the Court
We granted certiorari, 575 U. S. ___ (2015), to decide whether the Commission has statutory authority to regulate wholesale market operators’ compensation of demand response bids and, if so, whether the Rule challenged here is arbitrary and capricious. We now hold that the Commission has such power and that the Rule is adequately reasoned. We accordingly reverse.
II
Our analysis of FERC’s regulatory authority proceeds in three parts. First, the practices at issue in the Rule—market operators’ payments for demand response commitments—directly affect wholesale rates. Second, in addressing those practices, the Commission has not regulated retail sales. Taken together, those conclusions establish that the Rule complies with the FPA’s plain terms. And third, the contrary view would conflict with the Act’s core purposes by preventing all use of a tool that no one (not even EPSA) disputes will curb prices and enhance reliability in the wholesale electricity market.5
A
The FPA delegates responsibility to FERC to regulate the interstate wholesale market for electricity—both wholesale rates and the panoply of rules and practices affecting them. As noted earlier, the Act establishes a scheme for federal regulation of “the sale of electric energy at wholesale in interstate commerce.”
Opinion of the Court
regulations affecting or pertaining to such rates or charges.”
Taken for all it is worth, that statutory grant could extend FERC’s power to some surprising places. As the court below noted, markets in all electricity’s inputs—steel, fuel, and labor most prominent among them—might affect generators’ supply of power. See 753 F. 3d, at 221; id., at 235 (Edwards, J., dissenting). And for that matter, markets in just about everything—the whole economy, as it were—might influence LSEs’ demand. So if indirect or tangential impacts on wholesale electricity rates sufficed, FERC could regulate now in one industry, now in another, changing a vast array of rules and practices to implement its vision of reasonableness and justice. We cannot imagine that was what Congress had in mind.
For that reason, an earlier D. C. Circuit decision adopted, and we now approve, a common-sense construction of the FPA’s language, limiting FERC’s “affecting” jurisdiction to rules or practices that “directly affect the [wholesale] rate.” California Independent System Operator Corp. v. FERC, 372 F. 3d 395, 403 (2004) (emphasis added); see 753 F. 3d, at 235 (Edwards, J., dissenting). As we have explained in addressing similar terms like “relating to” or “in connection with,” a non-hyperliteral reading is needed to prevent the statute from assuming near-infinite breadth. See New York State Conference of Blue Cross &
Opinion of the Court
Blue Shield Plans v. Travelers Ins. Co., 514 U. S. 645, 655 (1995) (“If ‘relate to’ were taken to extend to the furthest stretch of its indeterminacy, then for all practical purposes [the statute] would never run its course”); Maracich v. Spears, 570 U. S. ___, ___ (2013) (slip op., at 9) (“The phrase ‘in connection with’ is essentially indeterminat[e] because connections, like relations, stop nowhere” (internal quotation marks omitted)). The Commission itself incorporated the D. C. Circuit’s standard in addressing its authority to issue the Rule. See 76 Fed. Reg. 16676, ¶112 (stating that FERC has jurisdiction because wholesale demand response “directly affects wholesale rates”). We think it right to do the same.
Still, the rules governing wholesale demand response programs meet that standard with room to spare. In general (and as earlier described), wholesale market operators employ demand response bids in competitive auctions that balance wholesale supply and demand and thereby set wholesale prices. See supra, at 7–8. The operators accept such bids if and only if they bring down the wholesale rate by displacing higher-priced generation. And when that occurs (most often in peak periods), the easing of pressure on the grid, and the avoidance of service problems, further contributes to lower charges. See Brief for Grid Engineers et al. as Amici Curiae 26–27. Wholesale demand response, in short, is all about reducing wholesale rates; so too, then, the rules and practices that determine how those programs operate.
And that is particularly true of the formula that operators use to compensate demand response providers. As in other areas of life, greater pay leads to greater participation. If rewarded at LMP, rather than at some lesser amount, more demand response providers will enter more bids capable of displacing generation, thus necessarily lowering wholesale electricity prices. Further, the Commission found, heightened demand response participation
Yet a FERC regulation does not run afoul of
And in setting rules for demand response, that is all FERC has done. The Commission’s Rule addresses—and addresses only—transactions occurring on the wholesale market. Recall once again how demand response works—and forgive the coming italics. See supra, at 7–8. Wholesale market operators administer the entire program, receiving every demand response bid made. Those operators accept such a bid at the mandated price when (and only when) the bid provides value to the wholesale market by balancing supply and demand more “cost-effective[ly]”—i.e., at a lower cost to wholesale purchasers—than a bid to generate power. 76 Fed. Reg. 16659, 16666, ¶2, 48. The compensation paid for a successful bid (LMP) is whatever the operator’s auction has determined is the marginal price of wholesale electricity at a particular location and time. See id., at 16659, ¶2. And those footing the bill are the same wholesale purchasers that
What is more, the Commission’s justifications for regulating demand response are all about, and only about, improving the wholesale market. Cf. Oneok, 575 U.S. 373 (considering “the target at which [a] law aims” in determining whether a State is properly regulating retail or, instead, improperly regulating wholesale sales). In Order No. 719, FERC explained that demand response participation could help create a “well-functioning competitive wholesale electric energy market” with “reduce[d] wholesale power prices” and “enhance[d] reliability.” 73 Fed. Reg. 64103, ¶16. And in the Rule under review, FERC expanded on that theme. It listed the several ways in which “demand response in organized wholesale energy markets can help improve the functioning and competitiveness of those markets”: by replacing high-priced, inefficient generation; exerting “downward pressure” on “generator bidding strategies”; and “support[ing] system reliability.” 76 id., at 16660, ¶10; see Notice of Proposed Rulemaking for Order No. 745, 75 id., at 15363–15364, ¶4 (2010) (noting similar aims); supra, at 7–8. FERC, that is, focused wholly on the benefits that demand response participation (in the wholesale market) could bring to the wholesale market. The retail market figures no more in the Rule’s goals than in the mechanism through which the Rule operates.
EPSA’s primary argument that FERC has usurped state power (echoed in the dissent) maintains that the Rule “effectively,” even though not “nominal[ly],” regulates retail prices. See, e.g., Brief for Respondents 1, 10, 23–27, 35–39; Tr. of Oral Arg. 26, 30; post, at 4–6. The argument
The modifier “effective” is doing quite a lot of work in that argument—more work than any conventional understanding of rate-setting allows. The standard dictionary definition of the term “rate” (as used with reference to prices) is “[a]n amount paid or charged for a good or service.” Black’s Law Dictionary 1452 (10th ed. 2014); see, e.g., 13 Oxford English Dictionary 208–209 (2d ed. 1989) (“rate” means “price,” “cost,” or “sum paid or asked for a . . . thing”). To set a retail electricity rate is thus to establish the amount of money a consumer will hand over in exchange for power. Nothing in
Consider a familiar scenario to see what is odd about EPSA’s theory. Imagine that a flight is overbooked. The airline offers passengers $300 to move to a later plane that has extra seats. On EPSA’s view, that offer adds $300—the cost of not accepting the airline’s proffered payment—to the price of every continuing passenger’s ticket. So a person who originally spent $400 for his ticket, and decides to reject the airline’s proposal, paid an “effective” price of $700. But would any passenger getting off the plane say he had paid $700 to fly? That is highly unlikely. And airline lawyers and regulators (including many, we are sure, with economics Ph. D.’s) appear to share that common-sensical view. It is in fact illegal to “increase the price” of “air transportation . . . after [such] air transportation has been purchased by the consumer.” 14 CFR §399.88(a) (2015). But it is a safe bet that no airline has ever gotten into trouble by offering a payment not to fly.9
EPSA’s second argument that FERC intruded into the States’ sphere is more historical and purposive in nature. According to EPSA, FERC deliberately “lured [retail customers] into the[ ] wholesale markets”—and, more, FERC did so “only because [it was] dissatisfied with the States’ exercise of their undoubted authority” under
That claim initially founders on the true facts of how wholesale demand response came about. Contra EPSA, the Commission did not invent the practice. Rather, and as described earlier, the impetus came from wholesale market operators. See supra, at 8. In designing their newly organized markets, those operators recognized almost at once that demand response would lower wholesale electricity prices and improve the grid’s reliability. So they quickly sought, and obtained, FERC’s approval to institute such programs. Demand response, then, emerged not as a Commission power grab, but instead as a market-generated innovation for more optimally balancing wholesale electricity supply and demand.
And when, years later (after Congress, too, endorsed the practice), FERC began to play a more proactive role, it did so for the identical reason: to enhance the wholesale, not retail, electricity market. Like the market operators, FERC saw that sky-high demand in peak periods threatened network breakdowns, compelled purchases from inefficient generators, and consequently drove up wholesale prices. See, e.g., 73 Fed. Reg. 64103, ¶16; 76 id., at 16660, ¶10; see supra, at 6–7. Addressing those problems—which demand response does—falls within the sweet spot of FERC’s statutory charge. So FERC took action promoting the practice. No doubt FERC recognized connections, running in both directions, between the States’ policies and its own. The Commission understood that by insulating consumers from price fluctuations, States contributed to the wholesale market’s difficulties in optimally balancing supply and demand. See 76 Fed. Reg.
Indeed, the finishing blow to both of EPSA’s arguments comes from FERC’s notable solicitude toward the States. As explained earlier, the Rule allows any State regulator to prohibit its consumers from making demand response bids in the wholesale market. See 76 id., at 16676, ¶114; 73 id., at 64119, ¶154; supra, at 12. Although claiming the ability to negate such state decisions, the Commission chose not to do so in recognition of the linkage between wholesale and retail markets and the States’ role in overseeing retail sales. See 76 Fed. Reg. 16676, ¶¶112–114. The veto power thus granted to the States belies EPSA’s view that FERC aimed to “obliterate[ ]” their regulatory authority or “override” their pricing policies. Brief for Respondents 29, 33. And that veto gives States the means to block whatever “effective” increases in retail rates demand response programs might be thought to produce. Wholesale demand response as implemented in the Rule is a program of cooperative federalism, in which the States retain the last word. That feature of the Rule removes any conceivable doubt as to its compliance with
C
One last point, about how EPSA’s position would subvert the FPA.
Yet state commissions could not regulate demand response bids either. EPSA essentially concedes this point. See Brief for Respondents 46 (“That may well be true”). And so it must. The FPA “leaves no room either for direct state regulation of the prices of interstate wholesales” or for regulation that “would indirectly achieve the same result.” Northern Natural Gas Co. v. State Corporation Comm’n of Kan., 372 U.S. 84, 91 (1963). A State could not oversee offers, made in a wholesale market operator’s auction, that help to set wholesale prices. Any effort of that kind would be preempted.
And all of that creates a problem. If neither FERC nor the States can regulate wholesale demand response, then by definition no one can. But under the Act, no electricity transaction can proceed unless it is regulable by someone. As earlier described, Congress passed the FPA precisely to eliminate vacuums of authority over the electricity markets. See supra, at 2–3. The Act makes federal and state
For that reason, the upshot of EPSA’s view would be to extinguish the wholesale demand response program in its entirety. Under the FPA, each market operator must submit to FERC all its proposed rules and procedures. See
And that outcome would flout the FPA’s core objects. The statute aims to protect “against excessive prices” and ensure effective transmission of electric power. Pennsylvania Water & Power Co. v. FPC, 343 U.S. 414, 418 (1952); see Gulf States Util. Co. v. FPC, 411 U.S. 747, 758 (1973). As shown above, FERC has amply explained how wholesale demand response helps to achieve those ends, by bringing down costs and preventing service interruptions in peak periods. See supra, at 20. No one taking part in the rulemaking process—not even EPSA—seriously challenged that account. Even as he objected to FERC’s compensation formula, Commissioner Moeller noted the unanimity of opinion as to demand response’s value: “[N]owhere did I review any comment or hear any testimony that questioned the benefit of having demand response resources participate in the organized wholesale energy markets. On this point, there is no debate.” 76 Fed. Reg. 16679; see also App. 82, EPSA, Comments on Proposed Rule (avowing “full[ ] support” for demand response participation in wholesale markets because of its “economic and operational” benefits).11 Congress itself
III
These cases present a second, narrower question: Is FERC’s decision to compensate demand response providers at LMP—the same price paid to generators—arbitrary and capricious? Recall here the basic issue. See supra, at 9–12. Wholesale market operators pay a single price—LMP—for all successful bids to supply electricity at a given time and place. The Rule orders operators to pay the identical price for a successful bid to conserve electricity so long as that bid can satisfy a “net benefits test”—meaning that it is sure to bring down costs for wholesale purchasers. In mandating that payment, FERC rejected an alternative proposal under which demand response providers would receive LMP minus G (LMP-G), where G is the retail rate for electricity. According to EPSA and others favoring that approach, demand response providers get a windfall—a kind of “double-payment”—unless market operators subtract the savings associated with conserving electricity from the ordinary compensation level. 76 Fed. Reg. 16663, ¶24. EPSA now claims that FERC failed to adequately justify its choice of LMP rather than
In reviewing that decision, we may not substitute our own judgment for that of the Commission. The “scope of review under the ‘arbitrary and capricious’ standard is narrow.” Motor Vehicle Mfrs. Assn. of United States, Inc. v. State Farm Mut. Automobile Ins. Co., 463 U.S. 29, 43 (1983). A court is not to ask whether a regulatory decision is the best one possible or even whether it is better than the alternatives. Rather, the court must uphold a rule if the agency has “examine[d] the relevant [considerations] and articulate[d] a satisfactory explanation for its action[,] including a rational connection between the facts found and the choice made.” Ibid. (internal quotation marks omitted). And nowhere is that more true than in a technical area like electricity rate design: “[W]e afford great deference to the Commission in its rate decisions.” Morgan Stanley, 554 U.S., at 532.
Here, the Commission gave a detailed explanation of its choice of LMP. See 76 Fed. Reg. 16661–16669, ¶¶18–67. Relying on an eminent regulatory economist’s views, FERC chiefly reasoned that demand response bids should get the same compensation as generators’ bids because both provide the same value to a wholesale market. See id., at 16662–16664, 16667–16668, ¶¶20, 31, 57, 61; see also App. 829–851, Reply Affidavit of Dr. Alfred E. Kahn (Aug. 30, 2010) (Kahn Affidavit). FERC noted that a market operator needs to constantly balance supply and demand, and that either kind of bid can perform that service cost-effectively—i.e., in a way that lowers costs for wholesale purchasers. See 76 Fed. Reg. 16667–16668, ¶¶56, 61. A compensation system, FERC concluded, therefore should place the two kinds of bids “on a competitive par.” Id., at 16668, ¶61 (quoting Kahn Affidavit); see also App. 830, Kahn Affidavit (stating that “economic efficiency requires” compensating the two equally given their equivalent function in a “competitive power mar-
That rationale received added support from FERC’s adoption of the net benefits test. The Commission realized during its rulemaking that in some circumstances a demand response bid—despite reducing the wholesale rate—does not provide the same value as generation. See 76 Fed. Reg. 16664–16665, ¶38. As described earlier, that happens when the distinctive costs associated with compensating a demand response bid exceed the savings from a lower wholesale rate: The purchaser then winds up paying more than if the operator had accepted the best (even though higher priced) supply bid available. See supra, at 10–11. And so FERC developed the net benefits test to filter out such cases. See 76 Fed. Reg. 16666–16667, ¶¶50–53. With that standard in place, LMP is paid only to demand response bids that benefit wholesale purchasers—in other words, to those that function as “cost-effective alternative[s] to the next highest-bid generation.” Id., at 16667, ¶54. Thus, under the Commission’s approach, a demand response provider will receive the same compensation as a generator only when it is in fact providing the same service to the wholesale market. See ibid., ¶53.
The Commission responded at length to EPSA’s contrary view that paying LMP, even in that situation, will overcompensate demand response providers because they are also “effectively receiv[ing] ‘G,’ the retail rate that they do not need to pay.” Id., at 16668, ¶60. FERC explained that compensation ordinarily reflects only the value of the
Moreover, FERC found, paying LMP will help demand response providers overcome certain barriers to participation in the wholesale market. See 76 Fed. Reg. 16667–16668, ¶¶57–59. Commenters had detailed significant start-up expenses associated with demand response, including the cost of installing necessary metering technology and energy management systems. See id., at 16661, ¶18, 16667–16668, ¶57; see also, e.g., App. 356, Viridity Energy, Inc., Comments on Proposed Rule on Demand Response Compensation in Organized Wholesale Energy Markets (May 13, 2010) (noting the “capital investments and operational changes needed” for demand response
Finally, the Commission noted that determining the “G” in the formula LMP-G is easier proposed than accomplished. See ibid., ¶63. Retail rates vary across and even within States, and change over time as well. Accordingly, FERC concluded, requiring market operators to incorporate G into their prices, “even though perhaps feasible,” would “create practical difficulties.” Ibid. Better, then, not to impose that administrative burden.
All of that together is enough. The Commission, not this or any other court, regulates electricity rates. The disputed question here involves both technical understanding and policy judgment. The Commission addressed that issue seriously and carefully, providing reasons in support of its position and responding to the principal alternative advanced. In upholding that action, we do not discount the cogency of EPSA’s arguments in favor of LMP-G. Nor do we say that in opting for LMP instead, FERC made the better call. It is not our job to render that judgment, on which reasonable minds can differ. Our important but limited role is to ensure that the Commission engaged in reasoned decisionmaking—that it weighed competing views, selected a compensation formula with adequate support in the record, and intelligibly explained the reasons for making that choice. FERC satisfied that standard.
IV
FERC’s statutory authority extends to the Rule at issue here addressing wholesale demand response. The Rule
It is so ordered.
JUSTICE ALITO took no part in the consideration or decision of these cases.
FEDERAL ENERGY REGULATORY COMMISSION, PETITIONER v. ELECTRIC POWER SUPPLY ASSOCIATION, ET AL.
Nos. 14–840 and 14–841
SUPREME COURT OF THE UNITED STATES
January 25, 2016
Cite as: 577 U. S. ____ (2016)
SCALIA, J., dissenting
I believe the Federal Power Act (FPA or Act),
I
A
I agree with the majority that FERC has the authority to regulate practices “affecting” wholesale rates.
The Act grants FERC authority to regulate the “generation . . . [and] transmission of electric energy in interstate commerce and the sale of such energy at wholesale.”
Properly framing the inquiry matters not because I think there exists “some undefined category of . . . electricity sales” that is “non-retail [and] non-wholesale,” ante, at 18, n. 7,* but because a proper framing of the inquiry is
So what, exactly, is a “sale of electric energy at wholesale”? We need not guess, for the Act provides a definition: “a sale of electric energy to any person for resale.”
It is therefore quite beside the point that the challenged “[r]ule addresses—and addresses only—transactions occurring on the wholesale market,” ante, at 19. For FERC’s regulatory authority over electric-energy sales depends not on which “market” the “transactions occu[r] on” (whatever that means), but rather on the identity of the putative purchaser. If the purchaser is one who resells electric energy to other customers, the transaction is one “at wholesale” and thus within FERC’s authority. If not, then not. Or so, at least, says the statute. As we long ago said of the parallel provision in the Natural Gas Act,
The demand-response bidders here indisputably do not resell energy to other customers. It follows that the rule does not regulate electric-energy sales “at wholesale,” and
B
The analysis could stop there. But the majority is wrong even on its own terms, for the rule at issue here does in fact regulate “retail electricity sales,” which are indisputably “matters . . . subject to regulation by the States” and therefore off-limits to FERC.
The majority resists this elementary economic conclusion (notwithstanding its own exhortation to “think back to Econ 101,” ante, at 5). Why? Because its self-proclaimed “common-sensical” view dictates otherwise. Ante, at 22. Maybe the easiest way to see the majority’s error is to take its own example: an airline passenger who rejects a $300 voucher for taking a later flight. Consider the following formulation of that example, indistinguishable in substance from the majority’s formulation. (Indistinguishable because the hypothetical passenger has exactly the same options and outcomes available to him.) Suppose the airline said to the passenger: “We have proactively canceled your ticket and refunded $400 to your account; and because we have inconvenienced you, we have also deposited an extra $300. The money is yours to use as you like. But if you insist on repurchasing a ticket on the same flight, you must not only pay us $400, but return the $300 too.” Now what is the effective price of the ticket? Sometimes an allegedly commonsensical intuition is just that—an intuition, often mistaken.
Moving closer to home, recall that demand-response participants must choose either to purchase a unit of energy at the prevailing retail price (say $10) or to withhold from purchasing that unit and receive instead an
In any event, the majority appears to recognize that the effective price is indeed $15—just as the effective price of the airline ticket in the hypothetical is $700. Ante, at 22–23, n. 9. That recognition gives away the game. For FERC is prohibited not just from directly setting or modifying retail prices; it is prohibited from regulating retail sales, no matter the means. Panhandle Eastern Pipe Line Co., supra, at 517. Whether FERC sets the “real” retail price (to use the majority’s idiosyncratic terminology, ante, at 23, n. 9) or the “effective” retail price is immaterial; either way, the rule—by design—induces demand-response participants to forgo retail electric-energy purchases they otherwise would have made. As noted, even FERC conceded that offering credits to retail customers would impermissibly regulate retail sales. The majority blithely overlooks this concession in favor of its own myopic view of retail pricing—all the while evading the inconvenient fact that fiddling with the effective retail price of electric energy, be it through incentive payments or hypothetical credits, regulates retail sales of electric energy no less than does direct ratesetting.
C
The majority cites dicta in several of our opinions expressing the assumption that state jurisdiction and federal jurisdiction under FERC cover the field, so that there is no
“[W]hen a dispute arises over whether a given transaction is within the scope of federal or state regulatory authority, we are not inclined to approach the problem negatively, thus raising the possibility that a ‘no man’s land’ will be created. That is to say, in a borderline case where congressional authority is not explicit we must ask whether state authority can practicably regulate a given area and, if we find that it cannot, then we are impelled to decide that federal authority governs.” Transcontinental Gas Pipe Line Corp., supra, at 19–20 (citation omitted).
That extravagant and otherwise-unheard-of method of establishing regulatory jurisdiction was not necessary to the judgments that invoked it, and should disappear in the Court’s memory hole.
The majority is evidently distraught that affirming the decision below “would . . . extinguish the wholesale demand response program in its entirety.” Ante, at 27. Alarmist hyperbole. Excluding FERC jurisdiction would at most eliminate this particular flavor of FERC-regulated demand response. Nothing prevents FERC from tweaking its demand-response scheme by requiring incentive payments to be offered to wholesale customers, rather than retail ones. Brief for Respondent Electric Power Supply Assn. (EPSA) et al. 47–48; Brief for Respondents Midwest Load-Serving Entities 10–11. And retail-level demand-response programs, run by the States, do and would continue to exist. See Brief for Respondent EPSA et al. 46–47; Brief for Respondents Midwest Load-Serving Entities
Moreover, the rule itself allows States to forbid their retail customers to participate in the existing demand-response scheme.
II
Having found the rule to be within FERC’s authority, the Court goes on to hold that FERC’s choice of compensating demand-response bidders with the “locational marginal price” is not arbitrary and capricious. There are strong arguments that it is. Brief for Robert L. Borlick et al. as Amici Curiae 5–34. Since, however, I believe FERC’s rule is ultra vires I have neither need nor desire to analyze whether, if it were not ultra vires, it would be reasonable.
* * *
For the foregoing reasons, I respectfully dissent.