delivered the opinion of the Court.
These three consolidated appeals present the question whether a state can constitutionally prohibit the exportation of hydroelectric energy produced within its borders by a federally licensed facility, or otherwise reserve for its own citizens the “economic benefit” of such hydroelectric power.
I
Appellant New England Power Co. is a public utility which generates and transmits electricity at wholesale. It sells 75% of its power in Massachusetts and much of the remainder in Rhode Island; less than 6% of New Hampshire’s population is serviced by New England Power’s wholesale customers. New England Power owns and operates six hydroelectric generating stations on the Connecticut River, consisting of 27 generating units. Twenty-one of these units—with a capacity of 419.8 megawatts, or about 10% of New England Power’s total generating capacity—are located within the State of New Hampshire. The units are licensed by the Federal En
New England Power is a member of the New England Power Pool, whose utility-members own over 98% of the total generation capacity, and virtually all of the transmission facilities, in the six-state region. The objectives of the Power Pool, as described in the agreement among its members, are to assure the reliability of the region’s bulk power supply and to attain “maximum practicable economy” through, inter alia, “joint planning, central dispatching . . . and coordinated construction, operation and maintenance of electric generation and transmission facilities owned or controlled by the Participants . . . .” New England Power Pool Agreement §4.1, App. 31a. All member-owned generating facilities are placed under the control of the Power Pool’s Dispatch Center. A computer calculates the cost of generation for each generating unit and assigns each unit an operating schedule that will minimize the cost of the region’s total power supply. Power generated at the various units, including New England Power’s Connecticut River hydroelectric stations, flows freely through the Pool’s regional transmission network, or “grid.” The energy is dispatched to members’ customers as their power needs arise, without regard to generating source. The Pool bills each member the amount it would have cost the utility to meet its customers’ load using only its own generating sources, minus that member’s share of the savings resulting from the centralized dispatch system. 1
“No corporation engaged in the generation of electrical energy by water power shall engage in the business of transmitting or conveying the same beyond the confines of the state, unless it shall first file notice of its intention so to do with the public utilities commission and obtain an order of said commission permitting it to engage in such business.” N. H. Rev. Stat. Ann. §374:35 (1966).
The statute empowers the New Hampshire Commission to prohibit the exportation of such electrical energy when it determines that the energy “is reasonably required for use within this state and that the public good requires that it be delivered for such use.” Ibid.
Since 1926, New England Power or a predecessor company periodically applied for and obtained approval from the New Hampshire Commission to transmit electricity produced at the Connecticut River plants to points outside New Hampshire. However, on September 19, 1980, after an investigation and hearings, the Commission withdrew the authority formerly granted New England Power to export its hydroelectric energy, and ordered the company to “make arrangements to sell the previously exported hydroelectric energy to persons, utilities and municipalities within the State of New Hampshire . . . .”
2
In its report accompanying the order,
The Commission did not, however, order New England Power to sever its connections with the Power Pool. So long as the electricity produced at New England Power’s hydroelectric plants continues to flow through the Pool’s regional transmission network, it will be impossible to contain that electricity within the State of New Hampshire in any physical sense. Although the precise contours of the Commission’s order are unclear, it appears to require that New England Power sell electricity to New Hampshire utilities in an amount equal to the output of its in-state hydroelectric facilities, at special rates adjusted to reflect the entire savings attributable to the low-cost hydroelectric generation. 3
We noted probable jurisdiction,
M h-H
The Supreme Court of New Hampshire recognized that, absent authorizing federal legislation, it would be “questionable” whether a state could constitutionally restrict interstate trade in hydroelectric power. 120 N. H., at 876,
The Supreme Court of New Hampshire nevertheless upheld the order of the New Hampshire Commission on the ground that § 201(b) of the Federal Power Act expressly permits the State to prohibit the exportation of hydroelectric power produced within its borders. It is indeed well settled
Ill
The national concern for planning, development, and comprehensive utilization of the country’s water resources was very early expressed by Congress under its Commerce Clause powers. The Federal Water Power Act, now Part I of the Federal Power Act, 16 U. S. C. §§791a-823 (1976 ed. and Supp. IV), was enacted in 1920. The potential of water power as a source of electric energy led Congress to exercise its constitutional authority over navigable streams to regulate and encourage development of hydroelectric power generation “to meet the needs of an expanding economy.”
FPC
v.
Union Electric Co.,
In 1935, Congress enacted Part II of the Federal Power Act, 16 U. S. C. §§ 824-824k (1976 ed. and Supp. IV), which delegated to the Federal Power Commission, now the Federal Energy Regulatory Commission, exclusive authority to regulate the transmission and sale at wholesale of electric energy in interstate commerce, without regard to the source of production.
United States
v.
Public Utilities Comm’n of California,
To support its argument to the contrary, New Hampshire relies on a single statement made on the floor of the House of
“[T]he Senate bill as originally drawn would deprive certain States, I think five in all, of certain rights which they have over the exportation of hydroelectric energy which is transmitted across the State line. This situation has been taken care of by the House committee, and I hope when you come to it, section 201 of part II, that you will grant us the privilege to continue, as we have been for 22 years, to exercise our State right over the exportation of hydroelectric energy transmitted across State lines but produced up there in the granite hills of old New Hampshire.” 79 Cong. Rec. 10527 (1935).
From this expression of “hope,” New Hampshire concludes that Congress specifically intended to preserve the very statute at issue here.
Reliance on such isolated fragments of legislative history in divining the intent of Congress is an exercise fraught with hazards, and “a step to be taken cautiously. ”
Piper
v.
Chris-Craft Industries, Inc.,
To be sure, some Members of Congress may have thought that no further protection of state authority was needed.
8
We conclude, therefore, that New Hampshire has sought to restrict the flow of privately owned and produced electricity in interstate commerce, in a manner inconsistent with the Commerce Clause. Section 201(b) of the Federal Power Act does not provide an affirmative grant of authority to the State to do so. For these reasons, the judgment of the Supreme Court of New Hampshire is reversed, and the case is remanded for further proceedings not inconsistent with this opinion.
So ordered.
Notes
Testimony before the New Hampshire Public Utilities Commission in these cases indicated that the savings have been substantial. For example, in 1979, the savings attributable to the Power Pool’s centralized dis
The order reads:
“ORDERED, that the permission granted New England Power Company (NEPCO) to transmit hydroelectric energy from within the boundaries of the State to outside the State is hereby withdrawn as of thirty (30) days from the date of this Order; and it is
“FURTHER ORDERED, that NEPCO make arrangements to sell the previously exported hydroelectric energy to persons, utilities and municipalities within the State of New Hampshire within thirty (30) days of the date of this Order; and it is
“FURTHER ORDERED, that upon the completion of both units at Seabrook the Commission will again re-examine the issue of exportation.”
For example, the Commission’s staff economist testified at the hearings that New England Power could “allocate the benefits of low-cost hydroelectric power to New Hampshire through billing mechanisms” pursuant to which the power would be sold in New Hampshire at “economic cost”—
i. e.,
the cost of producing the power, including depreciation, plus a return on invested capital. App. 38a-39a. The economist’s analysis of the
The court also dismissed several arguments advanced only by appellants Massachusetts and Roberts — that § 201(b), as so interpreted, exceeded Congress’ power under the Commerce Clause, Art. I, § 8, cl. 3, and violated both the Privileges and Immunities Clause, Art. IV, § 2, cl. 1, and the Tenth Amendment of the Constitution.
The parties inform us that the New Hampshire Commission has refrained from acting on remand pending this Court’s disposition of the appeals.
We find no merit in New Hampshire’s attempt to distinguish these cases on the ground that it “owns” the Connecticut River, the source of New England Power’s hydroelectricity. Whatever the extent of the State’s proprietary interest in the river, the pre-eminent authority to regu
Indeed, had Congress intended § 201(b) to confer upon the states powers which they would have lacked in the absence of the federal legislation, it would have been anomalous to speak in terms of “authority now exercised.” This language plainly assumes the prior existence of valid state authority; in addition, it appears to limit the saving effect of the provision to those few States in which the authority was in fact “exercised” in 1935.
On the other hand, it would not have been at all unusual had Congress taken care that the 1935 enactment not displace state authority in the area,
We need not speculate here as to the precise contours of § 201(b)’s saving effect.
Even were we to conclude that Congress intended §201(b) to override restraints placed on state regulatory power by the Commerce Clause, there would remain a substantial question whether the order of the New Hampshire Commission was entitled to protection under that provision. Section 201(b) seeks to protect only state regulation relating to the “exportation” of hydroelectric power. However, New England Power cannot terminate its out-of-state transmission of hydroelectricity without substantial alterations in the regional transmission- system to which its hydroelectric facilities are connected — alterations which the New Hampshire Commission did not appear to contemplate would be made.
Appeal of New England Power Co.,
120 N. H. 866, 876-877,