DALLAS/FORT WORTH INTERNATIONAL AIRPORT BOARD v. INET AIRPORT SYSTEMS, INCORPORATED; Michael F. Colaco; Hartford Fire Insurance Company, Inet Airport Systems, L.L.C., as Successor in Interest to Inet Airport Systems, Incorporated
Nos. 15-10390, 15-10600
United States Court of Appeals, Fifth Circuit
April 12, 2016
819 F.3d 245
This is not to say that the evidence would not support Rite Way‘s more mundane version of events. But the difficult task of resolving this “conflict in substantial evidence” falls to the jury. Long, 88 F.3d at 308 (internal quotation marks and citation omitted). We REVERSE and REMAND for further proceedings.
Joe D. Tolbert, Russell Rhea Barton (argued), Harris, Finley & Bogle, P.C., Luis Alfredo Galindo, Fort Worth, TX, for Plaintiff-Appellant.
David Alan Walton (argued), Beirne, Maynard & Parsons, L.L.P., Dallas, TX, Jason H. Anderson, Esq., Stephen L. Ram, Esq., Craig A. Taggart (argued), Stradling, Yocca, Carlson & Rauth, Newport Beach, CA, for Defendant-Appellee.
HAYNES, Circuit Judge:
The Dallas/Fort Worth International Airport Board (“DFW“) appeals the final judgments of the district court against DFW in favor of INET Airport Systems, Inc. (“INET“),1 Michael F. Colaco, and Hartford Fire Insurance Company (“Hartford“). The cross-motions for summary judgment and this appeal relate to a contract between DFW and INET for construction at DFW Airport. The parties accuse each other of breaching the contract following a dispute regarding the proper configuration and installation of rooftop air handling units for passenger boarding bridges in Terminal E of the DFW Airport. In addition to INET, DFW sued Colaco individually as an officer and director of INET, and Hartford as the bonding agency for INET on the contract at issue. INET counterclaimed for breach of contract against DFW, claiming entitlement to money DFW did not pay INET that INET alleged it was owed under their agreement, as well as attorneys’ fees and legal expenses. INET also counter-
The district court granted summary judgment against DFW on INET‘s affirmative defenses of excuse and prior material breach of the contract by DFW and also dismissed claims against Colaco. The court dismissed DFW‘s claims against Hartford based on Hartford‘s statute of limitations defense. Finally, the district court denied in part DFW‘s motion for summary judgment, which claimed that INET breached the contract, and granted DFW‘s motion in part as to INET‘s counterclaims of unjust enrichment and money had and received. DFW timely appealed these final judgments, and those appeals were consolidated before us.2
Because we find that material factual disputes remain unresolved, we REVERSE the district court‘s grant of summary judgment in favor of INET on INET‘s claims of excuse and prior material breach of the contract by DFW, and REMAND for trial. We also REVERSE and REMAND the district court‘s grant of summary judgment for Hartford, as disputes of material fact remain over whether DFW filed suit against Hartford within the statute of limitations. Finally, we VACATE the district court‘s subsequent final judgment awarding damages to INET because it was based on the district court‘s summary-judgment determination that DFW should be liable to INET.
I. Jurisdiction and Standard of Review
We have jurisdiction over DFW‘s appeals of the final orders of the district court under
II. Background
A. Factual Background
DFW and INET entered into Contract No. 9500377 (the “Contract“) in August 2009 for a project in Terminal E of DFW Airport, in which pre-conditioned air and rooftop air handling units (“Rooftop Units“) were to provide conditioned air (cooling and heating) to passenger boarding bridges and aircrafts parked at terminal gates. INET won the Contract through a competitive bidding process and agreed to follow the Contract‘s terms, plans, and specifications for the construction work. In submitting its bid proposal, INET certified that its proposal constituted prima facie evidence that it had examined “the site of the proposed work, the proposal, plans, specifications, and contract forms,” and satisfied itself as to the materials furnished, requirements of the Contract, plans, specifications, and site conditions.
Campos Engineering (“Campos“) prepared the design for the project for DFW, including the plans and specifications. INET was not allowed to substitute products or designs for those agreed upon in the Contract documents without authorization from DFW. The Contract also contained provisions requiring INET to alert DFW immediately to any “apparent error or omission in the plans or specifications” so that DFW could make a final decision about how to proceed. If the completion of the Contract required extra work for which payment had not been delineated, the Contract provided that this extra work should be covered by “a written change order” issued by DFW with “agreed prices for performing the change order work.” DFW was to reject any claim for payment not covered by written change order or supplemental agreement.
Trouble arose when INET expressed concern to DFW that the Rooftop Units specified in the plans and selected by INET in the Contract might not function correctly with the EG Water mixture. INET informed DFW of this potential problem during the construction kick-off meeting on October 14, 2009—specifically, that the EG Water supplied by DFW‘s pipes would be at sub-freezing temperatures, causing ice to build up on the outer surface of the Rooftop Unit coils and keeping the coils from performing as required. After receiving no immediate response to this concern, INET submitted a “Request for Information,” or “RFI,” asking how it should proceed (hereinafter, “RFI-2“).
DFW, Campos, and INET corresponded about this issue through extensive discussions that resulted in two proposals for how to add control sequences (“Control Sequence Proposal“) or revised piping (“Revised Piping Proposal“) to the Rooftop Units to prevent potential defects. The record does not indicate that the parties ever reached any agreement on whether to adopt these propоsals or how to proceed. Eventually, DFW notified INET that INET had failed to meet the substantial completion deadline and that DFW would begin assessing liquidated damages. DFW declined to pay at least one invoice submitted by INET after this date, and in April 2012, DFW made a claim against Hartford on the performance bond. DFW, INET, and Hartford corresponded throughout 2012. DFW had the remaining work on the Rooftop Units completed by a substitute contractor by contract dated July 9, 2013.
In June 2012, DFW took official action related to the Contract with INET. The parties dispute whether this action terminated the Contract and if not, when the Contract was terminated or abandoned. Timing is relevant because DFW filed suit on August 5, 2013, and the district court dismissed DFW‘s claims against Hartford as barred by Texas‘s one-year statute of limitations for suits on performance bonds. See
B. Procedural History
In response to the parties’ various motions, the district court granted DFW‘s
III. Discussion
The dispute between the parties turns on where the Contract allocated the risk of defective plans and specifications, whether the plans and specifications were in fact defective, and what was required of each party once INET claimed it found a defect that would prevent its performance. We conclude it was error to grant summary judgment for INET on the basis that DFW first breached the Contract. The record contains disputes of material fact regarding which party prevented performance by failing to fully cooperate in arriving at a solution once the parties discovered defects.
A. Defective Plans and Specifications and the Contract‘s Allocation of Risk
The district court correctly concluded there was no disputе of material fact regarding whether the plans and specifications were defective and had to be changed for the Rooftop Units to function properly. We therefore must determine how the Contract allocated the risk of defective plans and specifications. The district court concluded that the Contract allocated this risk to DFW and that DFW breached the Contract by insufficiently cooperating with INET to resolve problems created by the defective plans and specifications. We conclude that while DFW partly bore the risk of defective plans and specifications under this Contract, the language of the Contract requires both parties to participate in resolving such defects.
Texas law allows contracting parties to allocate the risk of defective designs, plans, and specifications to an owner (in this case, DFW), rather than the contractor (INET), but this “require[s] contractual language indicating an intent to shift the burden of risk to the owner.” ICC, 407 F.3d at 720; see also Millgard Corp. v. McKee/Mays, 49 F.3d 1070, 1071-73 (5th Cir.1995). The language of this Contract allocates the risk of defects at least partially to DFW, in that it requires DFW to cooperate through a change order or other actions in the event that INET brings a discrepancy to DFW‘s attention. For example, Special Provision4 6.0(D),
Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of Owner furnished material or design furnished by the OWNER or for the repair of any damage that results from any defect in material or designs furnished by the OWNER.
Special Provision 31.0 states:
In case of conflict, discrepancies, errors or omissions among the various Contract documents, the matter shall be submitted immediately by Contractor to the Construction Manager for decision, and such decision shall be final. Any Work affected by such conflicts, discrepancies, errors or оmissions which is performed prior to the Construction Manager[‘s] determination shall be performed at the Contractor‘s risk.
These provisions seem to allocate the risk of defects to DFW. Yet, the Contract allocated some duties to INET as well, duties that required INET to cooperate or take other actions in this case to help resolve the discrepancy between the Contract‘s requirements and the designs and specifications. Various General Provisions support INET‘s duties to: (1) inspect the plans and specifications and bring up discrepancies during the bidding process;5 (2) otherwise assume full responsibility for the compatibility of equipment and parts;6 and (3) fill in details necessary to complete the work as specified, including “[n]ecessary controls to provide auto defrost of the coils.”7 INET assumed “sole responsibility” for compliance with the Contract documents, and “full responsibility for satisfactory operation of all component parts of the mechanical systems to assure compatibility of all equipment and performance of the integrated systems in accordance with the requirements of the specifications.” Furthermore, INET had to strictly conform its performance to the designs, plans, and specifications of the Contract.8 Yet, the Contract allowed INET to submit potential errors or discrepancies to DFW and obtain approval for a change in the design.9
In sum, the Contract in this case contains a mixture of provisions that place the risk of defects on both DFW and INET. INET agreed that it would provide a control sequence and other mechanisms to ensure defrosting of the coils within the Rooftop Units; that it had inspected the plans and specifications and would point out potential problems before bidding; that all equipment would be compatible with DFW‘s system; and that it would fill in details as necessary. INET discovered a defect in the plans and specifications, which contained very detailed requirements that INET was not free to disregard or redesign without DFW‘s approval. Therefore, DFW also agreed to provide change orders if INET pointed out defects in the plans, and the Contract allows DFW and INET to resolve any such defеcts discovered after the Contract‘s execution by mutual agreement. The district court correctly concluded DFW had a duty to cooperate with INET and issue a change order if necessary to correct defects. However, INET‘s agreement was also required for such a process under the Contract, and INET had duties that required it to cooperate in finding a solution to any defects. We therefore address whether there are disputes of material fact in the record regarding which party breached the Contract by failing to cooperate and find a solution to the defect.
B. Breach of the Contract
Texas law excuses а party‘s performance under a contract when the other party‘s breach prevents its performance. See, e.g., Transverse, L.L.C. v. Iowa Wireless Servs., L.L.C., 617 F. App‘x 272, 277 (5th Cir.2015);11 L.H. Land Painting Co. v. S & P Constr., Inc., 516 S.W.2d 14, 16 (Tex.Civ.App.—Fort Worth 1974, writ dism‘d).12 Texas courts have held that an
The parties discussed two possible modifications of the plans and specifications that might have addressed the defects INET discovered, known as the Control Sequence Proposal and the Revised Piping Proposal. The record is clear that INET did not agree to the Control Sequence Proposal, as INET admits in its brief.13 In March 2010, Campos sent DFW another possibility, thе Revised Piping Proposal, which DFW forwarded to INET that same month.
A dispute of material fact remains regarding whether INET rejected the Revised Piping Proposal outright or hindered the process of agreeing to this or another solution. INET sent DFW requests for information related to the Revised Piping Proposal in April 2010, requesting details and formal documentation from DFW so that INET could “price this change.” DFW responded with information about some of the technical details of the Revised Piping Proposal, but the record does not show that DFW or INET ever formally priced this change or modified their Contract to incorporate the Revised Piping Proposal. Based on its requests for information, INET argues DFW breached the Contract by failing to cooperate in issuing a change order and incorporating the Revised Piping Proposal into the Contract.
However, DFW argues INET rejected the Revised Piping Proposal, pointing to correspondence between INET and DFW.14 For example, in April 2010, INET
performance by the other party, the latter‘s failure to perform will be excused and the offending party will not be permitted to recover damages for nonperformance. But, this principle has no application when the party whose performance was prevented entеred into the contract fully aware of the obstacles which would prevent his performance.” (citations omitted)); Owens v. William H. Banks Warehouses, Inc., 202 F.2d 689, 692 (5th Cir.1953) (same).
Significant evidence in the record suggests that the рarties attempted to agree about how to address INET‘s concerns, and that INET and DFW both took strong positions about the necessary solution. In these circumstances the Contract required both parties to participate in resolving defects. Any contractual modification or change order required the mutual assent of the parties, and questions of mutual assent are fact based. Sifting through the evidence to determine whether the parties reached agreement on a contractual modification is a task ill-suited for summary judgment on this record. For these reasons, and because disputes of material fact remain regarding whether DFW or INET breached the Contract by preventing an agreement about how to address defects in the Contract‘s plans and specifications, we reverse the district court‘s grant of summary judgment for INET.here.
C. Hartford‘s Statute of Limitations Defense
The district court dismissed DFW‘s claim against Hartford based on Hartford‘s affirmative defense that the claim was barred by the statute of limitations. DFW filed suit against Hartford and INET on August 5, 2013. In Texas, “[a] suit on a performance bond may not be brought after the first anniversary of the date of final completion, abandonment, or termination of the public work contract.”
1. Termination of the Contract
It is undisputed that on June 7, 2012, the Board passed the following resolution (“Resolution“):
BE IT RESOLVED BY THE [DFW] BOARD
That the Chief Executive or designee be authorized to terminate Contract No. 950377 . . . and to pursue any other relief to which the Board may be entitled.
On the same document containing the resolution, the “Description” section stated: “This action will terminate Contract No. 9500377 [with INET].” The Action section of the documеnt repeated the language of the Resolution itself just above the bulletpoint “Description.” Under “Justification,” the document says “Board staff recommends the termination of this contract and seeks authorization to pursue any relief to which the Board may be entitled by reason of the contractor‘s default.”
2. Abandonment of the Contract
The district court concluded in the alternative that INET abandoned the contract long before August 2012, noting in summary fashion that DFW alleged that after October 2010, INET would do no further work on the Contract. As with termination, Hartford has the burden to show the parties abandoned the Contract befоre August 2012. See Int‘l Shortstop, 939 F.2d at 1264-65. “‘Abandonment’ is principally a matter of intention which must be established by clear and satisfactory evidence,” and if relying on conduct, “the acts relied upon must be positive, unequivocal and inconsistent with the existence of the contract.” Capital Steel & Iron Co. v. Standard Accident Ins. Co., 299 S.W.2d 738, 740-41 (Tex.App.—Amarillo 1952, no writ) (citations omitted). We discern no such positive, unequivocal conduct that is inconsistent with the existence of a continuing Contract between INET and DFW. Rather, record evidence creates a fact issue about whether either party intended to terminate or abandon the Contract before August 2012. Accordingly, we reverse the district court‘s grant of summary judgment for Hartford and remand for further proceedings.
IV. Conclusion
Because disputes of material fact remain, we REVERSE the grants of summary judgment for INET and Hartford
