Welsbach Electric Corp. v. MasTec North America, Inc.Welsbach Electric Corp. v. MasTec North America, Inc.
Ordered that the order is affirmed insofar as appealed from, with costs.
In September 1999 the defendant, an entity incorporated in the State of Florida, entered into a primary contract with Telergy Metro LLC (hereinafter Tеlergy), a nonparty, to serve as general contractor for a construction project in New York City. The primary contract included a termination clause which provided the defendant with a right to terminate the contract if Telergy became insolvent.
Thereafter, on or about November 28, 2000, the defendant entered into an agreement with the plaintiff to serve as a subcontractor for the project (hereinafter the subcontract). The subcontract, which was governed by Florida law, included a “pay-when-paid” provision which made the defendant‘s obligation to pay the plaintiff contingent upоn and subject to the defendant‘s receipt of payment from Telergy for work performed. The subcontract also included a termination provision which provided that upon termination of the primary contract, the subcontract would also be terminated upon the same basis and upon the same effective date as the primary contract.
When Telergy became insolvent in August 2001, the primary contract and the subcontract were both terminated. Neither the plaintiff nor the defendant received payment for work performed on the project.
The plaintiff subsequently commenced this action to recover moneys allegedly due and outstanding under the subcontract. The defendant asserted, inter alia, as affirmative defenses that the pay-when-paid provision and the termination provision of the subcontract relieved it of any payment obligation. Thereafter, the plaintiff moved, among othеr things, for summary judgment dismissing those affirmative defenses, and the Supreme Court granted that relief. We affirm.
Generally, the courts of this State will uphold choice-of-law provisions unless the jurisdiction whose law is to be upheld has no reasonable relation to the subject agreement, or enforcement of the provisiоn would violate a fundamental public policy of this State (see Cooney v Osgood Mach., 81 NY2d 66, 78-79 [1993]; Schultz v Boy Scouts of Am., 65 NY2d 189, 202 [1985]; Culbert v Rols Capital Co., 184 AD2d 612, 613 [1992]).
The New York Court of Appeals stated in Schultz v Boy Scouts of Am. (supra at 202) that: “Public policy is found in the State‘s
Although the pay-when-paid provision at issue is enforceable under Florida law (see Everett Painting Co., Inc. v Padula & Wadsworth Constr., Inc., 856 So 2d 1059 [2003] [Fla App]), the New York Court of Appeals held in West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co. (87 NY2d 148 [1995]) that a pay-when-paid provision which forces a subcontractor to assume the risk that the owner will fail to pay the general contractor is void and unenforceable as contrary to public policy as set forth in
The
In West-Fair, the New York Court of Appeals reviewed the Legislature‘s intent in enacting
While we agree with our dissenting colleague that the foreign jurisdiction (i.e., the State of Florida) has a reasonable relationship to the subject agreement (see generally Finucane v Interior Constr. Corp., 264 AD2d 618, 620 [1999]) predicated on the defendant‘s incorporation in Florida and the underlying Florida choice-of-law provision, we nonetheless find that enforcement of the pay-when-paid provision would violate the public policy of this State (see West-Fair Elec. Constr. v Aetna Cas. & Sur. Co., supra).
Our dissenting colleague relies on the decision of the Appellate Division, First Department, in Hugh O‘Kane Elec. Co., LLC v MasTec N. Am., Inc. (19 AD3d 126 [2005]), in which that court determined that the pay-when-paid provision at issue was valid pursuant to the parties’ Florida choice-of-law provision, and that the prohibition against this type of provision is not a deeply rooted tradition of this State. However, we do not find the reasoning and conclusion of the Appellate Division, First Department, in O‘Kane to be persuasive.
In reaching its conclusion, the Appellate Division, First Department, indicated in O‘Kane that between 1929 (when
We note that
Notwithstanding the First Department‘s recognition in O‘Kane that before 1975, subcontractors could possibly waive their lien rights to the extent that where, as here, a pay-when-paid provision operates to effect a waiver expressly proscribed by
Therefore, in light of the foregoing, we conclude that the Supreme Court correctly granted the relief requested. Cozier, J.P., Mastro and Fisher, JJ., concur.
Krausman, J., dissents and votes to reverse the order insofar as appeаled from, on the law, deny that branch of the motion which was to dismiss the fifth and eleventh affirmative defenses, and reinstate those affirmative defenses, with the following memorandum:
As noted by the majority, the facts relevant to this appeal are largely undisputed. On September 10, 1999, the defendant MasTec North America, Inc. (hereinafter MasTec), was hired to construct a fiber optic telecommunications network for Telergy Metro, LLC (hereinafter Telergy). Over one year later, on or about November 28, 2000, MasTec entered into an agreement to subcontract electrical work to the plaintiff Welsbach Electric Corp. (hereinafter Welsbach). The subcontract, which the parties agreed would be governed by Florida law, contained a pay-when-paid provision which stated, inter alia, that “all payments to Subcontractor by Contractor are expressly contingent upon and subject to receipt of payment for the Work by Contractor from Owner.” Both the primary contract and the subcontract werе terminated in August 2001, apparently due to Telergy‘s
As a general rule, where the parties have agreed upon the law that will govern their contract, their choice of law will be given effeсt provided that the jurisdiction whose law is to be applied has a reasonable relationship to the agreement, and enforcement would not violate a fundamental public policy of New York (see Finucane v Interior Constr. Corp., 264 AD2d 618 [1999]; Marine Midland Bank v United Mo. Bank, 223 AD2d 119, 122-123 [1996]; Culbert v Rols Capital Co., 184 AD2d 612, 613 [1992]). Here, the record indicates that MasTec is a Florida corporation alleged to be headquartered in Miami. Thus, even though the subject agreement was for work to be performed in New York, Florida can be said to have a “reasonable relationship” to the parties’ contract (Finucane v Interior Constr. Corp., supra at 620). Accordingly, resolution of this appeal turns on the issue of whether New York should refuse to honor the рarties’ choice-of-law agreement on public policy grounds.
In Cooney v Osgood Mach. (81 NY2d 66, 78 [1993]), the Court of Appeals explained that a public policy exception to general choice-of-law principles applies “when otherwise applicable foreign law would ‘violate some fundamental prinсiple of justice, some prevalent conception of good morals, some deep-rooted tradition of the common weal’ (Loucks v Standard Oil Co. 224 NY 99, 111 [1918]).” While this State‘s constitution, statutes, and judicial decisions are a reflection of its public policy, the Court of Appeals cautioned in Cooney that “not every differenсe between foreign and New York law threatens our public policy.” Rather, “resort to the public policy exception should be reserved for those foreign laws that are truly obnoxious” (id. at 79). In my view, the public policy reflected by
As amended in 1975,
However, the fact that
Moreover, in determining whether enforcement of the pay-when-paid provision in the parties’ subcontract so contravenes the public policy of this State that their choice of law should be nullified, it is important to note that this agreement was freely