West-Fair Electric Contractors, and L.J. Coppola, Inc. v. Aetna Casualty & Surety Company, and Gilbane Building CompanyWest-Fair Electric Contractors, and L.J. Coppola, Inc. v. Aetna Casualty & Surety Company, and Gilbane Building Company
This appeal from a judgment of the United States District Court for the Southern District-of New York, Brieant, J., came on to be heard on the record from said district court and was argued by counsel.
We believe the resolution of the issues presented in this appeal depends on the resolution of unsettled questions of New York state law. Therefore, on consideration of the briefs, appendix, record and the oral argument in this appeal, it is hereby ordered that the Clerk of the Court transmit to the Clerk of the New York Court of Appeals a Certificate in the form attached, together with a complete set of the briefs, appendix, and record filed with this Court by the parties. This panel retains jurisdiction so that, after we receive a response from the New York Court. of Appeals, we may dispose of the appeal. The parties are hereby ordered to bear equally such fees and costs, if any, as may be requested by the New York Court of Appeals.
Certificate to the New York Court of Appeals pursuant to McKinney’s Revised 1993 New York Rules of Court § 500.17(b) (certification of unsettled questions of state law).
L.J.' Coppola, Inc. (Coppola) seeks to recover on its written subcontract with Gilbane Construction Co. (Gilbane),' or on a surety bond executed by Aetna Casúalty & Surety Company (Aetna), for plumbing work performed on a construction project in White Plains, New York. Gilbane organized Coppola and other subcontractors for the project under a general contract with Fischer-Reese White Plains Associates L.P. (Fischer-Reese), the project’s owner. Coppola, alleged in its complaint that, beginning on September 15,1993 Gilbane encouraged Coppola to accelerate and complete its work by representing that financing from Fischer-Reese was only available for work completed through October 14, 1993. Coppola substantially completed its work by that date, but was not paid approximately $220,000 it was owed under its subcontract. Gilbane in turn was not paid by Fischer-Reese, which subsequently became insolvent.
Coppola’s subcontract is silent as to the consequences of Fiseher-Reese’s insolvency. Fischer-Reese maintained no payment bond for Gilbane’s benefit, although Gilbane maintained a payment bond through Aetna for the benefit of all of its subcontractors. That bond did not incorporate, however, the terms of the subcontract between Coppola and Gil-bane. Section 3.2 of the subcontract ren *50 dered payment to Coppola dependent on Gil-bane’s receipt of payment from Fischer-Reese:
It is specifically understood and agreed that the payment to the trade contractor is dependent, as a condition precedent, upon the construction manager receiving contract payments, including retainer from the owner.
(emphasis added). Gilbane refused .to pay Coppola the amount owed under its subcontract based on this “pay-when-paid” provision, and Aetna likewise refused to pay the amounts owed on the surety bond based on Gilbane’s limitation of liability.
The pay-when-paid provision created a condition precedent that transferred the risk of Fischer-Reese’s default to Coppola.
See David Fanarof, Inc. v. Dember Constr. Co.,
Notwithstanding the provisions of any other law, any contract, agreement or understanding whereby the right to file or enforce any lien created under article two is waived, shall be void as against public policy and is wholly, unenforceable. This section shall not preclude a requirement for- a .written waiver of the right to file a mechanic’s lien [on full payment of a completed contract].
This result appears to run counter to New York public policy, which seeks to advance building and construction by assuring subcontractors of payment in the event of the insolvency of the owner or the general contractor. New York Lien Law § 3 permits a subcontractor which has performed work with the consent of the owner or its agent to have a Ken on the property for the principal and interest of the value or the agreed price of the labor or materials. This provision was intended to protect the functioning of the construction industry.
See Schaghticoke Powder Co. v. Greenwich & Johnsonville Ry. Co.,
The question of Aetna’s KabiKty on its surety bond likewise raises an unresolved issue of New York law. Aetna’s, bond required it to make payment if a subcontractor which fuKy performed had not been paid within ninety days:
The above named Principal [Gilbane] and . Surety [Aetna] hereby jointly and severally agree with the Owner [Fischer-Reese] that every [subcontractor] ... who has not been paid in fuK before the expiration of a period of ninety (90) days after the date on which the last of such [subcontractor’s] work or labor was done or performed, or materials were furnished by such [subcontractor], may sue on this bond for the use of such [subcontractor].... The Owner shall not be Kable for the payment of any costs or expenses of any such suit.
The bond is silent, however, as to the consequences of a nonpayment resulting from the Owner’s default, and the bond does not incorporate by reference the terms of Coppola’s subcontract with Gilbane.
Under New York law a surety’s duty generally is coextensive with that of the principal bn the bond.
See Eckstein v. Massachusetts Bonding & Ins. Co.,
The questions we certify to the New York Court of Appeals therefore are as follows: ■
(1) Whether a pay-when-paid provision in a subcontract, which transfers the risk of an owner’s default from a general contractor to a subcontractor, violates the public policy of New York as set forth in the Lien Law; and
(2) Whether a surety’s liability is contingent on the duty of a contractor to make payment to a subcontractor when the surety bond created an independent obligation to that subcontractor.
The parties have cited no precedent of the New York Court of Appeals that controls the disposition of these questions, and we have found none. The questions should be decided by the Court of Appeals because they require the interpretation of section 34 of New York Lien Law, as well as the state’s public policy supporting the enforcement of mechanic’s liens, and because they require a determination of the circumstances in which a surety’s obligation to a subcontractor arises independently of the obligation owed the subcontractor by a contractor. For these reasons the questions certified should be addressed “at this time.” New, York Rules of Court § 500.17(b).
As we stated in
Madden v. Creative Services, Inc.,
The foregoing two questions are hereby certified to the Court of Appeals for the State of New York as ordered by the United States Court of Appeals for the Second Circuit.
Dated at New York, New York, this 23 day of February, 1995.