Hugh O‘Kane Electric Co., LLC, Respondent, v MasTec North America, Inc., Doing Business as Wilde Construction, Appellant.
Appellate Division of the Supreme Court of New York, First Department
19 A.D.3d 126 | 797 N.Y.S.2d 45
Charles E. Ramos
Order, Supreme Court, New York County (Charles E. Ramos, J.), entered May 12, 2004, which, in an action by a subcontractor against a general contractor to recover for work performed under a subcontract, insofar as appealed from, denied the general contractor‘s motion for summary judgment dismissing the complaint and granted the subcontractor‘s cross motion to dismiss the third affirmative defense, unanimously modified, on the law, to the extent that the cross motion is denied and the third affirmative defense is reinstated, and otherwise affirmed, without costs.
The general contractor seeks dismissal on the basis of a provision in the subcontract making its obligation to pay the subcontractor “expressly contingent upon and subject to” its own receipt of payment from the owner for the subcontractor‘s work—a so-called “pay-when-paid” provision. Such provisions are void in New York as against public policy (see West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co., 87 NY2d 148, 158 [1995] [construing
It is the policy of the courts of New York to enforce choice-of-law clauses, provided that the law chosen has a reasonable relationship to the agreement and does not violate a fundamental public policy of New York (Finucane v Interior Constr. Corp., 264 AD2d 618, 620 [1999]). Since there is no dispute that the general contractor‘s Florida domicile justifies the choice of Florida law, the only choice-of-law issue is whether the public policy reflected in
Nevertheless, we affirm the denial of the general contractor‘s motion for summary judgment dismissing the complaint, there being an issue of fact as to whether the general contractor should be estopped from asserting the pay-when-paid provision. Such issue is raised by evidence that in discussions concerning the payment of amounts overdue under the subcontract, the general contractor, responding to the subcontractor‘s concerns about the owner‘s financial condition, represented that the owner had the money to pay, although the owner was then in default of certain loans extended by the general contractor, and thereby may have induced the subcontractor to continue working on the project to its detriment (see generally Florida Dept. of Health & Rehabilitative Servs. v S.A.P., 835 So 2d 1091, 1096, 1097 [Fla 2002]). We reject the subcontractor‘s argument that such evidence also raises an issue of fact as to waiver (see generally Gilman v Butzloff, 155 Fla 888, 891, 22 So 2d 263, 265 [1945]).
In light of the foregoing, the cross motion by the subcontractor to strike the general contractor‘s third affirmative defense based upon the subject pay-when-paid provision is denied.
Concur—Andrias, J.P., Friedman, Marlow, Gonzalez and Catterson, JJ.
Reargument granted and upon reargument, the decision and order of this Court entered herein on March 8, 2005 (16 AD3d 161 [2005]) is hereby recalled and vacated and a new decision and order substituted therefor. [See 6 Misc 3d 1006(A), 2004 NY Slip Op 51741(U) (2004).]
