Crown Plastering Corp. v. Elite Associates, Inc.Crown Plastering Corp. v. Elite Associates, Inc.
In an action by a subcontractor, inter alia, to recover the balance due on a subcontract, the
Ordered that the order is affirmed, with costs.
The defendant Elite Associates, Inc. (hereinafter Elite), the general contractor, еntered into a contract with the Nassau County Department of Public Works to construct the Nassau County District Courthouse. The plaintiff, Crown Plastering Corp. (hereinafter Crown), entered into a written subcontract with Elite to рerform, inter alia, the lath and plaster work for the project. The defendаnt Aetna Fire Underwriters Insurance Company issued a payment bond on behalf of the general contractor. After Crown substantially performed its contract, aside from certain minor items, the owner terminated thе prime contract with Elite. Thereafter, Elite commenced an action against the owner for wrongful termination of the contract аnd Crown commenced the instant action against Elite and Aetna to recover the balance due on the subcontract and the valuе of extra work. Relying upon the payment provisions of the subcontrаct, the defendants oppose the plaintiff’s motion for summary judgment on the ground that final payment is not due Crown until the general contractоr has received its payment from the owner.
Article 3 of the contrаct, after setting forth the contract price, expressly states that "[rjeceipt of payment from the owner for the subcontractor’s work is a condition precedent to payment by the Contractоr to the Subcontractor. The Subcontractor hereby acknowlеdges that it relies on the credit of the Owner, not the Contractor, for рayment of its work.” Article 5 further provides that "[f]inal payment shall be payable to the Subcontractor thirty (30) days after the general contrаct work is completed and accepted upon the cоndition that final payment is received by the Contractor from the Owner and provided the Work described in this subcontract is fully completed and performed in accordance with the Contract Documents and is sаtisfactory to the Owner, Architect and Contractor” (emphasis supрlied).
The law is well settled that absent a clear expression in the сontract that the credit risk of the general contractor and thе delay in payment frequently attending on construction projects are meant to be shifted to subcontractors, a contract prоvision that payment is not due the subcontractor until the owner has paid the general contractor is to be construed as merely fixing a time for payment and not establishing a
Although a party to a contract cannot rely on the failure of another to perform a cоndition precedent where he has frustrated or prevented the occurrence of the condition precedent (see, Kooleraire Serv. & Installation Corp. v Board of Educ.,