STANDING ROCK SIOUX TRIBE, еt al., Plaintiffs, v. U.S. ARMY CORPS OF ENGINEERS, et al., Defendants.
Civil Action No. 16-1534 (JEB)
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
MEMORANDUM OPINION
“Since the founding of this nation, the United States’ relationship with the Indian tribes has been contentious and tragic. America‘s expansionist impulse in its formative years led to the removal and relocation of many tribes, often by treaty but also by force.” Cobell v. Norton, 240 F.3d 1081, 1086 (D.C. Cir. 2001). This case also features what an American Indian tribe believes is an unlawful encroachment on its heritage. More specifically, the Standing Rock Sioux Tribe has sued the United States Army Corps of Engineers to block the operation of Corps permitting for the Dakota Access Pipeline (DAPL). The Tribe fears that construction of the pipeline, which runs within half a mile of its reservation in North and South Dakota, will destroy sites of cultural and historical significance. It has now filed a Motion for Preliminary Injunction, asserting principally that the Corps flouted its duty to engage in tribal consultations under the National Historic Preservation Act (NHPA) and that irreparable harm will ensue. After digging through a substantial record on an expedited basis, the Court cannot concur. It concludes that the Corps has likely complied with the NHPA and that the Tribe has not shown it will suffer injury
I. Background
DAPL is a domestic oil pipeline designed to move over a half-billion gallons of crude oil across four states daily. The oil enters the pipeline in North Dakota, crosses South Dakota and Iowa, and winds up in Patoka, Illinois, nearly 1,200 miles later. Although the route does not actually cross the Standing Rock reservation, it runs within a half-mile of it.
A project of this magnitude often necessitates an extensive federal appraisal and permitting process. Not so here. Domestic oil pipelines, unlike natural-gas pipelines, require no general approval from the federal government. In fact, DAPL needs almost no federal permitting of any kind because 99% of its route traverses private land.
One significant exception, however, concerns construction activities in federally regulated waters at hundreds of discrete places along the pipeline route. The Corps needed to permit this activity under the Clean Water Act or the Rivers and Harbors Act — and sometimes both. For DAPL, accordingly, it permitted these activities under a general permit known as Nationwide Permit 12. The Tribe alleges that the Corps violated multiple federal statutes in doing so, including the National Environmental Policy Act (NEPA) and the National Historic Preservation Act (NHPA). In its Complaint, the Tribe asserts that this DAPL permitting threatens its environmental and economic well-being, as well as its cultural resources.
Despite this broad lawsuit, however, the Standing Rock Sioux now seek a preliminary injunction only on the alleged violation of the NHPA. That statute encompasses sites of cultural or religious significance to Indian tribes and requires that federal agencies consult with tribes prior to issuing permits that might affect these historic resources. The Tribe claims that the
The statutes and permitting scheme involved in this Motion are undeniably complex. The Court first sets forth the operation of the NHPA, which the Tribe asserts was violated. It next explains the Clean Water Act and the Rivers and Harbors Act, under which the Corps permitted the DAPL activities. Subsequent sections lay out the factual and legal proceedings that have taken place thus far.
A. National Historic Preservation Act
Congress enacted the NHPA in 1966 to “foster conditions under which our modern society and our historic property can exist in productive harmony.”
The Advisory Council also promulgates the regulations necessary to implement Section 106, see
Things get more complicated where the agency cannot make this determination. In such a situation, the agency must complete a multi-step “consultation” process before it permits the undertaking.
The regulations then put meat on these aspirational bones by laying out the step-by-step consultative process that must occur. The process begins with initial planning, where the agency “determine[s] the appropriate SHPO . . . to be involved.”
Such parties then assist the agency to identify potential historic properties in the first phase. The permitting official, along with the SHPO, initially “[d]etermine[s] and document[s] the area of potential effects,” “[r]eview[s] existing information on historic properties within the area of potential effects,” “[s]eek[s] information, as appropriate, from consulting parties,” and “[g]ather[s] information from any [consulting] tribe . . . to assist in identifying properties” of potential significance to them.
Once the potentially relevant historic sites are identified, the official moves on to evaluating the historical significance of these sites in consultation with the SHPO and tribes.
A few important global rules also apply to each stage of this process. The permitting agency is empowered to “coordinate the steps of the Section 106 process, as appropriate, with the overall planning schedule for the undertaking and with any reviews required under” other statutes.
B. Clean Water Act
The CWA makes it unlawful to discharge dredged or fill material into navigable waters without a permit issued by the Corps. See
General permitting has obvious advantages over individual permitting. Most notably, general permits provide standing authority for an entire category of activities where those activities, alone and together, have minimal impact on regulated waters. See Sierra Club, 803 F.3d at 38-40; see also
But not every activity covered by a general permit receives this hands-off treatment. Actions proceeding under nationwide general permits also must comply with what are known as General Conditions. These GCs sometimes require that a particular covered action be subject to pre-construction nоtice and verification (PCN) by the Corps before the work begins. Where a discrete action requires a PCN, a Corps district engineer must confirm that the activity will comply with the general permit, cause no more than minimal adverse effects to the environment, and serve the public interest. See
The Corps here relies on one such general permit — Nationwide Permit 12 — to authorize “the construction, maintenance, repair, and removal” of pipelines throughout the nation, where the activity will affect no more than a half-acre of regulated waters at any single water crossing. See Reissuance of Nationwide Permits (NWP 12), 77 Fed Reg. 10,184, 10,271 (Feb. 12, 2012); see also Sierra Club, Inc. v. Bostick, 787 F.3d 1043, 1056 (10th Cir. 2015). Each stand-alone crossing of a waterway is considered to be a “single and complete project” for these purposes. See
Work that implicates tribal interests, however, cannot receive this laissez-faire handling. For example, GC 17 — not at issue here — prohibits the sanctioning of any activity under NWP 12 that will impair reserved tribal rights, including reserved water rights. See NWP 12 at 10,283. Of more relevance, GC 20 mandates a PCN for any permitted activity that “may have the potential to cause effects to any historic properties . . . including previously unidentified properties” of cultural or religious importance to a tribe.
NWP 12 also allows a district engineer to impose additional Regional Conditions where the district engineer deems the General Conditions insufficient to protect tribal interests. See ECF No. 6, Exh. 1 (Decision Document for NWP 12) at 10; see also
The Corps’ more general permitting regulations further purport to assure that, in the “processing and evaluating of [any] permit,” a district engineer give “maximum consideration [to] historic properties within the time and jurisdictional constraints of the Corps regulatory program.”
C. Rivers and Harbors Act
The RHA forbids certain construction activities within the “navigable water of the United States” without prior permission from the Corps. See
* * *
To sum up, the NHPA requires that the Corps, prior to issuing a permit under the CWA or the RHA, consider the potential effect of that permitted activity on places of cultural or religious significance to Indian tribes.
D. Factual History
The Standing Rock Sioux Tribe is a federally recognized American Indian Tribe with a reservation spanning the border between North and South Dakota. See ECF No. 1 (Complaint), ¶ 1. The sweep of the Tribe‘s historic and cultural connection to the Great Plains, however,
One place of particular significance to the Tribe lies at the traditional confluence of the Missouri and Cannonball Rivers.
The Tribe nevertheless continues to use the banks of the Missouri River for spiritual ceremonies, and the River, as well as Lake Oahe, plays an integral role in the life and recreation of those living on the reservation.
The conflict that has arisen since this revelation is, to say the least, factually complex. To ease digestion of the relevant information, the Court first describes how Dakota Access chose the pipeline route. It then lays out the facts surrounding the Corps’ permitting and concurrent Section 106 process for the project. These following summaries admittedly contain significant detail and may try the reader‘s patience. The Court nonetheless believes such a narrative is necessary because a key question here is whether the Corps engaged in sufficient consultation with the Tribe under Section 106.
1. DAPL
In the summer of 2014, Dakota Access crafted the route that brought DAPL to Standing Rock‘s doorstep. See ECF No. 22, Exh. B (Declaration of Monica Howard), ¶¶ 2-3. The plotted course almost exclusively trackеd privately held lands and, in sensitive places like Lake Oahe, already-existing utility lines. As only 3% of the work needed to build the pipeline would ever require federal approval of any kind and only 1% of the pipeline was set to affect U.S. waterways, the pipeline could proceed largely on the company‘s timeline.
Dakota Access nevertheless also prominently considered another factor in crafting its route: the potential presence of historic properties.
Where this surveying revealed previously unidentified historic or cultural resources that might be affected, the company mostly chose to reroute.
The company also opted to build its new pipeline along well-trodden ground wherever feasible. See ECF No. 22-1 (Declaration of Joey Mahmoud), ¶¶ 18, 24, 40. Around Lake Oahe, for example, the pipeline will track both the Northern Border Gas Pipeline, which was placed into service in 1982, and an existing overhead utility line.
Around the time the cultural survey work began, Dakota Access took its plan public. See Howard Decl., ¶ 12. On September 30, 2014, it met with the Standing Rock Sioux Tribal Council to present the pipeline project as part of a larger community-outreach effort.
2. Entry of Corps
Based on the current record, the Corps appears to have had little involvement in Dakota Access‘s early planning. The one exception is a June 2014 meeting between the two parties to discuss the company‘s plan to build a pipeline through the region. See ECF No. 21-18 (Declaration of Martha Chieply), ¶ 8. At this meeting, the Corps informed the company about its permitting requirements and explained the importance of tribal coordination for any actions taken under its jurisdiction.
3. Soil-Bore Testing at Lake Oahe
The Corps’ North Dakota office also received the first request for DAPL permitting around this time and launched a formal NHPA Section 106 consultation as a result. See ECF No. 21-19 (Declaration of Richard Harnois), ¶ 5. This solitary preconstruction request from Dakota Access sought permitting only to conduct preliminary soil-bore testing at the Lake Oahe site, not to actually begin any construction.
As a first cut, the Corps reviewed extensive existing cultural surveys both within and outside the Lake Oahe project area to determine whether the work might affect cultural resources.
The Corps mailed out this decision in a Determination of Effect letter to the North Dakota SHPO and all affected tribes on the same day.
At this point, the Court should note that the Tribe has not provided a declaration from Young about any of these early consultations (or lack thereof). This omission is problematic for its cause because many of the facts relevant to the Tribe‘s NHPA claim involve her. As a result, the rendition of the facts in the record is largely told through documentation and affidavits provided by the Corps, with the exception of letters from Young provided by the Tribe.
In any event, several weeks later, on March 2, 2015, the Corps finally received a letter from Young expressing concerns over sites that might be affected by the bore testing.
4. PCN Authorizations
In the meantime, Dakota Access initiated efforts on December 29, 2014, to secure five additional PCN authorizations under NWP 12 for pipeline-construction work in North Dakota. See Chieply Decl., ¶ 10. (Out of these, three were later withdrawn for various reasons.
While discussions between Dakota Access and the Corps were ongoing, the Corps also sent a form letter to Young on February 17, informing her that it was now considering 55 PCN requests across its offices for DAPL. See ECF No. 6, Exh. 5. The letter went on to explain that the majority of the pipeline work would occur in uplands that were not subject to Corps jurisdiction, but the Corps would need to permit crossings at the Missouri, James, Big Sioux, Des Moines, Mississippi, and Illinois Rivers.
On the date of the deadline to respond, Ames and Young exchanged emails, but the content of this exchange is not in the record. See Tribal Consultation Sheet at 8. Young did, however, formally respond on April 8. See ECF No. 6, Exh. 7. In her response this time, she acknowledged receipt of the Corps’ February 17 letter about the 55 construction-related PCNs.
5. Summer of 2015
Relations betwеen the Tribe and Corps did not improve in the summer of 2015. Ames attempted to speak with Young about the project in June, but she informed him via email that she was on an extended leave of absence until July 27. Id. at 8; see Ames Decl., ¶ 9. Ames was unable to determine whether anyone was empowered to act on the Tribe‘s behalf in her absence. See Ames Decl., ¶ 9. On July 22, Corps Operations Manager Eric Stasch also sent a letter to Standing Rock describing the planned use of HDD for the Oahe crossing. See Harnois Decl., ¶ 16; see also id., Exh. 3. In his letter, Stasch provided details about the areas of potential effects and explained that the Corps would consider the work a federal undertaking despite its location on private land. See id., Exh. 3 at 1-2. The letter went on to say that Dakota Access‘s cultural surveys had identified an additional cultural site within the proposed preparation and staging area
In August, the Tribe responded with two letters of its own. See ECF No. 6, Exhs. 8 (Letter from Archambault to Cross on Aug. 19, 2015), 9 (Letter from Young to Stasch on Aug. 21, 2015). The first, sent on August 19 from Chairman Archambault to Colonel Cross – the Corps’ Commander and District Engineer for the Omaha District – described the Chairman‘s frustration in not being contacted earlier in regard to DAPL. See Letter from Archambault to Cross (Aug. 19, 2015). Archambault invited Cross to the reservation to discuss the matter and provided contact information for his administrative assistant to arrange the visit. Id. The very same day, Ames emailed Archambault‘s assistant in an attempt to schedule a meeting, but without success. See Ames Decl., ¶ 10; see also Tribal Consultation Sheet at 8. The second letter responded directly to Stasch‘s offer to consult on the Lake Oahe crossing. See Letter from Young to Stаsch (Aug. 21, 2015). In it, Young again reiterated that the Section 106 consultation run by the Corps had failed to respond to concerns raised by the Tribe in their February letters about the soil-bore testing prior to the completion of that work. Id. She further expressed her frustration in being excluded from the Dakota Access surveying despite company promises to include tribal monitors, and she reiterated her concern that sites might be overlooked or damaged unless the Standing Rock Sioux participated in surveying. Id. In closing, Young again said the Tribe looked forward to participating in “future consultation prior to any work being completed . . . [and] to playing a primary role in any and all survey work and monitoring.” Id. at 2.
On the same day as Stasch‘s letter, Harnois also emailed Standing Rock Archaeologist Morgan to invite her to participate in the “working level, on-the-ground site visit of the proposed DAPL Oahe Crossing.” Id., ¶ 23. This sparked an email exchange between the two on logistics and dates. Id. The very next day, however, Morgan emailed the Corps to back out of the visit. Id., Exh. 4. In an attached letter, she explained that “after careful consideration the [Standing Rock] THPO has determined that it is in the best interest of the THPO to decline participation in the site visits and walking the project corridor‘s [area of projected effects] at this time until government-to-government consultation has occurred for this project per Section 106 requirements as requested by the Standing Rock Sioux Tribe.” Id. By this she seemed to mean that the Corps needed to first hold the previously requested meeting between Chairman Archambault and Colonel Henderson. Id. Despite the Tribe‘s withdrawal, the Corps ultimately proceeded to hold the onsite visit with the North Dakota SHPO. See Harnois Decl., ¶ 26.
6. Fall of 2015
In the fall, the Corps responded by redoubling its efforts to meet with the Tribe. On September 29, 2015, Ames, in a phone conversation with Chairman Archambault, scheduled a meeting between the Corps and the Tribe‘s Vice Chair for October 28. See Ames Decl., ¶ 13. But two days before that meeting, the Tribe canceled “because nobody from the tribe was available to attend.” Id. On the same day, the Tribe also canceled a meeting scheduled for November with Colonel Henderson, promising to meet with him instead “in a few months.” Id., ¶ 14. The Corps, moreover, documented ten different attempts to contact the Tribe over the course of the October to speak about the project. See Tribal Consultation Sheet at 14.
Then, in November, the Corps twice invited the Tribe to a general tribal meeting in Sioux Falls, South Dakota, scheduled for Dеcember 8 to 9. See Chieply Decl., ¶ 17; see also id., Exh. 10. This invitation contained a link to the cultural surveys provided by Dakota Access. Id. Five
During this tribal gathering, Morgan sent a letter to the Corps, indicating that the Tribe was “still interested in formal consultation on the proposed” pipeline despite its decision not to attend. See ECF No. 6, Exh. 12 (Letter from Morgan to Chieply on Dec. 8, 2015) at 1. The Tribe yet again noted that it had not received a response from the Corps about the concerns it had raised in regard to the bore testing. Id. Morgan also protested that the testing should not proceed prior to mitigation efforts and indicated that the Tribe did not concur in the “no effects” determination for this work. Id. at 2. This, of course, makes little sense given that Young had already acknowledged in previous letters from the Tribe that they were aware the soil-bore testing had already taken place back in the spring. See, e.g., Letter from Young to Henderson on Sept. 28, 2015 (recognizing “soil bore testing has already occurred despite our initial correspondence“). In any event, Morgan further indicated that the Tribe looked forward to playing a primary role in any surveying or monitoring and explained that it would refuse to participate in tribal meetings until Colonel Henderson came to their reservation to meet with them first. Letter from Morgan to Chieply (Dec. 8, 2015) at 1. Finally, she informed the Corps
Again, the Corps appears to have taken action in response to the Tribe‘s demands. Henderson ordered Omaha District Deputy Commandеr, Lieutenant Colonel Michael D. Sexton to attempt to schedule a meeting with Plaintiff for him. See Ames Decl., ¶ 17. He did so in response to the setbacks experienced by Ames in attempting to secure the same over the previous months. Id. The Tribe, however, never returned Sexton‘s calls about scheduling a meeting either, and Young subsequently left her position with the Standing Rock Sioux. Id.
On December 8, the Corps released a draft EA for the project, which contained a request for comment by January 8, 2016. See Shelman Decl., ¶ 8. In the portion of the EA describing the Section 106 process, the draft explained that consultations began in November 2014 for initial geotechnical explorations, which then closed in January 2015. See ECF No. 6, Exh. 13 (Draft EA, Nov. 2015) at 58. The draft next described the ongoing process, starting in July 2015, for consultation related to the actual pipeline construction. Id. In so doing, it acknowledged the Corps’ failure to secure onsite visits or government-to-government meetings to date. Id. at 58-59. In the very next section, the EA indicated that Young had said in the October 2014 meeting with Dakota Access that the Lake Oahe HDD process “appeared to avoid impacts to known sites of tribal significance.” Id. at 59.
7. 2016
The Tribe provided timely and extensive comments to the draft EA in letters on January 8 and March 24, 2016. See ECF No. 6, Exh. 14 (Standing Rock Comments on Draft EA); id., Exh. 15 (Standing Rock Supplemental Comments). In these comments, Archambault asserted that the Corps had failed to consult on the identification of cultural sites important to the Tribe. See
Colonel Henderson also attended several meetings with the Tribe. He first officiated at a third tribal summit on February 18-19, again with Standing Rock participation. See Chieply Decl., ¶ 22. Then, he attended meetings with Standing Rock on February 26, April 29, and May 14. See Ames Decl., ¶¶ 26, 33, 36. Through these conversations, Henderson committed the Corps to imposing several additional conditions on DAPL, such as double-walled piping, in response to tribal concerns about environmental safety. Id., ¶ 27. One of these summits also included an onsite visit to the Lake Oahe crossing. See Harnois Decl., ¶ 28; see also Archambault Decl., ¶ 19. During that visit, Chairman Archambault “pointed out areas of concern and explained the tribe‘s issues with the pipeline project.” Harnois Decl., ¶ 28. Indeed, in March, Archambault acknowledged that the Corps had recently made strides toward righting the Section 106 ship and indicated he felt this particular onsite visit was productive at identifying
The improved relationship, however, had its limits. In the spring, the Corps worked with Dakota Access to offer consulting tribes an opportunity to conduct cultural surveys at PCN locations where the private landowner would permit them. See Chieply Decl., ¶ 28. This included 7 of the 11 sites in North and South Dakota. Id.. Three tribes took the opportunity, and it paid off. See ECF No. 22, Exh. C (Declaration of Michelle Dippel) ¶ 28. The Upper Sioux Community identified areas of tribal concern at three PCN sites, and Dakota Access agreed to additional avoidance measures at all of them. Id.. At one of these sites, the tribal surveyors and the Iowa SHPO declared a site eligible for listing on the National Registry that had not previously been identified on Dakota Access‘s surveys. See Eagle Decl., ¶¶ 32-36; see also Mentz Decl., ¶¶ 38-39 (describing his hiring to conduct surveys for the Upper Sioux). Dakota Access agreed in response to this discovery to bury the piрeline 111 feet below the site to avoid disturbing it. See Mot. Hearing Trans. at 36. Similarly, the Osage Tribe identified areas through their surveys that they wished to monitor during construction, and the company granted that request too. Id.
Standing Rock took a different tack. The Tribe declined to participate in the surveys because of their limited scope. See Chieply Decl., ¶ 29. Instead, it urged the Corps to redefine the area of potential effect to include the entire pipeline and asserted that it would send no experts to help identify cultural resources until this occurred. Id. In a responsive email, the Corps expressed its regret that the Tribe would not participate and welcomed any knowledge or information regarding historic properties that it was still willing to provide. Id. The Corps went
The Tribe did engage in two more visits to Lake Oahe with the Corps around this time. See Eagle Decl., ¶¶ 13-14; Harnois Decl., ¶ 29. First, on March 8, Morgan and the Tribe‘s latest THPO, Jon Eagle, identified areas of potential cultural significance to the Corps and described the area‘s sacred importance to the Standing Rock people. See Harnois Decl., ¶ 29. Several of the sites they identified were in areas that the Corps had determined were well outside the area of potential impact for the project, such as a cemetery approximately 1.2 miles from the nearest bore pit and .6 miles from the HDD preparation and construction area. Id. The group also toured the Cannonball Village site. Id. At this site, Morgan and Eagle pointed out places in the mole dirt where “pottery shards, pieces of bone, flint and tools used for scraping hides and cutting” were visible. See Eagle Decl., ¶ 14. Eagle, in addition, pointed out a sacred stone in the area that is still used for prayer. Id., ¶ 15. During the visit, Corps staff acknowledged that they had been previously unaware of some of these cultural resources and committed to further study of them. Id., ¶ 14. Morgan and Harnois thereafter exchanged several follow-up emails to discuss the Tribe‘s “concerns and questions” generated by the onsite visit. See Harnois Decl., ¶¶ 30-31. The Corps nevertheless ultimately determined that the Cannonball Village site was not in the area that would be affected by DAPL-related construction work. Id., ¶ 29.
The Corps then sought to end the Section 106 process for the Lake Oahe crossing. On April 22, Harnois made a Determination of Effect for the site and emailed it to the consulting parties. Id., ¶ 33; see also ECF No. 6, Exh. 43. In it, Harnois described the project, explained the location, and discussed data on 41 potential historic sites in detail. Id. He concluded that one of the sites identified, 32MOx0570, was “not eligible” for listing and that the project overall had “no historic properties subject to effect.” Id. Four days later, the North Dakota SHPO concurred with his determination via email. See Harnois Decl., ¶ 34. Harnois then notified the Tribe of this concurrence. Id., ¶ 35. Both Chairman Archambault and Eagle formally objected to the determination. See ECF No. 6, Exh. 30 at 2 (“To date, none of our request for consultation or Class III Cultural Surveys has been honored.“); id., Exh. 31. As a result, the Tribe and Corps continued their dialogue on these issues. See Ames Decl., ¶ 36; Chieply Decl., ¶¶ 32, 35 (describing Corps response to these objections).
The Advisory Council – the agency responsible for commenting on NHPA compliance for federal undertakings – also sent the Corps a series of letters about the adequacy of the Section 106 process around this time. After the Corps published the draft EA, the Advisory Council requested verification from the Corps of its consultation efforts and relayed concerns expressed
The Corps responded to these letters with several of its own. On May 13, Henderson wrote to reiterate that the Corps could not exercise control over portions of the project not subject to its jurisdiction. See id.; see also id., Exh. 15. In his letter, Henderson contested the Advisory Council‘s conclusion that the permitted activity determined the entire right-of-way for the pipeline, instead contending that the crossing of jurisdictional waters did not ultimately control project alignment elsewhere. Id. He furthеr explained that the use of HDD in many places would avoid Corps jurisdiction altogether by eliminating any discharge of dredge or fill
The Corps then moved to close the book on the matter. On July 25, 2016, it issued an EA finding of “no significant impact” and verified all 204 PCN locations under NWP 12. See ECF No. 6, Exhs. 33-36; Ames Decl., ¶ 36. The PCNs, however, contained additional restrictions. See ECF No. 6, Exhs. 33-36. Most importantly, they instituted a “Tribal Monitoring Plan” that requires Dakota Access to allow tribal monitors at all PCN sites when construction is occurring. Id. Dakota Access immediately notified the tribes of its intent to begin construction at the PCN sites within five to seven days. See ECF No. 6, Exh. 49 (Letter from Dippel to Upper Sioux).
* * *
In summary, the Corps has documented dozens of attempts it made to consult with the Standing Rock Sioux from the fall of 2014 through the spring of 2016 on the permitted DAPL activities. These included at least three site visits to the Lake Oahe crossing to assess any potential effects on historic properties and four meetings with Colonel Henderson.
E. Procedural History and Recent Activities
Two days after the Corps issued the PCN authorizations, Standing Rock filed this suit against it under the
At the Motion hearing, Dakota Access revealed that most of the construction associated with DAPL is, in fact, already complete. Because only 3% of the pipeline is subject to federal permitting, Dakota Access has always been free to proceed with the vast majority of the construction, which will occur on private land. In fact, 48% of the pipeline had already been cleared, graded, trenched, piped, backfilled, and reclaimed. See Mot. Hearing Trans. at 24. The company also moved fast elsewhere; this figure included all but 11 of the 204 sites that the Corps had subjected to PCN authorization. Id. at 25. All of the necessary clearing and grading has also been done in South Dakota, and 90% of it is complete in North Dakota. Id. at 24. One of the few exceptions is the crossing leading up to the west side of Lake Oahe, which has not yet been cleared or graded.
The tribal monitoring and GC 21 unexpected-discovery protocols also appeared to be in place for the activity that was permitted by the Corps. Id. at 37-39. When construction is ongoing for such activities, Dakota Access allows archaeological and tribal monitors onsite to look for evidence of cultural or historic resources. Id. As of the hearing, construction had triggered the unexpected-discovery protocol six times. Id. at 39. In each case, construction stopped until the state, federal, and tribal representatives confirmed that the resources were not being damaged. Id. Each one turned out to be a false alarm. Id. At the conclusion of the hearing, the Court informed the parties that it would issue its decision on September 9, two
Nine days after the hearing, on Friday, September 2, the Tribe filed a supplemental declaration by Tim Mentz, the Tribe‘s former Tribal Historic Preservation Officer and a member of the Standing Rock Sioux Tribe. See ECF No. 29-1 (Supplemental Declaration of Tim Mentz, Sr.). In the declaration, Mentz explained that he had been invited by a landowner to conduct cultural surveys on private land along the DAPL route that had already been cleared for pipeline construction. See id., ¶¶ 2-3; see also id., Exh. 1. This land was about 1.75 miles from the construction activity that the Corps has actually рermitted at Lake Oahe. Id., ¶ 3. In other words, the area in question was entirely outside the Corps’ jurisdiction. The construction activity on it, as a result, never required a federal permit, and neither the Corps nor any other federal agency had any control over it. Because these activities do not require a federal permit, they are also not necessarily subject to the attendant restrictions to protect historic properties – i.e., GC 21 and tribal monitoring – placed by the Corps on the activities that it did permit.
Mentz, over the course of several days beginning on August 30, avers that he surveyed this private land around the pipeline right-of-way. Id., ¶ 6. During these surveys, he observed several rock cairns and other sites of cultural significance inside the 150-foot corridor staked for DAPL construction. Id., ¶¶ 7-11. He was, however, confined in his actual surveying to those areas immediately adjacent to the pipeline right-of-way and did not enter the corridor itself. Id. Mentz documented the presence of several sites that he believed to be of great cultural note nearby, including a stone constellation used to mark the burial site of a very important tribal leader about 75 feet from the pipeline corridor. Id., ¶ 10. Mentz did not observe any fencing or other protective measures around these sites. Id., ¶ 9. He also observed what he believed to be
The next day, on Saturday, September 3, Dakota Access graded this area. See ECF No. 30 (Emergency Motion for Temporary Restraining Order). On September 4, both the Tribe and the Cheyenne River Sioux Tribe filed for a Temporary Restraining Order on any additional construction work at the site described by Mentz – i.e., the length of the pipeline route for approximately two miles west of Highway 1806 in North Dakota – and for any additional construction work on the pipeline within 20 miles on either side of Lake Oahe, until the Court ruled on this Motion for Preliminary Injunction. Id. The Corps responded that it would not oppose the restraining order while awaiting this decision.
Dakota Access, not surprisingly, hotly contested Mentz‘s version of events in its opposition to the TRO motion. In a map of the area, the company sought to demonstrate that many of the sites documented by Mentz were in fact well outside the pipeline route. See ECF No. 34 (Response to TRO) at 6-8. The rest, according to Dakota Access, were directly over the existing Northern Border Natural Gas Pipeline that runs through the area and thus could not have been historic artifacts. Id. at 6. The company instead alleges that the route of the pipeline in this area proves its point: it twists and turns to avoid the finds that Mentz documented adjacent to the pipeline and thus demonstrates that Dakota Access did purposefully shift the route to avoid any sites of cultural significance in its planning phase. Id. The Court acknowledges that the map provided by the company does seem to indicate that the pipeline curves to accommodate the cultural sites. Id. at 7.
II. Legal Standard
“[I]njunctive relief” is “an extraordinary remedy that may only be awarded upon a clear showing that the plaintiff is entitled to such relief.” Winter v. Nat. Res. Def. Advisory Council, Inc., 555 U.S. 7, 22 (2008). “A plaintiff seeking a preliminary injunction must establish [1] that he is likely to succeed on the merits, [2] that he is likely to suffer irreparable harm in the absence of preliminary relief, [3] that the balance of equities tips in his favor, and [4] that an injunction is in the public interest.” Id. at 20. Before the Supreme Court‘s decision in Winter, courts weighed the preliminary-injunction factors on a sliding scale, allowing a weak showing on one factor to be overcome by a strong showing on another factor. See, e.g., Davenport v. Int‘l Bhd. of Teamsters, 166 F.3d 356, 360-61 (D.C. Cir. 1999). This Circuit, however, has suggested, without deciding, that Winter should be read to abandon the sliding-scale analysis in favor of a “more demanding burden” requiring plaintiffs to independently demonstrate both a likelihood of success on the merits and irreparable harm. See Sherley v. Sebelius, 644 F.3d 388, 392-93 (D.C. Cir. 2011); Davis v. Pension Benefit Guar. Corp., 571 F.3d 1288, 1292 (D.C. Cir. 2009).
Whether a sliding-scale analysis still exists or not, courts in our Circuit have held that “if a party makes no showing of irreparable injury, the court may deny the motion for injunctive relief without considering the other factors.” Dodd v. Fleming, 223 F. Supp. 2d 15, 20 (D.D.C. 2002) (citing CityFed Fin. Corp. v. Office of Thrift Supervision, 58 F.3d 738, 747 (D.C. Cir. 1995)). Likewise, a failure to show a likelihood of success on the merits alone is sufficient to defeat a preliminary-injunction motion. Ark. Dairy Co-op Ass‘n, Inc. v. USDA, 573 F.3d 815, 832 (D.C. Cir. 2009) (citing Apotex, Inc. v. FDA, 449 F.3d 1249, 1253 (D.C. Cir. 2006)). It follows, then, that the Court may deny a motion for preliminary injunction, without further inquiry, upon finding that a plaintiff is unable to show either irreparable injury or a likelihood of success on the merits. Here, Standing Rock fails on both grounds.
III. Analysis
The Corps gave the go-ahead, under NWP 12, for DAPL‘s construction activities in federally regulated waters at hundreds of discrete places along its nearly 1,200-mile route. In seeking a preliminary injunction, the Tribe contends that the Corps, in doing so, shirked its responsibility to first engage in the tribal consultations required by the NHPA. Because DAPL construction is ongoing, the Tribe further asserts that sites of great significance will likely be damaged or destroyed unless this Court pumps the brakes now. It also contends that the balance of harms and the public interest favor its position.
Defendants rejoin that preliminary-injunctive relief is inappropriate both because the Corps has satisfied its obligations under the NHPA – in other words, the Tribe is unlikely to succeed on the merits of its NHPA claim – and because the Tribe has failed to show that any harm will befall it in the absence of an injunction. As the Court agrees on both points, it need not consider the final two factors – balance of harms and the public interest – to deny the Motion. It now discusses the merits and the harm separately.
A. Likelihood of Success on the Merits
Although the Tribe‘s legal theory is not entirely clear, the Court believes it can infer four separate arguments that the Corps’ permitting of DAPL was unlawful. First, the Standing Rock Sioux assert that the Corps violated the NHPA when it promulgated NWP 12 without a Section 106 process. Next, they contend that, even if the Corps could defer site-specific Section 106 consultations when promulgating NWP 12, it violated the NHPA by permitting DAPL-related activities at some federally regulated waters without a Section 106 determination. Third, the Tribe maintains that, even where the Corps did conduct a Seсtion 106 process, it unlawfully narrowed the scope of its review to only those areas around the permitted activity, as opposed to the entire pipeline. Finally, the Tribe urges that the Section 106 process at the PCN sites was inadequate because the quality of the consultations was deficient. None of these claims appears likely to succeed on the merits at this stage.
1. NWP 12
Although many DAPL-related construction activities in federally regulated waters occurred or will occur at places where the Corps did not require a PCN verification, such activities nevertheless required approval from the Corps under the CWA or RHA. That approval was provided on a general level when the Corps re-promulgated NWP 12 in 2012. Because these activities thus were “permitted” by a federal agency, they fall within the NHPA‘s definition of a federal “undertaking.” See
As an initial matter, the Tribe‘s assertion that the Corps did not engage in any NHPA consultations prior to promulgating NWP 12 is false. Before issuing NWP 12, the Corps, in November 2009, sent an early notification to tribes, including Standing Rock, containing information pertaining to its proposed NWPs. See ECF No. 21, Exh. 14 (Letter from Ruchs to Brings Plenty on Nov. 9, 2009). The letter contained a graphic depiction of the types of activities that were most often authorized by nationwide permits in the Omaha District. Id. In addition, in 2010, the Corps proceeded to hold “listening sessions and workshops” with tribes to discuss their concerns related to the proposed nationwide permits. See ECF No. 21, Exh. 13 (Tribal Information Fact Sheet). In March 2010, the Corps contacted Standing Rock personally to discuss the permits and any additional regional conditions that the Tribe thought might need to be included to protect their cultural resourcеs. See Chieply Decl., ¶ 5.
Then, on February 10, 2011, the Corps sent a letter to the Standing Rock Sioux Tribal Chairman and THPO Young, notifying them of its plan to publish a proposal in the Federal Register to reissue NWP 12. See ECF No. 21, Exh. 13 (Letter from Ruchs to Murphy on Feb. 10, 2011). Attached to the letter, the Corps provided a description of the proposed NWP 12, as well as a draft of the current Omaha District regional conditions that would apply to the permit. Id. The Corps requested that the Tribe “consider this letter our invitation to begin consultation on the proposal to reissue the NWPs.” Id. It went on to say that the Corps “look[s] forward to consulting with you on a government-to-government basis on this issue” and requested that the Tribe notify the Corps if it was “interested in consulting.” Id. The Corps further committed to provide a “Corps representative at consultation and fact-finding meetings” and to “fully consider
To the extent that the Tribe now seeks in this Motion to launch a belated facial attack against NWP 12, then, it is unlikely to succeed. The Corps made a reasonable effort to discharge its duties under the NHPA prior to promulgating NWP 12, given the nature of the general permit. Cf. Sierra Club v. Bostick, 787 F.3d 1043, 1047, 1057 (10th Cir. 2015) (holding Corps permissibly interpreted CWA “to allow partial deferral of minimal-impacts analysis” because of “the difficulty of predicting the impact of activities allowed under nationwide permits”). Without definite knowledge of the specific locations that would require permitting in the future, it is hard to ascertain what else the Corps might have done, before issuing a general permit, to discharge its NHPA duties. In other words, the Corps, when it promulgated NWP 12, had no knowledge of DAPL or its proposed route. The CWA and RHA plainly allow the Corps to do just what it did here: preauthorize a group of similar activities that, alone and combined, have minimal impact on navigable waterways. This Court cannot conclude that the Corps does not
This conclusion is reinforced by the limited scale and scope of the federally sanctioned activities at issue. The Advisory Council’s regulations provide that the “agency official should plan consultations appropriate to the scale of the undertaking and the scope of the Federal involvement.”
The Tribe responds that the Corps was instead required to work out a “programmatic agreement” with any tribe that might one day be affected by the activities permitted under NWP 12. See Mot. at 22-23. A рrogrammatic agreement is an “agreement to govern the implementation of a particular program or the resolution of adverse effects from certain complex project situations or multiple undertakings” that is negotiated by the Advisory Council and the permitting agency. See
2. NWP 12 Applied at Non-PCN Sites
The Tribe next argues that NWP 12’s operation is unlawful because the Corps makes no site-specific Section 106 determination for numerous generally permitted activities – i.e., non-PCN sites. In particular, it claims that GC 20 improperly delegates authority to the permittee to assess whether its activities will have a potential effect on historic properties. To refresh the reader, GC 20 requires that “[i]n cases where the district engineer determines that the activity may affect [NHPA] properties . . . , the activity is not authorized, until the requirements of Section 106 of the [NHPA] have been satisfied.” 77 Fed. Reg at 10,284. The Advisory Council, too, seems to concur that, in individual cases of permitting under NWP 12, Section 106 is not satisfied where the Corps itself does not make a site-specific determination about whether a permitted activity has the potential to affect historic properties. See ECF No. 6, Exh. 50 at 1-2. As the Tribe and the Advisory Council read GC 20, the Corps never considers whether an
Standing Rock and the Advisory Council make a good argument. It is possible that the Corps’ permitting under NWP 12 would be arbitrary and capricious where it relies completely on the unilateral determination of a permittee that there is no potential cultural resource that will be injured by its permitted activity. Fortunately, this Court need not decide that issue because that is not how the Corps interpreted and applied GC 20 to DAPL. In this case, the Corps looked at reports and maps of the pipeline to determine which jurisdictional crossings had the potential to affect historic properties. See Chieply Decl., Exh. 16 at 1; see also id., Exh. 15 at 1. These extensive maps reflected cultural surveys conducted by licensed archaeologists (sometimes with SHPO participation). See Howard Decl., ¶¶ 4-10; see, e.g., ECF No. 6, Exh. 44. The Corps ultimately concluded that only 204 of the jurisdictional crossings triggered either GC 20 or some other concern that would require a PCN verification. See Chieply Decl., Exh. 16 at 1.
The Court must review that determination under the Administrative Procedure Act’s deferential standard. See
3. Scope of Section 106 Process at PCN Sites
The Tribe next asserts that the Corps’ Section 106 process was deficient even at those places where it did in fact require a PCN notification. Here, again, Standing Rock largely focuses its efforts on a sweeping claim that the Corps was obligated in permitting this narrow activity – i.e., certain construction activities in U.S. waterways – to consider the impact on potential cultural resources from the construction of the entire pipeline. In particular, the Tribe contends that the NHPA requires such an analysis because the statute defines the potential effect of an undertaking to include the indirect effects of the permitted activity on historic properties.
This argument, however, misses the mark. In its regulations concerning compliance with the adverse-effects analysis required by the NHPA, the Corps determined that entire pipelines need not be considered part of the analyzed areas. Rather, only construction activity in the
The Corps’ decision in this regard is also entitled to deference under the APA as it falls squarely within the expertise of the Corps, not the Advisory Council, to determine the scope of
The limited nature of the Corps’ jurisdiction, in fact, reinforces the reasonableness of the its decision not to consider the effects of the entire pipeline on historic properties before issuing the DAPL permitting. “[W]here an agency has no ability to prevent a certain effect due to its limited statutory authority over the relevant actions, the agency[’s action] cannot be considered a legally relevant ‘cause’ of the effect.” Dep’t of Transp. v. Public Citizen, 541 U.S. 752, 770 (2004). Section 106 analysis is designed only to “discourage[e] federal agencies from ignoring preservation values in projects they initiate, approve funds for or otherwise control.” Lee v. Thornburgh, 877 F.2d 1053, 1056 (D.C. Cir. 1989). That section does not require that the Corps consider the effects of actions over which it has no control and which are far removed from its
4. Sufficiency of Consultations
Plaintiff’s last point on the merits is that the Corps failed to offer it a reasonable opportunity to participate in the Section 106 process as to the narrow scope of the construction activity that the Corps did consider to be an effect of the permitted waterway activities. The factual proceedings recited in exhaustive detail in Section I.D., supra, tell a different story. The Corps has documented dozеns of attempts to engage Standing Rock in consultations to identify historical resources at Lake Oahe and other PCN crossings. To the reader’s relief, the Court need not repeat them here. Suffice it to say that the Tribe largely refused to engage in consultations. It chose instead to hold out for more – namely, the chance to conduct its own cultural surveys over the entire length of the pipeline.
In fact, on this record, it appears that the Corps exceeded its NHPA obligations at many of the PCN sites. For example, in response to the Tribe’s concerns about burial sites at the James River crossing, the Corps verified that cultural resources indeed were present and instructed Dakota Access to move the pipeline to avoid them. Dakota Access did so. See Ames Decl., ¶ 24. Furthermore, the Corps took numerous trips to Lake Oahe with members of the Tribe to identify sites of cultural significance. See Summit Lake Paiute Tribe of Nevada v. U.S. Bureau of Land Mgmt., 496 F. App’x 712, 715 (9th Cir. 2012) (not reported) (holding four visits with a tribe to site constituted sufficient consultation for resolution of adverse effects). Colonel
Contact, of course, is not consultation, and “consultation with one tribe doesn’t relieve the [agency] of its obligation to consult with any other tribe.” Quechan Tribe of Fort Yuma Indian Reservation v. U.S. Dep’t of Interior, 755 F. Supp. 2d 1104, 1112, 1118 (S.D. Cal. 2010). But this is not a case about empty gestures. As noted in Section I.D., supra, and the examples just above, the Corps and the Tribe engaged in meaningful exchanges that in some cases resulted in concrete changes to the pipeline’s route. “This is not a case like Quechan Tribe, where a tribe entitled to consultation actively sought to consult with an agency and was not afforded the opportunity.” Wilderness Soc’y. v. Bureau of Land Mgmt., 526 F. App’x 790, 793 (9th Cir. May 28, 2013) (not reported).
The Tribe nevertheless аsserts that the Corps’ failure to include it in the early cultural surveys rendered the permitting unlawful for at least some of the PCN sites. These surveys, however, were not conducted by the Corps or under its direction. Even setting this fact aside, neither the NHPA nor the Advisory Council regulations require that any cultural surveys be conducted for a federal undertaking. The regulations instead demand only that the Corps make a “reasonable and good faith effort” to consult on identifying cultural properties, which “may include background research, consultation, oral history interviews, sample field investigations, and field survey.”
B. Irreparable Injury
In seeking preliminary-injunctive relief here, the Standing Rock Sioux do not claim that a potential future rupture in the pipeline could damage their reserved land or water. Instead, they point to an entirely separate injury: the likelihood that DAPL’s ongoing construction activities – specifically, grading and clearing of land – might damage or destroy sites of great cultural or historical significance to the Tribe. The risk that harm might befall such sites is a matter of unquestionable importance to the Standing Rock people. In the eloquent words of their Tribal Chairman:
History connects the dots of our identity, and our identity was all but obliterated. Our land was taken, our language was forbidden. Our stories, our history, were almost forgotten. What land, language, and identity remains is derived from our cultural and historic sites. . . . Sites of cultural and historic significance are important to us because they are a spiritual connection to our ancestors. Even if we do not have access to all such sites, their existence perpetuates the connection. When such а site is destroyed, the connection is lost.
Archambault Decl., ¶¶ 6, 15. The tragic history of the Great Sioux Nation’s repeated dispossessions at the hands of a hungry and expanding early America is well known. See, e.g., Dee Brown, Bury My Heart at Wounded Knee (1970); United States v. Sioux Nation, 448 U.S. 371 (1980). The threat that new injury will compound old necessarily compels great caution and respect from this Court in considering the Tribe’s plea for intervention.
Although the potential injury may be significant, the Tribe must show that it is probable to occur in the absence of the preliminary injunction it now seeks. See Winter, 555 U.S. at 22 (“Issuing a preliminary injunction based only on a possibility of irreparable harm is inconsistent with [the Court’s] characterization of injunctive relief as an extraordinary remedy that may only be awarded upon a clear showing that the plaintiff is entitled to such relief.”) (emphasis added). This is the burden the law imposes for this form of relief. The Court must faithfully and fairly apply that standard in all cases, regardless of how high the stakes or how worthy the cause. After a careful review of the current record, the Court cannot conclude that the Tribe has met it.
To understand Standing Rock’s deficit in this regard, it is necessary to first consider the nature of the relief it seeks. The Tribe has not sued Dakota Access here for any transgressions; instead, this Motion seeks to enjoin Corps permitting of construction activities in discrete U.S. waterways along the pipeline route. Such relief sought cannot stop the construction of DAPL on private lands, which are not subject to any federal law. Indeed, Standing Rock does not point the Court to any law violated by the private contracts that allow for this construction or any federal regulation or oversight of these activities. From the outset, consequently, no federal agency had the ability to prevent DAPL’s construction from proceeding on these private lands. At most, the Corps could only have stopped these activities at the banks of a navigable U.S. waterway. An injunction of any unlawful permitting now can, at most, do the same.
The facts previously recited bear this simple conclusion out. Dakota Access, as has been explained, began its construction work on private lands long before it had even secured the Corps permitting that the Tribe now seeks tо enjoin. See Mahmoud Decl., ¶ 47. Standing Rock
The Tribe thus cannot demonstrate that the temporary relief it seeks here – i.e., a preliminary injunction to withdraw permitting by the Corps for dredge or fill activities in federally regulated waters along the DAPL route – can prevent the harm to cultural sites that might occur from this construction on private lands. In other words, Standing Rock cannot show that any harm taking place on private lands removed from the Corps’ permitting jurisdiction “will directly result from the action which [it now] seeks to enjoin.” Hunter v. FERC, 527 F. Supp. 2d 9, 14-15 (D.D.C. 2007) (explaining that to obtain preliminary relief, “the movant must . . . show that ‘the alleged harm will directly result from the action which the movant seeks to enjoin’”) (quoting Wisc. Gas Co. v. FERC, 758 F.2d 669, 674 (D.C. Cir. 1985) (emphasis added)); see also Buckingham Corp. v. Karp, 762 F.2d 257, 261 (2d Cir. 1985) (“The purpose of a preliminary injunction is to protect the moving party from irreparable injury during the pendency of the action.”). Powerless to prevent these harms given the current posture of the case, the Court cannot consider them likely to occur in the absence of the relief sought here. Put simply, any such harms are destined to ensue whether or not the Court grants the injunction the Tribe desires. As Standing Rock acknowledges, Dakota Access has demonstrated that it is determined to build its pipeline right up to the water’s edge regardless of whether it has secured a
There is a second related problem with the Tribe’s claim to irreparable injury, both on the private land and elsewhere along the pipeline. The risk that construction may damage or destroy cultural resources is now moot for the 48% of the pipeline that has already been completed. Id. at 24. As the clearing and grading are the “clearest and most obvious” cause of the harm to cultural sites from pipeline construction, id. at 18-19, 47 (recognizing that injunction is necessary anywhere not yet cleared “to prevent additional harm or construction until [cultural] surveys can take place”), moreover, the damage has already occurred for the vast majority of the pipeline, with the notable exception of 10% of the route in North Dakota, including at Lake Oahe. Here again, then, the Tribe has not shown for this substantial segment of the pipeline that any additional harm is likely to occur to cultural sites absent the preliminary injunction that it now seeks.
Yet a third problem bedevils the Tribe’s efforts to enjoin permitting along the entire pipeline route. Plaintiff never defined the boundaries of its ancestral lands vis-à-vis DAPL. Instead, Standing Rock asserts that these lands extend “wherever the buffalo roamed.” Even accepting this is true, to find that there is a likelihood that construction might run afoul of a site of cultural significance to the Tribe, this Court must ultimately decide where those culturally significant lands lie. There is at least some evidence in the record that they do not traverse the entirety of DAPL. For example, Jon Eagle, the Tribe’s current THPO, indicated prior to this litigation that at least some of the pipeline did not fall within the scope of what he considered ancestral tribal lands. See Chieply Decl., Exh. 14 (Letter from Jon Eagle to Martha Chieply on Mar. 22, 2016) (“Most of the DAPL pipeline route crosses Lakota/Dakota aboriginal land.”); see
So what activity remains subject to this Court’s injunctive powers? Any permitted DAPL activity that the Tribe has shown will likely injure a nearby site of cultural or historic significance to the Standing Rock people. As previously explained, 204 sites were subject to PCN authorizations and thus were clearly permitted by the Corps. Those sites are in play. Other discharges into jurisdictional waters at hypothetical locations along the route, however, may also have been permitted under NWP 12 without a PCN process. But it would be pure speculation based on the current record to determine where such permitting occurred. The Tribe points the Court to no specific crossing of cultural significance that the Corps permitted under NWP 12 without a PCN verification. In fact, many of the pipeline crossings were not permitted by the Corps, sometimes because Dakota Access’s use of HDD did not give rise to the dredge or fill activities that trigger federal jurisdiction under the CWA. For example, out of the five places in North Dakota that Dakota Access thought might require a PCN authorization, only three actually needed permitting at all. See Chieply Decl., ¶ 10. Of course, there may be many sites that the Corps permitted under NWP 12 that the Court has missed. But the burden is on the Tribe to indicate why this permitting must be enjoined to prevent an injury likely to occur to it. The Court, again, cannot guess that at some undefined locations there might be harm to the Tribe. It was Standing Rock’s burden to point to the specific NWP 12 permitting that was likely to cause
Returning to the 204 PCN sites, the vast majority must be excluded right off the bat. As previously noted, construction at 193 of the 204 PCN has already been completed. See Mot. Hearing Trans. at 24. For those sites, the die is cast. Whatever harms may have occurred from DAPL construction, the Court’s intervention to enjoin the permitting now can no longer avoid them. As a result, the Court must deny the Tribe’s request for an injunction as to permitting at those sites.
As to the other 11 PCN sites, the Tribe largely neglects to point the Court to any resources that may be affected by permitted activity. Plaintiff seeks to avoid its responsibility to identify a likely injury at these locations by claiming that this failure stems from the Corps’ refusal to properly consult in the first place and thus should be excused. See Mot. at 37 n.17. At least with regard to some of these sites, however, the Corps did offer the Tribе the opportunity to visit the sites or even conduct its own surveys, and the Tribe declined to do so. See Chieply Decl., ¶¶ 28-29. The record contains abundant evidence that the Corps also repeatedly sought other input on known cultural sites at these locations, and, in many cases, other tribes conducted site visits to search for any resources likely to be affected by the DAPL work. Id.. The Tribe cannot now ask the Court to speculate that there would be a likely injury at these places by claiming that it was prevented from assessing these sites.
These sites are also subject to several additional restrictions that make it unlikely that construction will damage or destroy sites of cultural significance to the Tribe. First, the Corps attached restrictions to its PCN authorizations. These restrictions mandate that tribal monitors and archaeologists be allowed at these sites to look for any evidence of previously overlooked
And then there was one: Lake Oahe. This is the sole permitting that the Tribe might arguably show is likely to cause harm to cultural or historic sites of significance to it. As previously discussed, Lake Oahe is of undeniable importance to the Tribe, and the general area is demonstrably home to important cultural resources. Even here, though, the Tribe has not met its burden to show that DAPL-related work is likely to cause damage. The Corps and the Tribe conducted multiple visits to the area earlier this year in an effort to identify sites that might be harmed by DAPL’s construction. See Eagle Decl., ¶¶ 13-14; Harnois Decl., ¶ 29. While the Tribe identified several previously undisсovered resources during those visits, these sites are located away from the activity required for the DAPL construction. See Harnois Decl., ¶ 29. Ultimately, the Corps considered these findings and determined that they would not be affected by the permitted activity. Id., ¶ 33. Most importantly, the North Dakota SHPO concurred in this opinion after having toured the site as well. See Harnois Decl., ¶ 34.
Several factors unique to the site also support this conclusion. The area around the permitted activity has been subject to previous surveying for other utility projects. See Mahmoud Decl., ¶¶ 18-19. DAPL likewise will run parallel, at a distance of 22 to 300 feet, to an
For all of the above reasons, the Tribe has not carried its burden to demonstrate that the Court could prevent damage to important cultural resources by enjoining the Corps’ DAPL-related permitting.
IV. Conclusion
As it has previously mentioned, this Court does not lightly countenance any depredation of lands that hold significance to the Standing Rock Sioux. Aware of the indignities visited upon the Tribe over the last centuries, the Court scrutinizes the permitting process here with particular care. Having done so, the Court must nonetheless conclude that the Tribe has not demonstrated that an injunction is warranted here. The Court, therefore, will issue a contemporaneous Order denying the Plaintiffs’ Motion for Preliminary Injunction.
/s/ James E. Boasberg
JAMES E. BOASBERG
United States District Judge
Date: September 9, 2016
