SIERRA CLUB, INC., Clean Energy Future Oklahoma, East Texas Sub Regional Planning Commission, Plaintiffs-Appellants, v. Lieutenant General Thomas P. BOSTICK, in his official capacity as Commanding General and Chief of Engineers of the U.S. Army Corps of Engineers; Major General Michael J. Walsh, in his official capacity as U.S. Army Commanding General for Civil and Emergency Operations; Colonel Richard Pratt, in his official capacity as Tulsa District Commander of U.S. Army Corps of Engineers; Colonel Richard Parnell, in his official capacity as Galveston District Engineer of the U.S. Army Corps of Engineers; United States Army Corps of Engineers, Defendants-Appellees, and TransCanada Keystone Pipeline LP, a Delaware limited partnership; TransCanada Corporation, a Canadian public company; Interstate Natural Gas Association, American Gas Association, Association of Oil Pipe Lines, American Petroleum Institute, Utility Water Act Group, Intervenors-Appellees.
No. 14-6099.
United States Court of Appeals, Tenth Circuit.
May 29, 2015.
787 F.3d 1043
We need not decide the scope or contours of a waiver rule here, particularly because the district court may not even need to reach the question on remand if it concludes that, assuming an EEOC waiver is possible, no such waiver occurred.
III. Conclusion
Because Title VII‘s verification requirement is not jurisdictional, we REVERSE and REMAND this case for the district court to determine whether the verification requirement was waived here.
Peter R. Steenland, Sidley Austin LLP, Washington, D.C. (Lauren C. Freeman, Lisa E. Jones, Sidley Austin LLP, Washington, D.C.; and Deidre G. Duncan, Andrew J. Turner, and Karma B. Brown, Hunton & Williams LLP, Washington, D.C., with him on the brief), for Intervenors-Appellees.
Before BACHARACH, Circuit Judge, BALDOCK, Senior Circuit Judge, and McHUGH, Circuit Judge.
BACHARACH, Circuit Judge.
This case involves the authority of the U.S. Army Corps of Engineers to issue nationwide permits under
TransCanada Corporation proposed to rely on the nationwide permit to build an oil pipeline, the Gulf Coast Pipeline,3 which would run approximately 485 miles and cross over 2,000 waterways. The Corps issued letters verifying that Nationwide Permit 12 would cover the proposed construction. Shortly thereafter, TransCanada began constructing the pipeline, which has since been completed and is currently transporting oil.
Three environmental groups (Sierra Club, Inc.; Clean Energy Future Oklahoma; and East Texas Sub Regional Planning Commission) have challenged the validity of the nationwide permit and verification letters. The district court rejected these challenges and entered judgment for the defendants.
In this appeal, we address and reject three sets of claims:
- Claims Involving the National Environmental Policy Act (NEPA): The environmental groups argue that the Corps violated NEPA by issuing the nationwide permit without considering the risk of oil spills and the cumulative environmental impacts of pipelines. These arguments are waived.
The environmental groups also argue that the Corps issued the verification letters without conducting a NEPA analysis. We conclude that this analysis was not necessary at the verification stage.
- Claims Involving the Clean Water Act: According to the environmental groups, the nationwide permit violates
the Clean Water Act by (1) effectively authorizing activities with more-than-minimal environmental impacts and (2) unlawfully deferring a portion of the minimal-impacts analysis to project-level personnel. We reject both arguments. The environmental groups have not shown that the permit authorizes activities with more-than-minimal impacts, and the Corps has permissibly interpreted the statute to allow partial deferral of its minimal-impacts analysis. - Claims Involving the Nationwide Permit 12: Finally, the environmental groups contend that the Corps incorrectly verified compliance with the nationwide permit without analyzing the cumulative effects or documenting the analysis of cumulative effects. We reject this contention. Corps officials did not need to include a cumulative-effects analysis in the letters, and the record shows that officials conducted the necessary analysis.
Based on our conclusions, we affirm the entry of judgment in favor of the defendants.4
I. Standard of Review
We review the challenges under the Administrative Procedure Act (APA). See
Review under the APA is narrow: “[T]he agency need only demonstrate that it considered relevant factors and alternatives ... and that the choice it made was reasonable based on that consideration.” Mt. Evans Co. v. Madigan, 14 F.3d 1444, 1453 (10th Cir.1994).
II. NEPA
The environmental groups make two arguments to challenge the district court‘s disposition of the NEPA claims:
- The Corps’ environmental analysis is deficient because the agency failed to consider the risk of oil spills and the cumulative impacts of pipelines.
- The Corps failed to conduct an environmental analysis when verifying that the pipeline was permissible under the nationwide permit.
We reject both arguments. The environmental groups waived their claims involving failure to address oil spills and cumulative impacts, and the Corps was not required to conduct an environmental analysis when verifying compliance with the nationwide permit.
A. Requirements of NEPA
NEPA requires an agency to take a “hard look” at the environmental impacts of proposed actions. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989). In taking this “hard look,” the agency must take appropriate steps: If the venture involves a “major Federal action” that would “significantly affect[] the quality of the human environment,” the agency must prepare a detailed environmental impact statement.
