History
  • No items yet
midpage
Standing Rock Sioux Tribe v. United States Army Corps of Engineers
205 F.Supp.3d 4
D.D.C.
2016
Read the full case

Background

  • Dakota Access Pipeline (DAPL) is a ~1,172-mile oil pipeline; ~99% on private land, but crossings of U.S. waters required Corps authorization under the Clean Water Act / Rivers and Harbors Act, mainly via Nationwide Permit 12 (NWP 12).
  • Standing Rock Sioux Tribe (Tribe) alleges the U.S. Army Corps of Engineers (Corps) violated Section 106 of the National Historic Preservation Act (NHPA) by failing to adequately consult about cultural/historic sites potentially affected by DAPL construction near the reservation (notably Lake Oahe).
  • Corps used NWP 12 and its General Conditions (including GC 20 requiring pre-construction notice (PCN) where historic properties may be affected and GC 21 discovery procedures). Corps identified 204 crossings requiring PCNs and verified them with conditions (including tribal monitoring); most PCN sites had construction already completed or nearly complete.
  • The Corps documents repeated efforts (letters, meetings, site visits) to consult with Standing Rock from 2014–2016; Tribe frequently declined participation or insisted on a broader scope (treating the entire pipeline as the undertaking) and challenged early soil-bore testing.
  • Procedure: Tribe sued under the Administrative Procedure Act and sought a preliminary injunction (PI) to enjoin Corps permitting; District Court held an expedited evidentiary record and denied the PI, finding Tribe unlikely to prevail on NHPA claims and failing to show likely irreparable harm preventable by injunction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Validity of NWP 12 absent Section 106 consultations NWP 12 was promulgated without adequate tribal consultation; Corps should have completed Section 106 before issuing NWP 12 Corps engaged in outreach and listening sessions before reissuing NWP 12 and reasonably deferred site-specific Section 106 to later PCN process Court: Corps adequately consulted for a general permit and reasonably deferred site-specific review; facial attack on NWP 12 unlikely to succeed
Corps permitting at non-PCN (general) sites under NWP 12 GC 20 improperly delegates Section 106 screening to permittees, so Corps unlawfully allowed activities without site-specific NHPA determinations Corps retained responsibility and used surveys/maps to identify which crossings needed PCNs; it reviewed data and required PCNs where appropriate Court: On this record Corps’ determination of which sites needed PCNs was reasonable and not arbitrary or capricious
Scope of Section 106: whether Corps had to treat the entire pipeline as the undertaking Tribe: Corps must analyze effects of entire pipeline (indirect effects) when permitting water-crossing activities Corps: its jurisdiction and control are limited to discrete water crossings and proximate APE; may limit analysis to federal undertaking scope Court: Corps’ narrower scope (crossings and adjacent APE) is reasonable and entitled to deference; not required to analyze whole pipeline
Sufficiency of consultations at PCN sites (including Lake Oahe) Tribe: consultations were inadequate, excluded tribal surveying and early input, producing a flawed Section 106 process Corps: documented numerous attempts, multiple meetings and site visits, SHPO concurrence, mitigation and monitoring measures; adjusted alignment when resources identified Court: Corps’ consultations were generally sufficient; Corps took meaningful steps and in some instances changed plans to avoid resources; Tribe unlikely to prevail

Key Cases Cited

  • Cobell v. Norton, 240 F.3d 1081 (D.C. Cir. 2001) (context on federal/tribal history cited in opinion)
  • Narragansett Indian Tribe v. Warwick Sewer Auth., 334 F.3d 161 (1st Cir. 2003) (Section 106 described as "stop, look, and listen")
  • Muckleshoot Indian Tribe v. U.S. Forest Serv., 177 F.3d 800 (9th Cir. 1999) (Section 106 consultation importance)
  • CTIA–Wireless Ass'n v. FCC, 466 F.3d 105 (D.C. Cir. 2006) (agency obligations under statutory process do not mandate particular substantive outcomes)
  • McMillan Park Comm. v. Nat’l Capital Planning Comm’n, 968 F.2d 1283 (D.C. Cir. 1992) (deference to Advisory Council regulations implementation)
  • Sierra Club v. U.S. Army Corps of Eng'rs, 803 F.3d 31 (D.C. Cir. 2015) (limited federal involvement does not require analysis of entire linear project)
  • Sierra Club, Inc. v. Bostick, 787 F.3d 1043 (10th Cir. 2015) (upholding partial deferral and Corps’ approach to nationwide permits)
  • Winter v. Nat. Res. Def. Council, 555 U.S. 7 (2008) (standard for preliminary injunction: likelihood of success and irreparable harm)
  • Sherley v. Sebelius, 644 F.3d 388 (D.C. Cir. 2011) (discussing preliminary injunction burden post-Winter)
  • Kleppe v. Sierra Club, 427 U.S. 390 (1976) (APA standard for agency action review)
  • Dep't of Transp. v. Public Citizen, 541 U.S. 752 (2004) (limits on agency causation where agency lacks authority to prevent effects)
  • Lee v. Thornburgh, 877 F.2d 1053 (D.C. Cir. 1989) (purpose of Section 106 is to discourage ignoring preservation values)
Read the full case

Case Details

Case Name: Standing Rock Sioux Tribe v. United States Army Corps of Engineers
Court Name: District Court, District of Columbia
Date Published: Sep 9, 2016
Citation: 205 F.Supp.3d 4
Docket Number: Civil Action No. 2016-1534
Court Abbreviation: D.D.C.