SOUTHWEST REGIONAL COUNCIL OF CARPENTERS et al. v. CITY OF LOS ANGELES et al.
B301374
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA SECOND APPELLATE DISTRICT DIVISION FOUR
Filed 3/7/22
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS. California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(a). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115(a).
James C. Chalfant, Judge.
SOUTHWEST REGIONAL COUNCIL OF CARPENTERS et al., Petitioners and Respondents, v. CITY OF LOS ANGELES et al., Defendants and Appellants; THE ICON AT PANORAMA, LLC, Real Party in Interest and Appellant.
(Los Angeles County Super. Ct. No. BS175189)
Michael N. Feuer, Los Angeles City Attorney, Leonard P. Aslanian, Assistant City Attorney, Terry Kaufmann Macias and Kathryn C. Phelan, Deputy City Attorneys; Thomas Law Group, Tina A. Thomas, Amy R. Higuera, and Christopher J. Butcher for Appellants, City of Los Angeles, Los Angeles City Council, and Department of City Planning.
Ambruster Goldsmith & Delvac LLP, Damon P. Mamalakis for
Lozeau Drury, Richard T. Drury, Brian B. Flynn and Rebecca L. Davis for Plaintiffs and Respondents, Southwest Regional Council of Carpenters and Laborers’ International Union of North America, Local 300.
Rob Bonta, Attorney General of California, Edward Ochoa, Senior Assistant Attorney General, Sarah E. Morrison, Supervising Deputy Attorney General, Scott J. Lichtig, Lani M. Maher, Deputy Attorneys General for Amicus Curiae Attorney General of California.
Cox, Castle & Nicholson, Michael H. Zischke and Amy F. Foo for Amicus Curiae California Building Industry Association, California Business Properties Association, Building Industry Association of the Bay Area.
Law Offices of Ryan Gordon and Ryan Gordon for Amicus Curiae Saul Mejia.
Remy, Moose, Manley, Whitman F. Manley and Nathan O. George for Amicus Curiae League of California Cities and California State Association of Counties.
California Renter‘s Legal Advocacy and Education Fund, Dylan Casey as Amicus Curiae.
David Petit for Amicus Curiae Natural Resources Defense Council, Planning and Conservation League and Coalition for Clean Air.
The Icon at Panorama, LLC (Icon) proposed a mixed-use commercial and residential development in the Panorama City neighborhood of Los Angeles, to be called The Icon at Panorama. The City of Los Angeles (City) certified a final environmental impact report (FEIR) and approved the project. Southwest Regional Council of Carpenters and Laborers’ International Union of North America, Local 300 (collectively, Petitioners), challenged the approval, principally arguing the City approved a project not described in the draft or final environmental impact reports. The trial court granted the unions’ writ petition, finding the City‘s draft environmental impact report (DEIR) and FEIR lacked an accurate, stable, and finite project description as required by cases interpreting the California Environmental Quality Act (CEQA). (See, e.g., County of Inyo v. City of Los Angeles (1977) 71 Cal.App.3d 185, 193 (Inyo); Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277, 288 (Washoe Meadows).) The trial court also concluded that the FEIR failed to adequately address a comment on local sewer capacity. It ordered the City to prepare and circulate a new or supplemental Environmental Impact Report (EIR).
FACTUAL BACKGROUND AND PROCEDURAL HISTORY
1. DEIR, April 6, 2017.
The developer, Icon, conceived of what the parties refer to as the Project as a mixed-use development on an approximately nine-acre site in Panorama City. The site is bounded on three sides by city streets: Roscoe Boulevard, Tobias Avenue, and Cedros Avenue.
Three commercial structures (a former Montgomery Ward, a restaurant, and an automotive repair shop, all vacant since 2003), occupy the Project site. The site is surrounded by a mix of residential, retail, office, and restaurant development, and is in a “Transit Priority Area.”
On April 6, 2017, the City, as lead agency,1 released the DEIR for public review and comment.2 As described in the DEIR, Icon proposed to demolish the existing structures and build seven buildings, consisting of 422 residences (totaling 387,000 square feet), an additional 200,000 square feet of commercial space, including a 1,200-seat theater complex, a grocery store, and associated parking for 1,690 vehicles in a multi-story parking structure. The commercial space would occupy five one- and two-story buildings with a six-level parking garage, and the residential units would occupy two seven-story buildings with two stories of above-ground parking. The Project would not include any affordable housing units.
The DEIR stated the Project was designed to provide for the efficient and functional development of the underutilized site, by allowing for regional commercial development through the replacement of vacant buildings and surface parking lots with new housing and commercial uses to meet community and regional demands. The Project would create new housing to meet the
The DEIR listed four smaller alternatives to the Project:
(1) The required “No Project” alternative of no development whatsoever.
(2) The “Reduced Project” alternative consisting of 283 residential units (257,300 square feet), 134,000 square feet of commercial space, and 1,132 parking spaces. The residential units would be in two buildings up to five stories high, and the commercial uses would be in three separate one- and two-story buildings. According to the DEIR: “The design and configuration of this alternative would be similar to the Project. The main difference would be the total square footage and building height, resulting in a mixed use development with approximately 67 percent of the mass of the [P]roject.”
(3) The “All Commercial Project” alternative containing no residential units and consisting of 583,000 square feet of floor area, with 2,500 parking spaces in a nine-story parking structure. Per the DEIR, “[t]he proposed shopping center would feature a mix of retail land uses that would complement the nearby Panorama Mall shopping center to the east.” The All Commercial Project would consist of multiple buildings of up to three stories with height limits of 60 feet.
(4) The “By-Right Project” alternative would be developed without the zoning change required for the Project and would include 350 residential units totaling 259,600 square feet, with approximately 160,000 square feet of commercial space, and 1,350 parking spaces. The DEIR noted: “To conform to the existing zoning requirements, the uses within the By-Right Project Alternative would be segregated. The residential units would be constructed within an L-shaped building up at the northeastern portion of the Project Site. The seven-story residential building would front Tobias Avenue and would wrap around a two-story commercial building. Two additional smaller commercial buildings (one and two stories) would front Roscoe Boulevard.”
Public comment on the DEIR highlighted two principal issues: hazardous soil contamination and traffic impact. Petitioners’ expert soil consultant (Soil Water Air Protection Enterprise (SWAPE)) opined the DEIR did not identify health risks to construction workers and failed to consider harm to the
Petitioners requested that the City adopt an alternative with reduced traffic impact, and suggested mitigation measures for emissions and traffic impacts.
2. Revised DEIR (RDEIR), August 31, 2017.
The City revised the DEIR after considering the comments, and on August 31, 2017, released the RDEIR for public review and comment. The RDEIR‘s primary focus was traffic. It noted the Project would affect seven intersections, but with roadway improvements and new signals, impacts could be reduced at one of the seven intersections. The RDEIR‘s description of the Project and alternatives was identical to the DEIR; it did not add any new alternatives to the project.
Again, Petitioners and others submitted written commentary, including Smith‘s opinion that the RDEIR underestimated traffic impacts and vehicle trips per day, and that the Project‘s significant and unavoidable impact would be more severe than the RDEIR disclosed. Smith recommended adoption of Alternative 2. SWAPE opined that due to this underestimation of traffic, air pollution was similarly understated in the DEIR. Further, SWAPE opined that an updated traffic analysis was required that should be based upon a correct estimation of vehicle trips per day.
3. Final EIR (FEIR), February 23, 2018.
On February 23, 2018, the City issued its FEIR for the Project. The Project description was the same as the DEIR, but the FEIR added a new “Alternative 5,” which consisted of 675 residential units (615,000 square feet of floor area), and a smaller commercial component consisting of 60,000 square feet of office space. Alternative 5 deleted the theater, grocery store, and parking
The reduction in commercial development reflected in Alternative 5 was intended to reduce adverse effects on traffic and air quality, while the increase in housing was designed to address regional housing shortages. The FEIR responded to Petitioners’ comments regarding air quality analysis related to construction activities.
In response, Smith opined that Alternative 5 would generate more traffic than the FEIR stated, and the FEIR failed to adopt an appropriate mitigation measure or the environmentally superior alternative. Petitioners’ written comments in response to the FEIR highlighted what they contended were excessive impacts on schools and the fire department, and the FEIR‘s inadequate responses to sanitation issues, in particular LASAN‘s comment described above.
4. Advisory Agency Approval of the Revised Project, A Smaller Version of Alternative 5, March 20, 2018.
In March 2018, City staff recommended approval of a smaller version of Alternative 5. This new alternative project had not been included in the DEIR, RDEIR or the FEIR. Therefore, the public had not received notice of or an opportunity to comment on it as part of the EIR process. The new proposal consisted of 623 residential units, with 60,000 feet of commercial space. The parties refer to this new alternative as the Revised Project. Compared to Alternative 5, the Revised Project contained 52 fewer residences (resulting in 99,430 fewer square feet of residential construction), and the same commercial area.
In particular, the residences all would be within two separate buildings, with one building spanning the entire frontage of the site along Cedros Avenue, and the other residential building positioned within the central portion of the site, overlooking the public plaza on Tobias Avenue. Both buildings would reach six- and seven-stories in height, with four and five stories of residential uses over two levels of podium parking. Commercial uses would be located within two separate one-story buildings, fronting on Roscoe Boulevard and Tobias Avenue, located on the eastern and southern
On March 20, 2018, the Advisory Agency of the Planning Commission approved the Revised Project. The Advisory Agency described it as a “slightly reduced” version of the FEIR‘s Alternative 5, designed to eliminate some unavoidable impacts of the original Project.
5. Petitioners Appeal to the Planning Commission and City Council, April and August 2018.
On April 3, 2018, Petitioners appealed the Advisory Agency approval of the Revised Project to the Planning Commission. Petitioners asserted the Revised Project did not comply with CEQA because the project description had changed after closure of public comments.3 Petitioners pointed out that there had been extensive comments for a project never approved, and that the approved project had unstudied impacts on traffic, air quality, schools, fire, police, and sewage. They asserted that such an EIR—one that added significant new information after the public comment period had expired—required new notice and recirculation for additional comments.
After a hearing held April 26, 2018, the Planning Commission observed that the Project was supported by local community groups, including the Chamber of Commerce, the LAPD, and area residents, and that the Revised Project had the same unavoidable impacts as the Project. The Planning Commission denied the appeal.
Petitioners appealed that decision to the Los Angeles City Council, raising the same arguments, but the Planning and Land Use Management Committee (which hears such appeals) denied the appeal. In August 2018, the City certified the Revised Project of 623 residential units and 60,000 square feet of commercial space.
6. Petition for Writ of Mandate.
Petitioners filed a verified petition for writ of mandate on October 1, 2018, seeking a set-aside of the Revised Project, the City‘s findings, and the project approval, based on (1) what they contend was an inadequate project description in the EIR because neither the DEIR, the RDEIR, nor the FEIR
Petitioners also argued that the revised project description violated the CEQA requirement of a “stable, accurate and finite project” description throughout the CEQA process. Respondents countered that the project remained a mixed-use project; as a result, the question was not whether the project description was stable, but rather whether the changes constituted “significant new information” requiring recirculation of the EIR under section 15088.5.
7. Trial Court Ruling.
The trial court granted the petition after finding the City violated CEQA by failing to provide a stable, accurate, and finite project description and failing to address LASAN‘s comment adequately.
The court first addressed the City‘s argument that the project description was accurate, stable and finite, and that the issue was properly framed as whether the Revised Project constituted “new information” addressable only under CEQA‘s recirculation provisions, section 21092.1 and CEQA Guidelines4 section 15088.5, subdivision (a). As framed by the trial court, “[t]he issue becomes whether the City‘s presentation and approval of the Revised Project can only be addressed as new information under [section 21092.1] and Guidelines section 15088.5, and not as a violation of the separate requirement for ‘an accurate, stable and finite’ project description.”
Although it found petitioners had waived any argument that recirculation of a new or revised EIR containing a description of the Revised Project was required by Guidelines section 15088.5, the court agreed that the Revised Project did not constitute “new information” requiring recirculation of the FEIR pursuant to that Guideline. The court held, however, that nothing in section 15088.5, foreclosed an argument that the project description had changed too much, i.e., was “unstable,” even though recirculation was not required under section 21092.1.
In evaluating the stability of the project description, the court analyzed and applied Inyo, supra, 71 Cal.App.3d 185, Washoe Meadows, supra, 17 Cal.App.5th 277, South of Market Community Action Network v. City and County of San Francisco (2019) 33 Cal.App.5th 321 (SoMa), and Citizens for a Sustainable Treasure Island v. City and County of San Francisco (2014) 227 Cal.App.4th 1036 (Treasure Island).
The trial court concluded the project description was impermissibly unstable. “As in Washoe Meadows and Inyo, the City‘s approval of the Revised Project must be set aside because the Project described in the DEIR, RDEIR, and FEIR differed significantly from the Revised Project adopted by the Advisory Agency. The difference between the Revised Project‘s 623 residential units and 60,000 square feet of commercial space and the Project‘s 422 residential units and 200,000 square feet of commercial space . . . runs afoul of the CEQA requirement . . . [that] ‘for a project to be stable, the DEIR, the FEIR, and the final approval must describe substantially the same project.‘” In particular, the court took issue with the fact the Revised Project was never subject to a formal comment period, which in the court‘s view presented a “moving target which impaired the public‘s ability to participate in the environmental review process.”
The court rejected the City‘s reliance on SoMa, where two project alternatives (one commercial and one residential) that had similar physical footprints were evaluated side-by-side, with public comment on both schemes. ”SoMa does not support the City‘s proposition that ‘a project description is not rendered inadequate by changes in the allocation of space between defined project uses.‘” The trial court distinguished SoMa, where there was one project with two options, and rejected the City‘s contention that the Revised Project was essentially the same mixed-use project as the original Project and the alternatives presented in the various iterations of the EIR, and was thus a “quintessential example of how CEQA” was supposed to operate as a project evolves in response to public comment.
The court opined, “an EIR‘s informative quality about environmental effects are irrelevant where different project descriptions vitiate the EIR process as a vehicle for intelligent public participation. . . . The issue is not whether the Revised Project has the same footprint, location, and environmental impacts as the Project, but rather whether the DEIR provided an accurate description of the Project and alternatives regardless of environmental impacts.” “In this case, the Revised Project, a variant of Alternative 5 proposed in the FEIR, was adopted and was materially different than any alternative in the DEIR.”
The court therefore concluded the DEIR “failed to identify a project or any alternative with a similar number of residential units and amount of commercial space as identified in the Revised Project. . . . The Revised Project‘s
The court observed that although failure to comply with CEQA‘s informational requirements does not require reversal unless the petitioner establishes prejudice, the differing project descriptions resulted in prejudice. The trial court concluded “the failure to include relevant information preclude[d] informed decision making and informed public participation, thereby thwarting the statutory goals of the EIR process,” citing Washoe Meadows. The court also addressed substantive arguments regarding the FEIR‘s evaluation of environmental impacts (air quality, traffic, health risks, and public service impacts), and found fault only with what it concluded was a failure by the City to respond adequately to LASAN‘s evaluation of local sewer capacity. The trial court found error in the City‘s failure to fully analyze sewage impacts based on a potential lack of immediately available local sewer line capacity.
The trial court ordered the FEIR certification and Revised Project approval set aside, and ordered the City to prepare a new or supplemental EIR for public comment.
The trial court entered final judgment on September 25, 2019, issuing a writ of mandate.
DISCUSSION
The City argues on appeal that (1) Petitioners waived any recirculation challenge; (2) the trial court erred in adding a “materially different” test to CEQA‘s stable project description requirement because “significant new information” under section 15088.5 is the only ground upon which a trial court can order recirculation of an EIR; (3) the project description was not unstable; and (4) the City‘s response to LASAN‘s comment regarding sewer impacts was adequate. Four amicus briefs5 argue in favor of project approval, contending the trial court erred in not applying the section 15088.5 standard, and further argue that the trial court‘s test injects uncertainty into the CEQA process, discourages lead agencies from approving smaller projects in response to comments, and will result in a slowdown of new housing construction in a time of need. The California
I. OVERVIEW OF CEQA AND STANDARD OF REVIEW.
A. CEQA‘s Purpose and the Function of an EIR.
CEQA advances four related purposes: (1) informing “the government and public about a proposed [project‘s] potential environmental impacts;” (2) identifying “ways to reduce or avoid environmental damage;” (3) preventing “environmental damage by requiring project changes via alternatives or mitigation measures when feasible;” and (4) disclosing “to the public the rationale for governmental approval of a project that may significantly impact the environment. [Citation.]” (California Building Industry Assn. v. Bay Area Air Quality Management Dist. (2015) 62 Cal.4th 369, 382 (CBIA).)
“To further these goals, CEQA requires [public] agencies follow a three-step process when planning an activity that could fall within its scope. [Citations.] First, the agency must determine whether a proposed activity is a ‘[p]roject,’ i.e., an activity that is undertaken, supported, or approved by a public agency and that ‘may cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment.’ [Citation.]” (CBIA, supra, 62 Cal.4th at p. 382.) “Second, if the proposed activity is a project, the agency must [determine] whether the project is exempt from the CEQA review process under either a statutory exemption [citation] or a categorical exemption set forth in the CEQA Guidelines [citations]. If the agency determines the project is not exempt, it must then decide whether the project may have a significant environmental effect. [If not,] the agency ‘must “adopt a negative declaration to that effect.“” [Citations.]” (Ibid., fn. omitted.) Finally, “if the agency finds the project ‘may have a significant effect on the environment,’ it must prepare an EIR before approving the project. [Citations.]” (Ibid.; Sierra Club v. County of Fresno (2018) 6 Cal.5th 502, 511-512 (County of Fresno).)
An EIR “is an informational document” designed to “provide public agencies and the public in general with detailed information about the effect [of] a proposed project. . . on the environment.” (
B. Standard of Review.
An agency abuses its discretion under CEQA either by failing to proceed in the manner CEQA requires or by reaching factual conclusions unsupported by substantial evidence. (Banning Ranch Conservancy v. City of Newport Beach (2017) 2 Cal.5th 918, 935 (Banning Ranch Conservancy).) This “procedural issues/factual issues dichotomy” works well for courts reviewing agency determinations. (County of Fresno, supra, 6 Cal.5th at p. 512.) Judicial review of these two types of error differs significantly, however. “While we determine de novo whether the agency has employed the correct procedures, ‘scrupulously enforc[ing] all legislatively mandated CEQA requirements’ [citation], we accord greater deference to the agency‘s substantive factual conclusions. In reviewing for substantial evidence, the reviewing court ‘may not set aside an agency‘s approval of an EIR on the ground that an opposite conclusion would have been equally or more reasonable,’ for, on factual questions, our task ‘is not to weigh conflicting evidence and determine who has the better argument.’ [Citation.]’ [Citation.]” (Banning Ranch Conservancy, supra, 2 Cal.5th at p. 935.)
“Where an EIR is challenged as being legally inadequate, a court presumes a public agency‘s decision to certify the EIR is correct, thereby imposing on a party challenging it the burden of establishing otherwise. [Citations.]” (Sierra Club v. City of Orange (2008) 163 Cal.App.4th 523, 530 (City of Orange).)
Our review in a CEQA case, as in other mandamus actions, is the same as that of the trial court. (In re Bay-Delta etc. (2008) 43 Cal.4th 1143, 1162 (Bay-Delta).) We review the agency‘s action, not the trial court‘s decision, and our inquiry extends only to whether there has been a prejudicial abuse of discretion on the part of the agency. (Id. at pp. 1161-1162.) We do not pass upon the correctness of the EIR‘s environmental conclusions, but only upon its sufficiency as an informative document. (Id. at p. 1161.) Generally, that inquiry is a mixed question of law and fact subject to de novo review, “but to the extent factual questions predominate, the more deferential substantial evidence standard” of review applies. (County of Fresno, supra, 6 Cal.5th at p. 516.)
The failure to comply with CEQA‘s informational requirements does not require reversal unless there is prejudice. (
II. THE REVISED PROJECT DESCRIPTION COMPLIED WITH CEQA.
A. CEQA‘s Stable Project Requirement.
The primary purpose “of an EIR is to give the public and government agencies the information needed to make informed decisions, thus protecting ‘not only the environment but also informed self-government.’ [Citation.]” (Bay-Delta, supra, 43 Cal.4th at p. 1162.) “The ultimate inquiry, as case law and the CEQA Guidelines make clear, is whether the EIR includes enough detail ‘to enable those who did not participate in its preparation to understand and to consider meaningfully the issues raised by the proposed project.’ [Citations.]” (County of Fresno, supra, 6 Cal.5th at p. 516.) The sufficiency of an EIR is to be evaluated in light of what is reasonably feasible. (California Oak Foundation v. Regents of the University of Southern California (2010) 188 Cal.App.4th 227, 262.) “The overriding issue on review is thus ‘whether the [lead agency] reasonably and in good faith discussed [a project] in detail sufficient [to enable] the public [to] discern from the EIR the “analytic route the . . . agency traveled from evidence to action.” [Citation.]’ [Citation.]” (Ibid.)
A draft EIR must contain a project description. (SoMa, supra, 33 Cal.App.5th at p. 332.) An accurate project description is the “sine qua non” of an informative and legally sufficient EIR. (Ibid.) The project description must include (a) the precise location and boundaries of the proposed project, (b) a statement of the objectives sought by the proposed project, (c) a general description of the project‘s technical, economic and environmental characteristics, and (d) a statement briefly describing the intended use of the EIR. (Guidelines, § 15124, subds. (a)-(d).)
The project description must be “accurate, stable and finite[.]” (Inyo, supra, 71 Cal.App.3d at p. 193.) “A project description that gives conflicting signals to decision makers and the public about the nature of the project is fundamentally inadequate and misleading. [Citation.]” (SoMa, supra, 33
Cal.App.5th at p. 332.) This description of the project is an indispensable element of a valid EIR. (Washoe Meadows, supra, 17 Cal.App.5th at p. 287.) Whether the EIR adequately describes the project is reviewed de novo. (Ibid.)
A quintet of cases evaluating whether a project description remained stable throughout the EIR process provides some guideposts for interpreting
1. Inyo.
Inyo was the first decision to articulate the need for a stable, definite, and unambiguous project description as part of
Inyo acknowledged that the EIR adequately described the broader project‘s environmental effects, and thus the informative quality of the EIR‘s environmental forecasts were not affected by the “ill-conceived, initial project description.” (Inyo, supra, 71 Cal.App.3d at p. 197 [elasticity of project concept did not vitally affect the impact sections of the report].) Nonetheless, the court concluded that the “incessant shifts among different project descriptions [within the same EIR] vitiate[d] the City‘s EIR process as a vehicle for intelligent public participation,” because “[a] curtailed, enigmatic or unstable project description draws a red herring across the path of public input.” (Id. at pp. 197, 198.)
2. Washoe Meadows.
More recently, in Washoe Meadows, supra, 17 Cal.App.5th 277, the court reiterated
Washoe Meadows found this project description legally impermissible under
Washoe Meadows found the Department was able to provide certainty; it had selected a preferred alternative as part of its public scoping process for the project. (Washoe Meadows, supra, 17 Cal.App.5th at pp. 283-284.) But it simply failed to “describe a project at all. Instead, it presented five different alternatives for addressing the Upper Truckee River‘s contribution to the discharge of sediment into Lake Tahoe, and indicated that following a period for public comment, one of the alternatives, or a variation thereof, would be selected as the project.” (Id. at p. 288.)
It did not matter to the Washoe Meadows court that the draft EIR thoroughly analyzed the alternative that was ultimately selected in the final EIR. (Washoe Meadows, supra, 17 Cal.App.5th at p. 288.) “[T]he problem with an agency‘s failure to propose a stable project is not confined to ‘the informative quality of the EIR‘s environmental forecasts.’ [Citation.]” (Ibid.) Rather, a failure to identify or select a project at all “impairs the public‘s right and ability to participate in the environmental review process.” (Ibid.)
3. SoMa.
The project in SoMa involved a four-acre site in downtown San Francisco in the area of Fifth and Mission Streets intended to provide
In SoMa, the petitioners challenged the FEIR as “inadequate” because it presented two different schemes, and as a result was confusing and hampered their “ability to understand which project was actually proposed and analyzed.” (SoMa, supra, 33 Cal.App.5th at p. 332.) SoMa rejected this contention because under both schemes, the project involved construction of ground floor space, similar massing of structures, retention of the historic Chronicle Building, demolition of all other buildings on the site, and construction of four new buildings ranging from 195 to 470 feet. (Id. at p. 333.) The DEIR contained text and tables describing in detail both schemes. (Ibid.) Thus, “the record reveals the EIR in this case described one project—a mixed-use development involving the retention of two historic buildings, the demolition of all other buildings on the site, and the construction of four new buildings and active ground floor space—with two options for different allocations of residential and office units. The analysis was not curtailed, misleading, or inconsistent. If anything, it carefully articulated two possible variations and fully disclosed the maximum possible scope of the project. The project description here enhanced, rather than obscured, the information available to the public.” (Id. at pp. 333-334, fn. omitted.)
In conclusion, SoMa observed “[p]laintiffs do not dispute the [draft] EIR‘s project description met
4. Treasure Island.
Treasure Island involved a 20-year development plan to convert a former military base on a man-made island in the San Francisco Bay into a new mixed-use community. (Treasure Island, supra, 227 Cal.App.4th at p. 1043-1044.) The island was contaminated with hazardous waste requiring extensive cleanup. (Id. at p. 1056.) As a result, the project proponents could not precisely predict when the island would be available for development. (Id. at pp. 1056-1057.)
The City and County of San Francisco certified the FEIR containing a mixed-use development consisting of up to 8,000 residential units (25 percent of which were to be below-market), up to 140,000 square feet of retail space and 100,000 square feet of new office space, restoration and reuse of historic buildings, 300 acres of park, plus bike and transit facilities. (Treasure Island, supra, 227 Cal.App.4th at p. 1044.) Due to the hazardous materials cleanup, the project was to be constructed in phases over a 15- to 20-year period. (Ibid.)
Treasure Island rejected claims that the project description was inadequate and misleading. (Treasure Island, supra, 227 Cal.App.4th at p. 1055.) Treasure Island concluded that a project description that included both fixed elements (such as street layouts) and conceptual elements (such as the shape of buildings or specific landscape designs) was all that could be meaningfully provided at present. (Id. at pp. 1053-1054.) Although the EIR in Treasure Island did not describe the details of all elements of the project, the agency committed to conduct subsequent
Treasure Island distinguished Inyo on the ground that Inyo did not address “a situation where the project was rendered unstable simply because specific building and design decisions were not made in the EIR. Rather, in [Inyo,] the parameters of the prospective project itself were unclear [because initially the] EIR described the project as a 51-cubic-feet-per-second increase in surface pumping to supply water used in the Owens Valley. [Citation.] The EIR, however, went on to analyze a project far greater in scope, including higher rates of pumping and a vast infrastructure
5. Stop the Millennium.
In 2008, Millennium Hollywood LLC (Millennium) proposed to build a mixed-use development with a hotel, office space, a sports club, residences, commercial space and restaurants. (STOPTHEMILLENNIUMHOLLYWOOD.COM v. City of Los Angeles (2019) 39 Cal.App.5th 1, 6 (Stop the Millennium).) The project site consisted of 4.47 acres near Hollywood Boulevard on Vine Street surrounding the historic Capitol Records building. (Ibid.) The project would consist of three separate towers arising out of low-rise buildings surrounding the preserved Capitol Records building and incorporate extensive open space. (Ibid.) The permit application contained detailed site plans, elevations for the buildings, and architectural renderings. (Id. at p. 7.) After being informed the enclosed balconies would require a variance, Millennium took no further action on the project until 2011. (Ibid.)
Millennium submitted a new proposal in April 2011. The proposal‘s project shared similarities with the 2008 project, but did not contain much detail about what Millennium proposed to build, instead describing a project that was “a mix of land uses, including residential dwelling units, luxury hotel rooms, office and associated uses, restaurant space, [a] health and fitness club [] and retail establishments.” (Stop the Millennium, supra, 35 Cal.App.5th at pp. 7-8.) The draft EIR similarly contained few specifics, stating that the project “would implement a Development Agreement . . . that would vest the [p]roject‘s entitlements, establish detailed and flexible development parameters for the Project Site and ensure that the [p]roject is completed consistent with [these parameters].” (Id. at p. 9.) Further, the DEIR stated that because flexibility was key, “a conceptual plan has been prepared as an illustrative scenario to demonstrate a potential development program.” (Id. at pp. 9-10.) The conceptual plan and two other scenarios were identified in the DEIR. (Id. at p. 10.) The FEIR, published in 2013, included without modification the project description in the DEIR. (Id. at p. 11.)
The trial court concluded the project description was not stable or finite because the conceptual approach used to define the project impermissibly deferred a portion of the environmental impact analysis. (Stop the Millennium, supra, 35 Cal.App.5th at p. 14.) Stop the Millennium relied on Inyo and Washoe Meadows. (Id. at p. 18) “In this case, the project description is not simply inconsistent, it fails to describe the siting, size, mass, or appearance of any building proposed to be built at the project site. The draft EIR does not describe a building development project at all. Rather, it presents different conceptual scenarios that Millennium or future developers may follow for the development of this site. These concepts and development scenarios—none of which may ultimately be constructed—do not meet the requirement of a stable or finite proposed project.” (Id. at p. 18.) Stop the Millennium affirmed the trial court, finding Millennium‘s conceptual approach to the project failed to present any concrete proposal, thereby creating an obstacle to informed public participation. (Id. at p. 20.)
B. The Revised Project—a Variant of Alternative 5—Complied With CEQA.
1. The Revised Project Retained the Same Components.
As the case law illustrates, the requirement of an accurate, stable, and finite project description is the “sine qua non” of an informative and legally sufficient EIR. (SoMa, supra, 33 Cal.App.5th at p. 332.) As noted above, this requirement has been reiterated in a number of cases since the seminal case of Inyo. (See, e.g., Treasure Island, supra, 227 Cal.App.4th at p. 1052 [“This court is among the many which have recognized that a project description that gives conflicting signals to decision makers and the public about the nature and scope of the project is fundamentally inadequate and misleading [citation.]“]; Communities for a Better Environment v. City of Richmond (2010) 184 Cal.App.4th 70, 84-89 [EIR failed as an informational document because the project description was inconsistent and obscure as to the true purpose and scope of the project]; San Joaquin Raptor Rescue Center v. County of Merced (2007) 149 Cal.App.4th 645, 653 [“[a]n EIR must include detail sufficient to enable those who did not participate in its preparation to understand and to consider meaningfully the issues raised by the proposed project[]“].)
Here, the City did not violate
The project started as a nearly equal balance of commercial (200,000 square feet) and residential (387,000 square feet, 422 units) uses. The four alternatives in the DEIR included a mixed-use project containing 283 residential units and a reduced commercial footprint, an all-commercial project of
Alternative Five, presented in the FEIR, consisted of 675 residences (615,000 square feet), and a reduced amount of commercial space (60,000 square feet), with the latter reduction in size intended to address comments regarding traffic impacts from commercial development. Ultimately, the Revised Project had a slightly smaller residential component than Alternative 5 (623 residences), and the same amount of commercial space (60,000 square feet).
In terms of the buildings’ profile, the initial DEIR presented a mix of building uses that ranged from seven buildings in the initial project (one- and two-story buildings), to the Reduced Project alternative in the DEIR (one- and two-story commercial uses with two five-story buildings comprising the residential component), the All Commercial Project (multiple buildings up to three stories, with a nine-story parking structure), and the By Right Project with a seven-story residential building. The Revised Project contained three fewer commercial buildings than the original project and contained the same number of residential buildings (two), each of which would be six to seven stories high.
An analysis of the various permutations of the project alternatives establishes that if residential units were added, commercial space was subtracted. Various arrangements of building profiles were proposed within this framework, yet the physical layout of the project itself remained consistent and within the defined outline of the project site. Admittedly, the approved project had a slightly different mix of residential versus commercial development than the alternatives presented in the DEIR and FEIR. While the number of residences in the approved project exceeded the number of housing units in the various alternatives in the DEIR, it was less than the number of residences in the FEIR‘s alternative 5. Under the circumstances, the project definition was sufficiently accurate and stable.
Inyo is readily distinguishable. In Inyo, the project description was flawed because it was internally inconsistent within the DEIR and because the actual project was much larger in scope than some versions of the project description in the DEIR. (Inyo, supra, 71 Cal.App.3d at pp. 197, 198.) Here, the public was given the opportunity to consider and comment on various alternative compositions of the proposed residential/commercial mixed-use development all within a defined project footprint. The alternative selected, although not included within the DEIR or FEIR, mitigated traffic impacts by altering the residential/commercial mix, stayed within the project footprint, and was consistent with the mixed-use project definition.
Washoe Meadows also is readily distinguishable. As noted above, in that case the state agency presented multiple project alternatives, all with different footprints and differing environmental impacts, leading the court to conclude the public was confused about which project to comment on. Here, the project alternatives presented for public input had the same footprint as each other and the Revised Project was very similar in scope and use to alternatives considered. There was no evidence of widely varying environmental impact between the various project alternatives presented to the public and the Revised Project.
In Treasure Island, the project description did not include all environmental mediation because the scope of the necessary work was not known at the time of the EIR. (Treasure Island, supra, 227 Cal.App.4th at p. 1055.) Here, the size and condition of the property was fixed and did not necessitate future evaluations.
In SoMa, there were two alternatives, one commercial and one residential, that were fully vetted in the EIRs. (Soma, supra, 33 Cal.App.5th at pp. 333-334.) Here, the Project, its alternatives, and the Revised Project all involved varying mixes of residential and commercial uses on a well defined site. Although the Revised Project was not publicly vetted, it was not so significantly different from the project alternatives in the DEIR to conclude the project definition was unstable.
Finally, unlike Stop the Millennium, which had no meaningful project description, the descriptions of the initial project, all alternatives, and the Revised Project were sufficiently detailed. Each project contained site renderings and layouts, square footages, and building descriptions.
In summary, we agree with the City‘s arguments that consideration of additional alternatives after a draft EIR is circulated does not render a project description unstable. Here, the DEIR contained all the mandatory elements under
2. Public Comment on the Revised Project was not Required.
We acknowledge that the public had no opportunity to comment on the specific project actually approved, because it was not included in any EIR circulated for comment. But
Although we believe decision-makers and the public would be better served if the public had an opportunity to comment on the actual project before approval, we decline to engraft that requirement into
Here, the City complied fully with
Moreover, petitioners cannot show any prejudice flowing from the City‘s inclusion of Alternative 5 in the FEIR and its approval of the Revised Project, although neither was circulated for an official period of public comment. The record establishes there was extensive commentary on the original alternatives, and that commentary on factors like traffic and environmental contamination were taken into account before preparation of the FEIR, and formed
C. Recirculation Under Section 15088.5
1. When Recirculation is Required.
The parties dispute whether recirculation under the standards of
“If the lead agency adds ‘significant new information’ to the EIR subsequent to the close of the public comment period but prior to certification of the final EIR,
“‘Significant new information’ requiring recirculation include[s], for example, a disclosure showing that: [¶] (1) A new significant environmental impact would result from the project or from a new mitigation measure proposed to be implemented[;] [¶] (2) A substantial increase in the severity of an environmental impact would result unless mitigation measures are adopted that reduce the impact to a level of insignificance[;] [¶] (3) A feasible project alternative or mitigation measure considerably different from others previously analyzed would clearly lessen the significant environmental impacts of the project, but the project‘s proponents decline to adopt it[;] [¶] (4) The draft EIR was so fundamentally and basically inadequate and conclusory in nature that meaningful public review and comment were precluded.” (
Under
2. Applying Section 15088.5, The Revised Alternative 5 Did Not Require Recirculation.
Here, although we agree Petitioners waived the
In Western Placer Citizens for an Agricultural & Rural Environment v. County of Placer (2006) 144 Cal.App.4th 890, a county‘s EIR analyzing a proposed aggregate mine did not violate
Indeed, here the Revised Project was presaged by the various alternatives in the original DEIR as discussed above. Further, the approach here, in which various components of the project were revised to meet the public commentary, complies with
III. THE CITY ADEQUATELY RESPONDED TO LASAN‘S COMMENTS.
As noted above, the trial court concluded the FEIR‘s response to LASAN‘s comment about local sewer line capacity was inadequate. The City principally argues (1) the City‘s response was adequate under
A. Factual Background.
The City prepared a Wastewater Facilities Plan in 1982 and updated it in 1991. The 1991 plan contained plans for facilities through 2010 and at the time of the DEIR regulated wastewater facilities in the City. In 1990, the City adopted Ordinance No. 166,060 to address the problem of insufficient wastewater treatment capacity. The ordinance established sewer permit allocation regulations for projects discharging wastewater to the Hyperion Water Reclamation Plant (Hyperion Plant).
The Hyperion Plant has the capacity to treat 450 million gallons per day of wastewater generated in the western portion of Los Angeles County and the City of Los Angeles. Quite apart from capacity at the Hyperion Plant or other treatment plants, the City requires, as part of the normal construction and building process, that an applicant confirm with the City that the capacity of the local and trunk lines that would service the project are sufficient to accommodate the project‘s sewer flows during the construction and operation phases. “Furthermore, a Project shall implement any upgrades to the sewer system serving the Project that could be needed to accommodate the Project‘s wastewater generation.”
Currently, the Project site is unoccupied. The Project was estimated to generate 89,320 gallons per day of wastewater. The DEIR outlined potential wastewater impacts on the infrastructure serving the Project. The existing sewer lines that currently serve and would continue to serve the Project site consist of two eight-inch lines on Cedros and Tobias Avenues, which join to feed an 18-inch line on Van Nuys Boulevard, which in turn feeds into a 60-inch line on Hart Street, and an 18-inch line on Hazeltine Street. The flow from Hazeltine Street feeds into a 36-inch line before discharging into a 54-inch sewer line on Chandler Boulevard.
The DEIR stated that although the Project would generate wastewater from the site, wastewater treatment facilities (namely, the Hyperion Plant) could accommodate the additional sewage flow. “As a result, the Project would not result in the need for new or additional wastewater treatment facilities. Therefore, Project impacts to Wastewater treatment capacity would be less than significant.”
In response at Comment 5-2, LASAN observed that “[b]ased on the estimated flows, it appears the sewer system might be able to accommodate the total flow for your proposed project. Further detailed gauging and evaluation will be needed as part of the permit process to identify a specific
In response to LASAN‘s comment, the City stated that “the comment includes information about sewer availability and provides the current approximate flow level and design capacities of the local sewer system. The commenter indicated that the sewer system might be able to accommodate the total flow of the Project, and that further detailed gauging and evaluation will be needed as part of the permit process. The commenter also indicates that the sewage from the Project will be conveyed to the Hyperion Treatment Plant, which has sufficient capacity to accommodate the Project. The comment validates the information provided in the draft EIR. No additional analysis is necessary.”
On March 19, 2018, Petitioners objected to the FEIR‘s statement that “no further analysis is necessary” of sewage capacity. “Clearly further analysis is required, as [LASAN] concludes that analysis is required. There are few more basic environmental issues than the proper disposal of sewage. It is well established that when a project will create a need for additional sewage capacity, the
Nonetheless, on April 26, 2018, the City‘s Planning Department rejected any challenge to the adequacy of the sewer analysis, finding LASAN stated that “the sewer capacity is adequate for the project.” The FEIR found “the sewer system might be able to accommodate the total flow of the project, and [] further detailed gauging and evaluation will be needed as part of the permit process. Comment Letter 5 in the Final EIR also indicates that the sewage from the project would be conveyed to the Hyperion Treatment Plant, which has sufficient capacity to accommodate the project.” Thus, the Planning Department concluded that LASAN had in fact validated the information provided in the DEIR.
The trial court found the City‘s response to LASAN‘s comment in the DEIR inadequate because the City “failed to fully analyze the sewage impacts
B. Discussion.
The City contends the response to LASAN‘s comment was adequate under
As explained in King & Gardiner, supra, 45 Cal.App.5th 814, “[t]he requirement for a ‘reasoned analysis’ is satisfied when the lead agency ‘particularly set[s] forth in detail the reasons why the particular comments and objections were rejected.’ [Citation.] The requirement for a detailed statement is designed to promote the integrity of the process by preventing stubborn problems or serious criticism from being swept under the rug. [Citation.] Also, conclusory statements afford no basis for a comparison of the problems involved with the mitigation proposed by the agency and the mitigation proposed in comments. [Citation.] Despite the requirements for details and a reasoned analysis, agencies ‘generally have considerable leeway’ regarding their response to a public comment. [Citation.]” (Id. at p. 880.)
Here, we conclude that the City‘s response to LASAN‘s comment was adequate. In addition to verifying the Hyperion Plant has sufficient capacity
There is no evidence in the record that any needed local sewer construction work would cause any environmental problems, other than possible temporary traffic delays that might be occasioned by opening streets for sewer line upgrades. That is an insufficient reason to require additional environmental review or invalidate the City‘s approvals of the revised project.
DISPOSITION
The judgment of the Superior Court is reversed. Appellants are to recover their costs on appeal.
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
CURREY, J.
We concur:
MANELLA, P.J.
MICON, J.*
* Judge of the Los Angeles County Superior Court, assigned by the Chief Justice pursuant to article VI, section 6 of the California Constitution.