History
  • No items yet
midpage
76 Cal.App.5th 1154
Cal. Ct. App.
2022
Read the full case

Background

  • Icon proposed a mixed-use redevelopment of an ~9-acre Panorama City site; initial DEIR (Apr 2017) described 422 residences (387,000 sf) and ~200,000 sf commercial space with several alternatives.
  • The RDEIR (Aug 2017) kept the same description; public comments raised concerns about traffic, contaminated soils, and local sewer connections; LASAN said Hyperion Plant had capacity but local gauging was needed.
  • The FEIR (Feb 2018) added Alternative 5 (675 units, 60,000 sf commercial). In March 2018 City staff proposed and the Advisory Agency approved a Revised Project (623 units, 60,000 sf commercial) that was not circulated for DEIR comment.
  • Petitioners (unions) sued, arguing the approved Revised Project differed materially from the DEIR/FEIR (violating CEQA’s requirement of an accurate, stable, finite project description), that recirculation was required, and that the FEIR inadequately addressed local sewer capacity.
  • The trial court agreed, granted the writ, and ordered a new/supplemental EIR; the Court of Appeal reversed, holding the project description remained sufficiently stable and the sewer response was adequate.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the approved Revised Project violated CEQA’s requirement that the DEIR/FEIR describe an accurate, stable, finite project The Revised Project (623 units/60k sf commercial) was not described in the DEIR/RDEIR/FEIR; public could not meaningfully comment on the actual approved project The project remained a single, defined mixed-use proposal on the same footprint; changes were only compositional (residential vs commercial) and contemplated by alternatives Reversed trial court: project description was sufficiently accurate, stable, and finite — Revised Project was a variant of alternatives and stayed within the defined project footprint
Whether recirculation under CEQA Guideline §15088.5 is the exclusive mechanism for addressing post-DEIR changes (i.e., whether a “materially different” test applies) CEQA requires recirculation or new EIR when significant new information or a materially different project is approved without public comment The City argued petitioners waived any recirculation claim and that §15088.5 governs recirculation; courts should not graft a separate “materially different” test Court held §15088.5’s recirculation standard governs and no separate materially-different project-description recirculation rule should be engrafted; recirculation was not required here
Whether the public was entitled to a new comment period on the Revised Project (procedural prejudice) Approval of an uncirculated Revised Project after close of DEIR comment deprived the public of its participation rights and prejudiced petitioners The public had extensive prior comment opportunities (92 days total) and multiple hearings after the Revised Project was proposed; petitioners waived a recirculation claim Court found no prejudicial failure: substantial public process occurred and petitioners failed to show loss of meaningful participation
Whether the FEIR’s response to LASAN’s sewer comment was adequate LASAN’s note that local sewer gauging was required meant the FEIR improperly deferred necessary environmental analysis of local sewer capacity and mitigation LASAN confirmed Hyperion Plant capacity and said local gauging would occur during permitting; any needed local line upgrades would be the developer’s obligation and would not present significant environmental effects Court held City’s response was adequate: Hyperion capacity addressed treatment and LASAN’s gauging requirement properly deferred to the permit stage; no substantial evidence of significant environmental impacts from local sewer upgrades

Key Cases Cited

  • County of Inyo v. City of Los Angeles, 71 Cal.App.3d 185 (Cal. Ct. App.) (project description must be stable, definite, unambiguous)
  • Washoe Meadows Community v. Department of Parks & Recreation, 17 Cal.App.5th 277 (Cal. Ct. App.) (DEIR must present a stable project rather than a set of disparate alternatives)
  • South of Market Community Action Network v. City & County of San Francisco, 33 Cal.App.5th 321 (Cal. Ct. App.) (two fully described options in DEIR acceptable where core project elements were stable)
  • Citizens for a Sustainable Treasure Island v. City & County of San Francisco, 227 Cal.App.4th 1036 (Cal. Ct. App.) (an EIR may include fixed and conceptual elements when project specifics cannot yet be locked down)
  • Laurel Heights Improvement Assn. v. Regents of Univ. of California, 6 Cal.4th 1112 (Cal. 1993) (recirculation required when significant new information is added after public comment)
Read the full case

Case Details

Case Name: Southwest Regional Council of Carpenters v. City of Los Angeles CA2/4
Court Name: California Court of Appeal
Date Published: Mar 7, 2022
Citations: 76 Cal.App.5th 1154; 291 Cal.Rptr.3d 863; B301374
Docket Number: B301374
Court Abbreviation: Cal. Ct. App.
Log In
    Southwest Regional Council of Carpenters v. City of Los Angeles CA2/4, 76 Cal.App.5th 1154