The Court of Appeal agreed that the EIR complied with the requirements of the California Environmental Quality Act (CEQA). 1 However, it reversed on the general plan issue, accepting the City's argument that the plan would be satisfied if the City worked with the commission after project approval, during the process for obtaining a coastal development permit.
In this court, the parties have briefed and argued both the general plan and CEQA questions. The CEQA dispute centers on whether an EIR must identify areas that might qualify as environmentally sensitive habitat areas (ESHA) under the California Coastal Act of 1976 (Coastal Act; § 30000 et seq.), and account for those areas in its analysis of project alternatives and mitigation measures. We hold that CEQA so requires. The City's EIR is inadequate because it omitted any consideration of potential ESHA on the project site, as well as ESHA that were already identified. Because BRC is entitled to relief on its CEQA claims, we need not address the general plan issues.
A. Banning Ranch, the General Plan, the Coastal Land Use Plan, and ESHA
Banning Ranch is a privately owned 400-acre tract of largely undeveloped property, containing both oilfield facilities and wildlife habitat. Significantly, it lies in the coastal zone that the Legislature has designated for special protection under the Coastal Act. (§ 30001.5.) Most development in the coastal zone requires a coastal development permit. (§ 30600.)
Although most of Banning Ranch is in unincorporated Orange County, all of it falls within the City's "sphere of influence" for zoning and planning purposes. (See Gov. Code, § 56425 et seq. ) The City's general plan sets out two alternative goals for the area. The preferred option is community open space, with development limited to nature education facilities and a park. The second alternative would allow construction of up to 1,375 residential units, 75,000 square feet of retail facilities, and 75 hotel rooms. As to both alternatives, the plan calls for consolidating the oil operations and restoring wetlands and wildlife habitats. A general plan "strategy" titled "Coordination with State and Federal Agencies" requires the City to "[w]ork with appropriate state and federal agencies to identify wetlands and habitats to be preserved and/or restored and those on which development will be permitted." (City of Newport Beach, General Plan (July 2006) ch. 3, Land Use Element, p. 3-76.)
In addition to having a general plan, every local government in the coastal zone must submit a local coastal program for Coastal Commission approval. The program consists of a coastal land use plan (CLUP) and implementing regulations. The CLUP may be completed first, with regulations developed later. (
The City did have a certified CLUP, but chose to exclude Banning Ranch from its scope. The general plan explains that "Banning Ranch is a Deferred Certification Area ... due to unresolved issues related to land
The Coastal Act specifies that "[e]nvironmentally sensitive habitat areas shall be protected against any significant disruption of habitat values, and only uses dependent on those resources shall be allowed within those areas." (§ 30240, subd. (a).) "Development in areas adjacent to environmentally sensitive habitat areas ... shall be sited and designed to prevent impacts which would significantly degrade those areas, and shall be compatible with the continuance of those habitat ... areas." (§ 30240, subd. (b).)
B. The Proposed Development and the Early Identification of ESHA
The City was unable to raise the funds to buy Banning Ranch for open space. In August 2008 Newport Banning Ranch LLC (NBR) submitted a proposal for a residential and commercial village reaching the maximum levels of development permitted by the general plan. At the City's request, the proposal included a report on "the extensive field survey work" by NBR's biological consultant "on potential special status habitats (potential ESHA)." The proposal explained that the project was designed to avoid all areas of ESHA as defined by the CLUP, with one exception. A major access road would have unavoidable impacts on 0.06 acre of potential scrub ESHA and 0.02 acre of potential riparian ESHA. These impacts would be fully mitigated. A map included in the biological report showed numerous potential ESHA throughout Banning Ranch.
The City was not satisfied with NBR's proposed road network. Banning Ranch is bordered by the Santa Ana River and other wetland areas to the west, and by 19th Street to the north. (For a map of the area, with the roadway plan ultimately approved by the City, see appen. A.) West Coast Highway, which runs along the coastline, forms the southern boundary. The eastern boundary is intersected or approached by 15th, 16th, 17th, and 18th Streets. The southeastern corner of the site is bordered by Sunset Ridge Park, a separate City project that was in progress at the time of NBR's proposal. NBR's plans called for a new "Bluff Road," running north from the highway and curving east to meet 15th Street, with another segment extending northward. The Orange County master plan of arterial highways (MPAH) envisioned Bluff Road as a six-lane divided road running north and south
The mayor and city council wanted Bluff Road to run all the way to 19th Street. NBR submitted a revised plan, saying it would accommodate the "road circulation network requested by the City of Newport Beach as a public benefit." NBR's biological consultant pointed out that the changes "would significantly impact scrub, wetlands, and riparian habitat that would be considered [ESHA] pursuant to the City's [CLUP] as well as the California Coastal Act.... It is important to note that impacts to ESHA are prohibited [by the] California Coastal Act except for certain allowable uses, and the proposed connectors would be problematic to the California Coastal Commission."
Under CEQA, the "lead agency" is "the public agency which has the principal responsibility for carrying out or approving a project." (§ 21067.) As lead agency for the NBR project, the City was responsible for preparing an EIR. (See § 21100, subd. (a).) The
The City retained its own environmental consultant. In March 2009, it gave notice that it would prepare a draft EIR for the Banning Ranch project. The notice stated that the project "includes areas that may be defined and regulated under the California Coastal Act ... as either wetlands or environmentally sensitive habitat areas (ESHAs)." The notice also explained that because the City did not have a certified local coastal program, it could not issue coastal development permits for the project. If the City approved the project plans, NBR would apply for a coastal development permit from the Coastal Commission.
A number of public comments on the notice mentioned the need to identify ESHA in the EIR. The City of Costa Mesa suggested that "[g]iven the significance of the project site, the EIR should consider the Coastal Commission thresholds for impacts to wild life and endangered species." A consultant and a board member for BRC, the group that eventually brought this lawsuit, also urged the City to use Coastal Commission standards to assess ESHA on the site. Another BRC member commented that the proposed Bluff Road extension crossed ESHA, and would not be approved by the commission.
The parties formalized a stipulation that commission staff's ESHA findings would be determinative only as to the two areas at issue, and that the commission would undertake a separate analysis of other areas in any future proceedings. The City and NBR noted their disagreement with the findings and retained the right to present evidence on whether other areas were ESHA. The commission adopted the staff findings, which included a determination that the unpermitted activity was inconsistent with policies in the City's CLUP. 4 It issued consent orders requiring the City and NBR to restore the damaged sites.
In March 2011, shortly before the consent orders were finalized, City and NBR representatives met with Coastal Commission staff to talk about Banning Ranch. Topics included attempts by commission staff to visit the project site, and the fact that there had been "no recent contacts with [commission] staff."
The reference to the City's park was to Sunset Ridge Park, the separate project bordering Banning Ranch to the southeast. The final EIR for the park project had been certified a year earlier. (See
Banning Ranch Conservancy v. City of Newport Beach
(2012)
C. The Park Road Dispute
Commission staff issued a report in October 2011 recommending that a coastal development permit be denied for Sunset Ridge Park. The report explained that the City sought access to its park through Banning Ranch under an agreement with NBR. The proposed access road crossed ESHA that were occupied by the endangered
The City and NBR would not agree to these conditions. The draft EIR for the Banning Ranch project, which had just circulated, proposed widening the road to four lanes. It would serve both the park and the NBR development, becoming a major arterial road used by thousands of vehicles a day. Commission staff observed that such a road would directly affect the ESHA already identified, and others that were likely to be determined. The staff report concluded:
"To summarize, staff has been working earnestly with the City to identify a [park] project that could be approved pursuant to modifications and special conditions to bring it into compliance with the Coastal Act. However, after further review, and after further communication with the City and with [NBR], it has become clear that they cannot address the threshold issue of foreclosing future expansion of the park access road, so that ESHA, buffers, and the California gnatcatcher that relies on them, are permanently protected.... Compromises on the widths and kinds of uses within buffers would also be required, that could only be offset by revegetating the buffers with [plants] suitable for use by gnatcatchers, and permanently preserving
In a responding letter, the City claimed it had no legal authority to revegetate the roadside areas, which would "create a new resource" instead of providing a buffer. The letter said "it continues to be the position of the City that its proposed park access road is
D. The Draft EIR and Public Comments
The City circulated a draft EIR for the Banning Ranch project in September 2011. The document explained that while the City could not issue coastal development permits, it did "review[ ] pending development projects for consistency with the General Plan, Zoning regulations, and the
Many comments on the Banning Ranch draft EIR complained about the omission of an ESHA analysis. One comment asserted that the avoidance of any ESHA determination was "egregious" because both NBR and the City
knew
there were ESHA on Banning Ranch because of the Coastal Commission consent orders. A consultant retained by BRC claimed that while the draft EIR did not include a map of probable ESHA, a computer search would
The Coastal Commission submitted 15 pages of staff comments, noting they "should not be construed as representing the opinion of the Coastal Commission itself." Staff said the City's CLUP provided "strong guidance" even though no local coastal program was in place. They suggested the EIR address whether the proposed development was consistent with policies in both the CLUP and the Coastal Act. Several comments pertained to ESHA.
Commission staff pointed out that under the Coastal Act, development must avoid impacts to ESHA. They said section 30240 does not permit "non-resource dependent impacts to an ESHA area," even if there is mitigation in other areas. "Rather, Section 30240 requires that proposed new development be located outside of ESHA areas. Additionally, Section 30240 requires siting, design, and appropriate buffers to ensure that development adjacent to ESHA does not result in" ESHA impacts. Staff recommended that the EIR use the CLUP to evaluate sensitive habitat areas and appropriate buffer zones. "[I]t is important that the EIR process incorporate a determination of probable ESHA areas and their required buffers before land use areas and development footprints are established." Staff proposed that ESHA, wetland, and buffer zone delineations be reviewed by commission biologists before the EIR was finalized.
Based on a "preliminary analysis," commission staff found that the proposed Banning Ranch development was inconsistent with the ESHA requirements of the Coastal Act, particularly the four-lane portion of Bluff Road connecting with West Coast Highway. They urged that the EIR "more fully consider alternative intensities of development on the site and alternative means to access the property," because any access road from West Coast Highway would likely
In the final EIR, the City responded to comments but did not change its position on ESHA determinations. Regarding the Coastal Commission consent orders, the City said the agreed-upon restoration plan was being implemented. It acknowledged that the commission had identified two ESHA on the project site. However, it said the commission "has not made an ESHA determination for the remainder of the ... site, and no conclusions of ESHA can and will be made by the City at this time as part of the EIR process that would in any way bind the Coastal Commission or elucidate on the Coastal Commission's ultimate conclusions [ sic ]. Rather, as appropriate under CEQA, the City has analyzed the impacts of the project, and concluded that they can be reduced to a less-than-significant level or avoided with appropriate measures. As stated in the Consent Orders, a separate analysis will be undertaken by the Coastal Commission in connection with any future Coastal Development Permit application or proceeding before the Coastal Commission involving these properties."
In a general discussion of ESHA, the City emphasized that Sunset Ridge Park and the NBR development were separate projects, and that the park was beyond the scope of the Banning Ranch EIR. Although the Coastal Commission was responsible for ESHA determinations, the City had "taken into consideration ... the policies of the Coastal Act in the Draft EIR and provide[d] a consistency analysis of the proposed Project and those policies." The City referred to a table in the draft EIR finding the project generally consistent with a list of Coastal Act provisions, but without any mention of ESHA. It recognized that "the proposed alignment of Bluff Road is within areas that were identified as ESHA by the Coastal Commission in the Consent Orders. The Coastal Commission has not reviewed the Newport Banning Ranch proposal and has not made any recommendations regarding Bluff Road at this time. The Coastal Commission has, however, reviewed the City's Sunset Ridge Park application which included a park access road in this same area and made recommendations on reconfiguring the entry road to minimize impacts to sensitive coastal resources in a manner that could be found consistent with the Coastal Act and Section 30240 in particular." The City did not mention that it had rejected those recommendations, saying only that it had later "revised its application for Sunset Ridge Park."
The City disavowed any obligation to further consider ESHA. It claimed it had "fulfilled its obligation under CEQA to analyze the significant impacts of a project on the physical environment." It maintained that ESHA findings were "within the discretion of the Coastal Commission, or a local agency as part of its [local coastal plan] certification process. While the Draft EIR must identify a project's impact on the environment, including biological resources
In response to commission staff's ESHA comments, the City stated: "The purpose of the Draft EIR is to analyze a proposed project's impact on the physical environment. It is not, in and of itself, a policy consistency analysis, except to the extent that such inconsistencies reveal environmental impacts that otherwise are not discussed.... [T]he Draft EIR analyzes the proposed Project's impact on biological resources, including federal and State listed endangered and threatened species, sensitive plant and animal species, and specific habitats such as wetlands and vernal pools. All impacts to these resources would be mitigated or avoided with the Mitigation Program.... The Draft EIR acknowledges that the Coastal Commission makes the determination as to whether any or all of these constitute ESHA under the Coastal Act, and application of the policies of the Coastal Act to the existing conditions on the Project site would be undertaken as part of the Coastal Commission's Coastal Development Permit process." The City did not directly respond to staff's concern about the identification of potential ESHA "before land use areas and development footprints are established." It did not respond at all to the suggestion that ESHA and buffer zone delineations be reviewed by commission staff before the EIR was finalized.
The City's response concluded: "Bluff Road through the property is reflected in the City's General Plan Circulation Element Master Plan of Streets and Highways and the Orange County MPAH. The City cannot eliminate this planned circulation improvement without amending its Circulation Element, and cannot unilaterally
F. Project Approval and the Litigation Below
The City certified the final EIR in July 2012. It also approved NBR's master development plan, a development agreement, and zoning changes for Banning Ranch. BRC challenged the project approval by seeking a writ of mandate. It contended the EIR did not adequately disclose or analyze environmental impacts and mitigation measures with respect to ESHA, instead deferring these critical functions. BRC also alleged that the City had violated its obligation under the general plan to work with the Coastal Commission
The City responded that CEQA does not require an EIR to include ESHA determinations. It defended its exercise of discretion under the general plan. The trial court rejected the CEQA claims, relying on
Banning Ranch I
,
supra
,
II. DISCUSSION
A. Sufficiency of the EIR
"[A]n agency may abuse its discretion under CEQA either by failing to proceed in the manner CEQA provides or by reaching factual conclusions unsupported by substantial evidence. (§ 21168.5.) Judicial review of these two types of error differs significantly: While we determine de novo whether the agency has employed the correct procedures, 'scrupulously enforc[ing] all legislatively mandated CEQA requirements' (
Citizens of Goleta Valley v. Board of Supervisors
(1990)
Whether an EIR has omitted essential information is a procedural question subject to de novo review. (
Vineyard
,
supra
,
The City argues that CEQA imposes no duty to consider the Coastal Act's ESHA
An EIR project description must include "[a] list of related environmental review and consultation requirements [found in] federal, state, or local laws, regulations, or policies. To the fullest extent possible, the lead agency should integrate CEQA review with these related environmental review and consultation requirements ." (Guidelines, § 15124, subd. (d)(1)(C), italics added; see also Guidelines, § 15006, subd. (i).) Toward that end, agencies are encouraged to "[c]onsult[ ] with state and local responsible agencies before and during preparation of an environmental impact report so that the document will meet the needs of all the agencies which will use it." (Guidelines, § 15006, subd. (g).) Here, the City ignored its obligation to integrate CEQA review with the requirements of the Coastal Act, and gave little consideration to the Coastal Commission's needs.
The Guidelines specifically call for consideration of related regulatory regimes, like the Coastal Act, when discussing project alternatives. An EIR must "describe a range of reasonable alternatives to the project," or to its location, that would "feasibly attain" most of its basic objectives
Evaluation of project alternatives and mitigation measures is "[t]he core of an EIR." (
Citizens of Goleta Valley v. Board of Supervisors
,
supra
,
Decisions as to the feasibility of alternatives and mitigation measures are subject to a rule of reason. (
Goleta Valley
,
supra
,
The City claims that identification of potential ESHA would be merely speculative. The argument fails for several reasons. First, no speculation was involved with respect to the two ESHA covered by the consent orders.
9
These areas were in the path of the Bluff Road access from West Coast Highway, yet the City approved the road without considering ESHA requirements. Further, the City knew that NBR's own biological consultant had identified numerous potential ESHA in other areas. The City's CLUP provided guidelines for identifying ESHA. The City was offered the assistance of Coastal Commission staff. It had ample bases for an informed discussion of the NBR project's potential ESHA impacts. "The fact that precision may not be possible ... does not mean that no analysis is required. 'Drafting an EIR ... involves some degree of forecasting. While foreseeing the unforeseeable is not possible, an agency must use its best efforts to find out and disclose all that it reasonably can.' (Guidelines, § 15144.)" (
It also appears that the City has evaluated ESHA impacts as a matter of course for other projects. The EIR explained that even
The City insists that ESHA would be fully considered during the permitting phase of the project. Such a delay is inconsistent with CEQA's policy of integrated review. (§ 21003, subd. (a).) As noted, a lead agency must consider related regulations and matters of regional significance when weighing project alternatives. (Guidelines, § 15126.6.) The City's argument is also undermined by
Citizens for Quality Growth v. City of Mt. Shasta
(1988)
The City's position finds no support in
Banning Ranch I
,
supra
,
Hanging over the City's briefing, and much of the Court of Appeal opinion, is the supposition that if the City were required to identify potential ESHA in the EIR, it would have to accept the ESHA designations and related measures proposed by commission staff. That is not the case. An EIR is an informational document, not a settlement agreement or a memorandum of understanding. The lead agency may disagree with the opinions of other agencies. (See
North Coast Rivers Alliance v. Marin Municipal Water Dist. Bd. of Directors
(2013)
The City correctly points out that the ultimate findings regarding ESHA on Banning Ranch will be made by the California Coastal Commissioners themselves, not commission staff. But both the commissioners and interested members of the public are entitled to understand the disagreements between commission staff and the City on the subject of ESHA. The requirement that the City spell out its differences with commission staff " 'helps [e]nsure the integrity of the process of decision by precluding stubborn problems or serious criticism from being swept under the rug.... [W]here comments from responsible experts or sister agencies disclose new or conflicting data or opinions that cause concern that the agency may not have fully evaluated the project and its alternatives, these comments may not simply be ignored.
There must be good faith, reasoned analysis in response
.' " (
People v. County of Kern
(1974)
Some information on ESHA and the disputes between the City and commission staff can be gleaned from a diligent search of the EIR appendices and other elements of the administrative record. However, such a fragmented presentation is inadequate. Readers of an EIR should not be required to "ferret out an unreferenced discussion in [related material].... The data in an EIR must not only be sufficient in quantity, it must be presented in a manner calculated to adequately inform the public and decision makers, who may not be previously familiar with the details of the project. '[I]nformation "scattered here and there in EIR appendices," or a report "buried in an appendix," is not a substitute for "a good faith reasoned analysis...." ' " (
Vineyard
,
supra
,
For all the reasons stated above, the Banning Ranch EIR is insufficient. The City did provide a detailed biological analysis of project impacts, which may have been adequate were Banning Ranch not in the coastal zone. But, however technically accurate the City's analysis might otherwise be, it fell short by failing to account for the Coastal Act's ESHA protections. "The preparation and circulation of an EIR is more than a set of technical hurdles for agencies and developers to overcome. The EIR's function is to ensure
We note that the City's handling of the Banning Ranch EIR not only conflicted with its CEQA obligations, but also ignored the practical reality
B. Reversal Is Required
By certifying an inadequate EIR, the City abused its discretion. "[F]ailure to disclose information called for by CEQA may be prejudicial 'regardless of whether a different outcome would have resulted if the public agency had complied' with the law (§ 21005, subd. (a))." (
Neighbors for Smart Rail v. Exposition Metro Line Construction Authority
(2013)
Accordingly, reversal is not called for whenever an agency may have failed to integrate its CEQA review with other environmental review procedures "to the maximum feasible extent." (§ 21003, subd. (a).) 10 To be prejudicial, a failure to account for related regulations must substantially impair the EIR's informational function. Here, the City's failure to discuss ESHA requirements and impacts was neither insubstantial nor merely technical. The omission resulted in inadequate evaluation of project alternatives and mitigation measures. Information highly relevant to the Coastal Commission's permitting function was suppressed. The public was deprived of a full understanding of the environmental issues raised by the Banning Ranch project proposal.
BRC is entitled to relief on its CEQA claim. We express no view on the general plan issues discussed by the courts below.
We reverse the Court of Appeal's judgment and remand for further proceedings consistent with the views expressed herein.
We Concur:
Cantil-Sakauye, C.J.
Werdegar, J.
Chin, J.
Liu, J.
Cuéllar, J.
Kruger, J.
Notes
Public Resources Code, section 21000 et seq. Unless otherwise noted, further statutory references are to the Public Resources Code.
Subsequent references to "Guidelines" are to the CEQA guidelines found in title 14 of the California Code of Regulations, section 15000 et seq.
The ecologist prepared a memorandum describing the December 2010 site visit. She noted that the parties had discussed "our approach to making an ESHA determination." The memorandum refers to the map of potential ESHA on Banning Ranch that was part of the biological report accompanying NBR's original project proposal. It observes that the biological report "was posted on the City of Newport Beach website and downloaded in August 2009; it has since been removed.... Given that the vegetation ... and ESHA ... exhibits portray the expert opinion of [NBR's consultant] at the time they were developed, we believe it is appropriate to consider this information, along with other sources, in our ESHA determination. We note that these data support our ESHA conclusions...."
Staff noted that until the City obtained certification of its local coastal program, Coastal Act standards governed permitting and enforcement. However, "because the City's CLUP has been certified and Banning Ranch is within the City's sphere of influence, it serves as a valuable guidance document in such matters." The report quotes at length from the CLUP's provisions regarding ESHA.
An e-mail from the City's planning manager to its environmental consultant, shortly before the final EIR was released, also indicates the City's expectation that NBR would shoulder the responsibility for meeting Coastal Commission requirements. When asked how much time and effort the consultant should spend preparing a response to anticipated commission staff comments on archaeological resources, the planning manager wrote: "Very little. After the EIR's certified, the work is done. It will be [NBR's] responsibility to get it through [the Coastal Commission]."
In general, an EIR must take "the regional setting" of a project into account, placing "[s]pecial emphasis ... on environmental resources that are rare or unique to that region and would be affected...." (Guidelines, § 15125, subd. (c).) "[T]he significant effects of the project [must] be considered in the full environmental context." ( Ibid .)
We express no view as to whether ESHA impacts must be avoided, as opposed to mitigated. (See
Bolsa Chica Land Trust v. Superior Court
(1999)
BRC contends the City
did
have legal authority to designate ESHA, relying on
Douda v. California Coastal Com.
(2008)
The
Douda
court, in the course of summarizing the terms of section 30600, which are less than crystalline, suggested that a local agency might be authorized to issue permits without either certifying a local coastal program or following section 30600, subdivision (b)(1). (
Douda v. California Coastal Com.
,
supra
,
BRC asserts the City had earlier determined that all of Banning Ranch was ESHA. The claim is misleading. As the City explains, a study referenced in a 2003 planning document had generally identified Banning Ranch as "ESHA." After Coastal Commission staff cautioned the City about the consequences of designating ESHA under the Coastal Act, the City changed its usage to refer to Banning Ranch as an "environmental study area."
We note that whether such a criticism may fairly be leveled in the first place is a question calling for application of a rule of reason, similar to the rule governing review of an EIR's analysis of "feasible" project alternatives. (See
Goleta Valley
,
supra
,
