SALAZAR, SECRETARY OF THE INTERIOR, ET AL. v. RAMAH NAVAJO CHAPTER ET AL.
No. 11-551
Supreme Court of the United States
Argued April 18, 2012—Decided June 18, 2012
567 U.S. 182
No. 11-551. Argued April 18, 2012—Decided June 18, 2012
Mark R. Freeman argued the cause for petitioners. With him on the briefs were Solicitor General Verrilli, Assistant Attorney General West, Deputy Solicitor General Kneedler, Barbara C. Biddle, John S. Koppel, Patrice H. Kunesh,
Carter G. Phillips argued the cause for respondents. With him on the brief were Michael P. Gross, Jonathan F. Cohn, Matthew D. Krueger, C. Bryant Rogers, Lloyd B. Miller, Donald J. Simon, and Daniel H. MacMeekin.*
JUSTICE SOTOMAYOR delivered the opinion of the Court.
The Indian Self-Determination and Education Assistance Act (ISDA or Act),
I
A
Congress enacted ISDA in 1975 in order to achieve “maximum Indian participation in the direction of educational as well as other Federal services to Indian communities so as
As originally enacted, ISDA required the Government to provide contracting tribes with an amount of funds equivalent to those that the Secretary “would have otherwise provided for his direct operation of the programs.”
Congress included a model contract in ISDA and directed that each tribal self-determination contract “shall . . . contain, or incorporate [it] by reference.”
B
During Fiscal Years (FYs) 1994 to 2001, respondent Tribes contracted with the Secretary of the Interior to provide services such as law enforcement, environmental protection, and agricultural assistance. The Tribes fully performed. During each FY, Congress appropriated a total amount to the Bureau of Indian Affairs (BIA) “for the operation of Indian programs.” See, e. g., Department of the Interior and Related Agencies Appropriations Act, 2000,
During each relevant FY, Congress appropriated sufficient funds to pay in full any individual tribal contractor‘s contract support costs. Congress did not, however, appropriate sufficient funds to cover the contract support costs due all tribal contractors collectively. Between FYs 1994 and 2001, appropriations covered only between 77% and 92% of tribes’
Respondent Tribes sued for breach of contract pursuant to the Contract Disputes Act,
II
A
In evaluating the Government‘s obligation to pay tribes for contract support costs, we do not write on a clean slate. Only seven years ago, in Cherokee Nation, we also considered the Government‘s promise to pay contract support costs in ISDA self-determination contracts that made the Government‘s obligation “subject to the availability of appropriations.” 543 U. S., at 634-637. For each FY at issue, Congress had appropriated to the Indian Health Service (IHS) a lump sum between $1.277 and $1.419 billion, “far more than the [contract support cost] amounts” due under the Tribes’ individual contracts. Id., at 637; see id., at 636 (Cherokee Nation and Shoshone-Paiute Tribes filed claims seeking $3.4 and $3.5 million, respectively). The Government contended, however, that Congress had appropriated inadequate funds to enable the IHS to pay the Tribes’ contract support costs in full, while meeting all of the agency‘s competing fiscal priorities.
As we explained, that did not excuse the Government‘s responsibility to pay the Tribes. We stressed that the Government‘s obligation to pay contract support costs should be treated as an ordinary contract promise, noting that ISDA “uses the word ‘contract’ 426 times to describe the nature of the Government‘s promise.” Id., at 639. As even the Government conceded, “‘in the case of ordinary contracts . . . if the amount of an unrestricted appropriation is sufficient to fund the contract, the contractor is entitled to payment even if the agency has allocated the funds to another purpose or assumes other obligations that exhaust the funds.‘” Id., at 641. It followed, therefore, that absent “something special about the promises here at issue,” the Government was obligated to pay the Tribes’ contract support costs in full. Id., at 638.
Our conclusion in Cherokee Nation followed directly from well-established principles of Government contracting law. When a Government contractor is one of several persons to be paid out of a larger appropriation sufficient in itself to pay the contractor, it has long been the rule that the Government is responsible to the contractor for the full amount due under the contract, even if the agency exhausts the appropriation in service of other permissible ends. See Ferris v. United States, 27 Ct. Cl. 542, 546 (1892); Dougherty v. United States, 18 Ct. Cl. 496, 503 (1883); see also 2 GAO, Principles of Federal Appropriations Law, p. 6-17 (2d ed. 1992) (hereinafter GAO Redbook).3 That is so “even if an agency‘s total lump-
This principle safeguards both the expectations of Government contractors and the long-term fiscal interests of the United States. For contractors, the Ferris rule reflects that when “a contract is but one activity under a larger appropriation, it is not reasonable to expect the contractor to know how much of that appropriation remains available for it at any given time.” GAO Redbook, p. 6-18. Contractors are responsible for knowing the size of the pie, not how the agency elects to slice it. Thus, so long as Congress appropriates adequate funds to cover a prospective contract, contractors need not keep track of agencies’ shifting priorities and competing obligations; rather, they may trust that the Government will honor its contractual promises. Dougherty, 18 Ct. Cl., at 503. In such cases, if an agency overcommits its funds such that it cannot fulfill its contractual commitments, even the Government has acknowledged that “[t]he risk of over-obligation may be found to fall on the agency,” not the contractor. Brief for Federal Parties in Cherokee Nation v. Leavitt, O. T. 2004, No. 02-1472 etc., p. 24 (hereinafter Brief for Federal Parties).
The rule likewise furthers “the Government‘s own long-run interest as a reliable contracting partner in the myriad workaday transaction of its agencies.” United States v. Winstar Corp., 518 U. S. 839, 883 (1996) (plurality opinion). If the Government could be trusted to fulfill its promise to
B
The principles underlying Cherokee Nation and Ferris dictate the result in this case. Once “Congress has appropriated sufficient legally unrestricted funds to pay the contracts at issue, the Government normally cannot back out of a promise to pay on grounds of ‘insufficient appropriations,’ even if the contract uses language such as ‘subject to the availability of appropriations,’ and even if an agency‘s total lump-sum appropriation is insufficient to pay all the contracts the agency has made.” Cherokee Nation, 543 U. S., at 637; see also id., at 638 (“[T]he Government denies none of this“).
That condition is satisfied here. In each FY between 1994 and 2001, Congress appropriated to the BIA a lump sum from which “not to exceed” between $91 and $125 million was allocated for contract support costs, an amount that exceeded the sum due any tribal contractor. Within those constraints, the ability to direct those funds was “‘committed to agency discretion by law.‘” Lincoln v. Vigil, 508 U. S. 182, 193 (1993) (quoting
The Government‘s contractual promise to pay each tribal contractor the “full amount of funds to which the contractor [was] entitled,”
As in Cherokee Nation, we decline the Government‘s invitation to ascribe “special, rather than ordinary,” meaning to the fact that ISDA makes contracts “subject to the availability of appropriations.”5 543 U. S., at 644. Under our previ-
III
A
The Government primarily seeks to distinguish this case from Cherokee Nation and Ferris on the ground that Congress here appropriated “not to exceed” a given amount for contract support costs, thereby imposing an express cap on the total funds available. See Brief for Petitioners 26, 49. The Government argues, on this basis, that Ferris and Cherokee Nation involved “contracts made against the backdrop of unrestricted, lump-sum appropriations,” while this case does not. See Brief for Petitioners 49, 26.
That premise, however, is inaccurate. In Ferris, Congress appropriated “[f]or improving Delaware River below Bridesburg, Pennsylvania, forty-five thousand dollars.”
This result does not leave the “not to exceed” language in Congress’ appropriation without legal effect. To the contrary, it prevents the Secretary from reprogramming other funds to pay contract support costs—thereby protecting funds that Congress envisioned for other BIA programs, including tribes that choose not to enter ISDA contracts. But when an agency makes competing contractual commitments with legally available funds and then fails to pay, it is the Government that must bear the fiscal consequences, not the contractor.
B
The dissent attempts to distinguish this case from Cherokee Nation and Ferris on different grounds, relying on
That interpretation, which is inconsistent with ordinary principles of Government contracting law, is improbable. We have explained that Congress ordinarily controls the
The better reading of
At minimum, the fact that we, the court below, the Government, and the Tribes do not share the dissent‘s reading of
C
The remaining counterarguments are unpersuasive. First, the Government suggests that today‘s holding could cause the Secretary to violate the Anti-Deficiency Act, which prevents federal officers from “mak[ing] or authoriz[ing] an expenditure or obligation exceeding an amount available in an appropriation.”
Third, the Government invokes cases in which courts have rejected contractors’ attempts to recover for amounts beyond the maximum appropriated by Congress for a particular purpose. See, e. g., Sutton v. United States, 256 U. S. 575 (1921). In Sutton, for instance, Congress made a specific line-item appropriation of $23,000 for the completion of a par-
The Ferris and Sutton lines of cases are distinguishable, however. GAO Redbook, p. 6-18. “[I]t is settled that contractors paid from a general appropriation are not barred from recovering for breach of contract even though the appropriation is exhausted,” but that “under a specific line-item appropriation, the answer is different.” Ibid.10 The different results “follo[w] logically from the old maxim that ignorance of the law is no excuse.” Ibid. “If Congress appropriates a specific dollar amount for a particular contract, that amount is specified in the appropriation act and the contractor is deemed to know it.” Ibid. This case is far different. Hundreds of tribes entered into thousands of independent contracts, each for amounts well within the lump sum appropriated by Congress to pay contract support costs. Here, where each Tribe‘s “contract is but one activity under a larger appropriation, it is not reasonable to expect [each] contractor to know how much of that appropriation remain[ed] available for it at any given time.” Ibid.; see also Ferris, 27 Ct. Cl., at 546.
Finally, the Government argues that legislative history suggests that Congress approved of the distribution of available funds on a uniform, pro rata basis. But “a fundamental principle of appropriations law is that where Congress merely appropriates lump-sum amounts without statutorily restricting what can be done with those funds, a clear infer-
IV
As the Government points out, the state of affairs resulting in this case is the product of two congressional decisions which the BIA has found difficult to reconcile. On the one hand, Congress obligated the Secretary to accept every qualifying ISDA contract, which includes a promise of “full” funding for all contract support costs. On the other, Congress appropriated insufficient funds to pay in full each tribal contractor. The Government‘s frustration is understandable, but the dilemma‘s resolution is the responsibility of Congress.
Congress is not short of options. For instance, it could reduce the Government‘s financial obligation by amending ISDA to remove the statutory mandate compelling the BIA to enter into self-determination contracts, or by giving the BIA flexibility to pay less than the full amount of contract support costs. It could also pass a moratorium on the formation of new self-determination contracts, as it has done
The desirability of these options is not for us to say. We make clear only that Congress has ample means at hand to resolve the situation underlying the Tribes’ suit. Any one of the options above could also promote transparency about the Government‘s fiscal obligations with respect to ISDA‘s directive that contract support costs be paid in full. For the period in question, however, it is the Government—not the Tribes—that must bear the consequences of Congress’ decision to mandate that the Government enter into binding contracts for which its appropriation was sufficient to pay any individual tribal contractor, but “insufficient to pay all the contracts the agency has made.” Cherokee Nation, 543 U. S., at 637.
The judgment of the Court of Appeals is affirmed.
It is so ordered.
CHIEF JUSTICE ROBERTS, with whom JUSTICE GINSBURG, JUSTICE BREYER, and JUSTICE ALITO join, dissenting.
Today the Court concludes that the Federal Government must pay the full amount of contract support costs incurred by the respondent Tribes, regardless of whether there are any appropriated funds left for that purpose. This despite the facts that payment of such costs is “subject to the availability of appropriations,” a condition expressly set forth
The Indian Self-Determination and Education Assistance Act provides: “Notwithstanding any other provision in [the Act], the provision of funds under [this Act] is subject to the availability of appropriations . . . .” Ibid. This condition is repeated in the Tribes’ contracts with the Government. App. 206; see also
Congress restricted the amount of funds “available” to pay the Tribes’ contract support costs in two ways. First, in each annual appropriations statute for the Department of the Interior from fiscal years 1994 to 2001, Congress provided that spending on contract support costs for all tribes was “not to exceed” a certain amount. The fiscal year 1995 appropriations statute is representative. It provided: “For operation of Indian programs . . . $1,526,778,000, . . . of which not to exceed $95,823,000 shall be for payments to tribes and tribal organizations for contract support costs . . . .”
Second, in
Given these express restrictions established by Congress—which no one doubts are valid—I cannot agree with the Court‘s conclusion that appropriations were “available” to pay the Tribes’ contract support costs in full. Once the Secretary had allocated all the funds appropriated for contract support costs, no other funds could be used for that purpose without violating the “not to exceed” restrictions in the relevant appropriations statutes. The Court agrees. Ante, at 194-195. That leaves only one other possible source of funds to pay the disputed costs in this case: funds appropriated for contract support costs, but allocated to pay
In reaching a contrary conclusion, the Court fails to appreciate the full significance of the “reduction” clause in
The Court rejects this reading of the “reduction” clause, on the ground that it would constitute a “radical departure from ordinary Government contracting principles.” Ante, at 196, n. 6. But the fact that the clause operates as a constraint on the “availability of appropriations” is evident not only from its text, which speaks in terms of “funds available,” but also from its placement in the statute, immediately following the “subject to the availability” clause. Under the Court‘s view, by contrast, the “reduction” clause merely “underscores the Secretary‘s discretion to allocate funds among tribes.” Ante, at 196. There is, however, no reason to suppose that Congress enacted the provision simply to confirm this “ordinary” rule. Ibid. We generally try to avoid reading statutes to be so “insignificant.” TRW Inc. v. Andrews, 534 U. S. 19, 31 (2001) (internal quotation marks omitted).
The Court maintains that its holding is compelled by our decision in Cherokee Nation of Okla. v. Leavitt, 543 U. S. 631
We ruled against the Government, but not because of any disagreement with its reading of the “reduction” clause. The basis for our decision was instead that “the relevant congressional appropriations contained other unrestricted funds, small in amount but sufficient to pay the claims at issue.” 543 U. S., at 641 (emphasis altered). Those funds were allocated for “‘inherent federal functions,’ such as the cost of running the Indian Health Service‘s central Washington office.” Id., at 641-642. They were not restricted by the “reduction” clause, because they were not funds for “‘programs, projects, or activities serving . . . another tribe.‘” Id., at 641 (quoting
As even the Tribes concede, Cherokee Nation does not control this case. Tr. of Oral Arg. 39 (counsel for the Tribes)
The Court also relies on Ferris v. United States, 27 Ct. Cl. 542 (1892). That case involved a Government contract to dredge the Delaware River. When work under the contract stopped because funds from the relevant appropriation had been exhausted, a contractor sued the Government for breach of contract, and the Court of Claims held that he was entitled to recover lost profits. As the court explained, “[a] contractor who is one of several persons to be paid out of an appropriation is not chargeable with knowledge of its
It is true, as the Court notes, ante, at 194, that each of the Tribes’ contracts provides that the Act and the contract “shall be liberally construed for the benefit of the Contractor.” App. 203; see also
This is hardly a typical government contracts case. Many government contracts contain a “subject to the availability of appropriations” clause, and many appropriations statutes contain “not to exceed” language. But this case involves not only those provisions but a third, relieving the Secretary of any obligation to make funds “available” to one contractor by reducing payments to others. Such provisions will not
