RICHLAND/WILKIN JOINT POWERS AUTHORITY, a Minnesota-North Dakota Joint Powers Authority v. UNITED STATES ARMY CORPS OF ENGINEERS; John McHugh, Secretary of the US Army Corps of Engineers (in his official capacity); Jo-Ellen Darcy, Assistant Secretary of the Army for Civil Works (in her official capacity); Col. Dan Koprowski, District Commander, St. Paul District, US Army Corps of Engineers (in his official capacity)
No. 15-2123
United States Court of Appeals, Eighth Circuit.
Submitted: February 11, 2016. Filed: June 20, 2016.
826 F.3d 1030
Fargo-Moorhead Flood Diversion Board of Authority, Intervenor Defendant-Appellant
State of North Dakota, Amicus on Behalf of Appellant
Minnesota Department of Natural Resources, Amicus on Behalf of Appellee
Counsel who presented argument on behalf of the appellee was Gerald Walter Von Korff, of Saint Cloud, MN. In addition to Mr. Von Korff, the following attorney(s) appeared on the appellee brief; Jonathan D. Wolf, of Saint Cloud, MN.
The following attorney(s) appeared on the amicus brief of State of North Dakota in support of appellant; Matthew A Sagsveen, AAG, of Bismarck, ND.
The following attorney(s) appeared on the amicus brief of MN Department of Natural Resources in support of appellee; Jill Schlick Nguyen, AAG of St. Paul, MN.
Before SHEPHERD, BEAM, and KELLY, Circuit Judges.
SHEPHERD, Circuit Judge.
The local sponsor, the Fargo-Moorhead Diversion Board of Authority (“Authority“), in the development of a diversion project on the Red River with the United States Army Corps of Engineers (“Corps“) alleges that the district court made numerous errors in granting a preliminary injunction to the Joint Powers Authority of Richland County, North Dakota, and Wilkin County, Minnesota (“JPA“), prohibiting the Authority‘s continued construction of a ring levee around the communities of Oxbow, Hickson, and Bakke, North Dakota
I.
The north-flowing Red River runs between Minnesota and North Dakota. In the spring, snow melt contributes to the river‘s volume and routinely causes the river‘s waters to migrate suddenly and unpredictably in all directions, sometimes causing flooding as far as three miles from the river‘s banks throughout its flat natural flood plain, extending from Oxbow to Fargo, North Dakota. Efforts to prevent flooding on one side of the river can redirect water to the other side and cause flooding.
After the 2009 flood, several entities proposed various permanent measures to reduce the flood risk to the Fargo-Moorhead metropolitan area. The alternatives were analyzed and two were carried forward, each involving a “control structure,” or high-hazard dam. A draft Environmental Impact Statement (“EIS“) was completed, proposing three possible plans. One plan, the Locally Preferred Plan (“LPP“), would divert 35,000 cubic feet of water per second on the North Dakota side. Pursuant to the joint request of Fargo, Moorhead, as well as Clay and Cass counties, the Assistant Secretary of the Army for Civil Works approved designation of the LPP as the tentatively selected plan.
Further modeling indicated that the LPP would have a more extensive downstream impact than had been anticipated. A supplemental EIS was released, tentatively recommending several changes, including reducing the diversion channel‘s capacity, adding storage and staging areas, and then compensating most affected landowners within the storage and staging areas. A Final Feasibility Report and EIS was released in July 2011, and the project was recommended for authorization. Subsequent design and engineering studies led to additional modification proposals, including the OHB ring levee, which would protect the OHB communities, all now within the flood-water staging area, from flooding caused by the larger diversion project. An additional supplemental environmental assessment evaluated different versions of this modification.
The Minnesota Department of Natural Resources (“MDNR“) determined that because the larger diversion project included a high-hazard dam, it required the MDNR, as the responsible government unit, to complete a full EIS. In May 2013, Minnesota environmental review commenced. In January 2014, the MDNR decided that the OHB ring levee was a step to advance the environmentally controversial part of the larger project still under review, so any construction on the OHB ring levee before the completion of MDNR‘s EIS would violate the Minnesota Environmental Procedure Act (“MEPA“). In reaching this conclusion, the MDNR considered the fact that the levee was designed to reach heights nine feet above the FEMA 100-year flood event level and the communities’ existing flood protection, which had been reexamined and modified in response to the 2009 flood. In August 2014, Minnesota Governor Mark Dayton wrote to the Assistant Secretary of the Army for Civil Works to express strong concern over the diversion project, including construction of the OHB ring levee. In the letter, Governor Dayton stated that “construction of the [OHB] Ring Levee, prior to the completion
Minnesota environmental review process is still ongoing. At the time of the district court‘s opinion, the MDNR expected to release its own State EIS in August 2015.
In 2014, Congress enacted the
In November 2014, the JPA filed its third amended complaint, listing the Authority as defendant-intervenor. In the complaint, the JPA alleged that the ongoing construction of the OHB ring levee violated
II.
“A district court has broad discretion when ruling on a request for preliminary injunction, and it will be reversed only for clearly erroneous factual determinations, an error of law, or an abuse of its discretion.” Novus Franchising, Inc. v. Dawson, 725 F.3d 885, 893 (8th Cir. 2013) (internal citation omitted). “We will not disturb a district court‘s discretionary decision if such decision remains within the range of choice available to the district court, accounts for all relevant factors, does not rely on any irrelevant factors, and does not constitute a clear error of judgment.” PCTV Gold, Inc. v. SpeedNet, LLC, 508 F.3d 1137, 1142 (8th Cir. 2007). “Abuse of discretion occurs if the district
A district court‘s decision to issue a preliminary injunction “depends upon a ‘flexible’ consideration of (1) the threat of irreparable harm to the moving party; (2) balancing this harm with any injury an injunction would inflict on other interested parties; (3) the probability that the moving party would succeed on the merits; and (4) the effect on the public interest.” Planned Parenthood Minn., N.D., S.D. v. Rounds, 530 F.3d 724, 729 n. 3 (8th Cir. 2008) (en banc) (citing Dataphase Systems, Inc. v. C L Systems, Inc., 640 F.2d 109, 113 (8th Cir. 1981) (en banc)). The Authority argues that the district court erred in its determination regarding each of the first three factors. Regarding harm, the Authority argues that the district court erred in determining that the continued construction of the OHB ring levee, prior to the MDNR‘s completion of an EIS, constituted a sufficient threat of irreparable harm, in part, because procedural harm alone cannot constitute irreparable harm. Next, the Authority argues that the court erred in balancing the harm that the Authority would face from potentially missing an additional construction season against the potential impact of continuing construction.
The Authority challenges the district court‘s determination regarding the probability that JPA will succeed on the merits as well. First, the Authority alleges that the district court applied the wrong threshold standard for likelihood of success. Second, the Authority argues that the district court erred in determining the likelihood that JPA‘s
III.
A. Findings of Fact
As an initial matter, the district court‘s finding of fact that the OHB project is a part of the larger diversion project is not clearly erroneous and broadly supports the district court‘s decision to grant the injunction. The district court determined that “[w]hile the OHB ring levee is being constructed in North Dakota, and while many other aspects of the diversion project will be built in North Dakota, they are all integral parts of a larger project that indisputably will be constructed, in part, in Minnesota.” The district court found that “arguments to the contrary—that the OHB ring levee is of independent value, for example—ignore[] the project‘s practical reality.” The district court based this on its finding that the OHB communities
There is evidence supporting the district court‘s determination. The Corps’ supplemental environmental assessment labels the OHB levee as a component of the overall diversion project and states that OHB levee serves the purpose of mitigating the effects of the to-be-constructed high-hazard dam. (Decl. of Coleman, Jan. 23, 2015, para 6). Indeed, the OHB levee was originally designed to protect against the depth of flooding that the diversion project would create, and even as modified, maintains a base width which permits for an increase in height that would provide that same protection. The district court‘s determination regarding the levee‘s purpose is further supported by evidence stating that the Oxbow community already has flood protection in place designed to protect that community. (Decl. of Miller, Berg, Hovland, Feb. 13, 2015, para 7). The Authority has not provided sufficient evidence that the OHB levee would have been funded irrespective of its ties to the larger diversion project to cause the district court‘s conclusion—that the OHB ring levee is a part of the larger project—to be clearly erroneous.
B. Threat of Irreparable Harm
For an injunction to be appropriate, “a party must show that the harm is certain and great and of such imminence that there is a clear and present need for equitable relief.” Roudachevski v. All-Am. Care Ctrs., Inc., 648 F.3d 701, 706 (8th Cir. 2011) (quoting Iowa Utilities Bd. v. Fed. Commc‘ns Comm‘n, 109 F.3d 418, 425 (8th Cir. 1996)). However, “the alleged harm need not be occurring or be certain to occur before a court may grant relief.” Michigan v. U.S. Army Corps of Eng‘rs, 667 F.3d 765, 788 (7th Cir. 2011) (citing United States v. W.T. Grant Co., 345 U.S. 629, 633 (1953)). Failure to comply with the process required by a national analogous statute, the
The plaintiff must additionally show irreparable harm to themselves, which can be accomplished through demonstrating “injury to their specific environmental interests,” created by the actions taken with “inadequate foresight and deliberation.” See id. This may be established by showing that not only will the environment suffer harm, but that the party in question uses the area which will suffer
The district court found adequate procedural harm and harm to the JPA‘s specific environmental interests sufficient to support a preliminary injunction. The procedural harm identified by the court was the Authority‘s continued work on “an integral part of the diversion project prior to the completion of the MDNR‘s environmental review.” This construction, prior to completing the review, could be presumed to risk real environmental harm. See Sierra Club, 645 F.3d at 995. To connect this harm to JPA‘s specific environmental interests, the court looked to declarations provided, specifically noting a declaration from Pleasant Township, a member of the JPA, stating that Pleasant Township faces significant flooding from the diversion project. (Decl. of Nipstad, Pleasant Township Clerk, Feb. 11, 2015). The district court recognized that any flooding that would occur “is likely years down the road[,]” but determined that “construction here is critically tied to that eventual harm, because the OHB levee is tied to one specific configuration of the diversion project that, if completed, will have a certain and significant impact on citizens in Pleasant Township and elsewhere.” Based on this certain impact, the court noted that there “will no doubt [be] immediate consequences in terms of property value, at minimum,” before reaffirming that the JPA had shown the procedural injury and sufficient threat of harm to specific environmental interests necessary to meet the standard set forth in Sierra Club. See Sierra Club, 645 F.3d at 995-96.
The Authority asks us to find that the district court erred. First, the Authority argues that only procedural harm has been established and procedural harm is not enough to create irreparable harm. Second, it argues that any impact on Pleasant Township or the JPA will not occur for at least seven years, and would occur as a result of the larger project, not the OHB ring levee. The Authority further argues that these potential future consequences are not certain, as they would result from only one formation of the project. The Authority points out that Sierra Club differs from the case at hand, in that the actual construction process in Sierra Club harmed the parties’ specific environmental interests by preventing Plaintiffs from using and enjoying the area through noise and pollution, while here, the construction process itself will not cause the flooding. This added a level of immediacy and certainty to the harm alleged in Sierra Club, which the Authority asserts is not present in this case. The Authority then points to James River Flood Control Ass‘n v. Watt, for the proposition that harm from flooding, years in the future, cannot support a preliminary injunction. 680 F.2d 543, 544-45 (8th Cir. 1982) (per curiam) (granting a stay for a preliminary injunction halting progress on a project, pending proceedings regarding the adequacy of the EIS).
C. Balance of Harms
Once the court has determined that there is a threat of irreparable harm to the moving party, it must balance this harm with any injury an injunction would inflict on other interested parties. Rounds, 530 F.3d at 729 n.3. The Authority argues that the district court erred in determining that the balance of harms favored granting the preliminary injunction. The district court acknowledged that the delay “may result in higher construction costs, continued risk of flooding for the OHB communities, and uncertainty for homeowners within the ring levee that are attempting to sell their homes,” but found these concerns were outweighed by the risk of irreparable harm to JPA. The district court based this determination, first, on its finding that the injunction would likely be short in duration because Minnesota‘s environmental review was likely to be completed soon.3 Second, the district court explained that the OHB community had already constructed significant flood protection; the new OHB ring levee was designed to protect the community from the flooding caused by the larger diversion project.
The district court did not abuse its discretion in finding that the balance of harms favored an injunction. The district court determined that the OHB communities were already somewhat protected, and that the real motivation for the project was to pave the way for the larger diversion project and protect against flooding which would only occur if the larger diversion project went forward. In light of these conclusions, the district court did not err
D. Likelihood of Success on the Merits
i. Standard
Once the court has considered the threat of irreparable harm and the balance of harms, the appropriateness of an injunction still depends on “the probability that the moving party would succeed on the merits.” Rounds, 530 F.3d at 729 n. 3. The plaintiff “need only establish a likelihood of succeeding on the merits of any one of [its] claims.” Am. Rivers v. U.S. Army Corps of Eng‘rs, 271 F.Supp.2d 230, 250 (D.D.C. 2003).
In determining the likelihood of succeeding, the district court applied the “fair chance of prevailing” standard. See 1-800-411-Pain Referral Serv., LLC v. Otto, 744 F.3d 1045, 1054 (8th Cir. 2014) (describing “this circuit‘s ordinary preliminary injunction test, [as] ask[ing] only whether a movant has demonstrated a ‘fair chance of prevailing’ in the ultimate litigation“). The Authority argues that this was the wrong standard because under Rounds, the court must sometimes apply a more stringent standard of “likely to prevail.” 530 F.3d at 730. In Rounds this court held that where a party seeks to enjoin the enforcement of a state statute, the court must apply a more rigorous threshold and determine whether the movant is “likely to prevail.” Id. For “administrative actions by federal, state or local government agencies,” the court may evaluate whether “the full play of the democratic processes” was involved in enactment, then determine which standard would be more appropriate. Id. at 732 n. 6 (internal quotation omitted). The district court found that the democratic process required by Rounds was not satisfied by the environmental planning process. As for the project‘s authorization under the WRRDA, the district court reasoned that the project was adopted pursuant to expert agency recommendation, something “far different than adopting a complex statute through fulsome debate.” The district court also noted that the injunction did not seek to enjoin the WRRDA, but merely delay a local partner‘s construction of part of a project pending Minnesota environmental review.
The Authority argues that the district court drew the category of government action that requires the “likely to prevail” standard too narrowly and that, in any case, the injunction did enjoin a state and federal statute, North Dakota‘s appropriation of funds and the WRRDA. However, Rounds notes that where an injunction is sought to stop anything other than “government action based on presumptively reasoned democratic process,” the familiar “fair chance of prevailing” test will still apply. Id. at 732. The district court did not err in finding that the WRRDA, which did not appropriate funds, merely represented
ii. MEPA
The Authority next argues that JPA‘s likelihood of succeeding on its
The Authority‘s first argument is that the district court erred because
Next, the Authority argues that the OHB ring levee has independent utility, so
iii. Dormant Commerce Clause
Next, the Authority argues that
The dormant Commerce Clause is the negative consequence of the Commerce Clause. Quill Corp. v. North Dakota, 504 U.S. 298, 312 (1992). Under it, states are barred from discriminating against or unduly burdening interstate commerce. Id. The dormant Commerce Clause “precludes the application of a state statute to commerce that takes place wholly outside of the State‘s borders, whether or not the commerce has effects within the State.” Healy v. Beer Inst., 491 U.S. 324, 336 (1989). If the regulation is not per se invalid and not discriminatory, the court balances whether the burdens are “clearly excessive in relation to the putative local benefits.” Pike v. Bruce Church, Inc., 397 U.S. 137, 142 (1970).
The district court determined that “[w]hile the OHB ring levee is being constructed in North Dakota, and while many other aspects of the diversion project will be built in North Dakota, they are all integral parts of a larger project that indisputably will be constructed, in part, in Minnesota.” The Authority disagrees, arguing that only the effects of the OHB ring levee will reach Minnesota. The district court reasoned that “laws governing a project that crosses the border between two states are bound to have some extraterritorial effect;” if North Dakota were permitted to begin building the diversion project in North Dakota, and could only be stopped once it reached the Minnesota border, the practical effect would be that for interstate projects, the state with more lenient laws would always control. Thus, as the district court found, “both states clearly have an interest in regulating the diversion project and their regulatory regimes will no doubt intersect.” The Authority points out that the presence of Minnesota actors within the Authority is not sufficient, but as already stated, such actors are not the lone connection between this project and Minnesota. By virtue of OHB ring levee‘s connection with the larger diversion project, its construction does not take place “wholly outside” Minnesota‘s borders. Minnesota has an interest in regulating the larger diversion project and its parts. Thus, the district court did not err in finding that the dormant Commerce Clause does not preclude JPA‘S
IV.
Finally, the Authority argues that the district court erred in failing to require the JPA to post a bond. The district court waived the security requirement, based on its characterization of the suit as public interest environmental litigation. The district court acted within its discretion in doing so.
Under
The Authority argues that it was error to not require a bond. But, in analogous
V.
For these reasons, we affirm the district court‘s ruling in its entirety.
