Mary Stockslager v. Carroll Electric Cooperative CorporationMary Stockslager v. Carroll Electric Cooperative Corporation
This action was brought by several land owners and the Arkansas Ecology Center to enjoin the construction of electric high voltage lines across or near the lands of some of the individual plaintiffs. The named defendant was Carroll Electric Cooperative Corporation, which was planning the construction of the line. In its complaint the plaintiffs alleged generally that the defendant cooperative was receiving federal funds for the project; that the project would adversely affect the environment and that the defendant had “failed to include in its reports to federal agencies * * * a detailed statement concerning the environmental impact of the proposed action * *
After a motion to dismiss was filed on behalf of the defendants pointing out that
On September 2, 1975, two orders were entered. The first order dismissed the complaint of certain named plaintiffs against whom state condemnation proceedings had already been instituted by the cooperative on the grounds that “in view of
On the same date Judge Williams entered an order conditionally granting a preliminary injunction against Carroll Electric Corporation as to constructing the 69 kilovolt line. The preliminary in
Neither of the defendants cross-appealed so the validity of the injunction is not before us except as to the two conditions of the injunction heretofore described which are being challenged by the plaintiffs.
As to the appellants’ first ground for appeal, the dismissal of several of the plaintiffs, the simple answer is that this court does not have jurisdiction to decide it. The dismissal of some of the plaintiffs, but not all, is not an appealable order in the absence of certification under
As to appellants’ contention that the trial court should not have required a $10,000 bond we need only look to
(c) Security. No restraining order or preliminary injunction shall issue except upon the giving of security by the applicant, in such sum as the court deems proper, for the payment of such costs and damages as may be incurred or suffered by any party who is found to have been wrongfully enjoined or restrained. * * *
The amount of the bond rests within the sound discretion of the trial court and will not be disturbed on appeal in the absence of an abuse of that discretion.
Commonwealth of Puerto Rico v. Price Commission,
The last question raised in this appeal is less easily disposed of. The district court granted a preliminary injunction against further construction of the power line except as to those lands which were the subject of condemnation proceedings in the Arkansas state courts prior to this federal court action. The reason given for limiting the scope of the injunction was the anti-injunction statute,
The anti-injunction statute prohibits interference with state court proceedings, subject to certain narrow exceptions.
2
The exception we are concerned with here, appearing on the face of
It is evident that the NEPA was enacted in response to deep concern about the deterioration of the national environment, and that it was felt that the best method of insuring environmental protection was by implementing a coordinated national policy.
See
U.S.Code Cong. & AdmimNews, p. 2751
passim
(1969). The words used throughout the Act indicate that Congress did not consider that halfway measures would suffice; it was plainly the intent of Congress that the full power of the federal government be brought to bear upon the problem in order to effectuate the policies expressed. The declared policy of the United States is “to use
all practicable means and measures”
to preserve the quality of life in our country.
The primary responsibility for effectuating the policy of the NEPA is undoubtedly with the federal government. That fact distinguishes this case from
Clean Air Coordinating Committee v. Roth-Adam Fuel Co.,
This case is remanded to the trial court for further proceedings consistent with the views expressed in this opinion.
Notes
.
A court of the United States may not grant an injunction to stay proceedings in a state court except as expressly authorized by Act of Congress, or where necessary in aid of its jurisdiction, or to protect or effectuate its judgments.
. The exceptions identified in
Mitchum
v.
Foster,
. In view of our decision that the anti-injunction statute does not apply to
. It is Carroll Electric’s contention that an environmental impact statement is not required because of applicable REA regulations. We do not reach this issue.