Norman W. BERNSTEIN, et al., Plaintiffs-Appellants/Cross-Appellees, v. Patricia A. BANKERT, et al., Defendant-Appellees, and Auto Owners Mutual Insurance Company, Defendant-Appellee/Cross-Appellant.
Nos. 11-1501, 11-1523
United States Court of Appeals, Seventh Circuit.
Decided Dec. 19, 2012.
Argued Oct. 31, 2011.
AFFIRMED
Robert M. Chemers (argued), Attorney, Pretzel & Stouffer, Chicago, IL, David L. Taylor (argued), Attorney, Taylor Law Firm, P.C., Indianapolis, IN, John A. Yeager (argued), Attorney, Willingham & Cote, PC, East Lansing, MI, for Defendants-Appellees/Cross-Appellant.
Before KANNE and WILLIAMS, Circuit Judges, and DeGUILIO, District Judge.*
DeGUILIO, District Judge.
This appeal is the latest chapter in the story of the Environmental Chemical and Conservation Company (“Enviro-Chem“), a defunct Indiana corporation with an expensive environmental legacy. Enviro-Chem conducted waste-handling and disposal operations at three sites north of Zionsville, Indiana, until it closed its doors in the early 1980s, and it left considerable amounts of pollutants behind. The plaintiffs in this action are the trustees of a fund created to finance and oversee the cleanup project at one of those three sites. The defendants are the former owners of the site, their corporate entities (including Enviro-Chem), and their insurers, none of whom have paid into the trust despite an alleged obligation to do so. The plaintiffs sued to recover cleanup costs under the
BACKGROUND
The appellants-plaintiffs below-are the trustees of the Third Site Trust Fund (“Trustees“). Third Site is a
Enviro-Chem ceased operations in 1982, and shortly thereafter the United States Environmental Protection Agency (“EPA“) undertook an extended effort to clean up
In 1996, the EPA countered the threat by issuing a Unilateral Administrative Order (“UAO“) outlining a plan to realign Finley Creek. The plan called for eliminating an oxbow, the top of which touched areas of high contamination at Third Site, and for rerouting the creek away from the site and to the south. The realignment project was designated a time-critical removal project, and the respondents to the UAO completed it in September 1996. Subject to periodic maintenance inspections, the EPA approved their performance.
Having averted any significant corruption of the drinking water supply, the EPA turned its attention to cleaning up Third Site itself. In October 1999, the EPA entered into an Administrative Order by Consent (“AOC“) with a number of respondents, each of whom was designated a potentially responsible party (“PRP“) for contamination at the site. The 1999 AOC was divided into two separate parts: one dealing with “Non-Premium Respondents” and one dealing with “Premium Respondents.” The Non-Premium Respondents agreed to undertake an Engineering Evaluation and Cost Analysis (“EE/CA“) of removal alternatives for Third Site. They also agreed to settle a trust-the Third Site Trust, of which the appellants are Trustees-and to fund it to the extent necessary to bankroll the EE/CA and any additional necessary work. Through the Trust, they would reimburse the EPA for past response and oversight costs as well as future oversight costs incurred in conjunction with the EE/CA project. The Premium Respondents, on the other hand, were alleged to be de minimis contributors to the contamination at Third Site. They were entitled to settle out with a defined, onetime monetary contribution to the Trust consistent with
The Non-Premium Respondents met their obligations under the 1999 AOC and obtained EPA approval of the final EE/CA report on October 24, 2000. No copy of the EPA notice of approval was included in the record, and we only know of it through affidavits submitted with the parties’ summary judgment briefs. But, in any case, the parties do not dispute that the 1999 AOC was complied with fully to its completion. In 2001, subsequent to approving the work done under the 1999 AOC, the EPA issued an Enforcement Action Memorandum selecting one of the removal actions for the site identified by the EE/AC and outlining cleanup objectives.
In November 2002, the parties entered into a second AOC to perform the work called for by the Enforcement Action Memorandum. For the most part, the 2002 AOC tracked the form of the 1999 AOC. It included separate provisions ad-
Under the terms of the 1999 and 2002 AOCs and the corresponding Trust Agreement, the Trustees are empowered to hold and manage funds; to retain engineers and others to carry out the work to be performed under the AOCs; to project future costs; to obtain additional funds as needed from the settlors (i.e., the Non-Premium Respondents); and, subject to prior approval, to bring suit against those who do not meet their obligations to the Trust. The Bankert appellees1 were listed as Non-Premium Respondents under the 1999 and 2002 AOCs, but have not met their obligations by paying into the Trust or otherwise.
On April 1, 2008, the Trustees filed a Complaint against the Bankerts and their various insurers in the Southern District of Indiana with six counts: Count I, a
On May 30, 2008, one of the Bankerts’ former insurers, Auto Owners Mutual Insurance Company (“Auto Owners“), moved to dismiss the Trustees’ Complaint against it pursuant to
On September 22, 2009, the Bankerts moved for summary judgment on statute of limitations grounds. The Trustees responded, and the Bankerts replied. On December 10, 2009, the Trustees moved to strike a portion of that reply or, in the alternative, for permission to file supplemental briefing. The district court heard oral argument on August 3, 2010. On September 29, 2010 the district court denied the Trustees’ motion to strike and granted summary judgment in the Bankerts’ favor. First, the district court found that the Trustees could not bring a
Next, the district court asked the parties to report on the status of Count VII, which sought a declaratory judgment of coverage against Auto Owners and the other insurers. All parties conceded that it was moot; insurance coverage was a non-issue without a controversy over the underlying liability. On October 13, 2010, the Trustees moved the court to reconsider the grant of summary judgment with respect to the
THE TRUSTEES’ APPEAL
The Trustees appeal the district court‘s dismissal at the summary judgment stage of their
I. Counts I and II: CERCLA Claims
We begin with the Trustees’
We review a district court‘s grant of summary judgment based on a statute of limitations de novo. Stepney v. Naperville Sch. Dist. 203, 392 F.3d 236, 239 (7th Cir. 2004). To the extent we are called upon to review the district court‘s interpretation of the statute, the standard of review is likewise de novo. Storie v. Randy‘s Auto Sales LLC, 589 F.3d 873, 876 (7th Cir. 2009). We are mindful, too, of the deference typically accorded to the summary judgment non-movant with respect to the resolution of factual issues, but note that this dispute is almost entirely a legal one, with the underlying facts undisputed: the Bankerts argue that the Trustees have advanced one type of
A. CERCLA and SARA Statutory Scheme
In 1980, Congress enacted the
Any person may seek contribution from any other person who is liable or potentially liable under
section 9607(a) of this title, during or following any civil action undersection 9606 of this title or undersection 9607(a) of this title.
(emphasis added). In Cooper Indus., Inc. v. Aviall Servs., Inc., 543 U.S. 157 (2004), the Supreme Court held that the italicized phrase has a limiting effect. “The natural meaning of this sentence is that the contribution may only be sought subject to the specified conditions[.]” Id. at 166 (emphasis added). To read the clause more expansively would render the italicized phrase superfluous, which the Court was loathe to do. Id. (citing Hibbs v. Winn, 542 U.S. 88, 101 (2004)). In short, “[t]here is no reason why congress would bother to specify conditions under which a person may bring a contribution claim, and at the same time allow contribution actions absent those conditions.” Id. After Cooper, a contribution action under
The second contribution right of action is codified at
A person who has resolved its liability to the United States or a State for some or all of a response action or for some or all of the costs of such action in an administrative or judicially approved settlement may seek contribution from any person who is not party to a settlement referred to in paragraph (2).6
(emphasis added). As the Supreme Court did with respect to
Furthermore, the phrase “resolved its liability . . . in an administrative . . . settlement,” used as a trigger in
Whenever the President has entered into an agreement under this section, the liability to the United States under this chapter of each party to the agreement, including any future liability to the United States, arising from the release or threatened release that is the subject of the agreement shall be limited as provided in the agreement pursuant to a covenant not to sue in accordance with subsection (f) of this section.
The “subsection (f)” to which the quotation refers provides:
(1) Discretionary covenants
The President may, in his discretion, provide any person with a covenant not to sue concerning any liability to the United States under this chapter, including future liability, resulting from a release or threatened release of a hazardous substance addressed by a remedial action, whether that action is onsite or offsite, if each of the following conditions is met:
(A) The covenant not to sue is in the public interest.
(B) The covenant not to sue would expedite response action consistent with the National Contingency Plan under section 9605 of this title.
(C) The person is in full compliance with a consent decree under section 9606 of this title (including a consent
decree entered into in accordance with this section) for response to the release or threatened release concerned.
(D) The response action has been approved by the President.
*
*
*
(3) Requirement that remedial action be completed
A covenant not to sue concerning future liability to the United States shall not take effect until the President certifies that remedial action has been completed in accordance with the requirements of this chapter at the facility that is the subject of such covenant.
Thus, reading the statutory scheme as a whole, as we are bound to do, see King v. St. Vincent‘s Hosp., 502 U.S. 215, 221 (1991), we see that an administrative settlement between the United States and PRP does not, and cannot, automatically resolve that PRP‘s liability. It does so only through the operation of a subsection (f) covenant not to sue. And, under the plain terms of the statute, a subsection (f) covenant not to sue cannot possibly take effect, thereby actually releasing the settling PRP from liability, until the PRP has satisfactorily discharged its obligation under the agreement and the President has certified its completion. See
In summary, each
B. Classifying the Trustees’ CERCLA Claim
The next step is to apply the statutory scheme to the facts to determine which sort of claim, or claims, the Trustees have advanced, and whether it is barred by the applicable statute of limitations. In Count I of the Complaint, the Trustees seek to recover the costs they incurred pursuant to the 1999 and 2002 AOCs. In order to determine which kind of
1. The 1999 AOC
Under the 1999 AOC, the Non-Premium Respondents took on significant responsibilities. They agreed to undertake the EE/CA study of removal alternatives for Third Site, to develop and submit an EE/CA report to the EPA,7 and to settle and fund the Third Site Trust. They also agreed to reimburse the federal government for the EPA‘s past response and oversight costs, for any future oversight costs incurred in conjunction with the EE/CA project, and for an amount certain to be expended by the Department of the Interior in addressing natural resource damages at Third Site. The 1999 AOC laid out deadlines for the Non-Premium Respondents to meet their obligations, and made clear that no release from
Except as expressly provided in Section XIII (Covenant Not to Sue), nothing in this Order constitutes a satisfaction of or release from any claim or cause of action against the Respondents or any person not a party to this Order, for any liability such person may have under CERCLA, other statutes, or the common law, including but not limited to any claims of the United States for costs, damages and interest under Sections 106(a) or 107(a) of CERCLA, 42 U.S.C. §§ 9606(a), 9607(a).8
The covenants not to sue referred to in the disclaimer above were expressly condi-
tioned on respondents’ fulfillment of their obligations under the Order:
Except as otherwise specifically provided in this Order, upon issuance of the [Notice of Completion], U.S. EPA covenants not to sue Respondents for judicial imposition of damages or civil penalties or to take administrative action against Respondents for any failure to perform actions agreed to in this Order[.]
*
*
*
[I]n consideration and upon Respondents’ payment of [the EPA‘s response costs], U.S. EPA covenants not to sue or take administrative action against Respondents under
Section 107(a) of CERCLA [.]
And, most explicitly, as modified by the attached errata sheet:
These covenants are conditioned upon the complete and satisfactory performance by Respondents of their obligations under this Order.
These conditional covenants are consistent with the statutory requirements for a release of
For the Non-Premium Respondents, then, the EPA‘s covenants not to sue-and accompanying release from
a. The Trustees have a § 9613(f)(3)(B) contribution claim for costs incurred under the 1999 AOC.
By the terms of the statute and of the AOC itself, when the Non-Premium Respondents completed performance of their obligations under the 1999 AOC and obtained a notice of approval from the EPA, the conditional covenants not to sue contained therein went into effect. At that point, the Non-Premium Respondents, and by extension the Trust, had “resolved [their] liability to the United States . . . for some or all of a response action or for some or all of the costs of such action” through an administrative settlement, thus satisfying the prerequisites for a contribution action pursuant to
Of course, the Trustees also incurred necessary costs of response consistent with the national contingency plan. They did not simply reimburse the EPA for a removal action it had already performed; they funded and executed the removal action themselves. In that sense, the trigger for a
We do not suggest that §§ 107(a)(4)(B) and 113(f) have no overlap at all. Key Tronic Corp. v. United States, 511 U.S. 809, 816 (1994) (stating the statutes provide “similar and somewhat overlapping remed[ies]“). For instance, we recognize that a PRP may sustain expenses pursuant to a consent decree following a suit under § 106 or § 107(a). See, e.g., United Technologies Corp. v. Browning-Ferris Industries, Inc., 33 F.3d 96, 97 (1st Cir. 1994). In such a case, the PRP does not incur costs voluntarily but does not reimburse the costs of another party. We do not decide whether these compelled costs of response are recoverable under § 113(f), § 107(a), or both.
Most circuits, after Atlantic Research, have not allowed a plaintiff to pursue a cost recovery claim when a contribution claim is available. See Solutia, Inc. v. McWane, Inc., 672 F.3d 1230, 1236-37 (11th Cir. 2012); Morrison Enters., LLC v. Dravo Corp., 638 F.3d 594, 603 (8th Cir. 2011); Lyondell Chem. Co. v. Occidental Chem. Corp., 608 F.3d 284, 291 n. 19 (5th Cir. 2010) (acknowledging, and not disturbing, district court‘s implicit decision that plaintiff could not pursue both remedies); Agere Sys., Inc. v. Advanced Envtl. Tech. Corp., 602 F.3d 204, 229 (3d Cir. 2010); Niagara Mohawk Power Corp. v. Chevron U.S.A., Inc., 596 F.3d 112, 128 (2d Cir. 2010); ITT Indus., Inc. v. BorgWarner, Inc., 506 F.3d 452, 458 (6th Cir. 2007). Two justifications are usually given for reaching that conclusion. First, courts have noted that, despite its passing acknowledgment of a possible overlap in Atlantic Research, the Supreme Court has repeatedly emphasized the procedural “distinctness” of the
The “contribution bar” argument, although common in the case law, is based on a faulty premise. The argument is that a
The problem, of course, is that
The other justification usually offered for limiting a plaintiff to one form of
b. The Trustees are time-barred from recovering costs expended pursuant to the 1999 AOC.
The statute of limitations for
No action for contribution for any response costs or damages may be commenced more than 3 years after--
(A) the date of judgment in any action under this chapter for recovery of such costs or damages, or
(B) the date of an administrative order under
section 9622(g) of this title (relating to de minimis settlements) or9622(h) of this title (relating to cost recovery settlements) or entry of a judicially approved settlement with respect to such costs or damages.
The Bankerts argue that because the de minimis parties, also known as the Premium Respondents, settled out pursuant to
(A) for a removal action, within 3 years after completion of the removal action, except that such cost recovery action must be brought within 6 years after a determination to grant a waiver under section 9604(c)(1)(C) of this title for continued response action; and
(B) for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action, except that, if the remedial action is initiated within 3 years after the completion of the removal action, costs incurred in the removal action may be recovered in the cost recovery action brought under this subparagraph.
We need not resolve the “coverage gap” dispute with respect to the work performed under the 1999 AOC, because the outcome is the same either way. Assuming for the moment that we agree with the Trustees that the limitations period for a cost recovery action should apply, we note that an EE/CA is a “removal action.” See
2. The 2002 AOC
After approving the work done under the 1999 AOC, the EPA issued an Enforcement Action Memorandum selecting a removal action and cleanup objectives. In November 2002, the parties entered into the second AOC to implement those solutions. The 2002 AOC included identical conditional covenants not to sue, and its structure was largely parallel to that of the 1999 AOC. To the extent that the Trustees’ suit seeks to recover expenses arising out of their performance of the 2002 AOC, it is not a contribution action. The Trustees have been subjected to no civil action under
What the Trustees have done, with respect to the work called for by the 2002 AOC, is incur costs of response consistent with the national contingency plan, as is required to file a cost recovery action under
The first problem with the Bankerts’ argument is that it has no basis in the text of the source case. In Atlantic Research, the Court was asked to decide whether the phrase “any other person” in
In response to the government‘s concern, the Court emphasized the procedural distinctness of the remedies. The Court contrasted a plaintiff who seeks to recover
We do not suggest that §§ 107(a)(4)(B) and 113(f) have no overlap at all. Key Tronic Corp. v. United States, 511 U.S. 809, 816 (1994) (stating the statutes provide “similar and somewhat overlapping remed[ies]“). For instance, we recognize that a PRP may sustain expenses pursuant to a consent decree following a suit under § 106 or § 107(a). See, e.g., United Technologies Corp. v. Browning-Ferris Industries, Inc., 33 F.3d 96, 97 (1st Cir. 1994). In such a case, the PRP does not incur costs voluntarily but does not reimburse the costs of another party. We do not decide whether these compelled costs of response are recoverable under § 113(f), § 107(a), or both. For our purposes, it suffices to demonstrate that costs incurred voluntarily are recoverable only by way of § 107(a)(4)(B), and costs of reimbursement to another person pursuant to a legal judgment or settlement are recover-
able only under § 113(f). Thus, at a minimum, neither remedy swallows the other, contrary to the Government‘s argument.
The Bankerts conclude, based on the quoted footnote, that only parties who voluntarily incur response costs can bring an action for cost recovery under
The second problem with the Bankerts’ position is that they have produced no legal authority in support of it. The cases they cite which did hold that PRPs who incurred cleanup costs under government settlements were bound to pursue a contribution claim did so because the statutory triggers for contribution claims were met, not because the costs were compelled as opposed to voluntary. See Niagara Mohawk, 596 F.3d 112 (holding that the plaintiff had a contribution claim under
The third, and most obvious, problem with the Bankerts’ argument is that they are asking us to impose a requirement that appears nowhere in the statutory text. Imposing a requirement not evident on the face of the statute arguably violates fundamental rules of statutory construction. See E.I. DuPont de Nemours and Co. v. United States, 508 F.3d 126, 133 n. 5 (3d Cir.2007). As outlined in detail above,
Beyond their characterization of Atlantic Research and subsequent case law, the Bankerts seem to suggest that the mere fact that the Trustees entered into a settlement is enough to give rise to a claim for contribution under
3. Conclusion of CERCLA Issues
In summary, the Trustees cannot recover for expenses incurred in carrying out the work performed under the 1999 AOC. At this point, that relief can only be sought through a contribution action, and a contribution action is time-barred, no matter which side is correct as to the triggering event. But the Trustees can recover for expenses incurred in carrying out the 2002 AOC. In that respect, Count I is a claim for cost recovery and is timely.
We recognize that neither party appears to have considered splitting the Trustees’ claim in the way that we do now. But the removal actions called for by the AOCs were temporally discrete projects. If that were not the case, the EPA would not have been able to certify the first action‘s completion before the second action had even been selected. They need not be treated as an indivisible whole. The removal action contemplated by the 1999 AOC was completed years ago, and supports a contribution action. The removal action contemplated by the 2002 AOC was ongoing at the time this suit was filed, and supports a cost recovery action. Each is governed by a different statute of limitations, and the fact that recovery with respect to the former is time-barred does not legally preclude the Trustees from pursuing recovery with respect to the latter, which is not. Furthermore, resolving the dispute in this manner does not require constructing a new claim that the plaintiff did not plead. Count I, as written, is an action for cost recovery, and we hold that it can stand as an action for cost recovery. Functionally speaking, this ruling simply limits the damages the plaintiff can recover. The district court‘s judgment is reversed with respect to Count I to the extent that the Trustees may seek to recover for costs incurred pursuant to the 2002 AOC.
Finally, we address the district court‘s dismissal of Count II, seeking a declaratory judgment of the Bankerts’ joint and several liability. Count II is based on
C. The District Court‘s Denial of the Trustees’ Motion to Strike
According to the Trustees, the Bankerts raised an argument in their summary judgment reply brief which they did not raise in their original motion. More specifically, the Bankerts raised the “contribution bar” argument, which we have previously discussed. The Trustees wanted the argument struck, but the district court let it stand. The Trustees now appeal that decision. We review the district court‘s grant or denial of a motion to strike for abuse of discretion. Stinnett v. Iron Works Gym/Executive Health Spa, Inc., 301 F.3d 610, 613 (7th Cir. 2002); Winfrey v. City of Chi., 259 F.3d 610, 618-19 (7th Cir. 2001). “Normally, the decision of a trial court is reversed under the abuse of discretion standard only when the appellate court is convinced firmly that the re
II. Count III: Indiana ELA Claim
We move next to the Trustees’ claim under the Indiana Environmental Legal Actions statute (“ELA“). In 1997, the Indiana General Assembly enacted a statute providing for an “environmental legal action” to “recover reasonable costs of a removal or remedial action” involving hazardous substances or petroleum. See Cooper Indus., LLC v. City of South Bend, 899 N.E.2d 1274, 1280 (Ind. 2009) (citing
We apply the statute of limitations of the state whose substantive law governs the claim, which in this case is Indiana. See Guaranty Trust Co. of N.Y. v. York, 326 U.S. 99, 110 (1945) (holding that statutes of limitations are considered substantive law for purposes of the Erie doctrine). When this action was filed, the ELA did not include its own limitations provision.10 Accordingly, both parties looked elsewhere in the Indiana code to find an applicable statute of limitations. The Trustees argue that Indiana‘s ten-year “catch-all” statute of limitations should apply. See
Pflanz v. Foster, 888 N.E.2d 756 (Ind. 2008), explains the application of the ten-year catch-all statute of limitations, and Peniel Group, Inc. v. Bannon, 973 N.E.2d 575 (Ind. Ct. App. 2012), explains the application of the six-year property damage statute of limitations. In combination, they provide the framework for the resolution of this case. Pflanz v. Foster concerned a dispute between the seller, Merrill Foster, and the buyers, Richard and Dolores Pflanz, of a parcel of land that was previously occupied by a gas station. When Foster sold the land to the Pflanzes in 1984, he advised them that underground petroleum tanks were present on the property, but were not in use and had been closed. 888 N.E.2d at 758. In fact, the tanks were still open and partially filled. Id. The Pflanzes first learned as much in 2001, when the Indiana Department of Environmental Management (“IDEM“) inspected the property and discovered that the tanks were leaking. Id. IDEM ordered the Pflanzes to clean up the property, see id. at 759, and the Pflanzes subsequently incurred over $100,000 in cleanup costs. Id. at 758. In 2004 and 2006, the Pflanzes filed complaints seeking contribution from Foster. Those complaints were dismissed on statute of limitations grounds, and the issue made its way up to the Indiana Supreme Court.
The Pflanzes’ claim was brought pursuant to the Underground Storage Tanks Act (“USTA“),
Next, the Indiana Supreme Court proceeded to determine when the ten-year limitations period began to run. Under the Indiana discovery rule, “a cause of action accrues, and the statute of limitations begins to run, when a claimant knows or in exercise of ordinary diligence should have known of the injury[,]” not of the mere possibility of an injury in the future. Id. In cases in which a party seeks to recover cleanup costs, “the damage [or injury] at issue is the cleanup obligation assessed by [the controlling government agency,]” not the mere fact of contamination. Id. The latter would be the injury in a suit to recover property damages, but suits to recover cleanup costs are different. Id. Following this path to its logical conclusion, the Indiana Supreme Court held that in an environmental cleanup case governed by the ten-year catch-all statute of limitations, the limitations period does not begin to run “until after the [plaintiff is] ordered to clean up the property.” 888 N.E.2d at 759. Since the Pflanzes brought their action within ten years of the cleanup order, their action was timely.
In Peniel Group, Inc. v. Bannon, the Indiana Court of Appeals confronted a different kind of claim. The plaintiffs were the current owner and manager of a parcel of real property. After discovering that levels of contamination on the property exceeded limits set by the state, thus requiring a cleanup, the plaintiffs sued the previous owners and tenants of the parcel under the ELA. Since the ELA did not include a limitations provision at the time the suit was filed, the Indiana Court of Appeals was tasked with deciding which other statute of limitations to apply. 973 N.E.2d at 581. Finding that the plaintiffs were the owners of the real property in question and were not themselves responsible in any way for the contamination at the site, the court concluded that the Peniel plaintiffs’ action was one for property damage. Id. at 581-82. That being the case, the six-year limitations period governing actions for damages to real property was applied, and that limitations period begins to run “when a claimant knows, or in the exercise of ordinary diligence should have known of the injury.” Id. at 582 (quoting Martin Oil Mktg., Ltd. v. Katzioris, 908 N.E.2d 1183, 1187 (Ind. Ct. App. 2009)). Under Indiana law, “parties are usually held accountable for the time which has run against their predecessors in interest.” Id. (citing Cooper, 899 N.E.2d at 1279). Since the plaintiffs’ predecessors in interest knew of the damage to the site more than six years before the action was filed, the Court of Appeals found that the action was barred.
Accordingly, the Trustees’ ELA claim is not limited by the statute under which it is brought, since no internal limitations provision existed, and it is not limited by the statute applicable to property damage suits, since it is not a suit for property damages. If the action “is not limited by any other statute[,]” see
The ten-year limitations period for an action to recover cleanup costs incurred as the result of an EPA order did not begin to run “until after the [Trustees were] ordered to clean up the property.” Pflanz, 888 N.E.2d at 759. But the parties’ second dispute concerns the application of that rule. There are multiple cleanup orders in this case, each of which inflicted an injury on the Trustees in the form of a cleanup obligation. The Bankerts latch onto the earliest AOC—issued
The Bankerts’ argument fails to persuade us for several reasons. First, the cleanup obligations that the Trustees incurred by executing the 1999 and 2002 AOCs simply were not incurred, either explicitly or implicitly, when the respondents to the 1996 AOC agreed to realign Finley Creek. Neither the Trustees, who did not yet exist in that capacity, nor the 1996 respondents, incurred any obligation at that time to engage in removal or remedial efforts at Third Site itself. Generally, parties bringing actions to recover cleanup costs “must wait until after the obligation to pay is incurred, for otherwise the claim would lack the essential damage element.” Pflanz, 888 N.E.2d at 759 (internal citations omitted). It is true, as the Bankerts and the district court observe, that “it is not necessary that the full extent of the damage be known or even ascertainable but only that some ascertainable damage has occurred” for the statute of limitations to be triggered. Doe, 673 N.E.2d at 842. But that just means an obligation to pay may be considered an “injury” for statute of limitations purposes even before it gives rise to an actual monetary loss. It does not, however, support conflating one obligation with another as though they create the same injury, which is what the Bankerts hope to do.
Furthermore, the Bankerts’ argument that the statute of limitations began to run with respect to the Trustees’ obligations under the 1999 and 2002 AOCs before they incurred those obligations would, if applied to other cases, lead to impractical results. What if the EPA‘s process had been more drawn out (as is often the case), and the AOCs governing the Third Site cleanup were not issued until 2010, or 2012? According to the argument advanced by the Bankerts, in that case, the statute of limitations would have run entirely on the Trustees’ requests for relief before they had even suffered the damages from which relief might be requested. They would have been legally required to bring their action based on nothing but speculation about what sort of cleanup might be ordered in the future at Third Site, what it
Finally, before moving on, we note that the Trustees suggested we might certify this issue to the Indiana Supreme Court. In deciding whether certification is appropriate, “the most important consideration guiding the exercise of our discretion is whether we find ourselves genuinely uncertain about a question of state law that is vital to a correct disposition of the case.” Craig v. FedEx Ground Package Sys., Inc., 686 F.3d 423, 429-30 (7th Cir. 2012) (citing Cedar Farm, Harrison Cnty., Inc. v. Louisville Gas & Elec. Co., 658 F.3d 807, 812-13 (7th Cir. 2011)). “Certification is appropriate when the case concerns a matter of vital public concern, where the issue will likely recur in other cases, where resolution of the question to be certified is outcome-determinative of the case, and where the state supreme court has yet to have an opportunity to illuminate a clear path on the issue.” Id. When considering certification, we are mindful of the state courts’ already busy dockets. Id. We also consider several factors when deciding whether to certify a question, including whether the issue “is of interest to the state supreme court in its development of state law.” Id. (citing State Farm Mut. Auto. Ins. Co. v. Pate, 275 F.3d 666, 671 (7th Cir. 2001)).
We see no reason to certify this question. First, we are not genuinely uncertain about it. While it is not at all a frivolous issue, we are confident in proceeding under the guidance provided by existing Indiana law. Between the settled rule that the nature or substance of an action governs which statute of limitations applies; the fact that this particular action plainly is not one for property damages; and the Indiana Supreme Court‘s previous application of the ten-year catch-all under substantially similar circumstances, the appropriate resolution is clear. Second, we cannot say this issue concerns a matter of vital public concern. The remediation of environmental hazards is certainly an issue of public concern, but the limitations issues discussed herein have by this time been resolved conclusively by legislative action in Indiana. The limitations period in effect at the time an action is brought governs that action, Connell, 725 N.E.2d at 506, and any future ELA actions will be governed by the independent limitations period legislatively added to the ELA. Accordingly, we can say with certainty that this issue will not reappear in any cases not already pending. Third, the Indiana law question is at most only partially outcome-determinative in this case. To the extent that the ELA claim will allow the Trustees to seek recovery of costs incurred under the 2002 AOC, it is merely duplicative of the CERCLA cost recovery claim we have already reinstated. To the extent that it will allow recovery of costs incurred under the 1999 AOC, it extends farther than the CERCLA claim, but that twist is not enough to offset the lack of genuine concern we have about its resolution, or to independently warrant certification. We move on to Count VIII.
III. Count VII: Seeking a Declaratory Judgment Against the Bankerts’ Insurers
In Count VII of the Complaint, the Trustees seek a declaratory judgment
AUTO OWNERS’ CROSS-APPEAL
Auto Owners Mutual Insurance Company is one of the Bankerts’ former insurers, targeted by the Trustees in Count VII of the Complaint. Early in this litigation, Auto Owners filed a motion to dismiss Count VII on res judicata and/or issue preclusion grounds. Auto Owners previously litigated several of the insurance policies in question during the Enviro-Chem Site cleanup in the 1980s and obtained relief in the form of a consent decree and a default judgment. As a result, Auto Owners believes the present claim against it is precluded. The district court treated the motion as one for summary judgment and denied it. To the extent that Auto Owners prevailed regardless when Count VII was dismissed as moot, the final judgment in the case was a favorable one. But they filed a conditional cross-appeal to hedge against a possible reversal, challenging the district court‘s adverse finding on the preclusion issue. The Trustees responded by challenging the procedural propriety of the cross-appeal and, in the alternative, by arguing that the district court reached the correct result. Because we have reinstated the CERCLA, ELA, and declaratory judgment claims originally dismissed in the district court‘s final judgment, we now reach Auto Owners’ conditional cross-appeal.
Background
Auto Owners is a party to the case because of its role as a Bankert insurer during the last years of Enviro-Chem operation. From 1977 until its closure in May 1982, Enviro-Chem was located primarily at 865 South State Road 431, Zionsville, Indiana—referred to earlier in this opinion as the Enviro-Chem Site. The Bankert family owned the site, and Jonathan Bankert, Sr., served as president of Enviro-Chem. His officers and directors were Roy Strong and David Finton. Two companies—Pratt & Lambert, Inc., and Union Carbide Corporation—transported industrial and commercial wastes to the Enviro-Chem Site, where they were held in tanks owned by Wastex Research, Inc. On May 5, 1982, Enviro-Chem ceased operations, leaving approximately 25,000 drums and 56 bulk storage tanks at the Enviro-Chem Site. The drums and tanks were located outside and, unfortunately, were permitted to deteriorate and release the waste they contained. In July 1983, the EPA responded by authorizing a $3 million cleanup project.
On September 21, 1983, the United States filed a complaint in the Southern District of Indiana against more than 250 defendants, including Enviro-Chem, Jonathan and Patricia Bankert, Roy Strong, David Finton, Gary Watson,14 Wastex, Pratt & Lambert, and Union Carbide. The complaint sought to recover EPA response costs and to obtain a declaratory judgment holding the defendants jointly
While the 1983 lawsuit progressed, another was in the works. Auto Owners had issued several insurance policies to Enviro-Chem, the Bankerts, and two other companies known as Technosolve and Hazardous Materials Management, Inc., during Enviro-Chem‘s last years of operation. On April 5, 1984, Auto Owners filed its own complaint in the Southern District of Indiana, naming the parties on both sides of the cross-claim in the simultaneously pending action as defendants. Auto-Owners sought a declaratory ruling that it owed no coverage for the potential liability of its insureds, pursuant to an exclusion contained in the policies at issue:
No coverage is provided by this policy for claims, suits, actions or proceedings against the insured arising out of the discharge, disposal, release or escape of smoke, vapors, soot, fumes, acids, alkalis, toxic chemicals, liquids or gases, waste material or other irritants, contaminants or pollutants into and upon land, the atmosphere or any water course or body of water.
Auto Owners’ suit was resolved piecemeal. On December 21, 1990, the court entered a default judgment in Auto Owners’ favor against Enviro-Chem, Roy Strong, David Finton, Gary Watson, Technosolve, and Hazardous Materials Management. On August 29, 1991, the court entered an agreed judgment between Auto Owners, the Bankerts, Union Carbide, Pratt & Lambert, and Wastex. The default judgment simply incorporated the complaint by reference and granted the relief requested therein, and the agreed judgment stipulated a dismissal without prejudice. In any case, it is undisputed that Auto Owners was successful in avoiding any duty of indemnification attendant to the Enviro-Chem Site litigation. Now, Auto Owners hopes to use the 1990 default judgment and the 1991 agreed judgment to preclude the Trustees from obtaining a declaration of coverage for Third Site.
Discussion
The first dispute concerns the propriety of the cross-appeal. The Trustees argue that Auto Owners’ cross-appeal should be dismissed because Auto Owners prevailed in the final judgment issued by the district court. Auto Owners argues in response that a conditional cross-appeal is a permissible way to hedge against an adverse finding on the main appeal. Neither party references the actual standard in our circuit for resolving this sort of dispute. The dispositive question is whether the relief sought in the cross-appeal is different from the relief already obtained by the cross-appealing party in the district court‘s final judgment. If it is not different, then the cross-appeal must be dismissed. See Weitzenkamp v. Unum Life Ins. Co. of Am., 661 F.3d 323, 332 (7th Cir. 2011) (reiterating the rule that “cross-
In this case, the district court did not specify, either in its separate order dismissing count six as moot or in its final judgment, whether the dismissal of count six was a dismissal with or without prejudice. Pursuant to
The relief Auto Owners requests in its cross-appeal, on the other hand—a dismissal on res judicata grounds—is a dismissal with prejudice. Auto Owners seeks a determination that the claims before the court in this case have previously been adjudicated on the merits; res judicata only bars an action if there was a final judgment on the merits in an earlier case and both the parties and claims in the two lawsuits are the same. See Matrix IV, Inc. v. Am. Nat‘l Bank & Trust Co., 649 F.3d 539, 547 (7th Cir. 2011); Johnson v. Cypress Hill, 641 F.3d 867, 874 (7th Cir. 2011). Obviously, in contrast to a dismissal without prejudice, any such determination disposes of the claims before the court permanently. If the Trustees’ declaratory judgment claim against Auto Owners cannot be brought in this instance due to an earlier, binding determination of the claim or of the dispositive issues, then it cannot be brought in any future instance without running into the same problem. See Walliser v. Hannig, 358 Fed. Appx. 715, 717 (7th Cir. 2009) (referring to a dismissal on res judicata grounds as a “final judgment on the merits“). The relief Auto Owners seeks in its cross-appeal, a dismissal with prejudice, is therefore different from the relief it won in the district court‘s disposition of the case, which was a dismissal without prejudice. A cross-appeal is proper under the circumstances, see Am. Bottom Conservancy, 650 F.3d at 661, and we proceed to the merits.
Because the prior decisions—the 1990 default judgment and the 1991 agreed judgment—were entered by the United States District Court for the Southern District of Indiana, we apply federal law to determine their preclusive effect. E.E.O.C. v. Harris Chernin, Inc., 10 F.3d 1286, 1290 n. 4 (7th Cir. 1993) (“Where the earlier action is brought in federal court, the federal rules of res judicata apply.“)
I. Issue Preclusion
We begin by addressing Auto Owners’ issue preclusion argument. The doctrine of issue preclusion “bars ‘successive litigation of an issue of fact or law actually litigated and resolved in a valid court determination essential to the prior judgment,’ even if the issue recurs in the context of a different claim.” Taylor v. Sturgell, 553 U.S. 880, 892 (2008) (quoting New Hampshire v. Maine, 532 U.S. 742, 748 (2001)). Issue preclusion requires an identity of issues: “the doctrine ‘applies only when (among other things) the same issue is involved in the two proceedings[.]‘” Coleman v. Donahoe, 667 F.3d 835, 853-54 (7th Cir. 2012) (quoting King v. Burlington N. & Santa Fe Ry. Co., 538 F.3d 814, 818 (7th Cir. 2008)). Additionally, it is well-settled that issue preclusion, like claim preclusion, only applies if the issue was previously determined by a “valid and final judgment.” Bobby v. Bies, 556 U.S. 825, 834 (2009).
We need not decide whether the relief obtained by Auto Owners in the 1984 action—a default judgment and a consented dismissal without prejudice—constitutes a “valid and final judgment,” and we need not decide whether the coverage issue was “actually litigated” therein. The issue in this case and the issue in that case are not identical. They are not identical because the effects of the pollution exclusion and personal injury provisions of the Auto Owners policies on coverage for contamination at the Enviro-Chem Site and for contamination at Third Site necessarily depend on different sets of facts. True, nobody disputes that Third Site was contaminated as a result of Enviro-Chem operations. But that does not mean that Enviro-Chem‘s operations at the Enviro-Chem Site and Enviro-Chem‘s operations at Third Site were identical in all material aspects. As the district court rightly observed, there is substantial—even undisputed—evidence in the record that contamination at Third Site was caused by the release of pollutants at Third Site, and that contamination at the Enviro-Chem Site was caused by the release of pollutants at the Enviro-Chem Site. It may yet turn out that the absolute pollution exclusion—to the extent that most of the policies at issue incorporate it—will prevent the Trustees from recovering against Auto Owners for costs they incurred in cleaning up Third Site. But if so, that will be because the contamination process at Third Site qualified as a “discharge, disposal, release or escape of smoke, vapors, soot, fumes, acids, alkalis, toxic chemicals,
II. Claim Preclusion
Next, we turn to Auto Owners’ claim preclusion argument. The doctrine of claim preclusion, also known as res judicata, “applies to bar a second suit in federal court when there exists: (1) an identity of the causes of actions; (2) an identity of the parties or their privies; and (3) a final judgment on the merits.” Kratville v. Runyon, 90 F.3d 195, 197 (7th Cir. 1996). With respect to the first element, “[a] claim is deemed to have ‘identity’ with a previously litigated matter if it is based on the same, or nearly the same, factual allegations arising from the same transaction or occurrence.” Id. at 198. With respect to the second, “[w]hether there is privity between a party against whom claim preclusion is asserted and a party to prior litigation is a functional inquiry in which the formalities of legal relationships provide clues but not solutions.” Tice v. Am. Airlines, Inc., 162 F.3d 966, 971 (7th Cir. 1998) (quoting Chase Manhattan Bank, N.A. v. Celotex Corp., 56 F.3d 343, 346 (2d Cir. 1995)). It is a fact-specific analysis, and short-hand terms like “virtual representation” are of little to no use in our circuit. Id. With respect to the final element, for the purpose of claim preclusion, the traditional rule is that “a judgment on the merits is one which is based on legal rights as distinguished from mere matters of practice, procedure, jurisdiction, or form.” Harper Plastics, Inc. v. Amoco Chems. Corp., 657 F.2d 939, 944 (7th Cir. 1981) (quoting Fairmont Aluminum Co. v. Comm‘r, 222 F.2d 622, 625 (4th Cir. 1955)).
Regardless of whether the parties are identical or whether the piecemeal resolution of the 1984 litigation qualified as a “final judgment on the merits,” claim preclusion is inappropriate because there is no “identity of the causes of action.” Federal law defines a “cause of action” as “a core of operative facts which give rise to a remedy[.]” Shaver v. F.W. Woolworth Co., 840 F.2d 1361, 1365 (7th Cir. 1988). Accordingly, the test for an “identity of the causes of action” is “whether the claims arise out of the same set of operative facts or the same transaction.” Matrix IV, Inc., 649 F.3d at 547 (citing In re Energy Coop., Inc., 814 F.2d 1226, 1230 (7th Cir. 1987)). “Even if the two claims are based on different legal theories, the ‘two claims are one for purposes of res judicata if they are based on the same, or nearly the same, factual allegations.‘” Id. (quoting Herrmann v. Cencom Cable Assocs., 999 F.2d 223, 226 (7th Cir. 1993)). The test is an outgrowth of the rule that a party must allege in one proceeding all claims and/or counterclaims for relief arising out of a single occurrence, or be precluded from pursuing those claims in the future. Id., 840 F.2d at 1365;
Auto Owners’ 1984 complaint sought a declaratory judgment that it owed no coverage to the Bankerts or any of their insured corporate entities under the policies listed therein for environmental damages at the Enviro-Chem Site. Supra, n. 14. The operative facts underlying the lawsuit were that the Enviro-Chem Site was polluted; that the EPA was engaged in a collaborative process to remedy that pollution; that litigation was underway to distribute liability for the cleanup costs between cooperative and uncooperative PRPs; and that Auto Owners insured the Bankerts and their corporate entities, who had not paid for any of the cleanup despite their PRP status, during several of the years in which the pollution occurred.
Those facts do overlap, to some extent, with the operative facts underlying Count VII in this case. The Trustees seek a declaration of coverage for the same insureds under the same insurance policies, although they focus on a different coverage provision within the policies. But there are also fundamental differences between the factual background of this suit and the factual background underlying Auto Owners’ 1984 complaint. For example, the same factual considerations which barred a finding of issue preclusion come into play here. This coverage dispute concerns whether the pollution activities at Third Site were covered by Auto Owners’ policies, while the previous dispute concerned whether the pollution activities at the Enviro-Chem Site were covered by Auto Owners’ policies. We need not reiterate why that distinction is important. It is enough to note that it means the claims are not identical; the success of each depends on fitting the facts that led to that contamination to the text of the exclusion provision in the insurance policies. After engaging in such an analysis, the district court could come to the conclusion that Auto Owners does owe coverage to the Bankerts for the pollution at Third Site, for example, without in any way contradicting the earlier finding that it does not owe coverage at the Enviro-Chem Site. See Harper Plastics, Inc., 657 F.2d at 944 (court looks to “whether the judgment in a second suit would impair rights established under the first judgment” when determining whether causes of action are identical). Again, the district court may well find that the pollution exclusion in Auto Owners’ contracts bars coverage for the pollution activities at Third Site, but not on claim preclusion grounds. We affirm with respect to both preclusion issues.
CONCLUSION
For the reasons stated, we reverse the district court‘s dismissal of Counts I, II, III, and VII. In Count I, the Trustees have made a timely CERCLA claim, under
Notes
The terms “removal action” and “remedial action” represent the two primary forms of response contemplated by CERCLA:
(23) The terms “remove” or “removal” means the cleanup or removal of released hazardous substances from the environment, such actions as may be necessary taken in the event of the threat of release of hazardous substances into the environment, such actions as may be necessary to monitor, assess, and evaluate the release or threat of release of hazardous substances, the disposal of removed material, or the taking of such other actions as may be necessary to prevent, minimize, or mitigate damage to the public health or welfare or to the environment, which may otherwise result from a release or threat of release. . . .
(24) The terms “remedy” or “remedial action” means those actions consistent with permanent remedy taken instead of or in addition to removal actions in the event of a release or threatened release of a hazardous substance into the environment, to prevent or minimize the release of hazardous substances so that they do not migrate to cause substantial danger to present or future public health or welfare or the environment.
42 U.S.C. § 9601(23) -(24) . Practically speaking, “removal actions are ‘those taken to counter imminent and substantial threats to public health and welfare,’ while remedial
(b) Subject to subsections (c), (d), and (e), a person may seek to recover the following in an action brought on or after the effective date of this section under IC 13-30-9-2 or IC 13-23-13-8(b) to recover costs incurred for a removal action, a remedial action, or a corrective action:
(1) The costs incurred not more than ten (10) years before the date the action is brought, even if the person or any other person also incurred costs more than ten (10) years before the date the action is brought.
(2) The costs incurred on or after the date the action is brought.
IfThe following actions must be commenced within six (6) years after the cause of action accrues:
(1) Actions on accounts and contracts not in writing.
(2) Actions for use, rents, and profits of real property.
(3) Actions for injuries to property other than personal property, damages for detention of personal property and for recovering possession of personal property.
(4) Actions for relief against frauds.
