Plaintiff W.R. Grace & Co.-Conn. (“Grace”) seeks to recover necessary response costs under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (“CERCLA”) for costs Grace incurred in cleaning up a certain contaminated site in New York. The District Court (Skretny,
J.)
concluded Grace, which is itself a responsible party, is not entitled to recovery under CERCLA because Grace had not previously been a party to a CERCLA civil action, and entered judgment in favor of defendant Zo-tos International, Inc. (“Zotos”).
W.R. Grace & Co.
—Conn.
v. Zotos Int’l, Inc.,
No. 98-CV-838S(F),
I. Background
In 1978, Grace acquired a facility known as the Brewer Road Site (the “Site”) when it purchased the assets of a chemical manufacturer, Evans Chemetics, Inc. (“ECI”). ECI had used the Site as a landfill for wastes from a Waterloo, New York, manufacturing facility (the “Waterloo Plant”) from 1950 through 1959. ECI manufactured organic compounds at the Waterloo Plant, and it formulated and packaged hair care products at the Waterloo Plant for sale to Zotos and other customers. Grace alleges that Zotos arranged for the disposal of certain of those wastes at the Site. Grace continues to own the Site today.
In 1983, the New York State Department of Environmental Conservation (“DEC”) conducted a Phase I preliminary investigation of the Site, and in 1984 Grace entered into its first administrative order on consent to perform a Phase II investigation at the Site. After DEC placed the Site on the New York Registry of Inactive Hazardous Waste Disposal Sites, Grace cooperatively entered into a second administrative order on consent with DEC in 1988 (the “Consent Order”). 1 Pursuant to that Consent Order, Grace agreed to reimburse DEC approximately $20,000 for response costs (including direct labor, analytical, and contractor costs) incurred investigating the environmental conditions. Grace also agreed to perform a remedial investigation and feasibility study (“RI/FS”), and to remediate the landfill. The Consent Order provided specifically that there had been no admission of guilt or finding of liability. Upon the successful completion of the remedy, DEC expressly agreed to release Grace from all claims arising under the New York Environmental Conservation Law (“ECL”) relative to the landfill.
The Consent Order stated that Grace “voluntarily consents to the issuing and entering of this Order, and without admitting any facts or the applicability of any law, waives its right to a hearing herein as provided by law, and consents to be bound by the provisions, terms and conditions of this Order.” The Consent Order provided that at the conclusion of the program, if DEC acknowledged that implementation was complete,
such acknowledgment [sic] shall constitute a full and complete satisfaction and release of each and every claim, demand, remedy or action whatsoever against [Grace], its officers and directors, which [DEC] has or may have as of the date of such acknowledgment [sic] pursuant to Article 27, Title 13, of the ECL relative to or arising from the disposal of hazardous or industrial waste at the Site.
The Consent Order also provided that Grace would reimburse DEC $20,967.64 for costs incurred in investigating the conditions at the Site and in preparing the Consent Order, as well as other sums concerning the costs of implementation of the *88 feasibility study and remedial design. The Consent Order set out that the “failure of [Grace] to comply with any provision of this Order shall constitute a default and a failure to perform an obligation under this Order and under the ECL,” and that “[n]othing herein shall be construed to bind any entity not specifically bound by the terms of this Order.” Pursuant to the Consent Order, Grace remediated the Site in 1993 and has thereafter maintained the Site. Through April 2004, Grace had expended approximately $1.7 million on remedial activities at the Site.
Grace commenced the instant action in December 1998, seeking contribution from Zotos pursuant to CERCLA section 113(f), 42 U.S.C. § 9613(f), and New York law for the costs incurred in connection with the investigation and remediation of contamination at the Site. Following a bench trial, the District Court rendered a final decision and order dated May 3, 2005, in which it concluded that Grace is not entitled to reimbursement pursuant to CERCLA section 113(f) because it was neither a party to a civil suit nor a party to a settlement. The court also denied Grace’s claims under state law.
Grace urges on appeal that it should have been entitled to seek contribution under § 113(f)(3)(B) due to its Consent Order with DEC. In the alternative, Grace argues that it was entitled to recover a portion of its costs pursuant to § 107(a)(4)(B).
II. Discussion
Because this case turns on the interpretation of a federal statute, our review is
de novo. Commander Oil Corp. v. Barlo Equip. Corp.,
A. CERCLA
CERCLA is a comprehensive federal law governing the remediation of hazardous waste sites. Unfortunately, CERCLA, which was hastily enacted on the eve of the lame-duck session of the 96th Congressional term, is known neither for its concinnity nor its brevity.
See, e.g., Exxon Corp. v. Hunt,
In order to achieve these dual purposes, the statute creates several distinct provisions that authorize parties in different procedural positions to recover costs incurred in cleaning up contamination: “(1) section 107(a), which permits the general recovery of cleanup and prevention costs;
2
(2) section 113(f)(1), which creates a contribution right for parties liable or potentially liable under CERCLA; and (3) section 113(f)(3)(B), which creates a contribution right for parties that have resolved their liability by settlement.”
Consol. Edison,
In
Cooper Industries,
the Supreme Court held that a party may pursue a contribution claim under section 113(f)(1) only if that party has been subject to a civil action as specified in that section,
id.
at 583, a limitation most courts had not previously imposed,
see, e.g., Bedford Affiliates v. Sills,
Subsequent to our decision in
Consolidated Edison,
the Supreme Court in
Atlantic Research
held that “the plain terms of § 107(a)(4)(B) allow a PRP to recover costs from other PRPs.”
That a PRP may assert a claim under section 107 as provided in
Atlantic Research,
however, does not put an end to the question of whether a party such as Grace may maintain a cause of action for recovery of response costs. As the Court stated in
Atlantic Research,
“§ 107(a) permits a PRP to recover only costs it has ‘incurred’ in cleaning up a site.”
B. Section 113(f)(3)(B)
On appeal, Grace first asserts that it should be able to bring a cause of action for contribution under section 113(f)(3)(B). In the alternative, Grace asserts it has a cause of action under section 107(a). We will first consider Grace’s arguments with respect to section 113(f)(3)(B). 3
Grace acknowledges that, after Cooper Industries, it may not bring a cause of action against Zotos under section 113(f)(1) because Grace has not already been subject to a civil suit under either section 106 or 107. Grace asserts that since its Consent Order with the DEC qualifies as an administrative settlement under section 113(f)(3)(B), it should be able to pursue a cause of action against Zotos pursuant to this section.
Under the principles enunciated in
Consolidated Edison,
we conclude Grace may not seek contribution under section 113(f)(3)(B).
The 1988 Order on Consent provides:
If the [DEC] acknowledges that the implementation is complete ... such acknowledgment shall constitute a full and complete satisfaction and release of each and every claim, demand, remedy or action whatsoever against [Grace], its officers and directors, which the [DEC] has or may have as of the date of such acknowledgment pursuant to Article 27, Title 13, of the ECL relative to or arising from the disposal of hazardous or industrial waste at the Site.
(emphasis added). The Consent Order further states: “Nothing contained in this Order shall be construed as barring, diminishing, adjudicating or in any way affecting ... (3) the [DEC’s] right to bring any action, at law or in equity against [Grace] ... with respect to areas or resources that may have been damaged as a result of the release or migration of hazardous or industrial wastes from the Site.” This text, which makes no reference to CERCLA, establishes that the DEC settled only its state law claims against Grace, leaving open the possibility that the DEC or the EPA could, at some future point, assert CERCLA or other claims. In the same way that the voluntary consent agreement in
Consolidated Edison
did not resolve Consolidated Edison’s liability under CERCLA, neither did this Consent Order resolve Grace’s liability under CERCLA.
See City of Waukesha v. Viacom Int’l Inc.,
The Consent Order at issue here did not resolve CERCLA claims that could be brought by the federal government. As the district court correctly observed, “[w]here a state proceeds on its own authority to identify a remedy and settle with a PRP, there is a risk the EPA will take later actions or select different remedies that could expose the PRP to additional liabilities.”
Grace,
C. Section 107(a)(4)(B)
Acknowledging that
Atlantic Research
holds that a potentially responsible party may assert a claim under section 107(a)(4)(B) to recover incurred cleanup costs, Zotos maintains that Grace may not pursue a claim for cost recovery because Grace has not incurred response costs within the meaning of section 107(a).
4
Specifically, Zotos contends that because Grace “was compelled to incur costs pursuant to an administrative order,” it has not incurred response costs within the meaning of section 107(a), and therefore has no cause of action against Zotos. To support its claim that Grace’s cleanup costs were not incurred costs within the meaning of the statute, Zotos cites
Consolidated Edison,
Generally, response costs are liberally construed under CERCLA,
see, e.g., Amoco Oil Co. v. Borden Inc.,
Under the plain language of the statute, the fact that a party enters into a consent order before beginning remediation is of no legal significance with respect to whether or not the party has incurred response costs as required under section 107(a). Our reliance on the statutory language conforms with the Supreme Court’s emphasis on the text of CERCLA in interpreting section 107(a).
See e.g. Atl. Research,
Section 107 “permits a PRP to recover only the costs it has ‘incurred’ in cleaning up a site.”
Id.
at 2338 (citing 42 U.S.C. § 9607(a)(4)(B)). Section 107(a) “permits cost recovery (as distinct from contribution) by a private party that has itself incurred cleanup costs.”
Id.
A party who “pays to satisfy a settlement agreement or a court judgment,” however, “does not incur its own costs of response. Rather, it reimburses other parties for costs
*93
that those parties incurred.”
Id; see also Kotrous v. Goss-Jewett Co. of N. Cal.,
Our holding that Grace incurred response costs even though it conducted the remediation pursuant to a consent order is consistent with prior decisions that have allowed potentially responsible parties to seek cost recovery under section 107(a) despite government involvement and oversight. In
Schaefer v. Town of Victor,
the plaintiff underwent eight years of enforcement proceedings from New York’s DEC with respect to a contaminated landfill and had entered into two consent orders with the DEC regarding the landfill’s closure and remediation.
Similarly, in
Consolidated Edison,
the plaintiff entered into a “voluntary cleanup agreement” with New York’s DEC after the agency had required the plaintiff to submit information concerning possible contamination at over 100 of its properties.
Consolidated Edison was no more an “innocent” volunteer than Grace. Both parties would have been vulnerable to suit by the state absent proper remediation conducted under the respective agreements with the state. More importantly, there is no doubt the DEC would not have precluded Grace from entering into a voluntary consent agreement merely because *94 Grace is a PRP. 8 Indeed, the DEC states in the Voluntary Cleanup Program Guide that a voluntary cleanup “agreement” may be characterized as an “order” upon the request of a party.
For the purposes of CERCLA, therefore, the voluntary agreement in Consolidated Edison differs from the Consent Order in Grace in title only — both were agreements made with the DEC to remed-iate voluntarily contaminated sites and to avoid liability. We note that the State of New York’s position, articulated in its amicus brief in this case, further supports this contention. New York asserts “there is no practical difference between an agreement under the Voluntary Cleanup Program and a settlement in the form of an administrative consent order under the State Inactive Hazardous Waste Disposal Site program, such as Grace signed.” Because the determination of whether a party has a cause of action under section 107(a) cannot turn on the semantics of the state program’s title, which will undoubtedly vary from state to state and be subject to internal state modifications, we find no reason to distinguish the case at bar from other cases in which we allowed PRPs who acted pursuant to administrative agreements to seek to recover expenses under section 107(a).
The relevant inquiry with respect to section 107(a) is whether the party undertook the remedial actions without the need for the type of administrative or judicial action that would give rise to a contribution claim under section 113(f).
See Atl. Research,
While it is “ ‘ultimately the provisions of our laws rather than the principal concerns of our legislators by which we are governed,’ ”
Cohen v. JP Morgan Chase & Co.,
We are also mindful that CERCLA was established with the intent that the federal and state governments would cooperate in order to remediate environmental hazards expeditiously and appropriately.
See United States v. Colorado,
Moreover, interpreting the statute such that a potentially liable party, like Zotos, bears no financial responsibility for remediation costs, while the party that actually consented without litigation to remediate a contaminated site bears the total financial burden of the remediation, does not comport with the intended purposes of the statute.
See Consol. Edison,
Faced with environmental hazardous waste contamination on its land, Grace did not wait for a lawsuit before attempting to remediate. Instead, it promptly entered into a consent order with a state agency and cleaned up the site. By doing so it avoided additional contamination caused by delay, as well as saved itself, other potentially liable parties, and the state and federal governments cleanup costs. We cannot conclude that Congress intended to bar such a plaintiff from seeking recovery of costs from other responsible parties, and to allow those potentially liable parties to avoid financial responsibility, particularly where nothing in the statute speaks to such a limitation. See 42 U.S.C. § 9607(a)(4)(B). Moreover, had Grace not acted responsibly by entering into the consent order with the DEC, and instead waited for suit, it would have had a cause of action for contribution under section 113(f)(1), but that course of action would arguably have occasioned both further contamination and greater expenses associated with the delay in instituting litigation.
D. Necessary Costs of Response
The statute allows for recovery of only “necessary costs of response ... consistent with the national contingency plan.” § 107(a)(4)(B), 42 U.S.C. § 9607(a)(4)(B). We note that Zotos stipulated at an earlier stage in the proceedings that “[a]t least some” of the costs Grace incurred were “necessary,” and “consistent with the National Contingency Plan,” and within the *96 meaning of 42 U.S.C. § 9607(a)(4)(B). Because the district court concluded that Grace had no cause of action, it made no determination with respect to the nature of the costs incurred. We make no judgment about that issue, which is a matter to be decided by the district court in the first instance.
III. Conclusion
We hold that parties who have not been subject to a civil action under section 106 or section 107 but who have remediated a contaminated site pursuant to a consent order entered with a state agency may bring a cause of action to recover necessary costs of response under CERCLA section 107(a). We affirm the judgment of the District Court with respect to its dismissal of Grace’s section 113(f)(3)(B) claim. With regard to Grace’s claim under section 107(a), we reverse and we remand for further proceedings consistent with this opinion.
Affirmed in part, reversed in part, and remanded.
Notes
. Because Grace does not seek response costs incurred pursuant to the 1984 order, only the response costs incurred pursuant to the 1988 consent order are the subject of the lawsuit.
. "We assume without deciding that § 107(a) provides for joint and several liability.”
Atl. Research Corp.,
. Initially, Grace asserted its cause of action under section 113(f) generally, and also specifically referred to section 113(f)(1).
Grace,
.
Atlantic Research,
. A "removal action” refers generally to temporary actions taken to address immediate threats to the environment. 42 U.S.C. § 9601(23). The clean-up action taken here was remedial in nature.
. The plain language of section 107(a) allows any person to seek recovery for "necessary costs of response” in removal or remediation action. 42 U.S.C. § 9607(a)(4)(B). There is no dispute that Grace is a "person” under the statute. 42 U.S.C. § 9601(21) ("The term 'person' means an individual, firm, corporation, association, partnership, consortium, joint venture, commercial entity, United States Government, State, municipality, commission, political subdivision of a State, or any interstate body.”).
. As the Supreme Court suggested, it may well be that a party who sustains expenses pursuant to a consent decree following a suit under section 106 or section 107(a) may have a cause of action under either section 113(f), section 107(a), or
both. Atl. Research,
. Grace adds that New York's Voluntary Cleanup Program was not adopted until 1994. Prior to that date, the only way a party could ‘Voluntarily” undertake a cleanup, obtain DEC’s approval and oversight of a remedial plan, and receive release of some liability was to enter a consent order with the DEC.
