In re RELIABILITY PLANS OF ELECTRIC UTILITIES FOR 2017–2021
Docket Nos. 158305 through 158308
Michigan Supreme Court
April 2, 2020
505 Mich 994
Syllabus
Chief Justice Pro Tem: David F. Viviano
Justices: Stephen J. Markman, Brian K. Zahra, Richard H. Bernstein, Elizabeth T. Clement, Megan K. Cavanagh
This syllabus constitutes no part of the opinion of the Court but has been prepared by the Reporter of Decisions for the convenience of the reader.
Reporter of Decisions: Kathryn L. Loomis
In re RELIABILITY PLANS OF ELECTRIC UTILITIES FOR 2017–2021
Docket Nos. 158305 through 158308. Argued on application for leave to appeal November 7, 2019. Decided April 2, 2020.
The Association of Businesses Advocating Tariff Equity (ABATE) (Docket Nos. 158305 and 158306) and Energy Michigan, Inc. (Docket Nos. 158307 and 158308) each appealed an order of the Michigan Public Service Commission (MPSC) implementing
In a unanimous opinion by Chief Justice McCORMACK, the Supreme Court, in lieu of granting leave to appeal, held:
Reversed and remanded to the Court of Appeals for further proceedings, including addressing whether the MPSC’s order complied with the APA.
©2020 State of Michigan
FILED April 2, 2020
S T A T E O F M I C H I G A N
SUPREME COURT
In re RELIABILITY PLANS OF ELECTRIC
UTILITIES FOR 2017–2021.
ASSOCIATION OF BUSINESSES
ADVOCATING TARIFF EQUITY,
Appellee,
v No. 158305
CONSUMERS ENERGY COMPANY,
Appellant,
and
MICHIGAN PUBLIC SERVICE
COMMISSION, ENERGY MICHIGAN,
INC., and MICHIGAN ELECTRIC AND
GAS ASSOCIATION,
Appellees.
Michigan Supreme Court
Lansing, Michigan
OPINION Chief Justice:
Bridget M. McCormack
Chief Justice Pro Tem:
David F. Viviano
Justices:
Stephen J. Markman
Brian K. Zahra
Richard H. Bernstein
Elizabeth T. Clement
Megan K. Cavanagh
ENERGY MICHIGAN, INC.,
Appellee,
v No. 158306
CONSUMERS ENERGY COMPANY,
Appellant,
and
MICHIGAN PUBLIC SERVICE
COMMISSION and MICHIGAN
ELECTRIC AND GAS ASSOCIATION,
Appellees.
ASSOCIATION OF BUSINESSES
ADVOCATING TARIFF EQUITY,
Appellee,
v No. 158307
MICHIGAN PUBLIC SERVICE
COMMISSION,
Appellant,
CONSUMERS ENERGY COMPANY,
ENERGY MICHIGAN, INC., and
MICHIGAN ELECTRIC AND GAS
ASSOCIATION,
Appellees.
ENERGY MICHIGAN, INC.,
Appellee,
v No. 158308
MICHIGAN PUBLIC SERVICE
COMMISSION,
Appellant,
and
CONSUMERS ENERGY COMPANY and
MICHIGAN ELECTRIC AND GAS
ASSOCIATION,
Appellees.
BEFORE THE ENTIRE BENCH
McCORMACK, C.J.
In 2016, the Legislature passed Public Act 341 to ensure reliability of the state’s electric grid. The act charged the Michigan Public Service Commission (MPSC), which regulates retail electricity markets, with setting what are known as “capacity requirements” for a four-year period. Those capacity requirements are imposed upon the state’s electricity providers.
At issue here is what exactly the MPSC can require of one category of those providers, known as “alternative electric suppliers,” under the act. Alternative electric suppliers sell electricity to retail customers in Michigan, but they use other providers’ infrastructure to deliver it. The name “alternative electric suppliers” reflects that these
providers give consumers a choice (i.e., an alternative) about the upstream provider of their power; it has no relationship to renewable energy.
As the Court of Appeals correctly observed, Act 341 requires every provider in the marketplace to meet the capacity requirements set by the MPSC, and capacity is measured using both a “planning reserve margin requirement” and a “local clearing requirement.” In re Reliability Plans of Electric Utilities for 2017–2021, 325 Mich App 207, 224-225; 926 NW2d 584 (2018). To explain, the planning reserve margin requirement is the total amount of electricity that a given provider must make available to meet its customers’ demand (think quantity). The local clearing requirement is the amount of that electricity which the provider must produce or purchase locally (think location). Important to the question we decide here, these are not original concepts. Although the terms have slightly different meanings in different contexts, the body to whom the federal regulator (the Federal Energy Regulatory Commission) has delegated operational responsibility over the wholesale electricity markets affecting most of Michigan, the Midcontinent Independent System Operator (MISO), also uses these terms for its capacity planning.
While the Court of Appeals also correctly observed that the act requires each provider to meet the planning reserve margin requirement and the local clearing requirement as set by the MPSC, it held that “no provision of
In particular, the panel misread the statute’s requirements that the MPSC coordinate with the organizations that are responsible for federal regulation of the wholesale electricity market—in this case, MISO—to mean that the MPSC must impose a local clearing requirement in the very same methodological manner that MISO does. Id. at 226. MISO, a different regulatory body from the MPSC with a very different jurisdiction and mandate, imposes a local clearing requirement with reference to certain geographic zones. But Act 341 does not refer to or contemplate zones at all. Moreover, and confusingly, the panel did not say what the relevant “zone” is or might be under
The Legislature authorized the MPSC to set a planning reserve margin requirement and a local clearing requirement for each energy provider in the state, including alternative electric suppliers, and required each, in turn, to meet those capacity measurements individually or face the consequences set by statute. We reverse and remand to the Court of Appeals for further proceedings not inconsistent with this opinion.
I. FACTS AND PROCEDURAL HISTORY
A. ELECTRICITY MARKETS AND REGULATION
Background
Electricity is unique. First, it cannot be stored in very large quantities (yet). Second, for technical reasons implied by the laws of physics (not among the laws this Court interprets authoritatively), the supply of electricity must match demand in real time; otherwise, the electrical system is susceptible to massive and highly disruptive blackouts and brownouts, which can cascade across the state and the country. Third, much of everyday life depends on its reliable supply, from smartphone addiction to the operation of businesses to the defense of the nation. Given electricity’s distinct qualities and our dependence on its ready availability for virtually everything, state and federal governments regulate power markets carefully, and the regulatory regime is complex.
By way of relevant background, state governments regulate retail power markets, while the federal government regulates wholesale power markets—where electricity generators send power to those who will ultimately deliver it to consumers—and the transmission of electricity among states.
Given the importance of meeting demand, the federal government also regulates “capacity.” As noted above, capacity is the ability to satisfy demand for electricity
Michigan has four categories of electricity providers that sell to retail customers: (1) investor-owned utilities, commonly referred to, simply, as utilities (or public utilities); (2) municipally owned utilities (munis); (3) cooperative electric utilities (coops); and (4) alternative electric suppliers. The Legislature delegated regulatory authority to the MPSC to “regulate all rates, fares, fees, charges, services, rules, conditions of service, and all other matters pertaining to the formation, operation, or direction of public utilities.”
Evolving regulatory regimes
Historically, geography determined a consumer’s electricity provider. The customer base for early utilities, munis, and coops was located within the geographic areas each served. For practical reasons—the wires connecting providers and consumers only ran so far and could carry only so much electricity—a provider could sell electricity only
Producers, Inc v Midcontinent Indep Sys Operator, Inc, 166 FERC ¶ 61,159, at p 3 (2019). For this opinion, it is sufficient to understand that the regulatory goal is making sure demand will always be enough to meet supply. Electrical capacity is sometimes expressed intuitively by analogy to a shopping mall parking lot. Shopping malls typically build parking lots with far more space than is required on average days. But they do so to plan for the very unusual days (during the holiday shopping periods) when the demand for parking space spikes. But for such sound planning, malls could not accommodate peak demand for parking. The importance of a stable electrical supply makes planning for peak electricity demand essential. Thus, electricity providers offer capacity in the form of promises to supply and demonstrations that they have resources they can call upon to meet demand.
within its geographical boundary, and a consumer could not receive service from a provider outside that boundary. This was the noncompetitive era of electricity.
The energy shortages of the 1970s along with technological and infrastructure improvements over recent decades eventually led to policy changes toward increased competition in electricity markets in many parts of the country. Reflecting such dynamics, the Legislature, in 2000, passed the Customer Choice and Electricity Reliability Act, Public Acts 141 and 142 of 2000,
existing local infrastructure. Electricity sold by alternative electric suppliers may even be generated outside Michigan.4
While the MPSC regulates in-state retail energy markets in Michigan, the Federal Energy Regulatory Commission (FERC) regulates interstate wholesale energy and transmission markets under the Federal Power Act,
The FERC has described this complicated, shared responsibility as follows:
[T]he question of jurisdiction over resource adequacy is a complex matter that represents “the confluence of state-federal jurisdiction.” While we are cognizant of the traditional role of state and local entities in regulating resource adequacy, we are also aware of our responsibility under the [Federal
Power Act] to ensure the reliability of the system and that wholesale rates are just and reasonable. We will defer to state and local entities’ decisions when possible on resource adequacy matters, but in doing so we will not shirk our congressionally-mandated responsibilities. We find that the adequacy of resources can have a significant effect on wholesale rates and services and therefore is subject to Commission jurisdiction. [California Indep. Sys. Operator Corp., 119 FERC ¶ 61,076, at p 212 (2007) (citation omitted).]
In short, because capacity (resource adequacy) has wholesale as well as retail implications, both federal and state governments regulate it.
Since 1999, the FERC has granted regional institutions known as Regional Transmission Organizations the authority to oversee some aspects of energy markets within large regional areas in order to improve efficiency and grid reliability, eliminate opportunity for discriminatory transmission practices, improve market performance, and facilitate lighter direct federal regulation. Regional Transmission Organizations, 89 FERC ¶ 61,285, at p 3 (1999). Regional Transmission Organizations are independent bodies formed as
Federal capacity requirements within MISO
MISO has been the primary Regional Transmission Organization overseeing the wholesale electricity markets in the Midwest, including most of Michigan, since it was authorized by the FERC in 2001.7 Id. MISO’s capacity market includes resource adequacy planning for its wholesale electric market. In plain English, MISO oversees a market to ensure that the supply of electricity will be sufficient to satisfy unexpectedly high demand. It does so looking ahead for a period of one year, successively.
MISO has divided its geographical jurisdiction into 10 “local resource zones” to maximize efficiency in the different wholesale markets. See Figure 1 below.
Figure 1. Map of MISO’s United States Region, Separated by Zone.8
Michigan participates in two of MISO’s zones. Most of the Lower Peninsula is in
The federal capacity planning process—through MISO—works about like this: each annual planning year, MISO requires all energy providers within a given MISO zone, including alternative electric suppliers, to submit documentation of the electric output each provider expects to be able to reliably produce during the upcoming year. MISO uses this reported amount to regulate capacity. In connection with the same forecasting, MISO also sets what it calls a planning reserve margin requirement for each provider. Midcontinent Indep. Sys. Operator, Inc., 165 FERC ¶ 61,067, at p 2 (2018). MISO’s planning reserve margin requirement is largely, but not only, a quantity measure; it also includes a location requirement. That is, the planning reserve margin requirement requires each provider to have sufficient “Zonal Resource Credits” from within a given MISO zone. Put differently, to meet its planning reserve margin requirement, as required by MISO, a provider must demonstrate the availability of not only enough capacity, but enough local capacity.
A local element is an important part of capacity planning because when there are insufficient local resources available to meet demand, resources must come from afar. Given the constraints of the electrical grid in moving power large distances from state to state, distant resources can undermine reliability. See, e.g., Borenstein & Bushnell, Electricity Restructuring: Deregulation or Reregulation?, 23 Reg 46, 51 (2000). Thus, there is a connection between the efficient and reliable supply of electricity, on the one hand, and meeting demand at least in part through local resources, on the other hand, which is why efficiency still requires some geographically based planning.
At the risk of slight oversimplification (a risk worth running in this context), technological and infrastructural dynamics presented the opportunity for greater competition by making possible the upstream supply of electricity from providers beyond a local utility only up to a point. To some extent, though, the supply of electricity is still constrained by local and regional factors. There is thus a trade-off between promoting competition in the form of facilitating supply from alternative and potentially far-off sources and protecting reliability by ensuring that most demand is satisfied locally and regionally to avoid the congestion that threatens reliability.
To help strike that balance, MISO determines the amount of local energy required by a provider’s planning reserve margin requirement in part by imposing the local clearing requirement. The local clearing requirement establishes the total amount of capacity that must originate within a MISO zone to reduce the risk of blackouts. Midcontinent Indep. Sys. Operator, Inc., 165 FERC ¶ 61,067, at p 2 (2018). MISO determines its local clearing requirement first by calculating the amount of resources a zone’s grid could reasonably be expected to import during peak demand times. This provides an indication of the extent to
which congestion constraints limit the amount of out-of-zone resources that can be used to satisfy (peak) demand. The rest must therefore be supplied locally or zonally in order to meet that demand. Midcontinent Indep. Sys. Operator, Inc., 148 FERC ¶ 61,091, at p 2 (2014). Thus the local clearing requirement is a component of each provider’s planning reserve margin obligation, and MISO’s “Zonal Resource Credits” are used to verify satisfaction of the local clearing requirement.
Stay with us. There are three ways an electricity provider can accumulate the Zonal Resource Credits to satisfy MISO’s version of the local clearing requirement, but one is less attractive than the others. It can: (1) self-supply those in-zone resources (i.e., generate it locally); (2) contract with other providers within the zone (i.e., buy it locally); or, if it cannot do either of those, it can (3) participate in MISO’s single-year “Planning Resource Auction.” MISO’s Planning Resource Auction is an auction to set wholesale capacity prices MISO conducts for each planning year. The auction serves as a marketplace through which any registered provider can sell or purchase units of capacity (essentially, guarantees of an ability to call on resources to meet demand).
After the auction, MISO totals the amount of in-zone capacity the zone’s providers report through self-supply (option 1), in-zone contracting (option 2), and the auction (option 3). If MISO concludes that the total in-zone capacity cannot meet demand at the highest peak moments (i.e., cannot satisfy the local clearing requirement), MISO punishes those providers in the zone who relied on the auction for enough Zonal Resource Credits to meet their planning reserve margin requirement. MISO does so by raising the auction’s
clearing price to a “penalty rate.”10 The penalty rate thus increases prices on every provider that cannot meet its planning reserve margin requirement with local resources—that is, those that resorted to the auction. In other words, if MISO believes that too much electricity will be coming into a given zone from other zones thereby jeopardizing reliability, MISO makes it expensive for providers who are not producing or buying electricity within that zone to rely on the capacity auction. Midcontinent Indep. Sys. Operator, Inc., 162 FERC ¶ 61,176, at p 24 (2018).
Thus, for purposes of the wholesale power market overseen by MISO, every provider has individual capacity obligations that include requirements for total quantity (how much power) and location (where it comes from). And with respect to the latter, MISO’s planning reserve margin requirement requires each energy provider to produce or purchase in-zone capacity, or risk paying a steep price. MISO’s penalty rate is imposed on individual providers—individual providers must pay it, and each
B. MISO’S 2016 TARIFF AND PUBLIC ACT 341
The specific authority that Regional Transmission Organizations like MISO derive from the FERC is reflected in “tariffs.” The FERC must approve tariffs with respect to all terms and conditions of electrical service, rates charged (prices), schedules, contracts, and service agreements. Thus, when MISO seeks any change in its rate-making authority, it must apply for a new tariff with the FERC. The FERC either approves MISO’s tariff, thereby setting rates and other terms, or not.
In November 2016, MISO sought the FERC’s approval of a newly proposed three-year capacity auction to complement its single-year auction described above. MISO’s goal in devising a three-year auction was greater assurance of longer-term grid reliability (three years instead of one) in states with competitive retail markets. The idea was that the best way to plan for longer-term reliability was to make plans for a longer term. MISO would have allowed these states to permit electricity suppliers to participate in a three-year auction instead of the one-year auction. Midcontinent Indep. Sys. Operator, Inc., MISO Transmittal Letter to the FERC, sent November 1, 2016 (FERC Docket No. ER17-284), p 5, available at <https://perma.cc/7R8Q-5P6J>. MISO’s proposal also included giving these states an opportunity to implement a “prevailing state compensation mechanism,” which would allow the state, instead of MISO, to take responsibility over its own long-term resource adequacy planning. Id. at 24.
More than a month later, with bipartisan support in both chambers and—to complicate matters—while MISO’s tariff request for a three-year auction plan was pending before the FERC, the Michigan Legislature passed Public Act 341 to promote and ensure the long-term reliability of Michigan’s electric grid. 2016 PA 341; 2016 Senate Journal
2137; 2016 House Journal 2502. The act imposes resource adequacy requirements on Michigan’s electricity providers in the retail market and enforced by the MPSC.11
Because the Legislature passed Act 341 while MISO’s application for the multi-year auction was pending before the FERC, the act recognized that the MPSC’s specific charge would depend on whether the FERC approved MISO’s pending tariff application. If the FERC approved it, then the MPSC could decide whether to allow Michigan electricity suppliers to have the option to participate in the three-year MISO auction, leaving longer-term planning to MISO, or, instead, whether the MPSC would implement a prevailing state compensation mechanism that would obviate the need for MISO’s planning.
The FERC rejected MISO’s tariff.12 Midcontinent Indep. Sys. Operator, Inc., 158 FERC ¶ 61,128, at p 4 (2017). That triggered the MPSC’s obligation under
To meet these new legislative mandates, the MPSC held technical conferences to engage the various electric providers collaboratively about how each would meet the requirements, as the methodology and math in this area can be challenging. In re Reliability Plans, order of the Public Service Commission, entered September 15, 2017
(Case No. U-18197), pp 2-4. The MPSC also accepted comments from stakeholders on issues related to timing, methodology, and the local clearing requirement in particular. Id.
Act 341 defined the local clearing requirement and the planning reserve margin requirement for state-law purposes as follows:
“Local clearing requirement” means the amount of capacity resources required to be in the local resource zone in which the electric provider’s demand is served to ensure reliability in that zone as determined by the appropriate independent system operator for the local resource zone in which the electric provider’s demand is served and by the commission under subsection (8).
“Planning reserve margin requirement” means the amount of capacity equal to the forecasted coincident peak demand that occurs when the appropriate independent system operator footprint peak demand occurs plus a reserve margin that meets an acceptable loss of load expectation as set by the commission or the appropriate independent system operator under subsection (8).
Following the MPSC’s technical conferences—which included consultation with
The MPSC concluded that
as set by the MPSC for four years forward. Id. at 47. The MPSC put off implementation of a new local clearing requirement for planning years 2018 through 2021 so that it could gather more information about how to assess it through a formal hearing process. Id.14
The MPSC designed this phased-in approach to mitigate any burden the local clearing requirement placed on alternative electric suppliers in particular. Id. at 22-23.
C. APPEAL OF THE MPSC’S ORDER
The Association of Businesses Advocating Tariff Equity (ABATE) and Energy Michigan, Inc., each appealed the MPSC’s September 15, 2017 order. They argued that the MPSC exceeded its authority by determining that it could impose a forward-looking local clearing requirement on individual alternative electric suppliers. The Court of Appeals consolidated the cases and reversed the MPSC’s decision. In re Reliability Plans, 325 Mich App at 210 & n 3. The panel concluded that
The panel further concluded that
Consumers Energy Company and the MPSC sought leave to appeal. We directed the Clerk to schedule oral argument on the applications, addressing “whether the Court of Appeals erred in holding that 2016 PA 341 does not authorize the Michigan Public Service Commission to impose a local clearing requirement on individual alternative electric suppliers.” In re Reliability Plans of Electric Utilities for 2017–2021, 504 Mich 894, 894 (2019); In re Reliability Plans of Electric Utilities for 2017–2021, 504 Mich 895, 895 (2019).
II. STANDARD OF REVIEW
We review whether the MPSC exceeded its scope of authority, a question of law, de novo. Consumers Power Co, 460 Mich at 157. We also review de novo questions of statutory interpretation. Mich Ass’n of Home Builders v Troy, 504 Mich 204, 212; 934 NW2d 713 (2019). Reviewing an issue de novo means that we review the legal issue independently, without deference to the lower court. People v Bruner, 501 Mich 220, 226; 912 NW2d 514 (2018).
III. ANALYSIS
ACT 341 AUTHORIZES THE MPSC TO IMPOSE A LOCAL CLEARING REQUIREMENT ON ALL ENERGY PROVIDERS, INCLUDING ALTERNATIVE ELECTRIC SUPPLIERS, INDIVIDUALLY
Final decisions, rulings, and orders of the MPSC must be authorized by law.
What authority a statute gives an agency is a matter of statutory interpretation. The primary goal of statutory interpretation is to give effect to the Legislature’s intent. Bank of America, NA v First American Title Ins Co, 499 Mich 74, 85; 878 NW2d 816 (2016). Statutory interpretation begins with examining the plain language of the statute. Id. When that language is clear and unambiguous, no further judicial construction is required or permitted. Here, the parties do not dispute that Act 341 delegated authority to the MPSC to plan for energy capacity in the retail market by setting and enforcing capacity obligations for all energy providers in the state. They disagree only about one particular aspect of that authority: whether the MPSC can impose one of those obligations, a local clearing requirement, on alternative electric suppliers individually.
The Court of Appeals correctly concluded that Subsection (8)(b) of the act requires each electric provider to show that it could meet the capacity obligations set by the MPSC,
In re Reliability Plans, 325 Mich App at 224, and that those capacity obligations include both a planning reserve margin requirement and a local clearing requirement, id. at 226. The statute also clearly gives the MPSC enforcement tools to use if a provider fails to show that it can meet these MPSC-set capacity obligations. For electric utilities, the MPSC has full jurisdiction and control, so it may use one of its preexisting regulatory tools.
Yet the Court of Appeals held that the MPSC could not impose a local clearing requirement on alternative electric suppliers individually. Id. at 224-225. The panel asserted that “reading
While the panel held
only that the zonal requirement meant the MPSC could not impose any location requirement on alternative electric suppliers individually, if the MPSC is limited to determining a local clearing requirement only for a zone, no individual provider would have to produce or purchase any set amount of locally produced electricity.18
This holding reflects a number of missteps. First, it read into the statutory text a requirement that the MPSC impose Michigan’s local clearing requirement using the same methodology MISO does. That misreading moreover misunderstood how MISO’s local clearing requirement really functions. MISO’s zonal local clearing requirement is only a tool for setting individual provider in-zone capacity requirements in another capacity measurement—Zonal Resource Credits. In addition,
A. THE COURT OF APPEALS MISREAD THE TEXT OF MCL 460.6w
The Court of Appeals justified its conclusion that the MPSC could only set a local clearing requirement “on a zonal basis” based on its “review of the entire statute.” In re Reliability Plans, 325 Mich App at 225. But that conclusion was not rooted in the statute’s text.
As explained,
Perhaps given this text, the appellees do not challenge the MPSC’s authority to impose a planning reserve margin requirement on providers individually; that is what the statute says. But despite the identical language describing the MPSC’s authority for determining both elements of capacity obligation, the Court of Appeals decided there was a difference based on its “review of the entire statute.” In re Reliability Plans, 325 Mich App at 225. That contextual reading, according to the panel, “suggests that the MPSC is obligated to apply the local clearing requirement in a manner consistent with MISO.” Id. We see no contextual reason to ignore the statute’s clear language. The parallel treatment of the MPSC’s authority as to both capacity obligations is meaningful—the MPSC can set a planning reserve margin requirement for each provider individually, and it can do the same for a local clearing requirement.
No less, we read the contextual language differently too. The statute requires cooperation with MISO, not adopting MISO’s methodology for one capacity obligation only.19
On its face, the statute requires the MPSC to seek the appropriate independent system operator’s assistance when it sets a local clearing requirement and planning reserve margin requirement:
In order to determine the capacity obligations, request that the appropriate independent system operator provide technical assistance in determining the local clearing requirement and planning reserve margin requirement. If the appropriate independent system operator declines, or has not made a determination by October 1 of that year, the commission shall set any required local clearing requirement and planning reserve margin requirement, consistent with federal reliability requirements. [
MCL 460.6w(8)(c) .]
The statute’s emphasis on cooperation makes sense: state retail capacity planning should be coordinated with federal interstate wholesale capacity planning.
The Court of Appeals read the requirement that the capacity obligations were to be “consistent with federal reliability requirements” somehow to mean that the MPSC must “observe MISO’s general practice of imposing local clearing requirements on a zonal, not an individual, basis.” In re Reliability Plans, 325 Mich App at 226. But the text of Subsection 8(c) does not support that reading whatsoever.
The statute gives the MPSC clear instructions: it must seek the technical assistance of the independent system operator (MISO) in determining the capacity obligations by October 1. If the independent system operator (MISO) declines to provide that assistance, or does not provide it
In fact, the MPSC sought and received technical assistance from MISO in determining a planning reserve margin requirement and a local clearing requirement before October 1, satisfying Subsection (8)(c). See In re Reliability Plans, order of the Public Service Commission, entered September 15, 2017 (Case No. U-18197), pp 30, 35, 48-49. The language of Subsection (8)(c) providing for what the MPSC must do in the event it lacked MISO’s assistance by October 1 was therefore not relevant here.
But even if MISO had not provided that assistance (or had not done so by October 1) and the MPSC was therefore to set the capacity measurements “consistent with federal reliability requirements,” still the Court of Appeals’ interpretation of “consistent with” was flawed. “Consistent” does not mean “exactly the same as.” Rather, it means “agreeing or accordant; compatible; not self-contradictory[.]” See Random House Webster’s College Dictionary (2d ed, 2003); see also Merriam-Webster’s Collegiate Dictionary (11th ed) (“[M]arked by agreement : COMPATIBLE – usu. used with with[.]”). As MISO itself explained, the MPSC’s local clearing requirement was consistent with its resource adequacy planning and the FERC’s precedent to defer to states that choose different but complementary adequacy requirements.
Additionally, the MPSC’s authority to assess a penalty—a “capacity charge”—on alternative electric suppliers that do not meet their capacity obligations also requires coordination with the federal resource capacity process.
A capacity charge shall not be assessed for any portion of capacity obligations for each planning year for which an alternative electric supplier can demonstrate that it can meet its capacity obligations through owned or contractual rights to any resource that the appropriate independent system operator allows to meet the capacity obligation of the electric provider. The preceding sentence shall not be applied in any way that conflicts with a federal resource adequacy tariff, when applicable. [
MCL 460.6w(6) ].
The statute requires that if there is a federal resource adequacy process, the MPSC’s assessment of a capacity charge cannot “conflict[] with” it. MISO has consistently described the MPSC’s proposed plan as complementary to its single-year capacity auction—the federal resource adequacy process. See, e.g., Brief for MISO as Amicus Curiae (November 5, 2018) (Docket No. 158305) at 2. The requirement that a capacity charge must also coordinate with, and not conflict with, MISO’s planning process does not require the MPSC to duplicate MISO’s zonal local clearing requirement.
“Conflict” is defined as “to be contradictory, at variance, or in opposition; clash; disagree” or “incompatibility or interference, as of one idea, event, or activity with another[.]” Random House Webster’s College
Webster’s Collegiate Dictionary (11th ed) (defining “conflict,” in part, as “to show antagonism or irreconcilability : fail to be in agreement or accord
B. THE COURT OF APPEALS MISUNDERSTOOD MISO’S CAPACITY PLANNING
The Court of Appeals made another mistake in determining that the MPSC was only permitted to impose a zonal local clearing requirement like MISO does. The panel’s interpretation misunderstood the differences between the wholesale and retail capacity markets, and especially MISO’s capacity planning process and the local clearing requirement’s function in that process.
As explained, MISO’s authority is limited to that approved by the FERC, which regulates the interstate power and capacity wholesale and transmission electricity markets. Electric Power Supply, 577 US at ___; 136 S Ct at 773.20
Any rate, rule, or practice the
FERC approves for MISO’s implementation must affect interstate wholesale rates but may not affect retail electricity sales. Id. at 774-775. The states have regulatory authority over electricity sales that stay within state boundaries, especially retail sales. Id. at 775. While MISO oversees the wholesale markets and the MPSC oversees the retail markets, the two regulatory bodies work cooperatively to ensure grid reliability and work together on capacity planning in particular, relevant to both.
The Legislature enacted
LLC, 578 US ___; 136 S Ct 1288; 194 L Ed 2d 414 (2016), which held that a state’s program to subsidize new power generation was preempted by federal law. The Court of Appeals cited legislative history to support its reading of the statute, finding meaning in the iterations of the text before the version that passed into law. In re Reliability Plans, 325 Mich App at 228-232. The Michigan Chamber of Commerce’s brief as amicus curiae explaining that the changes in bill drafts instead reflected the Legislature’s shifting view of its authority given these United States Supreme Court opinions persuasively rebuts the panel’s assumption about the legislative history. See Brief for the Michigan Chamber of Commerce as Amicus Curiae (October 26, 2018) (Docket No. 158305) at 5.
The Court of Appeals’ view that the MPSC must impose its local clearing requirement zonally because MISO uses a zonal measurement provides no hints about the economic tools the MPSC could employ to ensure that each Michigan electricity provider contributed to some zonal local clearing requirement or how the MPSC could restructure market costs—as MISO does—to penalize the providers responsible for years in which they do not meet it. In particular, the Court of Appeals did not make clear what the relevant “zone” would be in its interpretation of the local clearing requirement. If it meant that the MPSC could only impose a local clearing requirement that maps exactly onto MISO’s zonal measurement, that interpretation makes little sense given MISO’s zone geography and the MPSC’s authority. MISO oversees 10 regional zones that span 15 states, and its boundaries are not drawn according to state lines. (See Figure 1 of this opinion again). MISO’s Zone 1, for instance, includes all of North Dakota and parts of Montana, South Dakota, Minnesota, Wisconsin, Iowa, and Illinois. All providers in Zone 2—which includes Michigan’s Upper Peninsula and most of Wisconsin—and all in Zone 7—which includes most of Michigan’s Lower Peninsula only—meet MISO’s capacity measurements for the zone in which they participate. The MPSC, in contrast, is charged with ensuring the reliability of Michigan’s grid for retail consumers throughout the state.
The MPSC lacks any authority over Wisconsin providers, which it would need to impose a local clearing requirement over MISO Zone 2. And while the MPSC has authority over the southwest corner of the state that participates in a zone regulated by PJM Interconnection, a different Regional Transmission Organization, the MPSC similarly has no authority over those parts of Delaware, the District of Columbia, Illinois, Indiana,
Kentucky, Maryland, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, and West Virginia overseen by that system operator.
A contextual understanding of the
IV. CONCLUSION
In requiring that each provider, including alternative electric suppliers, meet an individual local clearing requirement, the MPSC did what the statute required of it to ensure reliability of retail electric markets in Michigan. We reverse the judgment of the Court of Appeals and remand to the Court of Appeals for further proceedings consistent with this opinion, including addressing whether the MPSC’s order complied with the Administrative Procedures Act.
Bridget M. McCormack
Stephen J. Markman
Brian K. Zahra
David F. Viviano
Richard H. Bernstein
Elizabeth T. Clement
Megan K. Cavanagh
