JACQUELINE GRACE GORMLEY et al. v. EFRAIN DIEGO GONZALEZ et al.
C093201
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA THIRD APPELLATE DISTRICT (Placer)
Filed 10/12/22
CERTIFIED FOR PUBLICATION
APPEAL from a judgment of the Superior Court of Placer County, Charles Wachob, Judge. Affirmed.
The Bankruptcy Group, Stephan M. Brown and Daniel J. Griffin for Defendants and Appellants.
Wilcoxen Callaham and Michelle C. Jenni for Plaintiffs and Respondents.
FACTUAL AND PROCEDURAL BACKGROUND
We have been provided with little information about the underlying lawsuits.3 We know there are 20 separate lawsuits; we know Plaintiffs are former patients of
As relevant here, we also know the parties entered into a global settlement agreement and general release (the Settlement Agreement) as to all 20 lawsuits. Section 3.1 of the Settlement Agreement provides the following:
“Defendants hereby agree to globally pay all Plaintiffs . . . the sum of Five Hundred . . . Seventy-Five Thousand Dollars ($575,000.00) . . . . Payment of the settlement shall be made as follows: (1) Two Hundred Fifty Thousand Dollars ($250,000) payment shall be delivered to [Plaintiffs’ law firm] . . . on or before April 30, 2019; and (2) The balance of Three Hundred Twenty-Five Thousand Dollars ($325,000) shall . . . be delivered . . . on or before July 31, 2019. Plaintiffs shall be solely responsible for allocating the settlement proceeds between them. Any portion of the aforementioned payments not paid in full by the deadlines set forth above would be assessed liquidated damages in the amount of Fifty Thousand Dollars ($50,000) per month, prorated at One Thousand Six Hundred Forty-Four Dollars ($1,644) per day until the balance is paid in full, with a cap not to exceed One Million Five Hundred Thousand Dollars ($1,500,000).” (Italics added.)
Once payment was made in full, Plaintiffs would dismiss the lawsuits with prejudice.
Defendants and their counsel signed the Settlement Agreement on March 7, 2019. Most, but not all, of the Plaintiffs signed the Settlement Agreement in March and early April of 2019, but it was not fully executed when the first payment became due on April 30, 2019. The parties thus agreed “that the first payment . . . would not be due until after receipt of a fully executed Agreement.” The last Plaintiff signed the Settlement Agreement on June 24, 2019. Thereafter, despite the fact that the Settlement Agreement was fully executed, Defendants made no payments.
Plaintiffs then filed a motion asking the court to determine the validity of the liquidated damages provision and the amount of liquidated damages, and to enter judgment against Defendants accordingly. Plaintiffs argued the liquidated damages provision was reasonable under the circumstances and thus valid pursuant to
In opposition to the motion, Defendants argued the liquidated damages provision was unenforceable under
DISCUSSION
I. The Law on Liquidated Damages
“The term ‘liquidated damages’ is used to indicate an amount of compensation to be paid in the event of a breach of contract, the sum of which is fixed and certain by agreement, and which may not ordinarily be modified or altered when damages actually result from nonperformance of the contract.” [Citation]. “Liquidated damages constitute a sum which a contracting party agrees to pay for breach of some contractual obligation.” (McGuire v. More-Gas Investments, LLC (2013) 220 Cal.App.4th 512, 521.)
In 1977, the Legislature adopted without change a California Law Revision Commission (the Commission) recommendation that repealed
As amended,
For nonconsumer contracts like the Settlement Agreement in this case, however, subdivision (b) of
In explaining the amendment, the Commission stated, “This new statutory provision would . . . reverse the basic disapproval of liquidated damages provisions expressed in
2. Analysis
Whether a liquidated damages provision is invalid under
We note that, in a footnote in their opening brief, Defendants contend this declaration from Plaintiffs’ counsel is “problematic” because, among other reasons, it contains parole evidence that contradicts the terms of the Settlement Agreement, and the trial court should thus have “disregarded” it. In their reply brief, they complain it also contains inadmissible hearsay. Because Defendants did not raise any objection to the declaration in the trial court, they have waived their right to object on appeal. (See
On appeal, Defendants rely primarily on two cases (neither of which they cited below) involving the enforceability of a liquidated damages provision in a settlement agreement: Greentree Financial Group, Inc. v. Execute Sports, Inc. (2008) 163 Cal.App.4th 495 (Greentree), and Vitatech Internat., Inc. v. Sporn (2017) 16 Cal.App.5th 796 (Vitatech). Because they are so central to Defendants’ argument, we discuss both cases in some detail.
The plaintiff in Greentree sued the defendant for breach of contract, alleging it failed to pay $45,000 due under the contract. On the day of trial, the parties settled the case by executing a stipulation for entry of judgment. The stipulation provided the defendant would pay the plaintiff $20,000 in two installments of $15,000 and $5,000, and if the defendant defaulted on either installment, the plaintiff would be entitled to have judgment entered for the amount prayed for in the complaint, plus interest, attorney fees and costs, less any amounts already paid. (Greentree, supra, 163 Cal.App.4th at p. 498.) The defendant defaulted on the first payment, and the plaintiff asked the trial court to enter judgment pursuant to the stipulation. The trial court entered judgment in the amount of $61,232.50, consisting of the $45,000 prayed for in the complaint, plus $13,912.50 in prejudgment interest, $2,000 in attorney fees, and $320 in costs. (Ibid.) The defendant appealed, arguing a judgment of $61,232.50 for failure to make a $15,000 payment constitutes enforcement of an illegal penalty, and the appellate court agreed. (Id. at pp. 498-501.)
Vitatech is similar. There, the plaintiff entered into a contract with the defendant to manufacture certain products. When the defendant failed to pay for those products, the plaintiff sued it for breach of contract, and sought approximately $166,000 in damages. The parties ultimately agreed to settle the lawsuit on the following terms: the defendant would pay $75,000 on or before June 5, 2015, and if it failed to do so, judgment would be entered against it in the amount prayed for in the complaint. (Vitatech, supra,
The court noted that although the “stipulation for entry of judgment does not use the phrase liquidated damages, . . . its legal effect is the same as a liquidated damages provision” because it “predetermines the amount of damages [the plaintiff] is entitled to receive if [the defendant] breached the stipulation by failing to timely pay the settlement amount.” (Vitatech, supra, 16 Cal.App.5th at p. 810.) Citing its earlier decision in Greentree, the court held the judgment was void because there was no reasonable relationship between the damages that could have been anticipated based on the defendant‘s failure to pay the $75,000 settlement amount when due and the $303,000 stipulated judgment. (Vitatech, at p. 808.) In essence, the court found the stipulation imposed a late fee that was four times the amount of the payment owed, and a late fee in such a high amount constituted illegal liquidated damages as a matter of law. The court remanded to the trial court with directions to reduce the judgment to $75,000. (Id. at p. 815.)
Defendants argue the Settlement Agreement in this case is similar to the settlement agreements in Greentree and Vitatech and must be invalidated for the same reasons. According to Defendants, the Settlement Agreement imposes liquidated damages for the failure to pay money at a rate that is nearly three times the amount owed, which is “absurdly usurious” and is invalid pursuant to
Here, the trial court considered the fact that the “settlement was negotiated with the assistance of counsel and after numerous drafts were exchanged between the parties,” and the liquidated damages provision in particular involved “significant negotiations.” In other words, these were parties with relatively equal bargaining power who were
The trial court also considered other circumstances that existed at the time the Settlement Agreement was made. For example, it noted that Plaintiffs understood they might not be able to collect anything from Defendants if they went to trial, because Defendants only had insurance for six of the 20 claims, and because Defendants’ burning limits insurance policy meant that costs and fees incurred defending the lawsuits would reduce the insurance money available to pay Plaintiffs (indeed, defense costs would even reduce the amount of insurance money available to pay any settlement). Plaintiffs thus agreed to accept a significantly reduced settlement amount ($575,000) in exchange for assurances that Defendants would be able to pay that reduced amount quickly. The liquidated damages provision was negotiated in order to incentivize prompt payment, and damages were capped at $1.5 million, which is the amount the parties estimated Plaintiffs would have recovered at trial (and we note the cap was not reached). Again, because courts are directed to consider ”All the circumstances existing at the time of the making of the contract,” (Cal. Law Revision Com. com., Deering‘s Ann. Civ. Code (2005 Ed.) foll. § 1671, p. 393, italics added), we find it was appropriate for the trial court to consider these circumstances, and all of them support its finding that Defendants failed to meet their burden of establishing the liquidated damages provision was unreasonable.
Defendants suggest that the amount Plaintiffs were estimated to recover if their lawsuits had proceeded to trial is irrelevant to the analysis under
Although the facts are different, Creditors Adjustment Bureau, Inc. v. Imani (2022) 82 Cal.App.5th 131 came to a similar conclusion. There, the plaintiff sued the defendant for breach of a commercial lease, and the parties acknowledged the amount due under the lease was $251,200.13. On the eve of trial, the parties entered into a stipulation for entry of judgment that provided the defendant (who was pro. per.) would pay $30,000 in 24 monthly installments, and if he defaulted, judgment would be entered in the full amount due under the lease. (Id. at p. 134.) The defendant defaulted, and judgment was entered against him for $251,200.13. He thereafter filed a motion to vacate the judgment, arguing it was void because it effectively imposed liquidated damages in an amount that bore no reasonable relationship to the damages the parties could have anticipated would be caused by his failure to pay the settlement amount. (Id. at pp. 134-135.) The appellate court disagreed. Among other things, it noted, “We cannot isolate the relevant breach of contract as only the breach of settlement agreement and excluding the underlying contract.” (Id. at p. 136.) We agree. When evaluating the reasonableness of the liquidated damages provision in this case, we cannot isolate only the breach of the Settlement Agreement and ignore the underlying medical malpractice lawsuits or the parties’ estimate that, had Plaintiffs proceeded to trial on those lawsuits they would have recovered $1.5 million. Again, the Legislature has directed courts to consider “all” circumstances when considering whether a liquidated damages provision is unreasonable, and when the liquidated damages provision is part of
One final note. Greentree and Vitatech both acknowledge that
We are, of course, bound by Ridgley, but Ridgley is distinguishable from this case for two reasons. First, Ridgley did not consider or address the Commission‘s instruction that ”All circumstances existing at the time of the making of a contract” should be considered when determining whether a liquidated damages provision in a nonconsumer contract is unreasonable. (Cal. Law Revision Com. com., Deering‘s Ann. Civ. Code (2005 Ed.) foll. § 1671, p. 393, italics added.) “It is axiomatic that cases are not authority for propositions not considered.” (People v. Ault (2004) 33 Cal.4th 1250, 1268, fn. 10.)
Second, the facts in Ridgley are different than the facts here and it is “axiomatic” that a case‘s holding “is ‘informed and limited by the fact[s]’ of the case in which it is articulated.” (Covenant Care, Inc. v. Superior Court (2004) 32 Cal.4th 771, 790, fn. 11.) Ridgley involved a late charge in a loan agreement that was triggered when one payment was late. This case, in contrast, involves an agreement to settle 20 medical malpractice lawsuits for a steep discount, with correspondingly steep liquidated damages imposed if the settlement payments are not made. The liquidated damages provision was actively negotiated and approved by counsel, and the parties expressly acknowledged the court retained jurisdiction to enforce the Settlement Agreement pursuant to
We find the trial court in this case properly considered all of the circumstances existing at the time the Settlement Agreement was negotiated, and it concluded Defendants failed to meet their burden of establishing the liquidated damages provision was unreasonable under the circumstances existing at the time the contract was made. We agree with the trial court. To quote our colleagues in Creditors Adjustment Bureau, ” ‘The purpose of the law of contracts is to protect the reasonable expectations of the parties . . . . There is . . . a price to be paid for breach of contract.’ [Citation.] Here, we protect the reasonable expectations of the parties. And there is still a price to be paid for breach of contract.” (Creditors Adjustment Bureau, Inc. v. Imani, supra, 82 Cal.App.5th at p. 133.) So, too, in this case. We find nothing unreasonable about holding Defendants to the price they agreed to pay for failing to keep their promise.
DISPOSITION
The judgment is affirmed and Plaintiffs shall recover their costs on appeal. (Cal. Rules of Court, rule 8.278(a)(1), (2).)
/s/
EARL, J.
I concur:
/s/
ROBIE, Acting P. J.
I would affirm the judgment because defendants have not demonstrated the trial court erred in concluding they did not meet their burden to establish the liquidated damages provision was “unreasonable under the circumstances existing at the time the contract was made.” (
/s/
RENNER, J.
