Opinion
Introduction
Plaintiff sued defendant for breach of contract, seeking a sum certain. Before trial, the parties agreed to settle the case for less than half the amount sought by the complaint, with defendant making installment payments. The terms of the settlement agreement provided that if defendant failed to make a payment, plaintiff could file a stipulation for entry of judgment, with the amount of the judgment being the entire amount sought in the complaint, as well as prejudgment interest, attorney fees, and costs. Defendant failed to make the first payment, and the trial court entered judgment pursuant to the terms of the parties’ stipulation for entry of judgment.
Under consistent authority, the judgment constitutes an unenforceable penalty because it bears no reasonable relationship to the range of actual damages the parties could have anticipated would flow from a breach of their settlement agreement. We publish this opinion to reaffirm that the rule set forth in
Sybron Corp. v. Clark Hosp. Supply Corp.
(1978)
Statement of Facts and Procedural History
On April 11, 2006, Greentree Financial Group, Inc. (Greentree), sued Execute Sports, Inc. (ESI), for breach of contract. The complaint alleged ESI had failed to pay $45,000 due under the contract in consideration of financial advisory services provided by Greentree. ESI answered the complaint, asserting affirmative defenses, including, but not limited to, failure to mitigate and prior material breach of the contract by Greentree.
On the day set for trial, the parties filed a notice of settlement with the court. The settlement was memorialized in a stipulation for entry of judgment (the stipulation). The stipulation provided that ESI would pay Greentree a total of $20,000, in two installments. If ESI defaulted on either one of its installment payments, Greentree would be entitled to “immediately have Judgment entered against [ESI] for all amounts prayed as set forth in [Greentree]’s Complaint in the above-entitled action, including interest, attorney fees and costs, less any amounts already paid by [ESI] . . . .”
ESI defaulted on the first installment payment of $15,000. On July 19, 2007, correctly anticipating Greentree would seek entry of judgment, ESI filed an opposition to entry of an excessive judgment. On the same day, Greentree submitted to the court a proposed judgment for $61,232.50, consisting of $45,000 in damages, $13,912.50 in prejudgment interest, $2,000 in attorney fees, and $320 in costs. Greentree also submitted a declaration from its attorney of record, attaching a copy of the stipulation and explaining the nature of ESI’s default. 1 Judgment in the amount of $61,232.50 was entered on August 1, 2007. ESI timely appealed from the judgment.
Discussion
ESI contends the $61,232.50 judgment, entered after ESI failed to make the $15,000 installment payment under the terms of the stipulation,
In determining whether the terms of the stipulation amount to an illegal penalty, we start with the language of Civil Code section 1671, subdivision (b): “[A] provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made.” In interpreting this statute, our Supreme Court has noted: “A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671 [, subdivision ](b), if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach. The amount set as liquidated damages ‘must represent the result of a reasonable endeavor by the parties to estimate a fair average compensation for any loss that may be sustained.’ [Citation.] In the absence of such relationship, a contractual clause purporting to predetermine damages ‘must be construed as a penalty.’ ”
(Ridgley
v.
Topa Thrift & Loan Assn.
(1998)
Greentree argues the amount set forth in the stipulation was reasonably related to the damages it suffered as a result of ESI’s breach of the underlying contract. But the breach we are analyzing is the breach of the
stipulation,
not the breach of the
underlying contract.
(See
Sybron, supra,
Greentree and ESI did not attempt to anticipate the damages that might flow from a breach of the stipulation. Rather, they simply selected the amount Greentree had claimed as damages in the underlying lawsuit, plus prejudgment interest, attorney fees, and costs. But the appellate record contains nothing showing Greentree’s chances of complete success on the merits of its
Also, the $61,232.50 amount in the judgment bears no reasonable relationship to the range of actual damages the parties could have anticipated from a breach of the stipulation to settle the dispute for $20,000. “[Djamages for the withholding of money are easily determinable — i.e., interest at prevailing rates . . . .” (Sybron, supra, 16 Cal.App.3d at p. 900.) The amount of the judgment, however, was more than triple the amount for which the parties agreed to settle the case.
In a slightly different context, late payment fees on loans are designed to encourage the borrower to make timely payments, and to compensate the lender “for its administrative expenses and the cost of money wrongfully withheld.”
(Garrett v. Coast & Southern Fed. Sav. & Loan Assn.
(1973)
The facts of
Sybron
are similar to those of the present case. A seller of hospital beds sued the buyers for almost $144,000; the buyers counterclaimed, arguing the beds were defective.
(Sybron, supra,
On appeal, the court determined the stipulated judgment constituted an unenforceable penalty. The appellate court acknowledged, “[c]ertainly there is paperwork and time involved in the collection of an installment obligation. The creditor is entitled to bargain that if the installment debtor imposes upon the creditor by a continuing course of dilatory payment the creditor may accelerate and collect the entire obligation, plus a reasonable amount to compensate for delay.”
(Sybron, supra,
The same is true here. The stipulated judgment of $61,232.50 would result in a penalty assessment of approximately $40,000 more than the total $20,000 due under the stipulation. A late payment penalty fee of approximately $40,000 bears no reasonable relationship to any actual damages that might flow from ESI’s failure to make the first installment payment. (See
Ridgley, supra,
Aside from trying to distinguish the consistent authority supporting reversal, Greentree has failed to cite any statutory or case authority supporting its view. Greentree cannot cite any such authority because it simply does not exist.
With regard to the disposition of this case, a question arises as to the severability of the penalty provision from the remainder of the stipulation. At oral argument, both parties agreed the provision was severable. We need not reach the issue of severability, but we do note that Civil Code section 1671 addresses the validity of a liquidated damages
provision,
rather than the validity of a
contract
containing such a provision. None of the cases we have cited,
ante,
directly addresses severability, but their dispositions either remove the penalty provision from the judgment
(Sybron, supra,
The stipulation does not contain any provision for an award of attorney fees or prejudgment interest, although the judgment included $2,000 in attorney fees and $13,912.50 in prejudgment interest. The $20,000 settlement sum in the stipulation is unallocated, and may or may not have included Greentree’s claimed attorney fees and prejudgment interest. We find no basis for awarding Greentree its attorney fees and prejudgment interest in addition to the stipulated settlement sum. Greentree is entitled to recover its costs in the trial court (Code Civ. Proc., § 1032), and postjudgment interest.
The judgment is reversed and the matter is remanded to the trial court with directions to reduce the judgment against ESI to $20,000, plus postjudgment interest and costs. In the interests of justice, neither party shall recover costs on appeal.
On May 28, 2008, the opinion was modified to read as printed above.
Notes
On our own motion, we augment the record on appeal with the declaration of Alan L. Brodkin in support of entry of judgment, filed August 1, 2007, in Greentree Financial Group, Inc. v. Execute Sports, Inc. (Super. Ct. Orange County, 2007, No. 06CC04986). (Cal. Rules of Court, rule 8.155(a)(1)(A).)
Sybron
was decided under former section 1671 of the Civil Code. (See
Sybron, supra,
