Eastern Steel Const. v. International FidelityEastern Steel Const. v. International Fidelity
Appeal from the Judgment Entered July 23, 2020
In the Court of Common Pleas of Centre County
Civil Division at No.: 2011-3233
Appeal from the Judgment Entered July 23, 2020
In the Court of Common Pleas of Centre County
Civil Division at No.: 2011-3233
BEFORE: LAZARUS, J., STABILE, J., and MUSMANNO, J.
OPINION BY STABILE, J.:
In this surеtyship action, Appellant/Cross-Appellee, Eastern Steel Constructors, Inc. (“Eastern” or “Claimant“), and Appellee/Cross-Appellant, International Fidelity Insurance Company (“IFIC“), appeal and cross-appeal, respectively, from the July 23, 2020 judgment entered in the Court of Common Pleas of Centre County (“trial court“). Following the prime contractor Ionadi Corporation‘s (“Ionadi“) failure to pay Eastern for work Eastern performed under a subcontract, Eastern sought to recover the outstanding payments from IFIC, Ionadi‘s surety. Eastern secured an arbitration award against Ionadi
I. BACKGROUND
In 2008, the Pennsylvania State University (“PSU“) entered into a prime contract (the “Construction Contract“) with Ionadi for the erection of steel on a project for the construction of the Millennium Science Center Complex at PSU‘s University Park Campus in Centre County, Pennsylvania (the “Project“).
On October 29, 2008, IFIC issued a $10,125,000.00 payment bond (“Payment Bond“) for Ionadi in connection with the Project.1 To do so, IFIC utilized The American Institute of Architects (“AIA“) standard form AIA Document A312, which the parties modified to suit their needs. In particular, the Payment Bond provided:
1. The Contractor2 and the Surety3, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner4 to pay for labor, materials and equipment furnished for use in the performance of the Construction Contract5, which is incorporated herein by reference.
2. With respect to the Owner, the obligatiоn shall be null and void if the Contractor:
2.1 Promptly makes payment, directly or indirectly, for all sums due Claimants . . . .
3. With respect to Claimants, this obligation shall be null and void if the Contractor promptly makes payment, directly or indirectly, for all sums due.
4. The Surety shall have no obligation to Claimants under this Bond until:
4.1 Claimants who are employed by or have a direct contract with the Contractor have given notice to the Surety (at the address described in Paragraph 12) and sent
a copy, or notice thereof, to the Owner, stating that a claim is being made under this Bond and, with substantial accuracy, the amount of the claim.
. . . .
6. When the Claimant has satisfied the conditions of Section 4, the Surety shall
promptly and at the Surety‘s expense take the following actions: 6.1 Send an answer to the Claimant, with a copy to the Owner, within 60 days after receipt of the claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed.
6.2 Pay or arrange for payment of any undisputed amounts.
6.3 The Surety‘s failure to discharge its obligations under this Section 6 shall not be deemed to constitute a waiver of defenses the Surety or Contractor may have or acquire as to a claim. However, if the Surety fails to discharge its obligations under this Section 6, Surety shall indemnify the Claimant for the reasonable attorney‘s fees the Claimant incurs to recover any sums found to be due and owing to the Claimant.
9. The Surety shall not be liable to the Owner, Claimants or others for obligations of the Contractor that are unrelated to the Construction Contract. . . .
. . . .
11. No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the location in which the work or part of the work is located or after the expiration of one year from the date (1) on which the Claimant gave the notice required by Subparagraph 4.1 . . ., or (2) on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract, whichever of (1) or (2) first occurs.
. . . .
15. DEFINITIONS
15.1 Claimant: An individual or entity having a direct contract with the Contractor or with a subcontractor of the Contractor to furnish labor, materials or equipment for use in the performance of the contract. The intent of this Bond shall be to include without limitation in the terms “labor, materials or equipment” that part of [all utilities] . . . or rental equipment used in the Construction Contract, . . . and all other items for which a mechanic‘s lien may be asserted in the jurisdiction where the lаbor, materials or equipment were furnished.
Payment Bond, 10/29/08, at 5-6 (emphasis added).
On November 11, 2008, Ionadi subcontracted (the “Subcontract“) with Eastern, a family-owned commercial subcontractor, for installation services relative to the steel reinforcing material. Specifically, Eastern agreed to, among other things, “supply labor and trade hand tools for installation of prefabricated reinforcing steel.” Subcontract, 11/11/08, at ¶ 1. For the reinforcing steel installation, the Subcontract set the unit price of structure rebar at $0.33/per pound. Id. The Subcontract also provided in pertinent part:
18. Payment schedules to [Eastern] will be made on or before the calendar 25th of each month, of an amount equal to 90% of the total value of work placed or performed during the preceding month. There will be a 10% retention holding. Retention release shall occur no later than 60 days after [Eastern‘s] reinforcing completion.
. . . .
19. [Eastern] shall receive a copy of all delivery tickets for all material which [Eastern] will be installing. With each delivery, a copy will immediately be issued to [Eastern] for its records, and all weights will be shown on delivery tickets from reinforcing suppliers.
. . . .
21. Rebar weights for payment to [Eastern], regarding installation, shall be actual bar weights as shipped, providing such weights are shipped for installation. . . . .
23. [Eastern] reserves the right to charge interest at one and one-half percent (1-1/2%) monthly on delinquent debt or payments, and to decline to perform any work except upon receipt of payment or security; or upon terms and conditions satisfactory to [Eastern]. [Eastern] shall be considered a direct obligee of [Ionadi‘s] bond assuring this [Subcontract]. Any costs incurred, direct and indirect, for which [Eastern] is subjected in pursuing any money, or consequential damages, legal fees, and costs of any kind to [Eastern] for nonperformance, will be [Ionadi‘s] and [IFIC‘s] responsibility.
. . . .
25. If any filing of claim, dispute, or legal actions are pursued and/or initiated against [Ionadi], such will occur and take place through means of the American Arbitration Association [(“AAA“)] by means of binding arbitration within the nearest local jurisdictional boundaries, or city, in which the [P]roject is located.
Id. at ¶¶ 18-19, 21, 23, and 25 (emphasis added).
Thereafter, on November 25, 2008, Eastern separately entered into a written agreement with Tinney Rebar Services, Inc. (“Tinney“), a reinforcing supplier, for the fabrication and supply of the reinforcing steel for the Project. The Tinney agreement also contained an AAA arbitration provision.
A. Payment Dispute
On February 28, 2009, pursuant to the Subcontract, Eastern began handling and installing reinforcing steel, supplied to Ionadi by Tinney, at the Project. Eastern concluded its work at the Project on September 4, 2010.
Eastern submitted requests for payment to Ionadi monthly by completing an AIA Application and Certification for Payment (“Payment Requests“). Each of the Payment Requests submitted by Eastern to Ionadi contained an invoice number, identified the amount of work performed within the covered time period, and listed the weight of reinforcing steel, among other things.
Ionadi paid Eastern on the first five Payment Requests for work performed at the Project through June 30, 2009. Thereafter, however, Ionadi either failed to pay the Payment Requests at all, or paid them only partially and late, citing cash flow problems.
On April 27, 2010, while work at the Project was ongoing, Eastern notified IFIC in writing of a claim under the Payment Bond for nonpayment of $622,182.90 by Ionadi. Eastern stated:
[Ionadi] is in default of payments due and owing to [Eastern], which Eastern is demanding payment by you as the surety co obligor[.] . . . [Ionadi] has admitted they have received payments that should have been forwarded to Eastern, however, due to their financial problems they have not. [Eastern] demand[s] prompt payment plus legal and statutory interest paid to Eastern.
Letter, 4/27/10. On April 29, 2010, IFIC notified Eastern that IFIC did not have sufficient information to determine whether all or any portion of the alleged amounts due was undisputed or disputed under the Payment Bond. See Letter, 4/29/10. IFIC directed Eastern to complete a proof of claim form. Id. On May 5, 2010, Eastern complied, submitting the required proof of claim to IFIC in support of its April 27, 2010 claim for nonpayment by
services it rendered on the Project. IFIC denied Eastern‘s claim on June 17, 2010. See Letter, 6/17/10. Eventually, however, IFIC reversed course and made payments to Eastern. On August 23, 2010, IFIC issued a check to Eastern for $277,295.00. Later, IFIC issued another check for $172,080.00 to Eastern оn December 23, 2010. In the aggregate, Eastern received $944,277.52 for its work on the Project. Eastern, however, claimed that, exclusive of interest, attorneys’ fees, costs, expenses and penalties, Eastern still was due $253,788.08 for its work on the Project.
B. Arbitration and Bankruptcy
On November 29, 2010, consistent with the Subcontract‘s AAA arbitration provision, Eastern filed a demand for binding arbitration against Ionadi. Eastern contacted and notified IFIC of the arbitration, but IFIC declined to participate. In September 2010, Tinney, Ionadi‘s reinforcing steel supplier who also had not been paid by Ionadi, filed a civil complaint against IFIC in the Court of Common Pleas of Allegheny County. IFIC filed preliminary objections, compelling Tinney to arbitrate its claims against Ionadi because Tinney‘s subcontract with Ionadi contained an AAA arbitration provision. Tinney subsequently in July 2011, filed a demand for arbitration and its arbitration was subsequently consolidated with Eastern‘s. As a condition for joining Eastern‘s arbitration proceeding, Tinney advised IFIC in writing of the proposed joinder, and like Eastern, invited IFIC to participate directly in the arbitration. IFIC once again declined. The joint arbitration hearing began on October 5, 2011, and Ionadi, despite having continual notice of the scheduled
arbitration hearing, elected not to participate therein. In spite of Ionadi‘s absence, the arbitrator required Eastern and Tinney to present their cases.
On the day arbitration began, Ionadi filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code in the Western District of Pennsylvania at case number 11-26204-TPA. On October 6, 2011, the arbitrator suspended the arbitration hearings pending efforts of Eastern‘s and Tinney‘s counsel to obtain a lift of the automatic stay of claims against Ionadi from the bankruptcy court. IFIC, despite notice, did not attend a hearing before the bankruptcy court to contest Eastern‘s motion to lift stay. On October 7, 2011, Eastern‘s and Tinney‘s counsel returned to the arbitrator‘s office from the bankruptcy court and advised the arbitrator that the bankruptcy court had issued an order lifting the automatic stay. See Arbitration Award, 11/9/11, at 1. As a result, the arbitration hearings prоceeded to conclusion. Id. On November 9, 2011, the arbitrator awarded Eastern $433,489.42 under the Subcontract,6 which included the $253,788.08 Eastern claimed it was owed by Ionadi under the Subcontract for the work it performed at the Project. Id. at 2. Additionally, the arbitrator directed Ionadi to reimburse Eastern for $19,933.94 in arbitration fees and expenses. Id. Neither Ionadi nor IFIC sought to vacate the arbitration award.
On February 9, 2012, the bankruptcy court held a hearing on Eastern‘s motion for relief from the automatic stay to determine whether to lift the stay so that Eastern could proceed to confirm the arbitration award. Despite attending the hearing, IFIC did not object to Eastern‘s motion. The bankruptcy court ultimately granted
Eastern then petitioned the Court of Common Pleas of Allegheny County to confirm and enter judgment on the arbitration award pursuant to
C. Centre County Action
On August 1, 2011, Eastern brought the instant Centre County action against IFIC under Section 11 of the Payment Bond by filing a writ of
summons. On November 7, 2011, Eastern filed a complaint against IFIC, which it amended on November 14, 2011. In its amended complaint, Eastern asserted multiple claims against IFIC. Count 1: breach of contract; Count 2: breach of contract (third party beneficiary); Count 3: action in assumpsit/civil action under the Public Works Contractors’ Bond Law of 1967,
On March 11, 2013, IFIC filed a “Motion for Partial Judgment on the Pleadings or, in the Alternative, Certification of Issues for Interlocutory Appeal.” IFIC sought dismissal, as a matter of lаw, of Count 5 (breach of contract — enforcement of arbitration award), Count 6 (action in assumpsit — enforcement of arbitration award), and Count 7 (bad faith), claiming that IFIC, as Ionadi‘s surety, was not bound by the arbitration award and the judgment thereon. In support, IFIC reasoned that there was no statutory predicate or case law in Pennsylvania that would obligate it to pay an arbitration award rendered against its principal and in favor of a subcontractor in an ex parte proceeding to which IFIC was not a party. In other words, IFIC argued that it
was not a party to the Subcontract containing the AAA arbitration provision and it did not participate in the resulting arbitration proceedings at which Ionadi failed to defend itself. Thus, according to IFIC, it was not liable to pay the arbitration award, as confirmed and reduced to judgment. With respect to Count 7, IFIC argued that Eastern‘s claim for bad faith was not cognizable against a surety and, therefore, should be dismissed as a matter of law. IFIC reasoned that there was no authority to support Eastern‘s claim that a surety contract constituted
On March 22, 2013, while IFIC‘s motion for partial judgment on the pleadings was pending, Eastern filed a motion for partial summary judgment with respect to Counts 1 through 3, 5, and 6 of the amended complaint. Eastern‘s summary judgment motion was premised, inter alia, on its contention that IFIC was indeed bound by the arbitration award and that, as a result, the award should be enforced against IFIC. Eastern based its summary judgment motion in large part on certain admissions made during the deposition testimony of Kathleen Maloney, IFIC‘s senior claims representative and admissions in IFIC‘s answer to the amended complaint.
Thereafter, on April 4, 2013, Eastern responded to IFIC‘s motion for partial judgment on the pleadings, asserting that IFIC was bound by the arbitration award entered against Ionadi. Eastern reasoned that IFIC, as a
co-obligor, was in privity with Ionadi and had notice of, and opportunity to participate in, the arbitration proceedings. Eastern claimed that “Ionadi, as well as co-obligor IFIC, had received advance notice, [and Ionadi] had responded to the demand fоr arbitration and participated in conferences with the arbitrator prior to the arbitration proceedings.” Answer to Motion for Partial Judgment on Pleadings, 4/8/13, at ¶ 4. Specifically, Eastern countered that it “notified IFIC of the filing of its demand for arbitration, and noticed IFIC when each breach was ripe, and on several occasions invited any claims agent of IFIC as an original promisor pursuant to the [Payment Bond] to intervene in the arbitration.” Id. at ¶ 6. Eastern further claimed that IFIC attended proceedings in Allegheny County on Eastern‘s petition to confirm and enter judgment on the arbitration award. Id. at ¶ 5. With respect to IFIC‘s contention that Eastern‘s bad faith claim should be dismissed, Eastern responded that the surety risk undertaking was insurance.
On August 27, 2013, the trial court issued an order on IFIC‘s motion for partial judgment on the pleadings and Eastern‘s motion for partial summary judgment. The court granted IFIC‘s motion for partial judgment to the extent IFIC sought certification for an interlocutory appeal. The trial court, however, denied IFIC‘s motion insofar as it sought the dismissal of Counts 5 and 6, concluding that IFIC was bound by the arbitration award entered against Ionadi and that IFIC chose not to participate in the arbitration, despite notice and opportunity. Trial court Opinion, 8/27/13, at 7-8. The court found that “the arbitration award entered against Ionadi is ‘at least prima facie evidence
against [IFIC].‘” Id. at 8. The trial court denied the motion with respect to the dismissal of Count 7, bad faith, concluding that the issue had to be further litigated. With respect to Eastern‘s motion for partial summary judgment, the trial court ordered the disposition thereof be held in abeyance in light of its decision to certify for interlocutory appeal issues raised in IFIC‘s motion for partial judgment on the pleadings. Id. at 10-11.
IFIC subsequently petitioned this Court for permission to appeal from the trial court‘s August 27, 2013 order. We, however, denied relief. See Eastern Steel Constructors, Inc. v. Int‘l Fid. Ins. Co., No. 81 MDM 2015 (Pa. Super. filed November 8, 2013). On January 22, 2014, the trial court denied Eastern‘s motion for partial
On December 22, 2014, Eastern renewed its motion for partial summary judgment based on IFIC‘s subsequent answers to interrogatories and subsequent document production. On February 4, 2015, the trial court denied the motion.
On March 9, 2015,10 IFIC filed a motion in limine, seeking to exclude evidence of the arbitration award and the resulting judgment. The trial court, despite its prior rulings, granted the motion, explaining without citation to any legal authority:
Ever mindful of the previous rulings of this [c]ourt, after thorough examination of the Pennsylvania authority, it is clear in this case that [Eastern] may not rely upon, and not even introduce, the outcome of the arbitration process. Our fundamental tenants of due process require that before the [c]ourt will accept and rule on evidence against any party, that the party has every opportunity to challenge, and to test, that evidence. Here, that has not been the case. [Eastern] urges that IFIC was on notice that the arbitration was to be conducted, but there were conditions and restrictions placed on IFIC that inclined IFIC to not participate. No contractual obligation bound [IFIC] to arbitrate, and no role was played by [IFIC] in the selection of the Arbitrator. Furthermore, no evidence was introduced or challenged by [IFIC] during the arbitration process. In fact, this [c]ourt is not aware that [IFIC] knows anything more about the arbitration than is contained in the two-page Award dated November 9, 2011.
Equally as significant to this [c]ourt is the fact that [IFIC] cannot be made to stand in the shoes of [Ionadi], as all evidence is that Ionadi essentially rolled over for the entry of a “Default Award” against them. This [c]ourt cannot fathom a trial strategy and delivery which is available to [IFIC] that would allow it to effectively demonstrate to any jury that the Award of the Arbitrator was incorrect, inflated, or in any way improper. If the Award is introduced to the jury, [IFIC] would be limited to the barest of collateral attacks on the court-sanctioned citadel of the arbitration. That outcome offends every sense of due process known to Pеnnsylvania law.
The unique facts of this case, together with a dearth of applicable case law upon which to rely, leave this [c]ourt only to retreat to the foundational principles of the law. There it finds no basis for
allowing [Eastern] to introduce the Award which would conclusively prejudice the open minds of any jury toward the outcome determined by the Arbitrator. [IFIC] would be left without any realistic opportunity to scrub that conclusion from the jurors’ minds.
Trial Court Opinion, 3/9/15, at 1-2. This order was a marked departure from the court‘s previous rulings on this issue.
On March 10, 2015, the matter proceeded to a jury trial, where Eastern attempted to introduce into evidence a white binder full of Tinney‘s delivery tickets that, according to IFIC, previously had not
On May 7, 2015, IFIC moved for partial summary judgment as a matter of law with respect to Counts 4 and 7 of the amended complaint. Eastern, in Count 4, sought recovery for attorneys’ fees and costs under Section 6.3 of the Payment Bond and Count 7, as noted earlier, was the bad faith claim. Eastern‘s claims for indemnification and bad faith centered on IFIC‘s alleged failure to promptly and timely comply with the requirement of Section 6 of the Payment Bond. In support of its summary judgment motion, IFIC argued that the evidence “demonstrates an absence of any genuine issue of material fact
as to IFIC‘s compliance with Section 6 of the [Payment] Bond.” IFIC Summary Judgment Motion, 5/7/15, at ¶ 7. Subsequently, the trial court declared the previously commenced jury trial to be a mistrial when Eastern dismissed its counsel. See Trial Court Order, 6/1/15.
Following a hearing, the trial court granted IFIC‘s motion for partial summary judgment. With respect to Count 4, the trial court concluded that IFIC satisfied its obligations under Section 6 of the Payment Bond by investigating “the claim promptly and notif[ying] Eastern [] within sixty days that it was disputing the entire amount of the claim due to lack of sufficient documentation to substantiate the claim[.]” Trial Court Opinion, 10/15/15, at 5-6. This ruling was a reversal of its March 16, 2015 order on this issue. On the bad faith claim (Count 7), the trial court revisited its prior rulings and concluded that
On September 21, 2016, IFIC filed a motion in limine to exclude delivery tickets. In particular, IFIC challenged the admissibility of Tinney‘s delivery documents that had been proffered during the March 2015 trial. IFIC contended that the delivery tickets were inadmissible because they were irrelevant, could not be authenticated properly, and constituted hearsay. Following a hearing, on April 11, 2017, the trial court denied the motion. The court concluded that the delivery tickets were relevant insofar as they created a presumption that the rebar delivered to the Project by Tinney was shipped for installation. Moreover, the court determined that the delivery tickets were
self-authenticating documents and satisfied the business records exception to the rule against hearsay. See Trial Court Opinion, 4/11/17, at 5.
On August 4, 2017, Eastern filed a motion in limine regarding the arbitration award and resulting judgment. Eastern argued that, despite the trial court‘s ruling that the arbitration award should not be shown to the jury, Eastern—to prove its claims—had to “introduce evidence and argue in the presence of the jury about matters relating to the arbitration other than the result, including Eastern‘s initiation of arbitration against Ionadi, the conduct of the arbitration and the fact that the arbitration proceeded to a result.” Eastern‘s Motion In Limine, 8/4/17, at ¶ 9 (emphasis added). On the same day, Eastern also filed a motion in limine to exclude expert testimony of Jim Bertoline on the amount of rebar installed at the Project. After yet another hearing, the trial court granted Eastern‘s motion on September
seeks clarification of this [c]ourt‘s ruling barring reference to the arbitration award. At trial, [Eastern] wishes to inform the jurors that an arbitration took place, as arbitration is required by the contract between [Eastern] and Ionadi. [Eastern] believes that if this fact is wholly excluded from trial, the jurors may believe that [Eastern] did not abide by the contract.
Although the [c]ourt agrees that excluding all mention of the arbitration could cause jurors to speculate, the [c]ourt also recognizes that allowing the parties to reference the outcome or the conduct at arbitration would likely prejudice the minds of the jurors. Therefore, the [c]ourt will draft a brief statement to be read by the [c]ourt during the trial which will address the binding arbitration clause of the [Subcontract].
Trial Court Opinion, 9/21/17, at 3. Accordingly, the trial court ordered that it would provide the following instruction to the jury:
There has been testimony relating to a [Subcontract] between [Eastern] and [Ionadi]. One provision of this contract requires disputes between the parties to be resolved through binding arbitration. I am instructing you now that [Eastern] has fully complied with the arbitration provision. You are not to use this information for any purpose other than to decide whether Eastern has met its obligations under the [Subcontract].
Id. at 5.11 On the issue of expert testimony, the trial court concluded that Mr. Bartoline‘s testimony was relevant to present IFIC‘s theory of payment to Eastern—that is, the amount of rebar installed at the Project instead of the amount of rebar shipped. Id. at 2-3. The court, therefore, denied Eastern‘s motion on this issue.
At some point in 2018, the trial judge, Judge Thomas King Kistler, retired from the bench and this matter was reassigned to Judge Brian K. Marshall. On August 17, 2017, Eastern sought reconsideration of the trial court‘s March 9, 2015 order issued by Judge Kistler, granting IFIC‘s motion in limine seeking to exclude evidence of the arbitration award and judgment thereon. On December 10, 2018, the trial court (Judge Marshall) denied Eastern‘s reconsideration motion. The court concluded that it was divested of jurisdiction to entertain the motion because it was patently untimely.
Furthermore, the trial court determined that the coordinate jurisdiction rule,12 which provides that judges of coordinate jurisdiction should not overrule each other‘s decisions, prevented it from revisiting Judge Kistler‘s March 9, 2015 order and that Eastern failed to establish an exception to that rule. See Trial Court Opinion, 12/10/18, at 2-5.
The parties thereafter filed additional motions in limine,13 which the trial court, following a hearing, disposed of on February 3, 2020. First, relying on its September 21, 2017 ruling, the trial court denied Eastern‘s motion with respect to the amount of rebar installed. The trial court then denied,
Eastern’s recovery. IFIC argued that during the aborted March 10, 2015 trial, Eastern’s President Judith Striebinger stated that the total amount due to Eastern was $220,029.09. Id. at 14. Yet, as IFIC pointed out, during a subsequent pretrial statement, dated March 11, 2019, Eastern claimed it was owed $253,758.72. Id. IFIC asked the court to consider as a judicial admission the testimony of Ms. Striebinger and bind Eastern thereto. Eastern countered that because Ms. Striebinger had not been cross-examined, her statement on the amount owed should not be viewed as a judicial admission. The trial court agreed, concluding that her testimony was incomplete and offered during an aborted trial. Id. at 15-16.
Retrial commenced on February 24, 2020 and, following close of the evidence, the trial court, among other things and without any objection, instructed the jury on the nature of suretyship as follows:
In this case, [Ionadi] and IFIC are separate legal entities who entered into a surety contract. A surety contract is a direct and original undertaking under which the surety provider, IFIC, is primarily and jointly liable with the principal, Ionadi. The liability of IFIC as surety is coextensive with that of Ionadi as principal. And accordingly, the surety, IFIC, is bound to perform whatever may be legally required of its principal, Ionadi.
N.T., Trial, 2/26/20, at 201 (emphasis added). The jury found in favor of Eastern. Id. at 213. On the verdict slip, the jury answered “no” to the question of whether Eastern was paid in full by Ionadi under the Subcontract for Eastern’s work on the Project. See Verdict Slip, 2/27/20, at ¶ 1. Having answered “no,” the jury then proceeded to the second and final question on the verdict slip, which required the jury to state the amount of monеy that Eastern was entitled to be paid for its work, over and above the amount that Eastern already has been paid. The jury determined that amount to be $253,788.06, which essentially mirrored the damages claimed under the Subcontract and awarded in arbitration. Id. at ¶ 2.
On March 2, 2020, IFIC filed a motion for post-trial relief, which it amended on March 9, 2020. On March 6, 2020, Eastern also moved for post-trial relief and sought to mold the verdict to include prejudgment interest. Following a hearing, the trial court denied the parties’ respective post-trial motions on July 1, 2020, but on July 17, 2020, molded the verdict to $330,427.70, reflecting an award of prejudgment interest of six percent (6%) per annum from May 5, 2010 until May 28, 2015.14 On July 23, 2020, the molded verdict was reduced to judgment in favor of Eastern. The parties
II. DISCUSSION
On appeal, Eastern presents the following issues for our review.
- As to the AAA arbitration award and judgment obtained by Eastern against . . . Ionadi, did the trial court commit an abuse of discretion and/or error of law as it relates to the following:
- Granting IFIC’s motion in limine to preclude entry into evidence the arbitration award at time of trial.
- Ruling that the arbitration award and judgment were not binding and conclusive upon IFIC.
- Refusing to allow into evidence exhibits of the arbitration award and entry of judgment obtained against [Ionadi].
- Fail[ing] to give a jury instruction that the arbitration award and judgment obtained against [Ionadi] was conclusive as against [IFIC].
- Did the trial court commit an abuse of discretion and/or error of law by granting IFIC’s motion for partial summary judgment and thereby denying Eastern the right to collect attorney’s fees and costs required by the [Subcontract]?
- Did the trial court commit an abuse of discretion and/or error of law by instructing the jury that it could not award counsel fees to Eastern as required by the [Subcontract]?
- Did the trial court err in limiting Eastern’s prejudgment interest to 6% and ignoring the [Subcontract’s] provision for 18% interest?
- Did the trial court commit an error of law and/or abuse of discretion in granting partial summary judgment as to Eastern’s bad faith claim?
Eastern’s Brief at 7-8 (unnecessary capitalizations omitted).
On cross-appeal, IFIC argues only that the trial court misinterpreted “the payment terms of [the Subcontract] for steel reinforcing material installation services to permit [Eastern] to recover payment for quantities of steel reinforcing material without introducing any evidence of ‘actual bar weights as shipped.’” IFIC’s Brief at 3.
A. Eastern’s Appeal
1. The Effect of the Arbitration Award Upon IFIC As Surety
We begin by addressing Eastern’s first claim on appeal, consisting of multiple subparts, raised principally within the context of the trial court deciding motions in limine, by answering the following question, as the answer to this question will be dispositive of the remaining subparts. Whether IFIC, as surety under the Payment Bond, is bound by an arbitration award entered and reduced to judgment against its principal, Ionadi, when IFIC, as surety, had full knowledge of the proceeding and an opportunity to participate in and defend against the arbitration claims.
With respect to motions in limine, our standard of review is well-settled.
A motion in limine is used before trial to obtain a ruling on the admissibility of evidence. It gives the trial judge the opportunity to weigh potentially prejudicial and harmful evidence before the trial occurs, thus preventing the evidence from ever reaching the jury. A trial court’s decision to grant or deny a motion in limine is subject to an evidentiary abuse of discretion standard of review. Questions concerning the admissibility of evidence lie within the sound discretion of the trial court, and we will not reverse the court’s decision absent a clear abuse of discretion. An abuse of discretion may not be found merely because an appellate court might have reached a different conclusion, but requires a manifest unreasonableness, or partiality, prejudice, bias, or ill-will, or such lack of support so as to be clearly erroneous.
In addition, to constitute reversible error, an evidentiary ruling must not only be erroneous, but also harmful or prejudicial to the complaining party.
Parr v. Ford Motor Co., 109 A.3d 682, 690-691 (Pa. Super. 2014) (citations omitted), appeal denied, 123 A.3d 331 (Pa. 2015), cert. denied, 136 S. Ct. 557 (2015).
Eastern argues that the trial court abused its discretion in prohibiting it from introducing and admitting at trial evidence of the arbitration award and the resulting judgment. Eastern contends that the arbitration award rendered in its favor was conclusive and enforceable against IFIC. Thus, according to Eastern, the jury should have been made aware of its existence. We agree.
We begin our analysis by examining the terms of the Payment Bond and Subcontract. Under the terms of the Payment Bond, IFIC as surety, and Ionadi as Contractor and Principal, jointly and severally, bound themselves to PSU to pay for all labor, materials, and equipment furnished for use in performance of the Construction Contract. Payment Bond ¶ 1. Under this provision, both Ionadi and IFIC agreed to be individually and/or jointly responsible for the entire payment obligation. Accordingly, anyone claiming payment from Ionadi could pursue payment in a joint action against Ionadi and IFIC, or by separate actions against any one of them.16 With respect to the Owner, the bond obligation would be deemed null and void if Ionadi made payment, directly or indirectly, for all sums due Claimants. Id. at ¶ 15.
“Claimants” are defined under the Payment Bond to include anyone, like Eastern, who has a direct contract with Ionadi.
With respect to “Claimants”, the Payment Bond separately provides that any obligation to make payment under the bond will be deemed null and void if the Contractor promptly makes payment, directly or indirectly, for all sums due. Id. at ¶ 3. Because the Payment Bond does not define “all sums due” to a subcontractor, logically, all sums due by necessity must be determined under the terms of the Subcontract that detail the work to be performed by a subcontractor and how it is to be paid. To this end, the Subcontract confirms that Eastern, as a subcontractor to Ionadi, shall be a direct obligee of Ionadi’s Payment Bond assuring the Subcontract. Subcontract at ¶ 23. As important, the Subcontract provides that any claim, dispute, or legal action between Eastern and Ionadi must be resolved by means of