Kidder Elec. of Fla., Inc. v. US Fidelity & Guar. Co.Kidder Elec. of Fla., Inc. v. US Fidelity & Guar. Co.
KIDDER ELECTRIC OF FLORIDA, INC., Appellant,
v.
UNITED STATES FIDELITY & GUARANTY CO., Appellee.
District Court of Appeal of Florida, Fifth District.
Joseph A. Lane of Lowndes, Drosdick, Doster, Kantor & Reed, Professional Ass'n, Orlando, for appellant.
Jon M. Wilson and Andrew V. Showen of Foley & Lardner, Van Den Berg, Gay, *476 Burke, Wilson & Arkin, Orlando, for appellee.
COWART, Judge.
A general contractor (Jendoco) provided an owner (Healthnet) with a payment bond (with the contractor as principal) and USF & G as surety, for the use and benefit of persоns supplying labor and material in performance of a construction contract to improve the owner's real property. (See § 713.23(1)(a), Fla. Stat.). An electrical subcontraсt between the general contractor and a subcontractor (appellant Kidder Electric of Florida, Inc.) contained a provision for arbitration of controvеrsies arising between the parties thereto.
When a controversy arose between the subcontractor and the general contractor, the subcontractor instituted an аrbitration proceeding by filing an appropriate demand for arbitration with a designated arbitration association to which the general contractor responded. Apparently because the general contractor did not neglect to or refuse to comply with the provision for arbitration, the subcontractor did not need to, and therеfore did not, "make application to the court for an order directing the parties to proceed with arbitration" as permitted under section 682.03(1), Florida Statutes. Thereafter, to toll the statute of limitations (§ 713.23(1)(f), Fla. Stat.) the subcontractor filed its action against the surety on the payment bond. In its complaint the subcontractor moved to stay the bond aсtion against the surety until the conclusion of the pending arbitration proceeding.
The general contractor, as intervenor in the bond action, and the surety company jointly mоved to stay the arbitration proceeding until the conclusion of the bond litigation. In this joint motion to stay, it was alleged that because the general contractor, as principal on the bond, was liable to the surety in the event the subcontractor recovered on the surety bond, the general contractor was a real party in interest in the bond litigatiоn and had agreed to defend the bond action on behalf of the surety. The trial court granted the motion of the general contractor and surety and ordered a stay of the аrbitration proceeding. The subcontractor appeals. We reverse.
The ultimate issue in the arbitration proceeding is whether the subcontractor is entitled to paymеnt from the contractor for labor and materials furnished by the subcontractor to improve the owner's real property under the construction contract between the сontractor and the owner. Because, in this case, the surety has actual notice of the arbitration proceeding whether or not the surety chooses to particiрate in the arbitration proceeding the surety will be bound by an arbitration determination that its principal (the contractor) is liable to the subcontractor and the subcontraсtor will be entitled to an order confirming any arbitration award in its favor, not only as against the contractor but also against the surety (see Von Engineering Co. v. R.W. Roberts Construction Co., Inc.,
By filing action on the bond, the subcontractor neither waived its contractual right to arbitrate its controversy with the сontractor, nor did it make any election of remedies.[2]
Section 682.03(3), Florida Statutes, is inapplicable to this litigation for several reasons, including the fact that no order for аrbitration or application for such order was made in this case, which is a clear condition precedent to the application of that statute.
The order staying thе arbitration proceeding is reversed with directions to enter an order staying the litigation on the bond until the conclusion of the arbitration proceeding.
REVERSED and REMANDED.
SHARP, C.J., and COBB, J., concur.
NOTES
Notes
[1] In Post Tensioned Engineering Corp. v. Fairways Plaza Associates,
[2] In an analogous case, U.S. v. Weiss Pollution Control Corp.,