MEMORANDUM OPINION AND ORDER
Defendant Tri-State Management Company (“Tri-State”) entered into a general contract with the United States Postal Service to perform work on a post office building expansion. As required by the Miller Act, 40 U.S.C. § 270a et seq., TriState executed a payment bond. 1 Defendant North American Specialty Insurance Company (“NAS”) signed the bonds as surety. Plaintiff Frontier Construction, Inc. (“Frontier”) entered into a subcontract with Tri-State to provide labor, equipment, and material for the post office expansion. Frontier claims that it was not fully paid, and consequently, it filed a Miller Act claim against Tri-State and NAS. 2 At the same time, it filed a demand for arbitration with Tri-State pursuant to their subcontract. Following an arbitration in which Tri-State failed to appear, an award was entered against Tri-State in the amount of $41,450.45 plus interest, as well as $7,521.09 in attorneys’ and arbitration fees. Frontier now moves to confirm this award and enter judgment against both Tri-State and NAS. I grant the motion in part, confirming the award and entering judgment against Tri-State only.
Tri-State, though properly served,
3
has not filed an appearance in this case and only NAS has objected to Frontier’s motion. NAS does not object to confirmation of the arbitration award, only to an entry of judgment against it. Under section 9 of the Federal Arbitration Act, 9 U.S.C. § 1
et seq.,
if the arbitration agreement indi
The only contested issue is whether judgment can be entered against NAS. Frontier does not argue that NAS was bound by the agreement to arbitrate contained in the Frontier/Tri-State subcontract. Thus, Frontier does not argue that the arbitration award was rendered against NAS as well as Tri-State. Indeed, the arbitration award was rendered against Tri-State only, with no mention of NAS. (Pl.’s Mot. for Confirmation of Award Ex. 6.) Frontier argues that NAS is nevertheless liable for the arbitration award rendered against Tri-State. In support of this position, Frontier cites
United States ex rel. Skip Kirchdorfer v. M.J. Kelley Corp.,
In those cases, like ours, subcontractors on federal public works projects obtained arbitration awards against general contractors. In subsequent suits under the Miller Act, the general contractors’ sureties were held liable for the arbitration awards. The theory upon which those cases rely is one of preclusion. Both
Skip Kirchdorfer
and
Aurora Painting
cited dicta in
Frederick v. United States,
The source of law that governs the pre-clusive effect of an arbitration award is not well developed.
See
18b Charles Alan Wright et al., Federal Practice and Procedure § 4475.1 (2d ed.2002). The court in
Skip Kirchdorfer,
without discussion of its reasons for doing so, applied both state and federal law in determining that the subcontractor’s arbitration award against the general contractor was preclusive as to the general contractor’s surety’s liability.
With respect to federal law, some circuit courts (such as the Sixth Circuit in
Skip Kirchdorfer
and the Ninth Circuit in
Aurora
Painting) follow the rule expressed in the
Frederick
dicta.
See Drill South, Inc. v. Int’l Fid. Ins. Co.,
Additionally, one circuit court has questioned whether the general rule that a judgment against a principal is binding on a surety with notice and opportunity to defend is even applicable in the Miller Act context.
United States Fid. & Guar. Co. v. Hendry Corp.,
Federal law is thus far from clear (and the Seventh Circuit has not weighed in) as to whether and in what circumstances a Miller Act surety may be liable for an arbitration award against its principal. Whichever rule is applied, however, leads to the same result. If the
Hendry/Pensacola Construction
rule is followed, NAS is not liable for the award against Tri-State because a surety cannot be bound by such an award. Even if the
Skip Kirchdor-ferjAurora Painting
rule applies, NAS is not liable because an arbitration in which a surety did not have an opportunity to defend itself is not preclusive as to the surety’s liability. Further, the arbitration award here was essentially a default judgment against Tri-State, as Tri-State failed to appear for the arbitration. (Pl.’s Mot. for Confirmation of Award Ex. 6.) As the argument that sureties are bound by an arbitration award against a principal is grounded in a theory of preclusion, the fact that a majority of federal courts (including the Seventh Circuit) do not give preclusive effect to default judgments,
Stephan v. Rocky Mountain Chocolate Factory,
Even if it is not federal law at all, but rather state law that determines the pre-clusive effect of an arbitration award, ap
Further, at least one court in this district applying Illinois law held in an analogous case that a prior default judgment against a principal was not preclusive in a suit against the principal’s guarantors.
Dale v. Frank,
No. 85 C 5891,
Regardless of whether federal or Illinois determines the preclusive effect of the arbitration award against Tri-State, the award does not conclusively establish liability of NAS to Frontier. Even assuming that arbitration awards against a contractor can be preclusive as to the contractor’s Miller Act surety’s liability, NAS has had no opportunity to present defenses either as to its own liability on the bond, or as to Tri-State’s liability on the subcontract, which NAS is entitled to assert in its own defense. Frontier is free to proceed with its Miller Act claim against NAS here; my ruling today is simply that the arbitration award itself does not conclusively establish liability. Entry of judgment against NAS at this point would be premature.
Plaintiffs motion for confirmation of the arbitration award and entry of judgment against defendants is GRANTED IN PART AND DENIED IN PART. The arbitration award is confirmed, and defendant Tri-State is hereby ordered to pay Frontier the sums described in the award. With respect to defendant NAS, however, Frontier’s motion for entry of judgment is denied.
Notes
. The Miller Act requires payment bonds in order to protect suppliers whose materials and labor go into federal public projects; normal state mechanics’ lien remedies are unavailable to subcontractors performing work on federal projects.
United States ex rel. Westinghouse Elec. Supply Co. v. Sisson,
. The complaint also included counts stating breach of contract and quantum meruit claims against Tri-State.
. Service may be effected pursuant to state law of the state in which the district court sits. Fed.R.Civ.P. 4(h)(1), (e)(1). In Illinois, process may be served on a corporation by serving the Secretary of State whenever the corporation’s registered agent cannot with reasonable diligence be found at its registered office in Illinois.
Dutch Farm Meats, Inc. v. Horizon Foods, Inc.,
