DUNHAM ENGINEERING, INCORPORATED, Appellant v. The SHERWIN-WILLIAMS COMPANY, Appellee.
No. 14-12-00369-CV.
Court of Appeals of Texas, Houston (14th Dist.).
May 30, 2013.
404 S.W.3d 785
Litigation Tactics
In her eleventh issue, Fautheree argues appellees’ pleading and litigation tactics “so improperly ‘skewed’ the litigation and motion hearing process, as to require reversal and remand.” To preserve a complaint for appellate review, a party generally must present it to the trial court by timely request, objection, or motion stating the specific grounds, and obtain a ruling.
Bich did not request any relief from the trial court based on appellees’ alleged litigation tactics. Accordingly, this issue is not preserved for our review. See
We affirm the trial court‘s judgment.
Vernon Childs Howerton Jr., Dallas, A.M. Landry, III, Houston, Randy E. Moore, Lake Jackson, for Appellee.
Panel consists of Justices CHRISTOPHER, McCALLY, and DONOVAN.
OPINION
TRACY CHRISTOPHER, Justice.
In this interlocutory appeal, Dunham Engineering, Inc. (DEI) appeals the trial court‘s denial of its motion to dismiss the Sherwin-Williams Co.‘s (Sherwin-Williams) claims of intentional interference with prospective business relationships, business disparagement, and product dis
I. FACTUAL AND PROCEDURAL BACKGROUND
In fall 2009, the City of Lake Jackson (the City) hired DEI to design and produce engineering plans and specifications, and a draft set of contract documents for the repainting and rehabilitation of a 500,000-gallon water tower (the Project). The City also hired DEI to advertise for contractor bids on, and assist the City in reviewing the bids and in selecting the winning bid for, the Project.
In its specifications for the Project, DEI specified that Tnemec Co., Inc.‘s (Tnemec) paint products were to be used. The specifications indicated that if a contractor submitting a bid wanted to substitute another manufacturer‘s paint products, then the contractor needed to apply to DEI and request substitution, and that DEI has final authority in approving a proposed substitute. The City advertised and solicited competitive bids on the Project. During the public bidding process, Sherwin-Williams submitted its paint products to DEI and requested substitution of Sherwin-Williams’ products for Tnemec‘s products. DEI—in particular, DEI‘s president and licensed professional civil engineer, Jimmy Dunham—informed the City‘s director of public works that DEI intended to turn down Sherwin-Williams’ request because Dunham did not consider Sherwin-Williams’ products to be “equal” to Tnemec‘s products. DEI then rejected Sherwin-Williams’ request.
Sherwin-Williams filed suit against DEI, alleging counts of intentional interference with prospective business relationships, business disparagement, and product disparagement. To its original petition, Sherwin-Williams attached a certificate-of-merit affidavit from James O‘Connor, a licensed professional civil engineer and engineering professor at the University of Texas at Austin.
In his affidavit, O‘Connor stated that he was familiar with the legal requirements and industry customs regarding competitive bidding on Texas public works projects. Based on O‘Connor‘s review of DEI‘s plan specifications, he concluded that specifications for the Project required competitive bidding, DEI‘s specification on paint products was a closed or sole-source specification, and DEI‘s paint specification did not allow for open competition and thus did not conform to Texas law. O‘Connor also opined that, by drafting and soliciting Project bids based on the sole-source specification, DEI and Dunham violated their duty under the Texas Board of Professional Engineers’ rules. O‘Connor also reviewed Sherwin-Williams’ request that its products be considered as a substitute, Dunham‘s communications with the City, and DEI‘s response rejecting Sherwin-Williams’ products. He opined that DEI‘s rejection of Sherwin-Williams’ products as a proposed substitute was in error from an engineering prospective because the rejection was based on what product has the highest test results, not compliance with a stated desired minimum value. O‘Connor further opined that DEI and Dunham disparaged Sherwin-Williams and its products when they reported to the City that Sherwin-Williams’ paint products were not “equal.”
DEI brings three issues on appeal. First, DEI argues Sherwin-Williams’ certificate of merit fails to comply with
II. STANDARD OF REVIEW AND APPLICABLE LAW
An order denying a motion to dismiss for failure to file a certificate of merit in accordance with
We review matters of statutory construction de novo. Epco Holdings, 352 S.W.3d at 269; Benchmark, 316 S.W.3d at 44. We construe statutory language to ascertain and effectuate legislative intent, and we look to the statute‘s plain meaning because we presume that the Legislature intends the plain meaning of its words. Epco Holdings, 352 S.W.3d at 269-70 (citing Sharp Eng‘g, 321 S.W.3d at 750). We view statutory terms in context, giving them full effect. Benchmark, 316 S.W.3d at 45 (citation omitted). We presume that every word of a statute was used for a purpose, and every omitted word was purposefully not chosen. See Epco Holdings, 352 S.W.3d at 270; Benchmark, 316 S.W.3d at 44-45. “Finally, in determining the plain meaning of a statute, we read the words in context and construe the language according to the rules of grammar and common usage.” Benchmark, 316 S.W.3d at 45 (citing
(a) In any action ... for damages arising out of the provision of professional services by a licensed or registered professional, the plaintiff shall be required to file with the complaint an affidavit of a third-party ... licensed professional engineer ... who:
(1) is competent to testify;
(2) holds the same professional license or registration as the defendant; and
(3) is knowledgeable in the area of practice of the defendant and offers testimony based on the person‘s:
(A) knowledge;
(B) skill;
(C) experience;
(D) education;
(E) training; and
(F) practice.
(b) The affidavit shall set forth specifically for each theory of recovery for which damages are sought, the negligence, if any, or other action, error, or omission of the licensed or registered professional in providing the professional service, including any error or omission in providing advice, judgment, opinion, or a similar professional skill claimed to exist and the factual basis for each such claim. The third-party ... licensed professional engineer ... shall be licensed or registered in this state and actively engaged in the practice of ... engineering ....
...
(e) The plaintiff‘s failure to file the affidavit in accordance with this section shall result in dismissal of the complaint against the defendant. This dismissal may be with prejudice.
(f) An order granting or denying a motion for dismissal is immediately appealable as an interlocutory order.
...
To the extent that we discuss case law interpreting it, the 2005 version of
(a) In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, the plaintiff shall be required to file with the complaint an affidavit of a third-party licensed architect, registered professional land surveyor, or licensed professional engineer competent to testify, holding the same professional license as, and practicing in the same area of practice as the defendant, which affidavit shall set forth specifically at least one negligent act, error, or omission claimed to exist and the factual basis for each such claim. The third-party professional engineer, registered professional land surveyor, or licensed architect shall be licensed in this state and actively engaged in the practice of architecture, surveying, or engineering.
Act of May 18, 2005, 79th Leg., R.S., ch. 208, § 2, 2005 Tex. Gen. Laws 369, 369-70, amended by Act of May 27, 2009, 81st Leg., R.S., ch. 789, § 2, 2009 Tex. Gen. Laws 1991, 1991-92.
III. ANALYSIS
A. Sherwin-Williams’ intentional tort claims are subject to section 150.002 .
We first address the threshold cross-issue raised by Sherwin-Williams. Sherwin-Williams argues that its intentional tort claims are not subject to
1. Each theory of recovery
Under the 2009 version, as well as the 2005 version, a certificate of merit is required “[i]n any action ... for damages arising out of the provision of professional services by a licensed or registered professional.”
Although in Benchmark1 we observed that “[t]he legislature has amended chapter 150 three times since it was enacted in 2003 and sought to broaden its application in each amendment,” 316 S.W.3d at 45, this court has not directly considered the scope of applicability of the 2009-amended
Other courts of appeals have applied the 2009 version of
Sherwin-Williams primarily relies on case law construing the 2005 version of
When construing
2. Provision of professional services
Sherwin-Williams contends that an engineer committing an intentional tort is not engaged in providing professional services, and therefore its intentional tort claims do not require a certificate of merit. Sherwin-Williams again relies on 2005-version case law to support its position. But we do not find these cases persuasive given their interpretation that the 2005 version limits the certificate-of-merit-requirement to claims involving allegations of negligence.
Here, Sherwin-Williams asserted claims seeking damages from DEI. To determine if a certificate of merit was required under
In its petition, Sherwin-Williams alleged that “[t]he City hired DEI to provide professional engineering services for the Project.” Sherwin-Williams further alleged that “[a]s part of their professional services, Dunham, acting as president of DEI, prepared or directed the preparation of plans and specifications for the Project,” including specifying the use of Tnemec‘s paint products. Sherwin-Williams alleged DEI and Dunham had been made aware that Texas law precludes using a closed paint specification “such as the Project paint specification prepared by DEI/Dunham.” Sherwin-Williams alleged that it submitted its paint products to DEI for approval on the Project as “equal” to Tnemec‘s products. According to Sherwin-Williams, DEI rejected Sherwin-Williams’ substitution application as not “equal” by letter and published this letter to the City. Sherwin-Williams alleged that “the City opted to defer to and relied upon the professional judgment of DEI and Dunham when specifying Tnemec as a sole source and refusing to approve Sherwin-Williams as Tnemec‘s ‘equal‘” and awarded the Project contract to a contractor whose bid included Tnemec‘s products. These allegations clearly indicate that Sherwin-Williams’ tort claims arise out of DEI‘s provision of professional services.
Although Sherwin-Williams asserts that it should not be required to file a certificate of merit because it alleges that DEI violated the law rather than a professional standard of care,
All of Sherwin-Williams’ claims against DEI pertain to its preparation of the Project plans and specifications, and DEI‘s actions in evaluating and providing its (negative) opinion of Sherwin-Williams’ paint products for the Project; thus, these claims arise out of the provision of professional services by a licensed or registered professional under the statute. Therefore, we conclude that Sherwin-Williams was required to submit a certificate of merit
B. Sherwin-Williams’ certificate-of-merit affidavit complies with section 150.002(a)(3) .
In its first issue, DEI argues Sherwin-Williams’ certificate-of-merit affidavit fails to comply with
We again consider the difference in language between the 2005 and 2009 versions of the statute. The 2009 version requires that the plaintiff file an affidavit of a third-party licensed professional engineer who “is knowledgeable in the area of practice of the defendant.”
Notwithstanding this “reduced” qualification requirement, DEI argues because O‘Connor did not state in his affidavit that he practices an engineering specialty remotely associated with DEI‘s practice, did not include a resume, did not describe previous work on water-tank projects, and did not indicate that he previously has drafted specifications for a water-tank rehabilitation project, his affidavit fails the “strict” requirements of
DEI further contends that, despite Sherwin-Williams’ insistence that the “crux” of its case involves improper engineering practices in conjunction with competitive bidding on a public works project, the actual engineering practice at issue is whether DEI and Dunham‘s recommendations regarding Sherwin-Williams’ products were false. Sherwin-Williams may need to show that its paint products could be considered an “equal” substitute to ultimately prove that “DEI‘s exclusion of [Sherwin-Williams] from competing to supply paint materials was unlawful” and DEI‘s recommendations to the City involved “false, disparaging words.” However, at the certificate-of-merit stage, before discovery and before other dispositive motions are available, the plaintiff is not required to fully “marshal his evidence.” See CBM Eng‘rs., Inc. v. Tellepsen Builders, L.P., No. 01-11-01033-CV, 403 S.W.3d 339, 346 (Tex.App.-Houston [1st Dist.] Jan. 10, 2013, pet. filed) (also noting that
In this case, the trial court had before it O‘Connor‘s sworn certificate indicating that he holds a Ph.D. in civil engineering, is licensed by the State of Texas as a professional engineer with the designation of “civil,” and currently serves as a professor in project management within the civil, architectural, and environmental engineering department at the University of Texas. This sworn certificate also indicated that O‘Connor, “[t]hrough [his] practice, research, and teaching, [is] familiar with both the legal requirements and industry customs regarding competitive bidding on public works projects, particularly in the State of Texas.” In addition, Sherwin-Williams alleged, and DEI does not dispute, that DEI provides professional engineering services and Dunham is a licensed professional engineer in Texas, and that DEI and Dunham were involved in the preparation and direction of plans and specifications for a Texas public works project. Finally, Dunham‘s credentials indicate that he is a professional engineer licensed in Texas who holds a master‘s in civil engineering. On this record, we cannot conclude the trial court abused its discretion in determining that O‘Connor “is knowledgeable” in DEI‘s area of practice, as required by
C. Sherwin-Williams’ certificate of merit complies with section 150.002(b) .
In its second issue, DEI argues that Sherwin-Williams’ certificate of merit affidavit fails to comply with
The statute does not define “factual basis,” but the purpose of the certificate of merit “is to provide a basis for the trial court to conclude that the plaintiff‘s claims
In his affidavit, O‘Connor stated the following: that based on applicable authority, sole-source specifications are not permitted for competitively bid public works projects; that DEI‘s paint specification was unlawful and, further, deficient because no objective requirements are provided; that Dunham violated a professional duty by 4 drafting and soliciting bids using the restrictive paint specification; that Dunham and DEI knew about the open-competition requirement from correspondence on other projects; that DEI‘s stated basis for rejecting Sherwin-Williams’ products (case studies from different products) was invalid; that the determination of an “equal” substitute must be made on whether the product achieves an acceptable minimum value not the highest value; that Dunham and DEI erred by conducting the procurement using an unlawful specification and advising the City it could do so; that this error prevented Sherwin-Williams from competing to supply paint; and that DEI and Dunham disparaged Sherwin-Williams and its products by reporting to the City that Sherwin-Williams’ paints were not an acceptable substitute. Based on his review of DEI‘s Project plans and specifications and of various correspondence by the parties, O‘Connor opined DEI‘s and Dunham‘s actions amounted to errors that violated their professional engineering duties. O‘Connor provided factual assertions underlying that opinion—namely, DEI submitted specifications for the Project that provided for a specific brand of paint products; did not provide objective, minimum-value criteria for what paint would be acceptable; rejected Sherwin-Williams’ paint products based on case studies for different products; and reported to the City
Thus, we conclude O‘Connor‘s affidavit sets forth a sufficient “factual basis” for Sherwin-Williams’ claims of intentional interference with prospective business relationships,7 business disparagement,8 and product disparagement9 because it describes the facts giving rise to Sherwin-Williams’ claims and thus provided the trial court a basis to conclude that Sherwin-Williams’ claims are not frivolous. See CBM Eng‘rs, 403 S.W.3d at 345; Benchmark, 316 S.W.3d at 48. On this record, we cannot conclude the trial court abused its discretion in determining that O‘Connor‘s affidavit meets the requirement of
Because Sherwin-Williams’ certificate of merit sufficiently meets
IV. CONCLUSION
Accordingly, we affirm the trial court‘s order denying DEI‘s motion to dismiss.
TRACY CHRISTOPHER
JUSTICE
