OPINION
Peleo Construction, Inc. appeals the trial court’s granting of two motions that dismissed Peleo Construction’s claims against Dannenbaum Engineering Corporation, Dannenbaum Engineering Company— Houston, LLC, Steven Lloyd McGarraugh, Alan D. Hirshman, Kurt Amundson, and Amundson Consulting, Inc. The dismissals were all based on Peleo Construction’s failure to file a certificate of merit along with its petition. In one issue, Peleo Construction argues that the trial court erred by dismissing its claims against appellees because a certificate of merit was not required for the claims it brought.
We affirm, in part, and reverse and remand, in part.
Background
The Oak Island Volunteer Fire Department’s fire station was destroyed by Hurricane Ike in 2008. Chambers County sought funding from the Federal Emergency Management Agency (“FEMA”) to reconstruct the fire station.
Chambers County entered into a master services agreement (“MSA”) with Dannenbaum Engineering Company— Houston, LLC to oversee the design and reconstruction of the fire station. Alan Hirshman, a licensed engineer, and Steven McGarraugh, a licensed architect, provided their services to Dannenbaum Engineering Company-Houston, LLC through another company: Dannenbaum Engineering Corporation. The parties draw no distinction between the two Dannenb-aum companies in their briefs and nothing in our analysis requires a differentiation. Accordingly, for the purposes of this appeal, we will treat the two companies as a single entity, “Dannenbaum Engineering.”
According to the terms of the MSA, the services provided by Dannenbaum Engineering were divided into two phases. The first phase consisted of assessment and design of the fire station. The second phase consisted of oversight of the construction of the fire station. The MSA provided, “Phase II shall not commence until the permanent repair project has been approved and funds have been provided by FEMA.”
As it neared the second phase of the MSA, Dannenbaum Engineering entered into a Staff Support Agreement with Amundson Consulting, Inc. Under the contract, Amundson Consulting provided the services of Kurt Amundson. Amund-son worked as an emergency management consultant. He had “28 years[’] experience in assisting local governments [with] obtaining FEMA] Public Assistance Grants to complete projects to repair damages sustained from natural disasters.” His work involved overseeing the bidding
Peleo Construction was one of the businesses that submitted a sealed bid to construct the fire station. Before submitting a bid, Peleo Construction met with representatives of Chambers County, Hirshman, and Amundson in a pre-bid conference. At the conference, Hirshman “discussed the construction plans and specifications for the reconstruction” of the fire station. Peleo Construction alleges that Hirshman and Amundson, among others, told it that FEMA funding for the fire station project had been approved.
Chambers County ultimately awarded the construction contract to Peleo Construction. One provision of Peleo Construction’s contract required Chambers County,
at the written request of [Peleo Construction], prior to commencement of the Work and thereafter, [to] furnish [Peleo Construction] reasonable evidence that financial arrangements have been made to fulfill [Chamber County’s] obligations under the Contract. Furnishing of such evidence shall be a condition precedent to commencement or continuation of the Work. After such evidence has been furnished, the Owner shall not materially vary such financial arrangements without prior notice to [Peleo Construction].
The parties dispute whether, at the time that Peleo Construction was awarded the contract, FEMA had approved the eon-struetion for reimbursement. Regardless, around the time that Chambers County began accepting bids on the contract, Amundson was working to obtain approval of an amendment with FEMA for increased costs. One of the reasons asserted for increased cost construction was “the building design had to be changed to meet new [Americans with Disabilities Act (‘ADA’) ] requirements. The new ADA requirements required that there be an ADA ramp inside the building not just on the outside of the building.” Adding the interior ramp would require increasing the size of the building.
At least by June 15, 2010, FEMA had determined that the interior ramp was not required under the law and, accordingly, “the request for an increase in building size for the interior ADA ramp is not eligible for FEMA funding.” Nevertheless, on July 8, Chambers County and appellees provided Peleo Construction with a construction plan, which included the interior ramp. The plan was stamped “approved for construction.” Dannenbaum told Peleo Construction to begin construction, and Peleo Construction began work on July 14 even though FEMA had not approved the final plan or funding for the interior ramp.
Over the next four months, as Peleo Construction continued work on the fire station, Chambers County and appellees continued to communicate with FEMA to obtain approval for the interior ramp and the corresponding increase in size of the building. At some point in September 2010, Chambers County informed FEMA that redesigning the building to remove the interior ramp was not possible because construction had already begun and a redesign would require a costly stop to the project.
On October 28, 2010, Amundson contacted Michael Ramirez, a project manager for
On November 17, 2010, FEMA gave tentative approval to constructing the firehouse with the interior ramp. On December 7, Hirshman, on behalf of Dan-nenbaum Engineering, instructed Peleo Construction to resume construction of the firehouse. Instead, on December 14, Peleo Construction sent Chambers County a notice of termination of the contract.
Peleo Construction filed suit against Chambers County on April 8, 2011. On November 3, 2011, Peleo Construction filed an amended petition, adding Dannenbaum Engineering, McGarraugh, Hirshman, and Amundson to the suit. Peleo Construction asserted a claim of fraudulent misrepresentation against Dannenbaum Engineering, McGarraugh, Hirshman, and Amund-son. The thrust of the claim was that Dannenbaum Engineering, McGarraugh, Hirshman, and Amundson had misrepresented that FEMA had approved the construction plans given to Peleo Construction and that Peleo Construction was injured by the order to stop work on the construction.
In March 2012, Dannenbaum Engineering, McGarraugh, and Hirshman filed a motion to dismiss on the basis that Peleo Consti’uction was required to file a certificate of merit along with the petition that brought them into the suit. They argued that, because Peleo Construction had failed to file the certificate of merit along with the petition, the claims against them must be dismissed with prejudice.
Peleo Construction filed its last amended petition on April 5th. This petition added Amundson Consulting as a defendant, including it in Peleo Construction’s claim for fraudulent inducement. The same day, Peleo Construction filed its response to the motion to dismiss. Peleo Construction argued that it was not required to file a certificate of merit for the fraudulent misrepresentation claims against Dannenb-aum Engineering, McGarraugh, and Hirshman. The trial court disagreed and dismissed with prejudice Peleo Construction’s claims against them.
A short time later, Amundson and Amundson Consulting also filed a motion to dismiss based on the same argument that Peleo Construction had failed to include a certificate of merit along with the petitions that brought them into the suit. Peleo Construction responded, again arguing that it was not required to file a certificate of merit for the claims it brought. The trial court granted Amundson and Amundson Consulting’s motion as well and dismissed Peleo Constructions claims against them with prejudice. Peleo Construction timely appealed the dismissal orders.
Certificate of Merit
In its sole issue on appeal, Peleo Construction argues that the trial court abused its discretion by dismissing its claims against appellees because a certificate of merit was not required for the claims it brought.
A. Standard of Review
An order granting or denying a motion to dismiss for failure to file a certificate of merit is immediately appealable. See Tex. Civ. Prao. & Rem.Code Ann. § 150.002(f) (Vernon 2011). We review a trial court’s ruling on a motion to dismiss for an abuse of discretion. Carter & Burgess, Inc. v. Sardari,
B. Analysis
A plaintiff is required to file a certificate of merit in “any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional.” Tex. Civ. Prac. & Rem.Code ANN. § 150.002(a). In this context, a “licensed or registered professional” includes “a licensed architect, licensed professional engineer ... or any firm in which such licensed or registered professional practices.... ” Id. § 150.001(1) (Vernon 2011). If a plaintiffs claim for damages implicates the special knowledge and training of an architect, it is a claim for damages arising out of the provision of professional services. See Sardari,
When required, the certificate of merit must be filed with the first-filed complaint asserting the relevant claim against a professional. See Tex. Civ. Prao. & Rem.Code Ann. § 150.002(a); Pakal Enters., Inc. v. Lesak Enters. LLC,
Peleo Construction did not file a certificate of merit along with its first-filed complaints of fraud against appellees. Accordingly, we must review Peleo Construction’s petition to determine whether its claims of fraudulent misrepresentation required a certificate of merit. In performing this review, we consider the live pleading on file when the trial court considered the motion. TDIndustries,
The relevant portion of Peleo Construction’s live pleading asserts the following:
88. Defendants McGarraugh and Hirshman, in them capacities as a registered architect and registered professional engineer and as representatives of Dannenbaum, and Amundson, in his capacity as a Florida professional emergency manager and as a representative of Dannenbaum, and all collectively as the construction managers appointed by Chambers County for the [fire station] project, made representations to Peleo in regard to the [fire station].
89. McGarraugh and Hirshman, through the construction plans stamped with their official seals, signatures and date of signing, indicated to Plaintiff that said documents were to be used for the construction of the [fire station],
90. As construction manager for [the fire station], Defendants then later directed Peleo to begin construction on the [fire station].... By doing so, Defendants represented to Peleo that the [fire station] project was approved for funding by FEMA.
91. This was not true; the improved project had yet to be approved by FEMA which Defendants had direct knowledge of. Relying on the representations made by Defendants, Peleo began construction of the [fire station].
92. A few months [later], on or about October 28, 2010, following commencement of construction on the [fire station], Peleo received a telephone call from Amundson, ... who stated that FEMA required the work on the [fire station] be stopped because Dannenb-*54 aum had not gotten approval of the construction plans from FEMA. Dannenb-aum further evidenced this in written correspondence dated October 28, 2010 stating:
“The ceasing of the construction operations is required while required administrative paper work for the construction of the project is reviewed and approved by FEMA. Once the required paper work has been approved, we will inform you so that you may resume your construction of the project.”
93. Relying on Dannenbaum’s statements regarding FEMA’s requirement that work be stopped, Peleo immediately ceased construction on the [fire station].
94. At no time did Chambers County or Defendants indicate to Peleo that the construction plans were not yet wholly approved by FEMA. Without FEMA approval, funding was not obtained as told to Peleo at the pre-bid conference. At no time did Chambers County or Defendants indicate to Peleo that if FEMA funding was lost that Chambers County was going to fund the reconstruction of the [fire station] itself.
95 .... After forty days, Dannenbaum sent correspondence stating Peleo was to remobilize and continue construction. 96. Peleo then sent Chambers County and Defendants notice of termination ... based upon the misrepresentations Defendants made to Peleo regarding FEMA requiring the work stoppage while reviewing and approving paper work Defendants, as Chambers County’s construction manager, failed to gain approval on prior to construction.
1. Dannenbaum Engineering, McGarraugh, and Hirshman
It is undisputed by the parties that McGarraugh is a licensed architect and that Hirshman is a licensed engineer. See Tex. Civ. Prao. & Rem.Code Ann. § 150.002(a) (requiring a certificate of merit to be filed in appropriate circumstances when the claim is against a licensed or registered professional); see also Tex. Civ. Prac. & Rem.Code Ann. § 150.001(1) (including licensed architects and engineers as licensed professionals). It is also undisputed that Dannenbaum Engineering is the firm in which McGar-raugh and Hirshman practice. See id. § 150.001(1) (including firm in which licensed professionals practice as licensed professional). The remaining question, then, is whether the claims Peleo Construction brought against them arose “out of the provision of professional services.” Id. § 150.002(a).
In the start of its section asserting fraudulent misrepresentation against ap-pellees, Peleo Construction explicitly recognized that McGarraugh and Hirshman “made representations to Peleo in regard to the” fire station “in their capacities as a registered architect and registered professional engineer and as representatives of Dannenbaum.” Moreover, all of the misrepresentations that Peleo Construction alleged that McGarraugh, Hirshman, and Dannenbaum Engineering made were made in the context of their participation in the redesign and construction of the fire station.
Peleo Construction argues that its claims of fraudulent misrepresentation did not require a certificate of merit because its claims concern misrepresentations regarding FEMA-approved funding and such misrepresentations are unrelated to the provision of professional services. We hold that this argument is based on too narrow of a reading of the statute.
In 2009, the Legislature amended section 150.002. Act of May 27, 2009, 81st Leg., R.S., ch. 789, § 2, 2009 Tex. Gen.
Contrary to Peleo Construction’s assertion, section 150.002 does not require the specific acts creating the claim for the tort also constitute the provision of professional services. Instead, the acts creating the claim must “aris[e] out of the provision of professional services.” Tex. Civ. Prac. & Rem.Code Ann. § 150.002(a); see also TDIndustries,
The Fort Worth Court of Appeals reached a similar conclusion in Capital One, N.A. v. Carter & Burgess, Inc.,
One of the plaintiffs arguments on appeal was that discussions about a land easement, its procurement, and its recording in the real property records “do not arise out of the provision of [Carter & Burgess’s] professional services.” Id. at 480. The court noted that the plaintiffs architect had contracted with Carter & Burgess to “provide professional engineering services in connection with” the development of the land. Id. at 480-81. The express language of the contract acknowledged the use of professional engineering and surveying services. Id. at 481. The court held that
the only reason that [the plaintiff] would have to rely upon [Carter & Burgess’s employee’s] alleged false representations ... was because the statements were made as part of [Carter & Burgess’s] performing a professional service necessary for the planning, progress, or completion of [its] engineering services — an activity that expressly constitutes “the practice of engineering.”
Id.
The same reasoning applies here. The alleged misrepresentations were made during a pre-bid conference where Hirsh-man and Amundson explained the project to Peleo Construction and during Dan-nenbaum Engineering’s oversight of Peleo Construction’s construction of the fire station according to Dannenbaum Engineering’s specifications. The matter of funding from FEMA also required Dannenbaum Engineering to communicate with FEMA to explain why the interior ramp was need
Peleo Construction relies on a number of eases for its argument that it did not have to file a certificate of merit. See M-E Engineers, Inc. v. City of Temple,
In M-E Engineers, the City of Temple sued an engineer and his firm, alleging negligence and breach of contract.
The most obvious distinction with this case is that no certificate of merit was filed here. More importantly, simply because any affiant for Peleo Construction would not have been required to explain how Peleo Construction meets every element for its fraudulent inducement claim does not mean that a certificate of merit was not required.
In Howe-Baker, the plaintiffs joined one defendant ten months after suit had been filed.
In Howe-Baker, there was no indication that the joined-defendant was providing professional services. See id. Accordingly, there were no professional services from which the alleged tort could have arisen. Here, the alleged fraudulent misrepresentations arose directly from the professional services that McGarraugh, Hirshman, and Dannenbaum Engineering were providing.
Similarly, in TDIndustñes, there was no indication that the defendant’s operation of a freight elevator arose from the provision of professional services. 339 S.W.3d at
While the defendant was a licensed professional engineering firm, there is no indication that its operation of the freight elevator arose from the provision of professional services. Id. In reaching this holding, we clarified that we did “not take the position that operation of a freight elevator could never implicate an engineer’s specialized knowledge or judgment; there is simply a reasonable basis for the trial court to determine that the circumstances pled by [the plaintiff] do not implicate such knowledge or judgment.” Id. at 755.
Curtis & Windham is part of a line of cases following the 2005 amendment of section 150.002 holding that, despite the changes to it, the statute required a certificate of merit for only negligence claims.
Similarly, Gomez also interpreted the 2005 amendment and held that the statute did not apply to claims other than negligence.
We hold that Peleo Construction was required to file a certificate of merit along with its first-filed petition asserting claims of fraudulent inducement against McGar-raugh, Hirshman, and Dannenbaum Engineering. We overrule Peleo Construction’s sole issue as it applies to them.
2. Amundson and Amundson Consulting
Section 150.002 requires a certificate of merit to be filed with any applicable claim brought against a “licensed or registered professional.” Tex. Civ. Prac. & Rem.Code Ann. § 150.002(a). “ ‘Licensed or registered professional’ means a licensed architect, licensed professional engineer, ... or any firm in which such licensed or registered professional practices.” Id. § 150.001(1). The term does not include, however, third-party contractors with the firm. See id.
Amundson Consulting had a contract with Dannenbaum Engineering to provide support personnel. Amundson was the only person identified as support personnel under the contract. While the contract provided that Amundson would work under the supervision, direction and control of Dannenbaum Engineering, Amundson remained an employee of Amundson Consulting. Peleo Construction argues that because Amundson and Amundson Consulting were not employees of Dannenbaum Engineering, they have no basis to claim any right to a certificate of merit afforded to Dannenbaum Engineering. We agree.
Amundson and Amundson Consulting acknowledge that they do not fit within the
In Capital One, the contract at issue required obtaining five easements.
On appeal, the plaintiff argued that it did not have to file a certificate of merit because Weigand was not a licensed or registered professional. Id. at 481. Wei-gand was an unlicensed intern. Id. The court noted, however, that the plaintiff sued Carter & Burgess, not Weigand. Id. It held that the plaintiff could not circumvent the requirements of filing a certificate of merit by alleging that the firm was liable for the negligence committed by an unlicensed employee in the course and scope of carrying out the firm’s provision of professional services. See id.
Similarly, in Sardari, the plaintiff sued Carter & Burgess without filing a certificate of merit.
These cases have no application to the present case. Peleo Construction is asserting a claim directly against Amundson and Amundson Consulting. It is not trying, in this instance, to hold another party liable for Amundson’s or Amundson Consulting’s actions.
We hold that Peleo Construction was not required to file a certificate of merit along with its claims against Amundson and Amundson Consulting. We sustain Peleo Construction’s sole issue as it applies to them.
Conclusion
We affirm the trial court’s order dismissing Peleo Construction’s claims against McGarraugh, Hirshman, and Dan-nenbaum Engineering. We reverse the trial court’s order dismissing Peleo Construction's claims against Amundson and Amundson Consulting. We remand for further proceedings.
