CAJUN INDUSTRIES, LLC v. CALGON CARBON CORPORATION and O‘NEAL CONSTRUCTORS, LLC
CAUSE NO. 1:24CV107-LG-RPM
IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI SOUTHERN DIVISION
February 11, 2026
MEMORANDUM OPINION AND ORDER GRANTING CALGON CARBON CORPORATION‘S MOTION TO DISMISS COUNTS 2, 4, AND 5 OF THE AMENDED COMPLAINT
Cajun Industries, LLC, filed this lawsuit against O‘Neal Constructors, LLC, and Calgon Carbon Corporation, seeking payment for work it performed on the Calgon Carbon G-Line Expansion Project in Bay St. Louis, Mississippi. Calgon, the project owner, has filed a [51] Motion to Dismiss Counts 2, 4, and 5 of Cajun‘s [15] Amended Complaint pursuant to
BACKGROUND
Calgon retained O‘Neal to serve as the general contractor on a construction project to expand its facility. O‘Neal entered into one subcontract with Cajun for site development work and another for concrete work. Cajun filed this lawsuit against O‘Neal and Calgon in the Circuit Court of Hancock County, Mississippi, and O‘Neal removed the case to this Court on the basis of diversity jurisdiction.
The situation became so poor that Calgon began taking over the project directly and directly paying subcontractors, fulfilling the contract obligations that O‘Neal had entered into. Indeed, Calgon created the expectation amongst those working on the project that Calgon would fulfill O‘Neal‘s obligations if O‘Neal failed to do so.
Am. Compl. [15] at 5. Cajun claims it “diligently performed its work and supplied its materials,” but O‘Neal and Calgon failed to pay Cajun what it is owed. Id. It has filed a breach of contract claim against O‘Neal, a claim for payment pursuant to
DISCUSSION
I. STANDARD OF REVIEW AND CHOICE OF LAW
When deciding a
Federal courts sitting in diversity apply the forum state‘s substantive law. In re Katrina Canal Breaches Litig., 495 F.3d 191, 206 (5th Cir. 2007) (citing Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78 (1938)). When analyzing substantive issues, the federal court first looks to the decisions of the state‘s highest court, if available. Cerda v. 2004-EQR1 L.L.C., 612 F.3d 781, 794 (5th Cir. 2010). Otherwise, the federal court generally looks to decisions of the state‘s immediate appellate court. Id. When state courts have not provided guidance, the federal court “must attempt to predict state law, not to create or modify it.” Am. Waste & Pollution Control Co. v. Browning-Ferris, Inc., 949 F.2d 1384, 1386 (5th Cir. 1991) (citation modified).
II. COUNT 2 OF THE AMENDED COMPLAINT
In Count 2, Cajun states that it is pursuing a “Section 85-7-405 Payment Action.” Am. Compl. [15] at 6. This statute provides:
A payment action for the recovery of the amount of the lien claimant‘s claim against the party he contracted with shall be commenced in county, circuit or chancery court within one hundred eighty (180) days from the date of filing for record of the lien claimant‘s claim of lien.
Calgon argues that this statute does not allow a contractor to file a payment action against a project owner when there is no contract between the contractor and owner. Cajun responds that “Calgon is correct that the statute requires that such an action be brought against ‘the party [the claimant] contracted with,’
However, just because the statute does not prohibit a payment action against an owner does not necessarily mean that it permits one. Under Mississippi law, “where a statute enumerates and specifies the subject or things upon which it is to operate, it is to be construed as excluding from its effect all those not expressly mentioned or under a general clause, those not of like kind or classification as those enumerated.” Jones Cnty. Sch. Dist. v. Dep‘t of Revenue, 111 So. 3d 588, 601 (Miss. 2013) (citation modified). The lack of a statutory provision that prohibits payment actions against project owners does not mean that the statute allows contractors to file payment actions against owners. Thus, Calgon cannot extend the scope of
In Count 2 of the Complaint, Cajun also seeks recovery of the prompt payment penalty set forth at
III. COUNT 4 OF THE AMENDED COMPLAINT
A. Alternative Relief
Cajun argues that the Court should allow its quantum meruit claim to
Cajun also argues, “[S]o long as any one of Cajun‘s alternative statements of recovery is sufficient, then the whole pleading is.” Pl.‘s Resp. Mem. [55] at 4 (citing Perkins v. United Surgical Partners Int‘l, Inc., No. 23-10375, 2024 WL 1574342 at *5 n.9 (5th Cir. 2024)). This argument is not well taken. In the unpublished Perkins decision, the Fifth Circuit panel cited
A party may set out 2 or more statements of a claim or defense alternatively or hypothetically, either in a single count or defense or in separate ones. If a party makes alternative statements, the pleading is sufficient if any one of them is sufficient.
Perkins, 2024 WL 1574342 at *5 n.9 (citing
B. Rule 12(b)(6) Analysis
“Quantum meruit recovery is a contract remedy which may be premised either on express or ‘implied’ contract, and a prerequisite to establishing grounds for quantum meruit recovery is claimant‘s reasonable expectation of compensation.” Tupelo Redevelopment Agency v. Gray Corp., 972 So. 2d 495, 514 (Miss. 2007) (citation modified).
The essential elements of recovery under a quantum meruit claim are: (1) valuable services were rendered or materials furnished; (2) for the person sought to be charged; (3) which services and materials were accepted by the person sought to be charged, used and enjoyed by him; and (4) under such circumstances as reasonably notified person sought to be charged that plaintiff, in performing such services, was expected to be paid by person sought to be charged.
Id. (citation modified). The doctrine can apply when a party seeks compensation for additional work not contemplated by a contract between the parties. Id. at 515. In this circumstance, a quantum meruit “award would require a finding by the court that the labor was not anticipated by the contract, and also that there were no provisions of the contract by which payment could be made for unanticipated labor.” Id. (citation modified) (quoting Citizens Nat‘l Bank v. L.L. Glascock, Inc., 243 So. 2d 67, 70 (Miss. 1971)).
“[G]enerally, where there is a contract, and the contract has not failed, the parties may not abandon the contract and resort to quantum meruit.” Waste Mgmt. of Miss. Inc. v. Jackson Ramelli Waste LLC, 301 So. 3d 635, 641 (Miss. 2020). Thus, “a sub-subcontractor cannot sue on quantum meruit against a primary contractor for work done under an express contract with another person” under Mississippi law. Redd v. L & A Contracting Co., 151 So. 2d 205, 208 (Miss. 1963). This is because, “in law and common sense, there cannot be an express and an implied contract for the same thing, existing at the same time.” Id. (quoting Walker v. Brown, 28 Ill. 378, 383 (1862)). Thus, the Redd court reasoned that a sub-subcontractor did not have any reason to believe a prime contractor owed it payment at the time the work was being done because the sub-subcontractors’ contract was with the subcontractor and not with the prime contractor. Id. at 208.
This Court has previously addressed a quantum meruit claim that arose out of the same project at issue here. See Cuevas Mach. Co., Inc. v. Calgon Carbon Corp., No. 1:24-CV-114-HSO-BWR, 2025 WL 1135035, at **7-9 (S.D. Miss. Mar. 20, 2025).2 There, the Court found that another subcontractor (Cuevas Machine Company, Inc.) had not stated a quantum meruit claim against Calgon because: (1) the work was performed pursuant to a subcontract with O‘Neal; (2) Cuevas did not have “a reasonable expectation of payment outside the ambit of a valid contract“; and (3) Calgon was not on notice that Cuevas would expect payment from it. Id. at *9.
In its Response Memorandum, Cajun claims that “Calgon represented directly to subcontractors that it would pay them.” Pl.‘s Resp. Mem. [55] at 3 (citing Am. Compl. [15] at 4-5). The Court has not located such an allegation in the Amended Complaint; rather, Cajun alleges that Calgon agreed to “purchase certain materials . . . directly from vendors secured by Cajun.” Am. Comp. [15] at 2 (emphasis added). Cajun also quoted the subcontract, which provided that Calgon would “directly make payment to Subcontractor‘s Vendor(s),” not Cajun. Id. at 3 (quoting Ex. A at 1; Ex. B at 11; Ex. C at 4). It is unclear how Calgon‘s promise to directly pay vendors could give Cajun a reasonable expectation that Calgon would pay Cajun for other materials or work. Furthermore, these allegations do not support a finding that Calgon‘s practice of directly paying vendors put Calgon on notice that Cajun would expect direct payment for other materials and work. As a result, Cajun‘s “direct purchase item” allegations do not state a plausible claim for quantum meruit.
Cajun also argues that it can recover under a quantum meruit theory
[I]n order to recover for work and labor on the theory of an implied contract, it is ordinarily deemed essential to show that the services were rendered under the reasonable expectation that they would be paid for by the person sought to be charged, and the person sought to be charged knew that the services were being performed with the expectation that he would pay for such work.
Id. at 243-44. The court noted that the Redd decision “reinforced” this general rule when it held that a sub-subcontractor “could only reasonably expect to be paid by the subcontractor” with which it had a contract. Id. at 244.
Here, it is undisputed that Cajun had a valid contract with O‘Neal. As a result, pursuant to Redd, Cajun could only reasonably expect to be paid by O‘Neal, and Calgon had no reason to believe that it would be expected to pay Cajun. Cajun has not stated a plausible quantum meruit claim against Calgon.
C. Whether The Court Should Reserve Ruling Until After Discovery Is Completed
Cajun argues that it is the Mississippi courts’ practice “to reserve rulings on
IV. COUNT 5 OF THE AMENDED COMPLAINT
A. Waiver
Cajun argues that Calgon waived its request for dismissal of its unjust enrichment for failing to adequately brief it. However, Calgon discussed Cajun‘s quantum meruit and unjust enrichment claims together, and it argued that the same principles apply to both claims. See Def.‘s Mem. [52] at 8-11, 12 n.2. Cajun‘s waiver argument is not well taken.
B. Rule 12(b)(6) Analysis
“To collect under an unjust enrichment or quasi-contract theory, the claimant must show ‘there is no legal contract but . . . the person sought to be charged is in possession of money or property which in good conscience and justice he should not retain, but should deliver to another.‘” Johnston v. Palmer, 963 So. 2d 586, 596 (Miss. Ct. App. 2007) (citation modified). “[U]njust enrichment is an implied contract claim comparable to quantum meruit . . . .” Miss. State Port Auth. at Gulfport v. Yilport Holding A.S., 416 So. 3d 83, 96 (Miss. 2025). Both this Court and the Mississippi Court of Appeals have applied the general rule recognized in Redd to an unjust enrichment claim:
As a general rule, in order to recover for work and labor on the theory of an implied contract, it is ordinarily deemed essential to show that the services were rendered under the reasonable expectation that they would be paid for by the person sought to be charged, and the person
sought to be charged knew that the services were being performed with the expectation that he would pay for such work.
O‘Brien v. Pegues, 325 So. 3d 1228, 1236 (Miss. Ct. App. 2021) (quoting Redd, 151 So. 2d at 20); Cuevas, 2025 WL 1135035, at **7-8. As a result, Calgon is correct that Cajun‘s unjust enrichment claim should be dismissed for the same reason as its quantum meruit claim.
Furthermore, “[t]here is nothing inherently unjust about enrichment“; an unjust-enrichment claim applies only to “enrichments . . . objectively seen as unjust.” Omnibank of Mantee v. United S. Bank, 607 So. 2d 76, 92 (Miss. 1992).
The mere fact that a third person . . . benefits from an arrangement between two other persons . . . does not make such third person liable in quasi contract, unjust enrichment, or restitution. Moreover, where a third person benefits from an agreement . . . entered into between two other persons, in the absence of some misleading or wrongful act by the third person, the mere failure of performance by one of the contracting parties . . . does not give rise to a right of restitution against the third person . . . .
Id. at 92-93. However, if the person who benefitted “participated in or caused a breach of some duty imposed in law,” the enrichment is unjust. Id. at 92; see also Indus. Indem. Co. v. Truax Truck Line, Inc., 45 F.3d 986, 991 (5th Cir. 1995) (finding that a district court erred when it held that a party was unjustly enriched without first determining “whether [that party] procured the ‘mistake’ or participated in or caused a breach of some duty imposed in law“); On-Site Fuel Serv., Inc. v. Loomis Armored US, Inc., No. 3:08CV658 HTW-LRA, 2010 WL 11682195, at *3 (S.D. Miss. Aug. 10, 2010) (a plaintiff that alleges no misleading or
In support of its unjust enrichment claim, Cajun alleges:
Cajun provided services to Calgon, both directly and through Calgon‘s general contractor, in the good faith understanding that Cajun would be paid for those services. Calgon benefited from Cajun‘s services. Despite formal demand for payment, Calgon refuses to pay. . . . By its failure to pay, Calgon has been unjustly enriched at Cajun‘s expense.
Am. Compl. [15] at 9. Since Cajun has not alleged that Calgon did anything to prevent O‘Neal‘s failure to pay under the subcontracts, it has not stated a plausible claim for unjust enrichment.
CONCLUSION
Calgon has not provided allegations sufficient to state a plausible claim for quantum meruit or unjust enrichment. It has also failed to state a claim for recovery under
IT IS THEREFORE ORDERED AND ADJUDGED that the [51] Motion to Dismiss filed by Calgon Carbon Corporation is GRANTED. Counts 2, 4, and 5 of Cajun Industries, LLC‘s Amended Complaint are DISMISSED WITHOUT PREJUDICE.
SO ORDERED AND ADJUDGED this the 11th day of February, 2026.
s/ Louis Guirola, Jr.
LOUIS GUIROLA, JR.
UNITED STATES DISTRICT JUDGE
