This is a suit brought by a subcontractor of a subcontractor against a primary contractor for labor done and materials furnished by plaintiff.
Appellant^ filed a declaration in two counts. The first count of the declaration alleged that the defendant entered into a construction contract with E. O. Spencer and others to build a bridge and roadway, and furnish all labor and material used in the project. It further alleged that L & A Contracting Company entered into a subcontract with one Perry Vance, d. b. a. Perry Vance Construction Company, to perform part of the initial contract work, namely, the making of a dirt fill, abutment and approaches to a bridge. Thereafter, Perry Vance employed appellants to make the aforementioned abutments and approaches. The declaration further charges that appellants proceeded to build the abutments and approaches with a knowledge and under the supervision of the primary contractor, L & A Contracting Company, a corporation. It is alleged that appellee knew that appellants were performing the work for Perry Vance, and that it agreed to see that appellants
The second count to appellants’ declaration reiterated the allegation that appellants did the work set out in the first count and furnished the labor and materials incident thereto. Appellants then charged that L & A Contracting Company supervised said work and accepted the benefits of same, and "that by reason of the Defendant having accepted the benefit of Plaintiffs work it became and is liable to Plaintiffs in the sum of $2,175.00.”
Appellee filed a demurrer to the declaration alleging that the declaration failed to state a cause of action; that the declaration shows that there was no privity of contract between B. P. Bedd and B. A. Hill and L & A Contracting Company; that the declaration sought to recover from L & A Contracting Company upon an alleged written guaranty and that the attached letters to the declaration "fails to take said demand out of the statute of frauds”; and that the alleged promise and agreement between appellants and appellee violated the statute of frauds, particularly Sec. 264, Miss. Code 1942, Bee.
The trial court sustained the demurrer upon the ground that (a) a stop notice, or written notice to stop pay
Appellants refused to plead further and the trial court dismissed the suit. Appellants appealed to this Court and allege that the action of the trial court in sustaining the demurrer was reversible error, because the second count of the declaration sufficiently alleges a cause of action of quantum meruit.
I.
Appellants admit concederé argumentum that the writing (letters) attached to the declaration are not sufficient to bind appellee, but it is said “that Count II of the declaration states a good and sufficient cause of action upon the theorem of quantum meruit.”
This Court has heretofore held that the contract bond of a principal contractor to the owner was not liable under Sec. 2276, Code 1930, or Sec. 374, Code 1942, to a remote materialman or remote subcontractor for the material sold to the subcontractor and used in the construction of a private building. The Alabama Marble Company v. U. S. F. & G. Co., et al.,
(Hn 1) We are of the opinion, and so hold, that the trial judge was correct in holding that when the subcontractor failed to pay the sub-subcontractor, Sec. 372,
(Hn 2) It is also apparent that tbe letters attached to tbe declaration are not sufficient as a guaranty to lift tbe alleged promise to stand for tbe debt or default of tbe subcontractor out of tbe statute of frauds, and are not sufficient to establish a written promise to pay tbe sub-subcontractor. (Sec. 264, Miss. Code 1942). See Craft v. Lott,
II.
Appellants contend that tbe demurrer to tbe second count of tbe declaration should have been overruled because defendant (appellee here) knowingly accepted tbe work and materials furnished by appellants for and on behalf of tbe primary contractor and that said work was done for appellee, that it accepted tbe benefits therefrom and since there was no contract between tbe parties, appellants are entitled to recover from appellee in as-sumpsit under tbe common law on tbe “theorem of quantum meruit.”
(Hn 3) Quantum meruit means literally “as much as be deserves”, 73 C. J. S. 1269. It is said of quantum meruit by way of example, in Bouvier’s Law Dictionary, 2d Ed., p. 800, that “When a person employs another to do work for him, without any agreement as to bis compensation, tbe law implies a promise from tbe employer to tbe workman that be will pay him for bis services as much as be. may deserve or merit.” See also 58 Am. Jur., Sec. 4, Work and Labor, p. 512.
(Hn 4) There was no express contract between the primary contractor (appellee here) and the (appellants) sub-subcontractors to work on the abutments and approaches to the bridge. Appellee had no reason to believe appellants were doing any work for it. On the other hand, appellee had sufficient reason'to believe the work was being done for the subcontractor, P. N. Vance, since appellants contracted with Vance and under this contract they were required to do the work for which they here sued the appellee. Appellants did not have any reason to believe appellee owed appellants at the time the work was being done. Appellants’ contract was with Vance and not with appellee, and there is no implied contract on the part of appellee to pay for the work due appellants by P. N. Vance.
In the case of Carter, et al. v. Collins,
In the case of Martin 0. Walker v. James Brown and James Hollingsworth,
“As in physics, two solid bodies cannot occupy the same space at the same time, so in law and common sense, there cannot be an express and an implied contract for the same thing, existing at the same time. This is an axiomatic truth. It is only where parties do not expressly agree, that the law interposes and raises a promise.
“The error in this whole proceeding arises upon the assumption, that the plaintiff in error might become liable, under the implication of law, that he should pay the reasonable worth of services, beneficial to him, bestowed upon his property, with his knowledge and acquiescence, notwithstanding such services were rendered under an express agreement with another person.
“An express contract, executory in its provisions, must totally exclude any such implication. One party agreed, in consideration of the other to pay, to render the service; the other, in consideration of a promise to render the service, agrees to pay. One is the consideration and motive for the other, and each equally excludes any other consideration, motive, or promise.”
In the case of Zalk-Josephs Company, d.b.a. Triange Steel & Supply Company v. Wells Cargo, Inc. (Nev.
In the case of Mid-State Tile Company v. Chaudoir, (La. App. 1955),
In the case of Woodward Iron Company v. Dabney,
(Hn 5) As a general rule, in order to recover for work and labor on the theory of an implied contract, it is ordinarily deemed essential to show that the services were rendered under the reasonable expectation that they would be paid for by the person sought to be charged, and the person sought to be charged knew that the services were being performed with the expectation that he would pay for such work. 71 C. J., Work and Labor, Sec.
6,
p. 41; 98 C. J. S., Work & Labor, Sec. 8, p. 724. This Court has adopted this rule in the following cases: Miller v. Fisher,
From the foregoing, we have reached the conclusion that the trial judge was correct in sustaining the demurrer to the declaration, and the judgment of the trial court should be sustained.
Affirmed.
