BUSINESS INTERIORS FLOOR COVERING BUSINESS TRUST VS. GRAYCOR CONSTRUCTION COMPANY INC. & others.
SJC-13507
Supreme Judicial Court of Massachusetts
June 17, 2024
Suffolk. February 7, 2024.
NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-1030; SJCReporter@sjc.state.ma.us
Present: Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, & Dewar, JJ.
Contract, Construction contract, Subcontract, Performance and breach, Impossibility of performance. Practice, Civil, Affirmative defense, Judgment, Summary judgment. Payment. Time. Judgment.
Civil action commenced in the Superior Court Department on September 15, 2020.
The case was heard by Diane C. Freniere, J., on a motion for summary judgment, and entry of separate and final judgment was ordered by her.
The Supreme Judicial Court on its own initiative transferred the case from the Appeals Court.
Matthew B. Lysiak (Mark B. Lavoie also present) for Graycor Construction Company Inc.
Andrew R. Dennington (Ryan O. Forgione also present) for the plaintiff1.
Joseph A. Barra, for Associated Subcontractors of Massachusetts, Inc., amicus curiae, submitted a brief.
KAFKER, J. The prompt pay act,
Graycor Construction Company Inc. (Graycor), a general contractor for a movie theater project in Boston‘s North End section, entered into a subcontract with Business Interiors Floor Covering Business Trust (Business Interiors). Graycor failed to approve or reject three separate applications for periodic payments made by Business Interiors for the flooring work it performed on the project. Business Interiors sued Graycor in the Superior Court for breach of contract and other claims. The Superior Court granted Business Interiors‘s motion for summary judgment on its breach of contract claim and entered separate and final judgment. Graycor appealed.
On appeal, Graycor asserts that there is a question of material fact as to whether the original contract is a “contract for construction” within the meaning of the act, because the prompt pay act references liens pursuant to
We hold that the prompt pay act cross-references liens that “may be established under sections 2 or 4 of chapter 254” for a limited purpose: to define in broad terms the types of contracts subject to the act.
This case also raises an important procedural question regarding the proper application of separate and final judgment pursuant to the prompt pay act. The fact that a payment has been withheld in violation of the act does not, alone, merit the entry of a separate and final judgment as the Appeals Court held in Tocci Bldg. Corp. v. IRIV Partners, LLC, 101 Mass. App. Ct. 133 (2022) (Tocci), a decision relied upon by the motion judge in the instant case. Rather, claims, cross claims, and counterclaims must all be carefully examined together to determine whether the various elements of
1. Background. a. Facts. In November 2018, Graycor entered into a general contract with Pacific Theatres Exhibition Corp. (Pacific) for the construction of a multi-screen movie theater known as ArcLight Boston Garden on property that Pacific leased from Podium Owner, LP, the owner of the property. The original maximum price for constructing the movie theater was $18,962,890. Graycor in turn executed a subcontract with Business Interiors for Business Interiors to complete the flooring for the movie theater. The subcontract had an original total price of $528,426. Change orders increased the final subcontract price to $608,158.
The subcontract includes various provisions addressing periodic payments, including the requirement that
“[t]he Subcontractor [Business Interiors] shall submit its periodic applications for payment of the Subcontract Price (the ‘Periodic Application‘) on a form acceptable to Contractor [Graycor] not later than the 15th calendar day of the month . . . .”
“Subject to the other terms of the Subcontract, the Contractor
will make payment of a Periodic Application for payment promptly upon the Contractor‘s receipt of payment from the Owner [Pacific] for the Work that is the subject of the Periodic Application, but in no event later than the date required by applicable law.”
On March 20, 2020, Business Interiors submitted an application for payment no. 19 to Graycor, seeking to be paid $75,745.40. Graycor did not dispute the dollar amount listed, nor did it provide written notice rejecting the application. Nevertheless, Graycor did not pay Business Interiors any portion of the $75,745.40. On April 22, 2020, Business Interiors submitted an application for payment no. 20 to Graycor for $26,421.30. Again, Graycor did not dispute the dollar amounts, nor did it provide written notice rejecting the application, but it did not pay any portion of the $26,421.30 requested. On August 18, 2020, Business Interiors submitted its final application for payment in the amount of $25,022.30. As with the other two applications for payment, Graycor did not dispute the dollar amount, provided no written notice rejecting Business Interiors‘s final application for payment, and did not pay any portion of the $25,022.30 itemized in the final application for payment.
Around the same time, Graycor was itself attempting to get paid by Pacific, which was experiencing financial difficulties due to the COVID-19 pandemic. In late March 2020, a Graycor project manager sent an e-mail message to Pacific‘s director of finance to determine the status of several overdue unpaid invoices. Pacific‘s director of finance responded that “due to COVID-19, all our theaters were forced to close and at this time we do not have any revenue coming in” and “all of our payables are being held until further notice.” After that, based on the record before us, it appears that communication between Pacific and Graycor ceased.
b. Procedural history. In September 2020, Business Interiors sued Graycor; Pacific; Podium Developer LLC; and Podium Owner, LP,3 in the Superior Court, seeking to recover the unpaid balances. Specifically, Business Interiors sued Graycor for breach of contract, breach of the covenant of good faith and fair dealing, violation of
In June 2022, Business Interiors served the parties with a motion for summary judgment on its breach of contract (count I) claim against Graycor. In response, Graycor, for the first time, raised an impossibility defense. At a December 2022 hearing on the motion, Graycor also argued for the first time that the subcontract was not covered by the prompt pay act because it was not eligible for a lien under
2. Discussion. a. Standard of review. We review the Superior Court‘s grant of summary judgment de novo. Adams v. Schneider Elec. USA, 492 Mass. 271, 280 (2023). “Summary judgment is appropriate where there is no material issue of fact in dispute and the moving party is entitled to judgment as a matter of law. We review the evidence in the light most favorable to the party against whom summary judgment entered, in this case, Graycor (quotations and alteration omitted).” Id., quoting Le Fort Enters., Inc. v. Lantern 18, LLC, 491 Mass. 144, 148-149 (2023).
b. Prompt pay act. The prompt pay act, like any other statute, “must be interpreted according to the intent of the Legislature ascertained from all its words construed by the ordinary and approved usage of the language, considered in connection with the cause of its enactment, the mischief or imperfection to be
i. Statutory framework of the act. The act “applies to certain private contracts for construction with respect to projects for the erection, alteration, repair, or removal of buildings or structures, or for other improvements to real property, where the ‘contract with the project owner has an original contract price of $3,000,000 or more.‘” Tocci, 101 Mass. App. Ct. at 134, quoting
The act provides that
“[e]very contract for construction shall provide reasonable time periods within which: (i) a person seeking payment under the contract shall submit written applications for periodic progress payments; (ii) the person receiving the application shall approve or reject the application, whether in whole or in part; and (iii) the person approving the application shall pay the amount approved.”
According to the act, “[a]n application for a periodic progress payment which is neither approved nor rejected within the time period shall be deemed to be approved unless it is rejected before the date payment is due.”
Under the plain language of the act, Graycor had twenty-two days from the date of submission of each of Business Interiors‘s three applications for payment to approve or reject the application.4 However, Graycor neither approved nor rejected Business Interiors‘s applications within these time periods. Thus, according to the act, all three applications for payment were “deemed to be approved,” and Graycor was required to pay them.
Graycor and Business Interiors appear to agree on this basic requirement of the act but disagree over whether this decides the question of summary judgment on count I. Graycor disputes whether the subcontract between it and Business Interiors is a “contract for construction” as defined by
ii. Definition of “contract for construction.” We conclude that the issue whether the subcontract meets the definition of a “contract for construction,” which was raised for the first time at the hearing on the summary judgment motion, was not properly raised, and that it was not an abuse of discretion for the motion
The act defines a “contract for construction” as “a contract for which a lien may be established under [
“A person entering into a written contract with the owner of any interest in real property, or with any person acting for, on behalf of, or with the consent of such owner for the whole or part of the erection, alteration, repair or removal of a building, structure, or other improvement to real property, or for furnishing material or rental equipment, appliances, or tools therefor, shall have a lien upon such real property . . . owned by the party with whom or on behalf of whom the contract was entered into . . . when notice of said contract is filed or recorded in the registry of deeds . . . .”
While
“Whoever furnishes labor, . . . or who furnishes material, or both labor and material, or furnishes rental equipment, appliances or tools, or who performs professional services, under a written contract with a contractor, or with a subcontractor of such contractor, may file or record in the registry of deeds . . . a notice of his contract . . . Upon filing or recording a notice . . . and giving actual notice to the owner of such filing, the subcontractor shall have a lien upon such real property . . . owned by the party who entered into the original contract . . . .”
The original contract price is over $3 million, so the only issue is whether the subcontract is “a contract for which a lien may be
By referencing contracts for which liens “may be established” pursuant to
Even Graycor recognizes that, at least when the contract was entered into, Business Interiors might have established a lien pursuant to
iii. Availability of common-law defenses under the act. The primary issue presented in this case is whether the prompt pay act precludes a general contractor from asserting common-law affirmative defenses to a breach of contract claim based on the failure to pay. As discussed supra, the act provides: “An application for a periodic progress payment which is neither approved nor rejected within the time period shall be deemed to be approved unless it is rejected before the date payment is due.”
“[A] statutory repeal of the common law will not be lightly inferred; the Legislature‘s ‘intent must be manifest.‘” Passatempo v. McMenimen, 461 Mass. 279, 290 (2012), quoting Comey v. Hill, 387 Mass. 11, 20 (1982). The Legislature‘s “intent may be ‘clearly expressed’ in one of two ways: by words in the statute itself clearly stating that the statute supersedes the common law, or by ‘necessary implication.‘” Chelsea Hous. Auth. v. McLaughlin, 482 Mass. 579, 590 (2019), quoting Lipsitt v. Plaud, 466 Mass. 240, 244 (2013). “A statute preempts common-law doctrine by necessary implication where the doctrine is so repugnant to and inconsistent with the statute that both cannot stand” (quotations and citation omitted). McLaughlin, supra at 591. In other words, “[c]an the common-law doctrine [at issue] and the statute reasonably
We emphasize that the act does not expressly preempt all common-law defenses to breach of contract. If the Legislature intended for the failure to accept or reject payment within the tight time frames established by the act to eliminate all common-law defenses, “we think it would have done so explicitly” (citation omitted). See Lipsitt, 466 Mass. at 248-249. We likewise conclude that the act does not completely eliminate common-law defenses by necessary implication. Rather the statutory requirements and the common-law defenses can coexist, so long as payment is required to be made prior to, or contemporaneous with, the raising of any such defenses in any proceeding relating to the enforcement of such invoices. See McLaughlin, 482 Mass. at 591. More precisely, as explained by Associated Subcontractors of Massachusetts, Inc. (ASM), in its amicus brief: “To the extent the [contractor] has any viable contract or common[-]law defenses to payment, such defenses are still available for presentation in a subsequent forum. However, the contractor must first pay the funds purportedly owed and then seek to disgorge such funds in a succeeding adjudication.”7
In sum, payment of overdue approved invoices must be made prior to, or contemporaneous with, raising common-law defenses, or the defenses cannot be raised.8
In the instant case, however, Graycor sought to raise and pursue defenses without ever paying the invoices. This it cannot do. Summary judgment was therefore properly allowed on count I of Business Interiors‘s complaint.
c. Separate and final judgment. Relying on the reasoning of the Appeals Court in Tocci, the Superior Court issued a separate and final judgment on count I of Business Interiors‘s
complaint. Because we conclude that the prompt pay act, particularly as clarified by our decision today, requires a traditional and not truncated
In Tocci, 101 Mass. App. Ct. at 142-143, rather than conducting a traditional analysis of the factors required for rule 54 (b) certification, the Appeals Court concluded that separate and final judgment was proper because “[t]o allow the defendants to retain the moneys wrongfully withheld in violation of the statute until the final resolution of their postcompletion contract action would eviscerate the scheme for prompt payment or rejection-and-resolution created by the Legislature.” Nothing, however, in the act‘s text indicates that the Legislature intended the prompt pay act to provide for immediate appeals of the failure to accept or reject a periodic payment.11 See DeCosmo v. Blue Tarp Redev., LLC, 487 Mass. 680,
695 (2021) (“If the [statute‘s] language is clear and unambiguous, it must be interpreted as written” [citation omitted]). “[A]bsent special authorization, an appellate court will reject attempts to obtain piecemeal review of trial rulings that do not represent final dispositions on the merits” (quotations and alteration omitted). Fabre v. Walton, 436 Mass. 517, 520-521 (2002), S.C., 441 Mass. 9 (2004), quoting Ashford v. Massachusetts Bay Transp. Auth., 421 Mass. 563, 565 (1995). The unduly expansive interpretation of the preemptive effect of the act‘s “scheme” set out in Tocci, and adopted by the motion judge here, undermines the ordinary principles cautioning against interlocutory
We therefore emphasize that the traditional
against Graycor, Pacific, and Podium in addition to its prompt pay act claim,13 and cross claims by Graycor against Podium and Pacific.14 All of these additional claims should have been considered as part of the motion judge‘s
omitted]). See also Yanis v. Paquin, 96 Mass. App. Ct. 134, 140 n.12 (2019) (extending counterclaim analysis in
3. Conclusion.16 The certification and entry, pursuant to
So ordered.
WENDLANDT, J. (concurring in part and dissenting in part, with whom Dewar, J., joins). Time is of the essence under the prompt pay act,
In other words, Graycor is in material breach of the agreement not only because it failed to pay Business Interiors‘s invoices but because it failed to pay those invoices promptly. G4S Tech. LLC v. Massachusetts Tech. Park Corp., 479 Mass. 721, 733-734 (2018), quoting EventMonitor, Inc. v. Leness, 473 Mass. 540, 546 (2016) (“a material breach of a contract occurs when the breach concerns an ‘essential and inducing feature of the contract‘“).
I also agree with the court that, under the act, failure to make timely payments does not waive defenses to breach of contract. See ante at . Nothing in the act itself suggests such a waiver. See
And I agree with the court‘s holding that the act provides no basis for dispensing with our usual stringent standard for entry of separate and final judgment under
But the act merely requires the inclusion of specific terms in construction contracts governing the processing of payments, which can be enforced through a breach of contract claim.2
The Legislature chose to go no further. Contrast, e.g., House Bill No. 4730 (May 8, 2008) (earlier version of bill more broadly establishing “rights and obligations prescribed by . . . statute,” including that parties to construction contracts “shall make all payments in accordance with the terms of that contract, which shall be in accordance with the provisions of this section“). For better or worse, this is a feature of the act, not a latent error to be fixed by judicial fiat. See Commonwealth v. Calvaire, 476 Mass. 242, 245 (2017) (“We do not read into the statute a provision which the Legislature did not see fit to put there, nor add words that the Legislature had an option to, but chose not to include” [citation omitted]). Indeed, analysis of the act and its history shows, as the court concludes, that no such waiver formed any part of the compromise legislation. See ante at note 7.
Contrary to the court‘s assertion, see ante at , the act still has “meaningful consequences.” For example, subject to certain conditions, the act renders “void and unenforceable” contractual terms that purport to require a subcontractor who has not been paid timely to continue to work.
See Boston Firefighters Union, Local 718, Int‘l Ass‘n of Fire Fighters, AFL-CIO v. Boston, 491 Mass. 556, 562 (2023), citing Garcia v. Department of Hous. & Community Dev., 480 Mass. 736, 747 (2018); Hull Mun. Lighting Plant v. Massachusetts Mun. Wholesale Elec. Co., 399 Mass. 640, 642-643 (1987) (affirming “preliminary injunction ordering [plaintiff] to continue making payments to [defendant] as required by [their contracts]“). This garden-variety tool, if granted, comports with the act‘s intent to ensure subcontractors receive prompt payment, see
By contrast, the court grants Business Interiors a Pyrrhic victory. On the one hand, it affirms summary judgment in favor of Business Interiors. On the other hand, it remands the case for
