2 TON PLUMBING, L.L.C., Aрpellee/Cross-Appellant, v. Gregory THORGAARD; Kendra Thorgaard; Washington Federal, Inc., dba Washington Federal Savings, et al., Appellants/Cross-Appellees.
No. 20120390
Supreme Court of Utah
Jan. 30, 2015
2015 UT 29 | 345 P.3d 1161
INTRODUCTION
¶ 1 This case involves interpretation of various provisions of the 2009 Mechanics’ Liens statute. Specifically, we are asked to consider (1) whether attorney fees and other costs may be included in the value of a mechanics’ lien, (2) when a notice of release of lien and substitution of alternate security is timely filed, and (3) whether the attorney fees award was reasonable.
BACKGROUND
¶ 2 Appellee/cross-appellant, 2 Ton Plumbing, L.L.C. (2 Ton), contracted with BNB Development LLC, Performance Construction, Inc., and Performance Construction of Utah, LLC (сollectively, Developers) to provide plumbing-related materials and labor to fourteen properties in the Hailstone at Stillwater development in Heber City, Utah. From June through September 2008, 2 Ton furnished improvements to Lot 30, one of the Hailstone properties, but was not paid for its work.
¶ 3 On January 30, 2009, 2 Ton recorded a notice of mechanics’ lien (original notice of lien) against Lot 30 and eight other lots in the development. The notice stated that it secured $7,470.72 for “furnishing plumbing, materials and installation,” “plus interest, costs and attorney fees.” Subsequently, BNB Development (BNB), the owner of Lot 30 at the time the lien was recorded, conveyed the property to BBRP, LLC. BBRP in turn executed a trust deed for Lot 30 in favor of Zions Bancorporation (Zions).
David R. Nielson, Tracy A. Wilder, Salt Lake City, for appellee.
Ronald G. Russell, Royce B. Covington, Jeffery A. Balls, Salt Lake City, for appellants.
Associate Chief Justice NEHRING authored the opinion of the Cоurt, in which Chief Justice DURRANT, Justice PARRISH, Justice LEE, and Judge KELLY joined.
¶ 4 On July 27, 2009, after filing its original notice of lien, 2 Ton filed a complaint seeking to enforce its mechanics’ liens against Lot 30 and the other eight properties. The complaint named BBRP and Zions as defendants in the lien foreclosure action against Lot 30 and also included various other claims against the Developers, including breach of contract and joint venture liability. The following day, 2 Ton recorded a lis pendens, providing notice of the lien foreclosure action against the nine properties. BNB and Zions
¶ 5 The Developers timely filed a joint answer to the complaint, which BBRP joined. In the joint answer, BNB asserted a counterclaim against 2 Ton alleging that 2 Ton had been overpaid for its work in the Hailstone development. BBRP also independently asserted 2 Ton‘s overpayment as a defense to the lien forеclosure claim against Lot 30.
¶ 6 On October 14, 2009, Appellants Gregory and Kendra Thorgaard purchased Lot 30 from BBRP. To secure their purchase loan, the Thorgaards executed a trust deed in favor of Appellant Washington Federal (Appellants, the Thorgaards and their lender Washington Federal, will be collectively referred to as “the Thorgaards“).
¶ 7 2 Ton filed an amended complaint on November 20, 2009, which did not name the Thorgaards as defendants. The same day, 2 Ton‘s counsel wrote to the Thorgaards advising them of the lien and warning them that there would be greater legal expense if further action was necessary. The letter invited the Thorgaards to voluntarily satisfy the lien and indicated the amount owed. The Thorgaards declined the invitation.
¶ 8 On April 30, 2010, 2 Ton filed a second amended complaint, for the first time naming the Thorgaards and Washington Federal as defendants in the lien foreclosure action. 2 Ton served the Thorgaards with the complaint on May 10, 2010 and Washington Federal on June 18, 2010. Like their predecessor in interest, BBRP, the Thorgaards also contested the validity of the lien on the basis that 2 Ton had been overpaid for its work.
¶ 9 That summer, on August 5, 2010, 2 Ton recorded an amended notice of mechanics’ lien against Lot 30 in the amount of $20,983.42. The amended notice provided that “there is currently believed to be owed a total of $20,983.42 consisting of principal of $7,147.41, plus lien fees of $110, plus interest and late fees of $2,480.30, plus pro rata costs of $942.44, plus pro rata attorney fees of $10,323.27, which amount could change, should additional credits, charges, interest, costs and attorney fees be incurred.”
¶ 10 On September 16, 2010, Washington Federal recorded its notice of release of lien and substitution of alternate security and made a cash deposit of $14,942.00. This document purported to release 2 Ton‘s original January 30, 2009 notice of lien with its claim of $7,147.41. Washington Federal did not address the amended nоtice of lien that 2 Ton had recorded the month before in the amount of $20,983.42.
¶ 11 On January 12, 2011, 2 Ton filed a third amended complaint which, among other things, sought to invalidate Washington Federal‘s lien release on the grounds that it attached insufficient alternate security. 2 Ton argued that the alternate security should have been 175 percent of the amount claimed in its amended notice of lien—$20,983.42. 2 Ton also asserted a claim against the alternate security, as required by
¶ 12 On January 28, 2011, the Thorgaards moved to dismiss two counts of 2 Ton‘s third amended complaint—the lien foreclosure claim, and the claim that the lien release and substitution of alternate security was invalid. The Thorgaards contended that their lien release was valid because they properly submitted a cash deposit in the amount of 200 percent of 2 Ton‘s original lien claim and thus fully complied with the pertinent section of the Mechanics’ Liens statute,
¶ 13 Ten days after the hearing on the motion to dismiss, on June 13, 2011, 2 Ton recorded a second amended notice of mechanics’ lien against Lot 30 in the amount of $38,714.98. The second amended notice of lien alleged, again, that $7,147.41 of this amount was for improvements to the property while the remaining sum consisted of lien fees, interest, late fees, costs, and attorney fees.
¶ 14 As the litigation continued, the Thorgaards and Developers continued to dispute the validity of the lien on the basis that 2 Ton had been overpaid for its work. Ultimately, on December 5, 2011, the Thorgaards stipulated to a finding of fact that the value of the services rendered, labor performed, or materials or equipment furnished or rented by 2 Ton that had not been paid on Lot 30 was $7,147.41.
¶ 15 Following the Thorgaards’ stipulation, 2 Ton submitted affidavit testimony and exhibits to support its claim for attorney fees. 2 Ton alleged that it had incurred $37,019.53 in attorney fees and $1,543.56 in costs prosecuting its lien against Lot 30. The Thorgaards contested 2 Ton‘s claim for attorney fees on the basis that the amount was unreasonable, that attorney fees should be allocated to those defendants who caused 2 Ton to incur the majority of those fees, and that attorney fees should be awarded on a per capita basis against all fourteen lots in the development.
¶ 16 On March 19, 2012, the district court entered a ruling and order on the award of attorney fees, and on April 16, 2012, it entered a judgment against Lot 30 in the amount of $57,972.42. The judgment included $7,147.41 in principal, $1,287.50 in costs, $110 for a lien filing fee, $4,569.81 in interest, and $44,857.70 in attorney fees. The Thorgaards also appeal from this judgment.
ISSUES AND STANDARDS OF REVIEW
¶ 17 The Thorgaards and Washington Federal raise three issues on appeal. First, they contend that the district court erred by ruling that attorney fees and costs are properly included in a mechanics’ lien and therefore erroneously found their notice of release of lien and substitution of alternate security was invalid. A district court‘s interpretation of relevant statutory provisions is reviewed for correctness, giving “no deference to the district court‘s decision.”2
¶ 18 Second, the Thorgaards argue that the district court erroneously held that 2 Ton‘s amended notices of lien were timely filed. Because we hold that the amended notices of lien were invalid, we do not addrеss this issue.
¶ 19 Finally, the Thorgaards challenge the district court‘s award of $44,857.70 in attorney fees. A district court‘s calculation of attorney fees will not be overturned absent a showing that the district court abused its discretion.3
¶ 20 2 Ton raises one issue on cross-appeal. It argues that the district court erred by allowing Washington Federal to record its notice of release of lien and substitution of alternate security more than ninety days after the original owner of Lot 30 was served with a summons and complaint in the lien foreclosure action. We review questions of statutory interpretation for correctness, granting no deference to the district court‘s decision.4
ANALYSIS
¶ 21 “Mechanics’ liens are statutory creatures unknown to the common law.”5 The Utah Mechanics’ Liens statute is to be “liberally construed” to effect its purpose,6 which is “to provide protection to those who enhance the value of a property by supplying labor or materials.”7 Of course, “[w]hile it is true that our statutes are to be liberally construed to give effect to their purpose and to promote justice,” we note that “it is equally true that they should not be distorted beyond the intent of the legislature.”8 Most statutes, including this one, are the result of a legislative balancing of “competing policy considerations.”9 Accordingly, we begin our analysis with the plain language of the statute. In so doing, we read the plain language of the Mechanics’ Lien Act “as a whole and interpret its provisions in harmony with other provisions in the same statute.”10 This is because a statute “is passed as a whole” and “[c]onsequently, each part or section should be construed in connection with every other part or section so as to produce a harmonious whole.”11 However, “where the statute fails, courts cannot create rights, and should not do so by unnatural and forced construction.”12 “[A] lien created solely by stаtute depends on the terms of the statute....” 13 Because a mechanics’ lien is a “statutory creature,” we begin with a review of the relevant statutory provisions of the Mechanics’ Liens statute.
¶ 23 Under
¶ 24
¶ 26
¶ 27 The statute requires that the notice of release of lien be filed within “90 days after the day on which the person filing a notice of release of lien and substitution of alternate security is served with a summons and lien foreclosure complaint.”28 Among other things, the notice must include “as an attachment a surety bond or evidence of a cash deposit” in an amount equal to either 150 percent, 175 percent, or 200 perсent of the amount claimed by the lien claimant on his or her notice of lien.29 The surety bond or evidence of a cash deposit must be “made payable to the lien claimant” and “conditioned for the payment of ... the judgment that would have been rendered, or has been rendered against the property in the action to enforce the lien; and ... any costs and attorneys’ fees awarded by the court.”30 If the property owner disputes the amount claimed in the notice of lien, he may petition the court to hold a hearing to determine the correct amount of the lien claim “for the sole purpose of providing alternate security.”31
¶ 28 Within thirty days of recording the notice of release of lien, the property owner must serve the lien claimant with a copy.32 And within ninety days of receipt of the notice, the lien claimant must add the alternate security as a party to the lien foreclosure action if a suit is pending.33 After meeting the statutory requirements set forth
¶ 29 In short, posting the alternate security causes the lien to no longer be secured by the original real estate, and instead the lien becomes secured by the bond or cash equivalent posted. The posting of alternate security does not eliminate the lien or alter the rights and obligations of the parties. Instead, the alternate security serves as substitute security for the lien and judgment on the action to enforce the lien.35 After alternate security is substituted for the property, the lien foreclosure action proceeds against the alternate security and the party “disput[ing] the correctness or validity of the lien,” but not the subject property.36
¶ 30 The procedures under
I. THE VALIDITY OF 2 TON‘S NOTICES OF MECHANICS’ LIEN
¶ 31 Resolution of the claims before us requires interpretation of Utah‘s Mechanics’ Liens statute. “It is well settled that when faced with a question of statutory interpretation, our primary goal is to evince the true intent and purpose of the Legislature.”41 “The best evidence of the legislature‘s intent is the plain language of the statute itself.”42 “[W]e presume that the legislature was deliberate in its choice of words and used each term advisedly and in accordance with its ordinary meaning. Where a statute‘s language is unambiguous and provides a workable result, we need not
¶ 32 However, “our plain language analysis is not so limited that we only inquire into individual words and subsections in isolation; our interpretation of a statute requires that each part or section be construed in connection with every other part or section so as to produce a harmonious whole.”44 When interpreting statutory text, we presume “that the expression of one [term] should be interpreted as the exclusion of another,”45 and will not “infer substantive terms into the text that are not already there.”46 “[W]e assume, absent a contrary indication, that the legislature used each term advisedly ... [and] seek to give effect to omissions in statutory language by presuming all omissions to be purposeful.”47
A. 2 Ton‘s Amended Notices of Lien Are Invalid Because Attorney Fees and Costs Should not Be Included in the Value of a Mеchanics’ Lien
¶ 33 2 Ton recorded three notices of lien, each for the same underlying claim, but the latter two amended the amount of 2 Ton‘s mechanics’ lien claim to include attorney fees and costs up to the date of the amended notices. The Thorgaards argue that the Mechanics’ Liens statute limits a mechanics’ lien to the “value of the service rendered, labor performed, or materials or equipment furnished or rented.”48 They maintain the Utah Code does not allow a lien claimant to include attorney fees or costs incurred in prosecuting the lien claim in the “amount of the lien claim” set forth in the notice of lien.49 We agree.
¶ 34 Any reference to “attorney fees” is notably absent from
¶ 35 Viewed as a whole, the Mechanics’ Liens statute shows that our legislature created a careful plan for awarding a lien claimant attorney fees. Allowing attorney fees and other costs to be included in the original amount of a mechanics’ lien would frustrate this plan.
¶ 36 Furthermore, to allow a lien claimant to include attorney fees and costs in the lien claim would distort the provisions for the posting of alternate security.54
¶ 37 2 Ton argues that attorney fees are part of a mechanics’ lien against the property because attorney fees are costs, and costs—in addition to the amounts owed on the lien—are paid from the property sale proceeds. In essence, they contend that because the property secures both the lien and costs, attorney fees that accrue may be added to the lien against the property even before the lien foreclosure action has been resolved.55
¶ 38 2 Ton‘s position not only conflicts with the plain language of the statutory scheme, but it is inconsistent with the very nature of a lien. “In its broadest sense and common acceptation, the word ‘lien’ is understood and used to denote a lеgal claim or charge collectible out of property either real or personal, as security, for the payment of some debt or obligation.”56 Since a party has no obligation to pay attorney fees in a lien foreclosure action unless the action has concluded and that party has lost, such attorney fees cannot properly be included in the mechanics’ lien, claim amount. In Park v. Jameson, we held that attorney fees could constitute a lien on the property, but this was only after judgment on the action to enforce the lien had been awarded by the court in favor of the lien claimant.57 It would not make sense to include attorney fees in the amount of the lien claim when those attorney fees can neither be ascertained nor awarded to the lien claimant until the conclusion of the lien enforcement action (and only if the lien claimant has prevailed).
¶ 39 Our conclusion that a meсhanics’ lien is limited to “the value of the service rendered, labor performed, or materials or equipment furnished or rented”58 is supported both by a common understanding of the word “lien”59 as well as language throughout the statute that indicates that the terms “lien” and “costs and attorney fees” are separate and distinct.60 For example,
(2) A notice of release of lien and substitution of alternate security ... shall ... have as an attachment a surety bond or evidence of a cash deposit that ... is conditioned for the payment of:
(A) the judgment that would have been rendered, or has been rendered against the property in the action to enforce the lien; and
(B) any costs and attorneys’ fees awarded by the court....61
¶ 40 In view of the legislature‘s separation of subsection (A) and (B) by the conjunctive “and,” it follows that the terms “lien” and “costs and attorneys’ fees” represent separate and distinct concepts. If a mechanics’ lien could be amended to include costs and attorney fees, subsеction (B) would be rendered superfluous.62 Moreover, our own court of appeals has noted that “attorney fees should not be confused with the more generic term ‘costs’ because without specific statutory language, costs do not include attorney fees.”63
¶ 41 Section 38-1-28 reinforces the tie between the lien enforcement action, the alternate security amount used to obtain the lien release, and attorney fees. When the owner of any interest in real property is subject to a mechanics’ lien in an amount of less than $15,000 she must attach either a surety bond or evidence of a cash deposit that is 200 percent of the amount claimed by the lien claimant.64 If the lien claimant prevails, the amount of security in excess of the lien claim may be used towards attorney fees. However, attorney fees will only be awarded to the lien claimant if the lien claimant (1) timely files an action to enforce the lien under
¶ 42 Finally, our conclusion that a mechanics’ lien does not secure attorney fees and costs is supported by existing case law in other jurisdictions.66 Appellants’ contend that the value of a mechanics’ lien is limited to “the value of the service rendered, labor performed, or materials or equipment furnished or rented.”67 This is consistent with both the language of the statute as well as our decisions recognizing that mechanics’ liens “protect original contractors, subcontractors, and others who enhance the value of real property through improvements.”68
¶ 43 We conclude that the district court erred when it determined that the lien claim amount listed in a mechanics’ lien notice may include attorney fees and costs. Because the amount of a mechanics’ lien claim is limited to the value of the services, labor, and material that the lien claimant alleges he is owed, we hold that it is improper to add attorney fees and costs to that amount.70 Accordingly, we hold that 2 Ton‘s amended notices of lien are invalid because they improperly included attorney fees and costs in the amount of the lien claim. 2 Ton‘s original notice of lien, however, was and is valid.
¶ 44 Because we hold that the amended notices of lien are invalid, we do not address the Thorgaards’ alternative argument that the notice of lien was not timely amended.
B. 2 Ton‘s Cross-Appeal
¶ 45 2 Ton argues that the district court erred by allowing the Thorgaards to record their notice of release of lien and substitution of alternate security more than ninety days after service was accomplished on the property‘s original owner in violation of
¶ 46
¶ 47 We disagree with 2 Ton‘s interpretation of the statute. The amount of alternate security does not affect the court‘s ability to “apportion the costs according to the right of the case,” which includes awarding the successful party “a reasonable attorneys’ fee.”74
¶ 48 2 Ton argues that allowing subsequent owners to post alternate security under
¶ 49 Here, the Thorgaards were subsequent owners of Lot 30—they purchased the property from BBRP and Washington Federal replaced Zions as the lender. Washington Federal was served with a summons and lien foreclosure complaint on June 18, 2010. “[B]efore the expiration of 90 days after” being served, Washington Federal made a cash deposit of $14,942 as alternate security and at the same time recorded its notice of release of lien as required by
¶ 50 In sum, we conclude that 2 Ton‘s amended and second amended notices of lien are invalid because 2 Ton improperly amended them to include attorney fees and costs. However 2 Ton‘s original notice of lien was and remains valid, as not only was it properly filed, but the parties stipulated to its validity
II. DUE TO ITS ERROR, THE DISTRICT COURT MUST RECALCULATE THE ATTORNEY FEE AWARD
¶ 51 The Thorgaards ultimately stipulated that the amount of the lien claim stated in 2 Ton‘s original notice of lien—$7,147.41—was correct. On December 27, 2011, the district court entered a judgment against the defendants in the lien foreclosure action, which included the Thorgaards and Washington Federal. Because 2 Ton was the successful party in the lien action, it was entitled to have its сosts awarded, including reasonable attorney fees.80 On April 16, 2012, the district court awarded 2 Ton $44,857.70 in attorney fees.
¶ 52 The Thorgaards argue that the district court abused its discretion when it awarded 2 Ton $44,857.70 in attorney fees. Specifically, they argue (1) that the district court improperly failed to allocate the attorney fees, first, between the contract and lien claims and, second, among the defendants who incurred the attorney fees; (2) that the court should have allocated attorney fees on a per capita basis to all fourteen lots; and (3) that an award of attorney fees that is more than six times the principal lien amount is per se unreasonable.
¶ 53 “Calculation of reasonable attorney fees is in the sound discretion of the trial court, and will not be overturned in the absence of a showing of a clear abuse of discretion.”81 Though “an award of attorney fees must be supported by evidence in the recоrd,” “trial courts enjoy broad discretion in evaluating evidence to determine what constitutes a reasonable fee.”82 In this case, the district court abused its discretion by awarding attorney fees on the basis of an invalid notice of lien. Therefore, we must remand for the district court to recalculate the award after considering the fees incurred by the Thorgaards, who had to defend themselves against 2 Ton‘s improperly amended notices of lien, and whose property was not properly released under
¶ 54 Mechanics’ liens are wholly creatures of statute, having no place at common law. In this setting, the only access to an attorney fees awаrd is that granted by that statute. Attorney fees first appear in
between the owner and the contractor ... according to the right of the case, but in all cases each subcontractor exhibiting a lien shall have his costs awarded to him, including ... such reasonable attorneys’ fees as may be incurred in preparing and recording said notice of claim of lien.83
Under
¶ 55 However, because 2 Ton improperly amended its notice of lien to reflect an improper calculation, and because the court erroneously accepted the amendments and re-
CONCLUSION
¶ 56 We conclude that the district court erred when it permitted 2 Ton to include attorney fees and costs in the amount of its lien claim. Thus, 2 Ton‘s amended and second amended notices of lien were invalid. But 2 Ton‘s original notice of lien was valid. The Thorgaards’ notice of release of lien and substitution of alternate security was timely recorded and properly referenced 2 Ton‘s original notice of lien. Because the Thorgaards complied with all statutory requirements, the district court erred in refusing to release Lot 30 from the lien. Yet because the Thorgaards stipulated to the accuracy of the original lien claim, 2 Ton, as the prevailing party, was entitled to recover its costs and a reasonable attorney fee award. We hold that the district court must recalculate that award after considering the effect of the errors on the fees incurred by both parties.
NEHRING
Associate Chief Justice
Having recused herself, Justice DURRANT does not participate herein. District Judge KEITH A. KELLY sat.
