- (a) Notice of Funding Availability ("NOFA"). All MFDL funds from the annual allocation will be distributed through a NOFA that provides the specific collapse dates and deadlines as well as set-aside and RAF amounts applicable to the MFDL program, along with Application information. Other funds may be distributed by NOFA or through other method approved by the Board. Set-aside, RAF, and total funding amounts may increase or decrease in accordance with the provisions herein without further Board action as long as the NOFA itself did not require Board action.
- (b) Date of Receipt. Applications will be considered received on the business day of receipt. If an application is received after 5pm Austin Local Time, it will be determined to have been received on the following business day. Applications received on a non-business day will be considered received on the next day the Department is open. Applications will be considered complete at the time all required third party reports and application fee(s), in addition to the application, are received by the Department. Within certain set-asides, the date of receipt may be fixed, regardless of the earlier actual date a complete application is received. If multiple applications are received on the same date, in the same region, and within the same set-aside, then score, as described in §13.6 for MFDL or §11.9 for Applications layered with 9% HTC, will be used as the determining factor affecting the ranking of the application.
- (c) Applications. MFDL Applicants must follow the applicable requirements in 10 TAC Chapter 10, Subchapter C, Application Submission Requirements, Ineligibility Criteria, Board Decisions and Waiver of Rules for Applications. Failure to timely respond to any notice of Administrative Deficiency will result in a reestablishment of the date of receipt of the Application to the final date at which the cure to the notice was received by the Department. If the date of receipt of the Application is reestablished, an Application could be de-prioritized in favor of another application received prior to the new application submission date.
(d) Eligibility Criteria. The Department will evaluate the Application for eligibility and threshold at the time of full Application pursuant to the requirements of this Chapter and Chapter 10 of this title (relating to Uniform Multifamily Rules). If there are changes to the Application at any point prior to MFDL loan closing that have an adverse effect on the score and ranking order and that would have resulted in the application being ranked below another application in the ranking, the Department may terminate the Application.
- (1) Applicants requesting MFDL as the only source of Department funds may meet the Experience Requirement under §10.204(6) of this Chapter or by providing evidence of the successful development, and operation for at least 5 years, of at least twice as many affordability restricted units as requested in the Application.
(2) Applications for Developments previously awarded Department funds under any program, or where construction has already started or been completed, regardless of fund source and are not proposing acquisition and rehabilitation, except distressed Developments under §13.3(a), must be found eligible by the Board. The Board may find other applicants eligible for good cause such as Developments assisted by the Department that have encountered adverse factors beyond their control that could materially impair their ability to provide the affordable housing. An application that requires a finding of eligibility by the Board must identify that fact in their application so that the staff may present the matter to the Board for an eligibility determination. A finding of eligibility under this section does not guarantee an award. In general, these applications will not be funded with HOME or NHTF funds.
- (A) Requests for eligibility determinations under this paragraph must be received with the Application, so that staff may present the matter to the Board for an eligibility determination, and will not be considered more than 30 calendar days prior to the first Application acceptance date published in the NOFA.
(B) Criteria for the Board to consider would include (i) - (iii) of this subparagraph:
- (i) evidence of circumstances beyond the Applicant's control which could not have been prevented by timely start of construction; or
- (ii) Force Majeure events; and
- (iii) evidence that no further exceptional conditions exist that will delay or cause further cost increases
Source Note:The provisions of this §13.5 adopted to be effective January 8, 2017, 41 TexReg 10589.