- (a) "Indirect costs," as used in §62.47(a)(8) of this chapter, is defined as any cost not directly identified with a single, final cost objective, but identified with two or more final cost objectives or with at least one intermediate cost objective. For additional guidelines on "indirect costs," entities should consult UGMS.
- (b) The OAG will not allow indirect costs unless the organization submits a cost allocation plan approved by a cognizant agency and the costs are approved by the OAG.
- (c) The OAG reserves the right to limit indirect costs charged to a contract regardless of an applicant's cost allocation plan.
Source Note:The provisions of this §62.55 adopted to be effective August 31, 2005, 30 TexReg 4969.