Weeks Woodlands Ass'n v. Dormitory AuthorityWeeks Woodlands Ass'n v. Dormitory Authority
In the Matter of WEEKS WOODLANDS ASSOCIATION, INC., et al., Appellants, v DORMITORY AUTHORITY OF THE STATE OF NEW YORK et al., Respondents. [945 NYS2d 263]—
Appeals from order, Supreme Court, New York County (Emily Jane Goodman, J.), entered January 18, 2011, which, to the extent appealed from as limited by the briefs, denied petitioners’ motion for a preliminary injunction and granted the cross motion of respondent New York State Department of Health to dismiss the petition as against it, and from order and judgment (one paper), same court and Justice, entered August 9, 2011, which to the extent appealed from as limited by the briefs, granted the motion of respondent Dormitory Authority of the State of New York for summary judgment declaring that it had the authority to provide financing for the subject construction project, denied petitioners’ motion to renew, granted the cross motion of respondent New York City Department of Buildings for summary judgment dismissing the proceeding as against it, and denied petitioners’ motion for summary judgment with respect to the applicability of
Petitioners seek to enjoin a construction project to modernize a hospital for disabled children operated by a not-for-profit corporation, based primarily on alleged noncompliance with zoning requirements. Petitioners concede that they did not seek injunctive relief against the project going forward upon their appeal to this Court from Supreme Court‘s denial of their motion for a preliminary injunction. It now appears that the excavation, foundation walls, steel superstructure, concrete slabs, metal stud frames and duct work are complete. We see no evidence that the work was performed in bad faith, and the work completed could not be readily undone without undue hardship. While we would adopt the dissent‘s cogent analysis of the zoning issue if we were to reach the merits, in view of petitioners’ failure to seek injunctive relief from this Court and the advanced stage of work on the project, we find that the appeal has become moot and therefore must be dismissed (see Matter of Citineighbors Coalition of Historic Carnegie Hill v New York City Landmarks Preserv. Commn., 2 NY3d 727 [2004]; Matter of Dreikausen v Zoning Bd. of Appeals of City of Long Beach, 98 NY2d 165 [2002]; Sutherland v New York City Hous. Dev. Corp., 61 AD3d 479, 479-480 [2009], lv denied 13 NY3d 703 [2009]; William Israel‘s Farm Coop. v Board of Stds. & Appeals of City of N.Y., 25 AD3d 517 [2006]).
The dissent is mistaken in asserting that the Court of Appeals decisions in Citineighbors and Dreikausen support the position that this appeal is not moot. At the same time that it recognized that “a race to completion cannot be determinative [of mootness]” (Dreikausen, 98 NY2d at 172), the Court of Appeals identified as the “[c]hief” factor in the mootness inquiry “a challenger‘s failure to seek preliminary injunctive relief or otherwise preserve the status quo to prevent construction from commencing or continuing during the pendency of the litigation” (id. at 173). In this case, to reiterate, after Supreme Court denied their motion for a preliminary injunction, petitioners sought no injunctive relief from this Court upon the instant appeal.
Indeed, over a year‘s time, petitioners repeatedly chose not to apply to this Court for injunctive relief to preserve the status quo pending further proceedings.1 Hence, by August 2011 (five months before this appeal was argued), bonds in the amount of $102,200,000 had been issued to finance the project, approximately $30 million of the bond proceeds had been drawn down, and, according to the main respondents’ initial brief, “excavation and foundations [were] complete, the erection of the steel superstructure [was] 70% complete, the installation of the concrete slabs on the basement floor [was] complete and the concrete slabs on the ground floor [were] 50% complete.” In light of this history, the dissent would turn the law on its head by penalizing a not-for-profit institution, and the public agencies cooperating with it, for having gone forward with this project in reliance on (1) the issuance of all necessary governmental permits, (2) Supreme Court‘s denial of all applications for
Petitioners and the dissent fail to come to grips with the fact that petitioners, by failing to seek injunctive relief from this Court upon any of the occasions when they were denied relief by Supreme Court, are themselves complicit in the project‘s having reached its present advanced stage. Instead, the dissent makes an emotional appeal, essentially accusing us of coming to the aid of those having “the power and the money to proceed with dispatch” (internal quotation marks omitted), as if this matter concerned a for-profit project aimed at enriching private developers at the expense of local homeowners. Putting aside that the status of the proponents of this project has no particular bearing on petitioners’ rights, the dissent seems to have lost sight of the fact that the intended beneficiaries of the project are the sick and disabled children served by respondent hospital, a not-for-profit institution. Although the identity of those to be served by the project is also essentially irrelevant to the issues raised on this appeal, we do not think it accurate to characterize these children as persons well-endowed with “power” and “money.”2 We add that the dissent is simply wrong in saying that respondents have acted “with a blatant disregard for [petitioners‘] rights.” Respondents have at all times acted under color of law, and their construction of the zoning provision in question, while erroneous, certainly falls within the bounds of reason (especially given that the question is apparently one of first impression), and, after all, was accepted by Supreme Court.
The dissent argues that, to avoid mootness, it sufficed for petitioners to seek injunctive relief in Supreme Court, even if they subsequently failed to apply for such relief upon their appeal to this Court. Dreikausen indicates otherwise. In Dreikausen, the Court of Appeals cited with approval Matter of Fallati v Town of Colonie (222 AD2d 811 [1995]), in which the appeal was found moot because (as summarized by the Court of Appeals) “no injunction [was] sought before [the] Appellate Division” (98 NY2d at 173). The petition in Fallati sought, inter
The dissent‘s position finds no support in Matter of Watch Hill Homeowners Assn. v Town Bd. of Town of Greenburgh (226 AD2d 1031 [1996], lv denied 88 NY2d 811 [1996]), a case that the Court of Appeals distinguished in Dreikausen (98 NY2d at 173). The panel that decided Watch Hill included two justices of the panel that decided Fallati only a few months before and three justices of the panel that decided G.Z.T. Indus. about a year and a half later. Thus, we see little merit in the dissent‘s suggestion that Watch Hill abrogates or relaxes the requirement that a party seeking to halt construction move for injunctive relief at each level of litigation. Moreover, nowhere in the Watch Hill decision do we find any support for the dissent‘s assertion that the Court retained jurisdiction of the appeal notwithstanding the petitioners’ “failure to repeatedly seek injunctive relief.” And, to reiterate, the following year, in G.Z.T. Indus., three of the same justices reaffirmed that an appeal seeking to halt construction may be dismissed as moot where the appellant made no effort to preserve the status quo “[d]uring the pendency of [the] appeal” (245 AD2d at 742).4
Also misplaced is the dissent‘s reliance on Matter of Friends of Pine Bush v Planning Bd. of City of Albany (86 AD2d 246 [1982], affd 59 NY2d 849 [1983]), another Third Department decision distinguished in Dreikausen (98 NY2d at 173). Far from supporting the dissent‘s contention that the present matter is not moot, Pine Bush expressly held that the matter before the Court was moot because the petitioners had not been diligent in seeking injunctive relief against construction activity (see 86 AD2d at 247). Indeed, Pine Bush found that the matter was moot on the ground that the petitioners, after their motion to extend the automatic stay of the respondent‘s action was denied, took “no further action” to maintain the status quo, and, on their appeal from a subsequent judgment of the trial court “made no motion for a stay pursuant to
In Dreikausen, the Court of Appeals distinguished both Watch Hill and Pine Bush as cases in which “[c]ourts . . . have retained jurisdiction notwithstanding substantial completion in instances where novel issues or public interests such as environmental concerns warrant continuing review” (98 NY2d at 173). In this case, the environmental concerns invoked by petitioners are the increased traffic and the aesthetic cost anticipated to result from the enlargement and expansion of the hospital buildings. In view of the advanced stage the work on the project has reached and petitioners’ failure to “d[o] all they could to timely safeguard their interests” (Vitiello, 255 AD2d at 507), the concerns they invoke, while not to be deprecated, must be weighed against the public interest to be served by the upgrading of respondent hospital‘s antiquated 1950s-era facilities. The latter interest, to reiterate, is the enhancement of the hospital‘s ability to treat and rehabilitate sick and disabled children. Taking all of the circumstances into account, we find that the interests invoked by petitioners do not warrant retaining jurisdiction of their appeal notwithstanding their failure to take all available steps to protect their own interests.
We disagree with the dissent‘s suggestion that respondents’ proceeding with the modernization of the children‘s hospital could reasonably be viewed as an instance of “bad faith,” notwithstanding that Supreme Court denied petitioners’ motion for a preliminary injunction and petitioners then failed even to request such relief upon this appeal. While we agree with the dissent that, on balance, petitioners have the stronger argument on the merits, not even petitioners have suggested that respondents’ position on the merits is frivolous or lacking in a good faith basis. If petitioners wished to cast the risk of going forward with the work upon respondents, it was imperative for them at least to seek relief preserving the status quo at each
Finally, while the dissenter states that he “seriously doubt[s] the veracity of the respondents’ statements that the structure is virtually completed,” we find that respondents have established that, as of the time the appeal was argued, the construction was so far advanced that it could not be undone without undue hardship. Under this standard, the construction need not be “virtually completed” to render the dispute moot (see William Israel‘s Farm Coop., 25 AD3d at 517 [appeal was dismissed as moot where the petitioner did not seek injunctive relief against the construction and “the new building‘s superstructure (was) 75% complete“]). That the current stage of the construction is not reflected in the record is irrelevant because “mootness is an issue that can be raised at anytime and, in fact, it is incumbent upon counsel to inform the court of changed circumstances which render a matter moot” (Gabriel v Prime, 30 AD3d at 956 [internal quotation marks, brackets and citation omitted]). Concur—Friedman, Freedman and Manzanet-Daniels, JJ.
Saxe, J.P., and Catterson, J., dissent in a memorandum by Catterson, J., as follows:
I must respectfully dissent. In my opinion, by dismissing this appeal as moot and declining to reach the merits of the zoning issue the majority has essentially affirmed an error of law. As set forth more fully below, the error fatally infects the State Environmental Quality Review (hereinafter referred to as SEQRA) negative declaration issued on the project which is a 90,000-square foot expansion of St. Mary‘s Hospital in the Weeks Woodlands section of Bayside, Queens.
More significantly, the majority‘s holding ignores the fact that the erroneous interpretation of the zoning resolution infects the SEQRA negative declaration on the project issued by the respondent Dormitory Authority of the State of New York (hereinafter referred to as DASNY). Declining to reach the merits of the zoning issue is a total abnegation of this Court‘s responsibility. (See Save Audubon Coalition v City of New York, 180 AD2d 348, 355 [1st Dept 1992] [“(j)udicial review of a lead agency‘s SEQRA determination is limited to . . . whether, substantively, the determination was affected by an error of law“] [internal quotation marks omitted].)
DASNY‘s negative declaration was based on a finding that the project will not have a “significant adverse effect on the environment” because it “does not involve the introduction of any land uses or new structures that do not conform to or
For example, DASNY‘s report on the adverse impact of increased traffic in the neighborhood stated that there would be no adverse impact because the expansion plans did not include an increase of inpatient beds. As the petitioners correctly point out, “inpatients” do not increase traffic. Instead, the critical inquiry should have been into St. Mary‘s expansion of outpatient/ambulatory services which are the types of daily services that increase traffic around a hospital. It is small wonder that DASNY‘s SEQRA review of the $200 million project, which, contrary to taking a “long hard look,” was completed within 21 business days, now turns out to be based on an error of law.
The majority blithely dispenses with this SEQRA deficiency by summarizing the petitioners’ concerns as “increased traffic and the aesthetic cost.” This completely misses the point that the SEQRA negative declaration at issue is based on an acknowledged zoning violation. Yet, the majority overlooks this violation of the law because it views the facility as one for a disadvantaged group. Hence, in my opinion, the majority is compelled to fabricate the requirement that injunctive relief must be sought in the Appellate Division.
In this case, it is undisputed that the petitioners repeatedly and unsuccessfully sought injunctive relief in the court below. The petitioners opposed the expansion on the grounds that it violates
The respondents in this action include the New York State Department of Health (hereinafter referred to as DOH) which initially approved the project; the New York City Department of Buildings which issued the building permit; DASNY which conducted the SEQRA as well as providing the financing for the project, and St. Mary‘s.
It is undisputed that St. Mary‘s is one of the few nonresidential uses in the area, and that the current building was constructed in 1950. In December 2006, St. Mary‘s submitted a certificate of need for major modernization to DOH. It initially envisaged a new five story addition constructed on the east side of the existing building between the south wing and the cloister garden. The original design attempted to reduce the overall impact of the addition by “tucking” it into the existing facility.
In February 2008, DOH determined that the project was a Type I action for SEQRA purposes and that the lead agency would be Queens County or the authority having jurisdiction. It approved St. Mary‘s request, subject to certain conditions and contingencies including confirmation that all necessary local zoning approvals had been granted.
On October 6, 2008, St. Mary‘s sought confirmation from DOB that the maximum FAR for its building was 1. DOB denied the request, stating, “proposed hospital enlargement[/]alteration shall comply with ZR 24-111 with FAR 0.5 or secure BSA [Board of Standards and Appeals] approval for FAR more than 0.5.” A FAR of 0.5 denotes that the total floor area of a built structure on a parcel of property cannot exceed half the square footage of that parcel.
On May 12, 2010, DASNY voted to go forward with the financing of St. Mary‘s expansion. On May 21, 2010, DASNY proposed to designate itself the lead agency under SEQRA. Within just one month, on June 22, 2010, DASNY issued a negative declaration determining that St. Mary‘s expansion would “not have a significant adverse effect on the environment.”
On June 23, 2010, DASNY‘s board authorized the issuance of bonds for St. Mary‘s. On July 12, 2010, DOB issued a building permit, and St. Mary‘s announced it would begin construction on August 24, 2010. At the time of this appeal, St Mary‘s was proceeding with the construction of a new 90,000-square-foot building connected to its existing building.
Meanwhile on August 6, 2010, the petitioners brought the instant
On August 26, 2010, the petitioners filed an amended petition. The petitioners alleged, inter alia, that DOB and St. Mary‘s had failed to comply with
The motion court‘s order was entered January 18, 2011. The petitioners filed a timely notice of appeal on or about March 7, 2011. They perfected the appeal by the end of March, and moved
On or about April 5, 2011, the petitioners moved the court below to renew, and for a TRO enjoining construction pending a decision on the motion to renew. They stated that DOB had responded to their FOIL request after the motion court rendered its initial decision. The response included decisions by DOB and Board of Standards and Appeals (hereinafter referred to as BSA) which interpreted
DOB opposed the petitioners’ motion to renew and cross moved for summary judgment. The petitioners cross-moved for summary judgment on the ground that the building permit that DOB issued to St. Mary‘s violated
The petitioners appealed on or about August 10, 2011, and the respondents moved to consolidate the two appeals and adjourn them to the December term. The petitioners opposed on the grounds that delaying the preliminary injunction appeal could foreclose it as moot. This Court calendared the appeals for the December term. At oral argument on January 18, 2012, the respondents represented to this Court that the construction of the new building was essentially complete.
On appeal, the petitioners assert that the court below erred in its interpretation of the exception clause in
As a threshold matter, the decision to grant or deny a preliminary injunction lies within the discretion of the motion court and generally should not be disturbed unless it is demonstrated that the court abused its discretion. (See Borenstein v Rochel Props., 176 AD2d 171 [1st Dept 1991].) Here, however, the court did not make the determination as an exercise of discretion by weighing the elements upon which a preliminary injunction is usually granted or denied. (See Aetna Ins. Co. v Capasso, 75 NY2d 860, 862 [1990] [in addition to likelihood of success, movant must show irreparable harm in absence of injunction, and the balance of equities in movant‘s favor].) Instead, it denied the preliminary injunction based solely on its determination that statutory interpretation forecloses the petitioners’ zoning claim. Unfortunately, as the majority agrees, the court below erred on the law.
It is well settled that “[t]he primary consideration of the courts in the construction of statutes is to ascertain and give effect to the intention of the Legislature.” (
The intention of the Legislature is first to be sought from “a literal reading of the act itself.” (
Further, statutes must be given “a reasonable construction, it being presumed that a reasonable result was intended by the Legislature.” (
In relevant part, the exception clause of
St. Mary‘s states that its original certificate of occupancy is dated 1952, and that it provides that plans for St. Mary‘s were filed in 1948. St. Mary‘s therefore concludes simply—and simplistically: “Since the plans were filed with Department of Buildings before 1972, [St. Mary‘s Hospital] is not subject to ZR section 24-111 (a)‘s restriction to a 0.5 FAR.”
Moreover, relying on “the ordinary definition of amendment, that is correction or modification” respondent adds: “[A]s DOB pointed out, and as Supreme Court correctly held the plans for the horizontal enlargement are a ‘subsequent amendment’ to the original plans, in that the enlargement is a modification of the scope of the project as shown in plans filed prior to 1972.”
Such an interpretation, however, violates a cardinal rule of statutory construction by impermissibly rendering superfluous a phrase of the provision drafted by the legislative body, in this case, the CPC. (See Levine v Bornstein, 4 NY2d 241, 244 [1958] [“all parts of an act are to be read and construed together to determine the legislative intent“].) The interpretation desired by the respondents does not require the phrase “including any subsequent amendments thereof.” Had the drafters truly intended to grant a community facility like St. Mary‘s a continuing and eternal right to expand its building up to a FAR of 1.0, just because plans for its 1951 facility were filed before November 15, 1972, it could have accomplished the exemption by simply stating that “the provisions shall not apply to buildings for which plans were filed prior to November 15, 1972.” St. Mary‘s contention that “subsequent amendments” in this case refers to the plans for the new construction at St. Mary‘s Hospital does not render it any less superfluous: There simply would be no necessity for the phrase if St. Mary‘s interpretation of the provision were the correct one.
On the other hand, I find persuasive the petitioners’ assertion that the term “subsequent amendments” has a specific meaning which precludes the term being applied loosely to any modification or alteration—especially one made more than 60 years after the original plans were filed. In the absence of definitions
Thus, any “subsequent amendments” to the hospital plans filed in 1948 would be amendments reflecting changes or modifications to the hospital building envisioned in the 1948 plans and could have been submitted only before the 1951 facility was completed and before the issuance of its certificate of occupancy. The respondents make no such claim for their current plans.7
Contrary to the motion court‘s decision, therefore, no new language needs be imported into the exception clause to limit the “buildings” therein to projects in the pipeline. The reference to “subsequent amendments” per se limits the scope of the exception clause to projects which were commenced prior to November 15, 1972 and were still “in the works” awaiting final inspection and certificates of occupancy. Hence, I conclude that the term “subsequent amendments” simply cannot apply to plans filed by St. Mary‘s with DOB in 2010, more than a half-century after St. Mary‘s original plans were filed with DOB.
This interpretation is further supported by the legislative history of the 1973 Zoning Resolution, and comports with the legislative intent of CPC as expressed in its report recommending adoption of the provisions. The report establishes that in 1973, CPC clearly intended to correct the overbuilding of community facilities in residential neighborhoods by limiting FAR for projects that would negatively impact residential neighborhoods in the future. The concern of the drafters was that the availability of “community facilities bulk . . . has caused build-ings
The report states clearly that the provisions aimed at reducing the FAR are intended to guide the development of “[a] significant number of [community facilities which] are presently being built or planned using community facilities bulk” (emphasis added). The CPC report, however, recognized the “concern of sponsors who have invested large amounts of time and energy on preparing plans for these facilities and who fear the delay occasioned by another round of approvals.”
The report further states: “[Community facilities] may continue to locate in R1 to R7 residential districts as-of-right so long as they have the same floor area ratio as residential buildings. In R1 and R2 districts, floor area bonuses will go as-of-right only to those community facilities which had their plans on file with the [DOB] as of November 15, 1972” (emphasis added). Hence, it is evident, that the CPC enacted the provisions for community facilities in the process of being planned, constructed and built at that time. As the petitioners assert, it is more logical to draw the inference that the purpose of the exception clause was to protect a developer‘s investment in current plans rather than exempt non-conforming structures for which plans had not been filed—and would not be filed for another 37 years.
Specifically, the use of “as of” in the context of discussing ongoing projects suggests a “cut-off” date/deadline for projects in the planning stages at the time the 1973 provisions were being drafted. Neither the tenor nor the language of the report even remotely suggests that November 15, 1972 is a “grandfathering” date allowing future expansion up to a FAR of 1 by all the buildings already in existence throughout the city.
Interestingly, in September 2011, CPC issued proposals for new amendments to the Zoning Resolution. One was a proposal to amend
More significantly, the record reflects that DOB has interpreted the exception clause inconsistently. Until October 20, 2008 when DOB reversed its opinion and granted St. Mary‘s a permit for its expansion plans, it appears to have adhered to the interpretation urged by the petitioners.
In their motion to renew, the petitioners presented evidence, obtained after a formal FOIL request, that in 2006, DOB denied an application for expansion by Our Lady of Snow Church, Queens, also defined as a community facility under the ZR. The church argued that the exception clause of
Furthermore, DOB initially denied St. Mary‘s application on the same basis. When the agency reversed itself within a period of just 14 days, it gave an explanation totally at odds with its prior denials, that is, it exempted St. Mary‘s from the 0.5 FAR because “building was built prior to Nov. 15th, 1972.” DOB gave no explanation for its change of position. It now states, without explanation, that its ruling in the Our Lady of Snow application was “erroneous.”
Lastly, the petitioners correctly assert that their interpretation of the exception clause comports with the well established requirement that “grandfathering” provisions must be narrowly construed. (Matter of Albert v Board of Stds. & Appeals of City of N.Y., 89 AD2d 960, 961-962 [1982], appeal dismissed 59 NY2d 673 [1983] [“(w)hile it is customary for a zoning ordinance to be strictly construed in favor of the property owner, there are countervailing considerations when the ordinance limits the extension of nonconforming uses, because such uses detract from the effectiveness of the comprehensive zoning plan“] [citations omitted].)
Given the finding that the petitioners would prevail on their zoning claim, I would reject the respondents’ argument that both appeals are moot because construction is “substantially
The Court provided guidelines for evaluating mootness. Chief among the factors it enumerated is “a challenger‘s failure to seek preliminary injunctive relief.” (Dreikausen, 98 NY2d at 173; see also Citineighbors, 2 NY3d at 730 [“under Dreikausen . . . petitioners were required, at a minimum, to seek an injunction“] [emphasis added]). In Dreikausen and Citineighbors, the petitioners did not seek a TRO or a preliminary injunction when they filed their article 78 proceeding. (See 98 NY2d at 171; 2 NY3d at 728.) By contrast, in the case at bar, the petitioners sought a TRO when they filed their original petition, but it was denied. They sought a preliminary injunction in their amended petition in August 2010, but the court denied it in January 2011. Subsequently, they moved to renew, and again made an application for a preliminary injunction, which was also denied. The respondents’ further reliance on Dever v DeVito (84 AD3d 1539 [3d Dept 2011], lv dismissed 18 NY3d 864 [2012]) and Matter of Sherman v Planning Bd. of Vil. of Scarsdale (82 AD3d 899 [2d Dept 2011]) is misplaced even though the petitioners acknowledge that the requirement to provide a bond for delaying construction of a multi-million dollar project has deterred them from seeking a stay in this Court. In Dever, the appellant not only failed to seek a stay in the Appellate Division but also “eventually withdrew her appeal and thereafter failed to pursue any additional legal relief to preserve the status quo or prevent further construction of defendants’ residence.” (84 AD3d at 1541.) In Sherman, the appellants not only failed to move for a preliminary injunction in the Appellate Division but also failed to so move in Supreme Court. (82 AD3d at 899-900.) Indeed, the record reflects that petitioners in this case have had applica-tions
In my opinion, while it is clear that the Court in Matter of Fallati v Town of Colonie (222 AD2d 811 [3d Dept 1995])—a case upon which the majority relies because it is cited with approval by the Court of Appeals—found mootness when petitioner failed to seek injunctive relief in the Appellate Division, it is equally clear that in Matter of Watch Hill Homeowners Assn. v Town Bd. of Town of Greenburgh (226 AD2d 1031 [3d Dept 1996], lv denied 88 NY2d 811 [1996]), also cited with approval by the Court of Appeals, petitioner‘s failure to repeatedly seek injunctive relief did not lead to dismissal of the appeal. In my opinion, the majority‘s reasoning that, because two justices were common to the panels of both cases, Watch Hill does not abrogate or relax the requirement of moving for relief “at each level of litigation,” is incoherent. Specifically, the majority does not address the import of the plain and unequivocal language of Watch Hill which appears to apply directly to the case at bar: “While construction . . . can render a challenge of this type moot when the petitioner has not made any attempt to preserve its rights pending judicial review . . . that is not the circumstance here, for petitioner sought preliminary injunctive relief—which was denied—as soon as it became aware that construction was imminent. Respondents were thus placed on notice that if they proceeded with construction, it would be at their own risk.” (Matter of Watch Hill, 226 AD2d at 1032 [emphasis added].)
In other words, a finding of mootness is not mandated by the fact that a petitioner has failed to seek injunctive relief at any particular stage of litigation; rather the analysis must focus on the stage of construction, and whether a petitioner has sought injunctive relief before construction is substantially completed. (See Matter of Dreikausen v Zoning Bd. of Appeals of City of Long Beach, 98 NY2d 165, 171-174 [2002].)
The majority‘s dictate that the petitioners should have immediately come to this Court blatantly ignores the fact that in August 2010 on the day the TRO (temporary restraining order) was denied, the motion court immediately set the case down for oral argument on a preliminary injunction for early September, and the application was before that court until January 2011 when the motion court‘s denial was entered as an order.
The respondents were therefore on notice prior to beginning construction. Specifically, they were on notice, as of the petitioners’ motion to renew in April 2011, of the fact that even the
Instead, I find that the respondents’ increased construction activity at this time is all the more egregious since it strongly suggests that they simply ignored the admonition of the Court of Appeals that “a race to completion cannot be determinative.” (Dreikausen, 98 NY2d at 172.)
In my opinion, the majority paints itself into a corner because it appears to ignore the Dreikausen Court‘s holding that mootness, and consequently dismissal of an appeal, is found by “weighing” various factors. In turn, weighing means assessing the relative importance or significance of the factors in a given set of circumstances. Hence, in some cases, courts have dismissed appeals because petitioners waited until construction was virtually complete before seeking injunctive relief; in others “notwithstanding . . . completion . . . novel issues or public interests such as environmental concerns warrant continuing review.” (Dreikausen, 98 NY2d at 173, citing with approval Matter of Friends of Pine Bush v Planning Bd. of City of Albany, 86 AD2d 246 [3d Dept 1982] [appeal should not be dismissed on ground of mootness since a question of general interest and substantial public importance is present and is likely to recur if not judicially resolved], affd 59 NY2d 849 [1983]; Watch Hill, 226 AD2d 1031.)
In declining to rule on the zoning issue, the majority leaves the door open for any community facility which initially filed plans before 1972 to be granted permission by DOB to expand up to a maximum floor to area ration (hereinafter referred to as FAR) of 1.0 in an R2A residential neighborhood. The majority‘s view that agreement by the majority and dissent on the interpretation of the zoning regulation tends to make such a situation unlikely to recur, in my opinion, is simply an evasion of the issue since that interpretation is nothing more than dicta at this point.
Finally, the Court of Appeals determined that an equally significant factor in evaluating mootness is whether the work was undertaken without authority and in bad faith. (Dreikausen, 98 NY2d at 173.) While St. Mary‘s did obtain approval from the DOH and DOB, it cannot be said that it was unaware that the petitioners alleged a zoning violation. The petitioners filed a challenge with DOB, then filed their petition with Supreme Court. Subsequently the petitioners moved to renew, and noticed appeals in both proceedings.
■ In the Matter of CRISTINA PAYANO, Petitioner, v ELIZABETH R. BERLIN et al, Respondents. [945 NYS2d 287]—
Determination of New York State Office of Temporary Disability Assistance (OTDA), dated April 20, 2010, after a hearing, that it lacked jurisdiction to review New York City Human Resources Administration‘s (HRA) decision to discontinue petitioner‘s public assistance benefits, unanimously confirmed, the petition denied, and this proceeding brought pursuant to
Substantial evidence supports OTDA‘s determination that