Vasquez v. Urbahn Associates Inc.Vasquez v. Urbahn Associates Inc.
Christian Vasquez, Respondent-Appellant, v Urbahn Associates Inc., Defendant, and Great American Contracting Corp. et al., Appellants-Respondents. (And a Third-Party Action.) [918 NYS2d 1]
Order, Supreme Court, New York County (Edward H. Lehner, J.), entered August 6, 2009, which granted the motion of defendants Great American Contracting Corp. and Home Again in Harlem LLC for summary judgment dismissing the complaint only insofar as it sought to dismiss the
Whether the collapse or failure of a permanent structure gives rise to liability under
The dissent takes the untenable position that in denying plaintiff‘s cross motion for summary judgment on his claim pursuant to
Zimmer v Chemung County Performing Arts (65 NY2d 513 [1985]) does not alter our holding because it fails to address the pertinent issue. Of course it is true, as the court held in Zimmer, that when safety devices are required pursuant to
The dissent‘s second position, while sound public policy, is both legally and factually untenable. While as a policy matter, a defendant who takes a head-in-the-sand approach should not be rewarded for such gross neglect, we find no support for the dissent‘s imputation of foreseeability solely because a defendant takes no steps which would enable him or her to foresee that an accident is likely. Foreseeability is “[t]he risk reasonably to be perceived . . . ; it is risk to another or to others within the
Acosta and Freedman, JJ., dissent in part in a memorandum by Acosta, J., as follows: Because I believe that the majority is reading into
The plain language of
The majority heavily relies on Jones v 414 Equities LLC (57 AD3d 65 [2008]) wherein this Court held that a plaintiff who was engaged in a protected activity (demolition work) at the time of his accident was not entitled to judgment as a matter of law where he failed to demonstrate that the collapse of the floor on which he was standing was foreseeable. I concurred with the majority opinion in Jones. However, upon a closer examination of the statute and in the absence of any Court of Appeals case directly on point, I now believe that a better approach would be to not read into the statute a foreseeability requirement, lest we encourage contractors, as here, to take a head-in-the-sand approach to their statutory obligations.
Moreover, given the dangerous conditions of construction and demolition sites, imposing a foreseeability requirement may result in unnecessary and preventable injuries to workers. Placing on plaintiffs the burden to demonstrate a particular accident was foreseeable disturbs the balance struck by the Legislature between employee safety and employer cost in promulgating this absolute liability statute. It is hardly within
Indeed, reading such a requirement into the statute goes directly against the legislative intent. For instance, the sponsors of the 1969 amendments to the
The Court of Appeals has also held that “this statute is one for the protection of workmen from injury and undoubtedly is to be construed as liberally as may be for the accomplishment of the purpose for which it was thus framed” (id. at 520-521 [emphasis added]). Reading into the statute a foreseeability requirement would, therefore, not only limit the scope of the statute and go against Court of Appeals guidance on the issue, but also fly in the face of the statute‘s legislative intent, which primarily is to ensure the safety of workers, not to limit contractor liability to accidents that are foreseeable.2
In any event, were foreseeability a required element, I would nevertheless find that plaintiff has demonstrated that he is entitled to summary judgment on his
Moreover, unlike the building in Jones, the building here had a hole in the roof, thus exposing the floors to the elements. The building had been abandoned by the City since 1974, until it was purchased by the owner from the City in 2003 in “as is”
Most troubling to me, however, is the fact that the general contractor and the owner took a head-in-the-sand approach to their safety obligations, and now cavalierly claim that the accident was not foreseeable. There is no indication whatsoever that the general contractor or owner took any reasonable step to ensure the safety of their workers.
For instance, the principal of the entity hired by the general contractor to perform the demolition and debris removal work testified that there was no engineering survey performed by a qualified structural engineer before the work began. This survey is essential to determine the stability of the interior and the risk of an unplanned collapse. He further testified that he never saw any inspection reports from any inspections of the flooring, that there was no safety officer, and he was not aware of any safety meetings having been held with employees. Significantly, he testified that the structural integrity of the floors was checked by merely walking on them.
Plaintiff‘s expert affidavit, on the other hand, made clear that proper inspection and safety procedures for a construction project of this magnitude were not in place, and that, to the extent that any inspections were performed at all, they were not done by a professional structural engineer qualified to evaluate the changing structural conditions of the building. It is thus clear that defendants did not even take minimal precautions at the work site. I do not believe that defendants’ failure to ensure their workers’ safety should now allow them to claim the accident was not foreseeable. This Court should be cautious in making
The majority‘s position that an owner or contractor can completely ignore any safety hazards in a work site completely obfuscates the purpose of the “extreme protection” afforded by the statute, and defies logic. If the majority‘s reasoning is accepted, no matter how obvious a condition may be, if an owner or contractor simply asserts that it did not know of the condition because it took no preventive measure whatsoever, it will
The majority cites to the universally recognized Palsgraf case to define foreseeability as “[t]he risk reasonably to be perceived . . . ; it is risk to another or to others within the range of apprehension” (Palsgraf v Long Is. R.R. Co., 248 NY 339, 344 [1928] [emphasis added]). Yet, in the same breath the majority urges that through “neglect” a defendant will have no obligation to perceive a dangerous situation. I do not believe Judge Cardozo meant to define reasonableness as looking the other way. The majority‘s conclusion here is that whether this accident was foreseeable is a question of fact. However, this question would have to be resolved by determining whether defendants knew or should have known of a dangerous condition had they taken reasonable steps. Unfortunately, based on the majority‘s logic, whether defendants should have known of the perilous condition is irrelevant, inasmuch as the majority makes clear that “albeit through their own neglect . . . defendants would have had no reason to perceive or apprehend that prior to the accident the stairs were in a condition such that they were likely to collapse.”
Furthermore, such a position is completely at odds with Court of Appeals precedent. In Zimmer v Chemung County Performing Arts (65 NY2d 513 [1985]), the Court of Appeals explicitly recognized that
The majority also astonishingly holds that inasmuch as permanent structures are not “normally” expected to collapse, defendants are not required to comply with the strict requirements of the statute. This position is a slippery slope that defeats the clear legislative intent to protect workers. Moreover, the grafting of a foreseeability element into
Permanent structures, like temporary structures, are bound to collapse depending on the nature of the work being done on the structure. Thus, as here, if the permanent structure has been abandoned for three decades, and exposed to the elements, and the supporting beams of the floors were loosened, the requirement of proper safety devices is based not on some intangible element of foreseeability, but rather on the nature of the work (i.e., elevation-related construction).
As a final matter, the majority‘s flawed logic is further highlighted when in addressing plaintiff‘s