UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF EXPOSED ROOF DESIGN, LLC v. TANDEM ROOFING, LLC еt al.
CASE NO. 23-2293
UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA
November 15, 2023
NANNETTE JOLIVETTE BROWN
SECTION: “G“(5)
ORDER AND REASONS
Before the Court is Defendant Tandem Roofing, LLC‘s (“Tandem“) Motion to Dismiss, Sever, and Transfer Venue.1 In this litigation, Plaintiff Exposed Roof Design LLC (“Exposed“) seeks to recover payments for work it performed but which Tandem and other Defendants did not tender.2 Tandem moves to dismiss Exposed‘s Miller Act and Federal Prompt Payment Act claims under Rule 12(b)(6).3 Tandem also moves to sever the state common law claims Exposed asserted against it and transfer those claims to the Northern District of Texas because of a forum selection clause in the contract between Exposed and Tandem.4 In response, Exposed filed an Amended Complaint, which withdraws the Miller Act and Federal Prompt Payment Act claims against Tandem mooting the Rule 12(b)(6) arguments.5 Exposed also argues that the inconvenience non-signatory Defendants to the contract containing the forum selection clause would face if the case is severed and transferred, as well as judicial economy concerns, favor keeping the case in this
Court.6
I. Background
On June 30, 2023 Exposed filed a Complaint against Defendants Tandem, E&F Construction (“E&F“), Markel Insurance Company (“Markel“), and SureTec Insurance Company (“Suretec“) in this Court.7 Exposed seeks to recover damages for work it allegedly performеd but was not paid for as a subcontractor on a construction project (“Project“) related to the repair of two buildings at the Naval Air Station Joint Reserve Base New Orleans in Belle Chasse, Louisiana.8 Exposed is a construction company that among its services, provides roofing materials and performs roofing work.9 Tandem is a commercial and industrial roofing company that was a subcontractor to E&F, the prime contractor that contracted with the Department of the Navy to work on the Project.10
Exposed alleges that on or around August 29, 2022, it entered into a $215,635 subcontract with Tandem to “provide labor and install the roofing system” for the Project.11 Exposed alleges that it priced its labor according to Tandem‘s estimate that the Project would be completed in four weeks.12 Exposed alleges that it then performed work from September 12, 2022 to October 7,
2022, but Tandem caused significant delays to the Project.13
Exposed alleges, however, Tandem later notified Exposed “it no longer had the funds to keep [Exposed] on the Project.”16 Exposed alleges that as a result of this news and to preserve its rights under the Miller Act, Exposed “timely sent its notice of intent to E&F on or around November 15, 2023.”17 Exposed further alleges that from November 2022 through mid-May 2023, Tandem “repeatedly represented” to Exposed that it would be paid the additional $215,625 under the Change Order, but ultimately, Tandem did not pay Exposed.18 Exposed alleges that it finally sent Tandem a formal demand letter for payment on March 24, 2023, to which Tandem responded that it would send payment of the $215,625 in two checks.19 Exposed alleges that it received the first check from Tandem on April 17, 2022, but the check could not be cashed because there were
insufficient funds.20
Exposed alleges that E&F secured a payment bond, Bond No. 4415766 (“Payment Bond“), issued by Markel and Suretec on or about June 10, 2020, as part of its obligations under the Miller Act.22 Exposed alleges that it sent a letter to E&F notifying them of a claim for $327,238.28 (“Miller Act Notice“).23 Exposed alleges that after it provided Miller Act Notice, Tandem paid it $102,718.75.24 Exposed further alleges that Defendants are jointly and severally liable for the $215,625 left on the balance of its claim.25
In the original Complaint, Exposed brought several causes of action against Defendants. First, Exposed brought a breach of contract cause of action against Tandem, alleging that Tandem failed to make payment under the Agreement despite Exposed performing the work it was required to under the Contract.26 In addition to recovering payment owed from the Agreement, Exposed sought “interest, reasonable attorney‘s fees under Texas Civil Practice & Remedies Code Chapter 38, and costs incurred in the prosecution of this lawsuit ...”27 Second, Exposed brought a Miller Act claim against all Defendants, asserting that when Suretec and Markel issued the Payment Bond, they “undertook a direct obligation with the United States of America to act as the surety
with respect to E&F and Tandem‘s obligations to make payments to subcontractors and suppliers for labor and matеrials furnished to the Project.”28
On August 29, 2023, Tandem moved to dismiss the Miller Act and Federal Prompt Pay Act claims against it, sever the breach of contract and quantum meruit claims against it from the claims asserted against E&F, Markel, and Suretec, and transfer those claims to the Northern District of Texas.32 On August 29, 2023, Exposed file a response opposing Tandem‘s motion.33 On the same day, Exposed also filed a First Amended Complaint to withdraw its Miller Act claim against Tandem and the Federal Prompt Payment claim against all Defendants.34 Exposed also added a Texas Prompt Payment Act against Tandem, alleging that Tandem received payment for
the work that Exposed furnished to Tandem but that Tandem did not pay Exposed within seven days of Tandem‘s receipt of those payments.35
II. Parties’ Arguments
A. Tandem‘s Arguments in Support of the Motion
1. Rule 12(b)(6) Motion to Dismiss
First, Tandem argues that Exposed‘s Miller Act claim against it should be dismissed because the Miller Act only allows a party to bring a claim for payment on the payment bond against the sureties that issued the payment bond rather than against Tandem as a subcontractor on the Project.38 Second, Tandem contends that Plaintiffs Federal Promрt Payment Act claim should be dismissed because the Federal Prompt Payment Act does not create a private cause of action.39 As discussed above, these arguments are moot because Exposed withdrew these claims in the Amended Complaint.
2. Severing Other Claims Against Tandem and Transferring Venue to the Northern District of Texas
Tandem argues that Exposed‘s breach of contract and quantum meruit claims against it should be transferred to the Northern District of Texas because the Agreement between Exposed
and Tandem contains a forum selection clause requiring litigation related to the Agreement to be filed in Dallas County, Texas.40
Tandem contends that this mandatory forum selection clause, in part, requires the breach of contract and quantum meruit claims to be severed from the Miller Act claims Exposed has asserted because this Court is the required venue for the Miller Act claims.43 Tandem points to In re Rolls Royce Corp., which sets forth the Fifth Circuit‘s test for severance and transfer of venue when not all of the Defendants are bоund by the mandatory forum selection clause and contends that this analysis weighs towards severance and transfer.44
As to the first Rolls Royce prong, Tandem contends that the
Tandem argues that under the second Rolls Royce prong, the Court needs to look at the five factors that the Fifth Circuit follows for a Rule 21 severance analysis.46
economies in overseeing the Miller Act claims by limiting and simplifying the issues to be adjudicated under that statute.”53
As to the third Rolls Royce prong, Tandem contends that severance and transfer of the state law claims would be beneficial for judicial economy because the Northern District of Texas could adjudicate the amount owed to Exposed under the Agreement, which would “limit[] and simplify[]” the issues to be adjudicated under the Miller Act in this Court.54 Tandem notes that “the Miller Act claims are contingent on the disputed amounts to be owed under Tandem‘s contract with the Plaintiff.”55 Tandem has also offers that the Court could “fashion other relief in connection with the severance and transfer to mitigate any burden, such as that suggested by the Fifth Circuit in the Rolls Royce opinion—common discovery and other pretrial matters, video depositions for use in both cases, stipulations, etc.”56
B. Exposed‘s Arguments in Opposition to Tandem‘s Motion
Exposed filed a response opposing Tandem‘s motion.57 First, Exposed argues that because it removed the Miller Act and Federal Prompt Payment Act claims against Tandem in the First Amended Complaint, Tandem‘s arguments regarding those claims are now moot.58
Second, Exposed argues that the Rule 21 severance factors weigh against severance.59 As to the first factor, Exposed asserts that the claims against Tandem arise directly out of the same
transaction as the Miller Act claim against E&F, Mаrkel, and SureTec because they all “derive from Tandem‘s failure to pay Exposed the $215,625 it remains owed under the Agreement.”60
Third, Exposed argues that the Section 1404(a) private interest factors as applied to E&F, Markel, and Suretec weigh against transfer.65 Exposed contends that most of the witnesses and
evidence rеlated to the litigation would be found in this district, as the Project was located in Belle Chasse, Louisiana.66
Fourth, Exposed argues that the Section 1404(a) public interest factors disfavor transfer because its claims against Tandem and its claims against E&F, Markel, and Suretec are so connected that a court would need to reach the merits of the claims against Tandem in order to determine the merits of the claims against E&F, Markel, and Suretec.68 Exposed also argues that this case concerns a local controversy that should be decided in this district because this case is a dispute regarding a federal construction project at the Naval Air Station Joint Base New Orleans.69
III. Legal Standards
A. Rule 21 Severance
Motions to sever are generally governed by
20 for guidance in the absence of any standards in Rule 21,73
B. Transfer Under 28 U.S.C. § 1404(a)
Pursuant to
consented.”77
Usually, a court applying the doctrine of forum non conveniens must determine whether there is an adequate alternative forum and, if so, determine which forum is best-suited to the litigation by considering “a variety of private- and public-interest factors and giving deference to the plaintiff‘s choice of forum.”79 “The private-interest factors include ‘relative ease of access to sources of proof; availability of compulsory process for attendance of unwilling, and the cost of obtaining attendance of willing, witnesses; possibility of view of premises, if view would be appropriate to the action; and all other practical problems that make trial of a case easy, expeditious and inexpensive.”80 “The public-interest factors include ‘the administrative difficulties flowing from court congestion; the local interest in having localized controversies decided at home; [and] the interest in having the trial of a diversity case in a forum that is at home with thе law.‘”81 A plaintiff‘s choice of forum is typically given some significant, but not determinative, weight.82
However, the existence of a mandatory, valid forum selection clause simplifies the analysis in two ways: (1) the “the plaintiff‘s choice of forum merits no weight’ because, by contracting for a specific forum, ‘the plaintiff has effectively exercised its ‘venue privilege’ before a dispute
arises;‘”83 and (2) the “private-interest factors ‘weigh entirely in favor of the preselected forum,’ so that the ‘district court may consider arguments about public-interest factors only.”84
In analyzing a forum selection clause, a court must first determine whether the forum selection clause is mandatory or permissive.87 Once a court makes this determination, it must decide whether the forum selection clause at issue applies to this specific case, which involves two separate inquiries: (1) whether the forum selection clause is valid and enforceable and (2) whether the present case falls within the scope of the forum selection clause.88
C. Severance and Transfer Under Rolls Royce
In situations where some but not all parties have entered into a forum selection clause, the Fifth Circuit hаs instructed that the severance and transfer inquiry requires courts to apply the three prongs analysis in Rolls Royce.89 First, “the private factors of the parties who have signed a forum agreement, must, as [a] matter of law, cut in favor of severance and transfer to the contracted for
forum.”90 Second, the Court “must consider the private factors of the parties who have not signed a forum selection agreement as it would under a Rule 21 severance and section 1404 transfer analysis.”91
IV. Analysis
Tandem argues that Exposed‘s Miller Act claim against it must be dismissed because Tandem is not a contractor within the meaning of the Miller Act and Exposed‘s Federal Prompt Payment Act against it must also be dismissed because there is no private cause of action.96 As
discussed above, these arguments are moot because Exposed withdrew these claims in the Amended Complaint.
Tandem also argues that Exposed‘s breach of contract and quantum meruit claim against it should be severed and transferred to the Northern District of Texas because of a mandatory forum selection clause in the Agreement between Exposed and Tandem.97 Exposed opposes, arguing that the severance and transfer analysis favors keeping the case in this Court because severing and transferring to the Northеrn District of Texas would principally inconvenience E&F, who did not sign the contract containing the mandatory forum selection clause, and strain judicial resources by duplicating the proceedings.98 The Court addresses each issue in turn.
A. The mandatory forum selection clause favors severance and transfer.
Under the first prong of Rolls Royce, the existence of a mandatory forum selection clause, must as a matter of law, weigh in favor of severance and transfer.99 Here, the Agreement between Exposed and Tandem contains a forum selection clause that states “the venue for any arbitration proceeding or litigation between the parties to this agreement shall be in Dallas County, Texas.”100 E&F, Markel, and Suretec were not signatories to the Agreement containing the forum selection clause.101 The parties do not dispute the validity and enforceability of the forum selection clause identifying Dallas County as the forum for disputes related to the Agreement or that this litigation
is within the scope of the forum selection clause.102
B. The private factors of non-signatory Defendants weighs against severance and transfer.
Under the second prong of the Rolls Royce analysis, the Court “must consider the private factors of the parties who have not signed a forum selection agreement as it would under a Rule 21 severance and section 1404 transfer analysis.”103
1. Rule 21 private interest factors
The Court considers the following factors in a Rule 21 severance analysis: (1) whether the claim arose out of thе same transaction or occurrence; (2) whether the claims present common questions of law or fact; (3) whether settlement or judicial economy would be promoted; (4) whether prejudice would be averted by severance; and (5) whether different witnesses and documentary proof are required for separate claims.104
Under the first Rule 21 factor, Exposed‘s breach of contract and quantum meruit claims against Tandem arose out of the same events that gave rise to Exposed‘s Miller Act claims against E&F, Markel, and Suretec. All of the claims arise from Defendants’ alleged failure to pay Exposed for work it performed on the Project. Therefore, the first factor disfavors severancе.
The second factor also disfavors severance as there are common questions of fact related to whether Exposed satisfied its labor and services obligations under the Agreement, whether any of the Defendants have failed to pay Exposed for the labor and services it provided, and the amount
of payment owed to Exposed. The elements of a Miller Act claim share similar elements to the breach of contract and quantum meruit claims.
The Miller Act provides in part that:
Every person that has furnished labor or material in carrying out work provided for in a contract for which a payment bond is furnished ... and that has not been paid in full within 90 days after the day on which the person did or performed the last of the labor or furnished оr supplied the material for which the claim is made may bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought ...105
The elements of the breach of contract and quantum meruit claims, meanwhile, also concern whether Exposed performed work for Tandem under the Agreement and whether Tandem failed to make payments for the work performed by Exposed. Therefore, the Miller Act claims against non-signatory Defendants and the state law claims against Tandem are inextricably linked. As Tandem admits, “the Miller Act claims are contingent on the disputed amounts alleged to be owed under Tandem‘s contract with the Plaintiff ...”106
The third factor also disfavors severance because judicial economy would be undermined with two similar cases proceeding in two federal district courts. If the state law claims were transferred, this Court would either have to stay the case here while Exposed and Tandem determine how much is owed to Exposed or proceed with duplicate proceedings to determine Tandem and the other Defendants’ liabilities to Exposed.107
Under the fourth factor, non-signatory Defendants may face prejudice if the claims against Tandem were to proceed in the Northern District of Texas without them. If this claims against the
non-signatory Defendants were stayed in this Court, while the claims against Tandem proceeded
As for the fifth factor, the same witnesses and documents would likely be presented to prove each of the claims. As discussed in more detail above, the elements of a Miller Act claim are related to the elements of the breach of contract and quantum meruit claims. Therefоre, the Rule 21 factors strongly disfavor severance.
2. Section 1404(a) private interest factors
Under the second prong of Rolls Royce, the Court must also consider the Section 1404(a) private interest factors as they relate to the non-signatory Defendants.109 “The private-interest factors include ‘relative ease of access to sources of proof; availability of compulsory process for attendance of unwilling, and the cost of obtaining attendance of willing, witnesses; possibility of view of premises, if view would be appropriate to the action; and all other practical problems that make trial of a case easy, expeditious and inexpensive.”110
Many of the Section 1404(a) private interest factors are neutral, except for the last factor. Because the Project occurred in Belle Chasse, Louisiana, within this district, the relevant non-
corporate witnesses are likely to be here. However, the heart of this case is a commercial
The last factor, whether transfer poses any practical problems that make trial of a case easy, expeditious, and inexpensive, is the most relevant factor and it disfavors transfer of the claims against Tandem. Transfer would result in two trials and would be inconvenient and prejudicial for E&F, Markel, and Suretec. Tandem suggests that the claims against the non-signatory Defendants could be stayed pending resolution of the claims against Tandem in the Northern District of Texas. However, a stay would slow down adjudication for the non-signatory Defendants. Moreover, costs would significantly increase with duplicate proceedings if non-signatory Defendants had to be joined to the transferred case or otherwise participate in the case.
C. The judicial economy interest in keeping all claims in one case outweighs the private interests embedded in Exposed and Tandem‘s forum selection clause.
The third prong of Rolls Royce requires courts to ask whether the preliminary weighing under the first and second prongs is “outweighed by the judicial economy considerations of having all claims determined in a single lawsuit.”112 A primary concern of the Section 1404(a) public
interest factors is also judicial economy. “The [Section 1404(a)] public-interest factors include ‘the
While this Court and the Northern District of Texas would not be so overwhelmingly congested with the transfer of this case, transfer nonetheless would result in unnecessary duplication of cases that strains judicial resources. Although Exposed and Tandem negotiated the forum selection clause to be in Dallas County, where Exposed has its principal place of business, the events that gave rise to this litigation occurred here in this district and Tandem also has its principal place of business within this district in Kenner, Louisiana.116 Because this litigation concerns a Project at the Naval Air Station Joint Reserve Base in Belle Chasse, thеre is a local interest in having that localized controversy decided here.117 As to “the interest in having the trial
of a diversity case in a forum that is at home with the law,” the case here only concerns federal
Therefore, judicial economy interests favor keeping all claims in this Court to be resolved in one proceeding, outweighing the first prong of Rolls Royce that favors transfer. As discussed above, severing the cases would require additional expenses and time, as resolutiоn of the Miller Act claims against the non-signatory Defendants is dependent on the resolution of the state law breach of contract claims against Tandem.119 If the claims against Tandem were transferred to Texas, there would be a duplication of proceedings as the state law claims against Tandem revolve around the same set of facts and similar elements as Exposed‘s Miller Act claims against non-signatory Defendants.120 Although Tandem has offered to participate in common discovery, video depositions, and stipulations to ease judicial economy concerns related to severance and transfer,
the result is still that there would be two duplicate cases that require more judicial resources than
V. Conclusion
Although the mandatory forum selection clause favors severance and transfer under the first prong of Rolls Royce, the second and third prongs of the Rolls Royce analysis disfavor severance and transfer because of inconvenience to non-signatory Defendants and the strain on judicial economy. Accordingly, for the reasons discussed above,
IT IS HEREBY ORDERED that Tandem‘s Motion to Sever and Transfer is DENIED.121
IT IS FURTHER ORDERED that Tandem‘s Motion to Dismiss Pursuant to Rule 12(b)(6)122 is MOOT.
NEW ORLEANS, LOUISIANA, this 14th day of November, 2023.
NANNETTE JOLIVETTE BROWN
CHIEF JUDGE
UNITED STATES DISTRICT COURT
