Town of Poughkeepsie, Respondent, v Thomas Espie et al., Appellants.
Supreme Court, Appellate Division, Second Department, New York
840 N.Y.S.2d 600
Ordered that the order is modified, on the law, by deleting the provision thereof denying that branch of the motion which was pursuant to
On September 4, 2002 the Town of Poughkeepsie commenced an action in the United States District Court for the Southern District of New York (hereinafter the federal action) against, among others, Thomas Espie and Betty Espie alleging, among other things, a violation of the competitive bidding requirements of
In both the federal action and the instant action, the Town alleged that the Espies and others engaged in a scheme to defraud the Town of money by securing the payment of bribes in order to garner support in steering the Town to agree to lease the Espies’ warehouse as the police and court facility, with an option to purchase the property, and to engage the Espies to renovate the property.
The lease provided that it would terminate when the Espies conveyed title to the warehouse to the Town, which would occur upon the Town’s exercise of an option to purchase the warehouse contained in the lease. On May 30, 1995 the Town executed a purchase and sale agreement, thus enabling it to exercise the option to purchase the warehouse for the sum of $5,350,000. At some point after accepting the assignment of the renovation agreement, the defendants hired the contractor Roy C. Knapp & Sons, which commenced renovations on the warehouse.
On July 17, 1996 the Town Board adopted a resolution authorizing the execution of an amended lease agreement. The amended lease agreement increased the monthly rental fee to the sum of $80,000, extended the term of the lease to 20 years, and increased the purchase price of the property from the sum of $5,350,000 to the sum of $6,950,000. The amended lease agreement was executed on July 18, 1996.
The Town alleged that the Espies represented that the increase was necessary for unexpected renovation needs, including heating, ventilation, conversion of a pole barn on the property into an automobile maintenance center, installation of a more extensive telecommunications system than the extant system, and the purchase of an emergency power backup system. The Town alleged that these representations were false when made and made with the intent to defraud the Town of money.
The Town alleged that, upon completion of the renovations to the warehouse, it immediately exercised the option to purchase. The parties closed on the sale of the warehouse on September 18, 1996.
The Supreme Court erred in denying that branch of Espies’ motion which was to dismiss, as time-barred, the first cause of action predicated on a violation of
In applying this limitations period, we conclude that the competitive bidding violation cause of action accrued on April 20, 1995 when the renovation project was assigned to the Espies as part of the lease agreement. “A cause of action accrues, for the purpose of measuring the period of limitations, ‘when all of the facts necessary to the cause of action have occurred so that the party would be entitled to obtain relief in court’” (Matter of Motor Veh. Acc. Indem. Corp. v Aetna Cas. & Sur. Co., 89 NY2d 214, 221 [1996], quoting Aetna Life & Cas. Co. v Nelson, 67 NY2d 169, 175 [1986]).
The Supreme Court also erred in not granting that branch of the Espies’ motion which was to dismiss, as time-barred, the second cause of action predicated on fraud. A cause of action alleging fraud must be commenced within six years after the date on which the cause of action accrued or within two years after the time the plaintiff could with reasonable diligence have discovered the fraud (see
The Town’s fraud cause of action accrued on July 18, 1996 when the Town executed the amended lease agreement, which it alleges was falsely represented as necessary for unexpected renovation costs. The Town Board approved the significant price increase a day earlier. By this time the Town knew, or should have known, whether the alleged renovation costs were legitimate by duly investigating the matter (see Prestandrea v Stein, 262 AD2d 621, 622-623 [1999]). Moreover, contrary to the Town’s contention, the injury occurred on July 18, 1996 upon the execution of the amended lease agreement, when the Town bound itself to terms increasing the option purchase price (see generally Matter of Neidich, 290 AD2d 557, 558 [2002]; Matter of Blake, 282 AD2d 905, 906 [2001]; Pommer v Trustco Bank,
The third cause of action is predicated on breach of contract. The Town alleged that “[p]ursuant to the agreement between it and [the Espies], all renovations were to be performed in a good and workmanlike fashion.” The Town alleged that the Espies breached this agreement. Subsequent to the transfer of title on September 18, 1996, the building became damaged by cracks in the concrete slab under the building and sinking of the slab caused by a settling of the underlying soil. The Town further alleged that the condition of the building violated certain provisions of the Building Code in effect at the time. This, according to the Town, resulted in the need to make costly and unanticipated repairs.
To the extent that the Town claims that the Espies breached a guarantee that the renovations would be performed in a certain manner, “[n]o warranty attaches to the performance of a service . . . [i]f the service is performed negligently, the cause of action accruing is for that negligence. Likewise, if it constitutes a breach of contract, the action is for that breach” (Aegis Prods. v Arriflex Corp. of Am., 25 AD2d 639, 639 [1966]; see Milau Assoc. v North Ave. Dev. Corp., 42 NY2d 482, 488 [1977]).
Claims for damages for breach of construction contracts are generally governed by a six-year limitations period (see
Here, the record is unclear as to the time when the renovations on the warehouse were substantially completed. If the renovations were substantially completed before September 4, 1996, then the commencement of the federal action on September 4, 2002 would render the breach of contract cause of action time-barred, based on the governing six-year limitations period (see
Similarly, the breach of contract cause of action cannot be dismissed at this time based on the statute of frauds. There is no indication in the record that the alleged renovation agreement was reduced to a writing. Thus, whether the renovation agreement is enforceable is governed by the statute of frauds (see
The Espies’ remaining contentions are without merit.
Schmidt, J.P., Crane, Krausman and Dickerson, JJ., concur.
